RECLAIMED WATER MAIN EXTENSIONS PHASE 6
Solicitation number
B-26-13
Issued by
Volusia County, Florida

About this file

This is an addendum document issued by the City of Tallahassee, Florida, related to the Reclaimed Water Main Extensions Phase 6 project. The addendum modifies the original invitation to bid for construction of approximately 5,600 linear feet of reuse transmission main and 6,400 linear feet of reclaimed distribution mains to serve the Forest Trace and Mallory Square subdivisions. The addendum clarifies project specifications, technical requirements, and bidding procedures. Bidders are required to acknowledge receipt of the addendum as part of their bid submission. The document addresses modifications to plans, specifications, and general conditions outlined in the original bid documents.

The addendum serves to ensure all prospective bidders have consistent and complete information regarding project requirements, material specifications, and construction standards. Any pricing adjustments or scope modifications resulting from the addendum should be incorporated into bid proposals. Bidders must comply with all conditions set forth in both the original bid documents and this addendum, with the addendum taking precedence in cases of conflict. The City of Tallahassee retains the authority to accept or reject any or all bids and to waive any informalities in the bidding process.

View the file

Other files

File Type Posted
B2613RCA.pdf PDF
B2613Tabulation.pdf PDF
B2613ADD5.pdf PDF
B2613PriceSheetRevised.xlsx XLSX spreadsheet
B2613ADD3.pdf PDF
B2613ADD2.pdf PDF
B2613ADD1.pdf PDF
B2613PriceSheet.xlsx XLSX spreadsheet
B2613Plans.pdf PDF
B2613Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 4

Project Name:

Reclaimed Water Main Extension Phase 6 Client: City of DeLand

Project Location: DeLand, Florida Client Representative: Jim Ailes Project Number: 1000706-220871.01 Mead & Hunt, Inc. Manager: Casey Cissell, PE Date: June 15, 2026 Mead & Hunt Inc. Phone: (386) 761-6810

TO ALL BIDDERS: You are requested to make all changes and/or additions contained in this Addendum to the Bidding Documents. Failure to acknowledge this Addendum in Proposal shall result in rejection of bid.

BID DATE AND TIME SHOULD CORRESPOND TO DATE AND TIME INDICATED IN

ADVERTISEMENT FOR BIDS, UNLESS DATE AND TIME HAS BEEN CHANGED IN THIS OR

PREVIOUS ADDENDUMS.

I. GENERAL

A. Bids will be received until Thursday, June 18, 2026.

QUESTIONS

1. Does this project have any certified payroll requirements?

Answer: Certified payroll is not required on the project.

2. Does this project have any BABA requirements?

Answer: BABA requirements are not part of this project.

3. Does this project have any AIS requirements?

Answer: AIS requirements are not part of this project.

4. Are signed and sealed MOT plans required?

Answer: FDOT indexes are provided in the plan set. If specific MOT not covered by the indexes shall be designed and submitted by a qualified individual.

5. Will a laydown yard be required?

Answer: A laydown area is not required.

6. Will the owner pay for the water used for Pigging, Flushing, Testing?

Answer: The City does not pay for water use. Contractor to obtain a hydrant meter and pay for the water consumption.

7. What are the hours/days allowed for work?

Answer: Hours of work are Monday to Friday from 7:00am to 7:00pm

8. Are there any MBE or DBE goals?

Answer: MBE / DBE do not apply to this project.

9. Is a field office required?

Answer: A field office is not required.

10. Is Builders Risk Insurance required?

Answer: Builders Risk Insurance is not required.

11. Will the owner reimburse the contractor for any required permits and/or fees such as ROW permit, etc.?

Answer: Permit fees will be reimbursed if applicable through the allowance line item.

12. Please provide a copy of all the permits obtained by the owner for this project.

Answer: Applicable permits will be included in the project manual.

13. Please provide all the permits, including fees, that the Contractor is responsible for.

Answer: No permits.

14. Can we use hydroseed for restoration?

Answer: Hydroseed will not be allowed for the restoration. Sodding of like kind is required.

15. Please advise whether there are any known contaminated areas within the project site or vicinity?

Answer: There are no known contaminated areas along the project route.

16. What is the anticipated NTP date?

Answer: NTP will be determined at the preconstruction meeting once the project is awarded.

17. Is there an available water source?

Answer: Water source would be the closest fire hydrant to the work taking place.

18. 150 days for substantial completion is an incredibly tight timeframe for this whole project to be completed. Is that 150 days from notice to proceed or 150 days from mobilization to the site?

Answer: The contract duration is 150 days from NTP to substantial completion and 30 for remaining close out work.

For the Directional Drilling, we have the following questions

1) Are signed and sealed HDD calcs required?

Answer: Signed/sealed HDD calcs are not required on this project.

2) Do we need to de-bead the HDPE at the fusion joints?

Answer: De-beading the HDPE is not required on this project.

3) Is wireline guidance required for this project?

Answer: Wireline is not required on this project.

4) Is a mud engineer required for the drilling operations?

Answer: A mud engineer is not required on this project.

5) Do all fusion joints need to be recorded with a Datalogger?

Answer: Datalogging will not be required on this project, however fusion joints are required to be done by a certified fusing technician.

6) May HDPE-to-DI/PVC connections be made using stainless steel internal stiffeners with mechanical joint wedge-type restraints in lieu of HDPE MJ adapters?

Answer: Stainless steel internal stiffeners with MEGA-Lug restraints are required. MJ adapters are not allowed on this project.

7) Can we drill deeper than what it shown on the plans/profile? What is the max drill depth?

Answer: Drill depths shall follow what is shown on the plans/profile. The City will need to access the mains for service and repairs.

8) Can we extend the drills?

Answer: Drill lengths may be adjusted in the field with City/EOR approval.

9) Are we allowed to work Saturday and Sunday to prevent frackouts?

Answer: Weekend work will need to be requested 72 hours in advance and receive approval by City staff/EOR.

Please also note the following plan / bid sheet errors and inconsistencies

1. Sheets 102 and 103 call out a 12"x12" Tee and a blowoff assembly that does not exist at that location.

Answer: Disregard, bid what is shown on the plans.

2. Sheet 103A calls out (2) 12" sleeves and (2) 12" Gate valves at each connection to the HDD lines instead of one each.

Answer: Bid what is shown on the plans.

3. There is a call out on Sheet C-105 for 38LF of 6" PVC by open cut that is not pointing to anything.

Sidewalk Restoration is also shown in this area even though the RCWM is being drilled at this location.

Answer: Disregard this call out.

4. The 12" sleeve on the north end of the short drill on sheet C-107 is not shown.

Answer: Bid what is shown on the plans. It will be covered in the ADD/DELETE Fittings.

5. The plan errors in items 1 and 2 resulted in the bid form showing (11) 12" Gate Valves and (8) Blowoff assemblies.

Answer: Please update this to show 9 Gate valves and 6 blowoff assemblies to match the plans

6. There are only two ARVs shown on the project even though there are 9 drills. Will more ARVs be necessary? If so, please update the bid form to reflect the necessary amount.

Answer: Additional ARVs are not necessary.

7. The 8" cross on Sheet C-111 is shown in the middle of an 845 ft long drill with no profile. How deep will this connection be? Can the drill be split up so that this connection will be at a high point with 3' of cover to minimize restoration and traffic disturbance at the intersection?

Answer: Yes, this connection point can be made at this location and is meant to be shallow for maintenance reasons.

8. The bid form calls out (2) 2" reclaim water services to common areas. These services are not shown on the plans. Where do they get installed?

Answer: These services will be determined whether needed or not during construction per the HOAs.

END OF ADDENDUM