B2612Final.pdf
PDF 21 MB Posted
- Solicitation number
- 26-12
- Issued by
- Volusia County, Florida
About this file
This is a Bid Package and Instructions to Bidders document issued by the City of DeLand, Florida for the DeLand Municipal Airport South-Central Apron Rehabilitation project (Bid #B-26-12). The project encompasses cold-in-place recycling (rotomixing) of the existing apron, removal of existing aircraft tiedowns, paving and grading, application of new airfield markings, and installation of new aircraft tiedowns at the DeLand Municipal Airport. A mandatory pre-bid conference will be held on Tuesday, May 5, 2026 at 2:00 PM at the Airport Administration Building (1000 Flightline Boulevard, DeLand, Florida 32720), with bids due by Thursday, May 21, 2026 at 3:00 PM at City Hall (120 South Florida Avenue, DeLand, Florida 32720). The project has an expected duration of eighty-three (83) calendar days. Bidders must submit sealed bids with a 5% bid bond, evidence of state authorization to do business, contractor license information, subcontractor and supplier lists, and required affidavits and certifications. Bids will be publicly opened immediately following the deadline, with award of contract anticipated thereafter pending evaluation of responsible bidders submitting responsive bids.
Pricing is to be submitted on a lump sum basis for the base bid and any identified alternates, with all prices remaining firm for a minimum of sixty (60) days after bid opening. The City of DeLand is exempt from Florida sales and use taxes, and such taxes must not be included in the bid price. Upon award, the successful bidder must furnish a 100% Performance and Construction Bond and maintain comprehensive public liability insurance with minimum limits of $1,000,000 per occurrence (or $2,000,000 combined single limit) and $1,000,000 automobile liability coverage. Worker's compensation insurance at statutory limits is also required. The project is subject to FAA Buy American Preference requirements, and bidders must certify compliance with 49 U.S.C. §50101 and related Made in America provisions, submitting evidence of domestic product sourcing or requesting a formal waiver if unable to meet 100 percent domestic content requirements. Payment will be made in accordance with Florida's Local Government Prompt Payment Act, with the City utilizing a VISA Purchasing Card where applicable. All bidding documents are available through Demandstar and Vendorlink websites, and the project is federally funded through FAA oversight.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB 26-12 Lawn Maintenance as Specified for City Facilities.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DELAND MUNICIPAL
AIRPORT
SOUTH-CENTRAL APRON
REHABILITATION
BID # B-26-12
City of DeLand
1102 South Amelia Avenue
DeLand, Florida 32724
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 01 PROJECT TITLE PAGE
0002-1 NOTICE TO BIDDERS
C-200 INSTRUCTIONS TO BIDDERS
INVITATION TO BID
C-111 BID ADVERTISEMENT
00300 NON-COLLUSION AFFIDAVIT/DRUG FREE WORKPLACE/E-VERIFY/HUMAN TRAFFICKING
PUBLIC ENTITY CRIME FORM
SCRUTINIZED COMPANY FORM
CERTIFICATION OF TAX DELINQUENCY STATUS
BUY AMERICA COMPLIANCE CERTIFICATION
00150 TRENCH SAFETY
C-410/C-451 BID FORM/QUALIFICATIONS
INSURANCE REQUIREMENTS
3768115 CONSTRUCTION CONTRACT
C-550 NOTICE TO PROCEED
C-610 PERFORMANCE BOND
C-615 PAYMENT BOND
C-625 CERTIFICATE OF SUBSTANTIAL COMPLETION
C-626 ACCEPTIBILITY
C-700 STANDARD GENERAL CONDITIONS
C-800 STANDARD GENERAL CONDITIONS SUPPLEMENTARY
C-940 WORK CHANGE DIRECTIVE
C-941 CHANGE ORDER
C-942 FIELD ORDER
EXHIBIT 1
FAA PROVISIONS
EXHIBIT 2
Plans
SUBMIT TO:
CITY OF DeLAND FINANCE DEPT., 2nd Floor Receptionist
120 SOUTH FLORIDA AVENUE
DeLAND, FLORIDA 32720
CONTACT PERSON:
Purchasing Coordinator
PHONE:
purchasing@deland.org
BID TITLE:
DeLand Municipal Airport South- Central Apron Rehabilitation
BID #
26-12
SUBMITTAL DEADLINE
Thursday, May 21st, 2026 at
3:00 p.m.
PRE BID DATE, TIME AND LOCATION: Tuesday, May 5th, 2026 at 2:00 P.M. at the Airport Administration Building - 1000 Flightline Blvd, DeLand, FL 32720
SUBMITTALS RECEIVED AFTER ABOVE DATE
AND TIME WILL NOT BE CONSIDERED
RESPONDENT NAME:
MAILING ADDRESS:
BID BOND REQUIRED 5 %
CITY – STATE – ZIP:
TELEPHONE #:
FAX #: AUTHORIZED SIGNATURE
EMAIL: Printed Name
FEDERAL ID # OF SOCIAL SECURITY #:
Title Date
By my signature I certify that this offer is made without prior understanding, agreement, or connection with any corporation, firm, business entity, or person submitting an offer for the same materials, supplies, equipment, or service(s), and is in all respects fair and without collusion or fraud. I further agree that if the offer is accepted, the offeror will convey, sell, assign, or transfer to the City of DeLand all right, title, and interest in and to all causes of action it may now or hereafter acquire under the Antitrust laws of the United States and the State of Florida for price fixing relating to the particular commodity(s) or services(s) purchased or acquired by the City of DeLand. At the City’s discretion, such assignment shall be made and become effective at the time the City tenders final payment to the bidder.
THIS FORM MUST BE COMPLETED AND RETURNED WITH YOUR RESPONSE
GENERAL CONDITIONS AND INSTRUCTIONS
****PLEASE READ CAREFULLY****
1. SUBMISSION OF OFFERS: All offers shall be submitted in a sealed envelope or package. The invitation numbers, title, and opening date shall be clearly displayed on the outside of the sealed envelope or package. The delivery of responses to the receptionist located on the 2nd floor of City Hall prior to the specified date and time is solely and strictly the responsibility of the offeror. Any submittal received after the specified date and time will not be considered.
Responses shall be submitted on forms provided by the City. Additional information may be attached to the submittal. Facsimile submissions are NOT acceptable. No offer may be modified after acceptance. No offer may be withdrawn after opening for a period of sixty (60) days unless otherwise specified.
2. EXECUTION OF OFFER: Offer shall contain a manual signature in the space(s) provided of a representative authorized to legally bind the offeror to the provisions therein. All spaces requesting information from the offeror shall be completed.
Responses shall be typed or printed in ink. Use of erasable ink or pencil is not permitted.
Any correction made by the offeror to any entry must be initialed.
3. OPENING: Opening shall be public at City Hall immediately following the advertised deadline date and time for receipt of submittals. Pursuant to Section 119.073(3)(0) Florida Statutes (1991) no further information regarding offers submitted will be made public until such time of intended award or ten (10) days, whichever is earlier.
4. PUBLIC RECORD: The City of DeLand, Florida, is governed by the Public record Law, Chapter 119, Florida statutes. Pursuant to chapter 119 only trade secrets as defined in Section 812.081, Florida Statute shall be exempt from disclosure.
5. TABULATION: Anyone wishing to receive a copy of the tabulation of offers is required to enclose a stamped, self-addressed envelope with submittal, or include a written request to have the tabulation emailed to the email address listed above.
6. CLARIFICATION/CORRECTION OF ENTRY: The City of DeLand reserves the right to allow for the clarification of questionable entries and the correction of OBVIOUS
MISTAKES.
7. INTERPRETATION/ADDENDA: Any questions concerning conditions and specifications shall be directed to the designated contact person. Those interpretations which may affect the eventual outcome of the invitation/offer shall be furnished I in writing to prospective offerors.
No interpretation shall be considered binding unless provided in writing by the City of DeLand in the form of an addendum. Any addenda issued shall be acknowledged by signature and returned with offeror’s response.
Failure to acknowledge addenda may result in the offer not being considered.
8. INCURRED EXPENSES: This invitation does not commit the City to make an award nor shall the City be responsible for any cost or expense which may be incurred by any respondent in preparing and submitting a reply, or any cost or expense incurred by any respondent prior to the execution of a purchase order or contract agreement.
9. PRICING: Unless otherwise specified prices offered shall remain firm for a period of at least sixty (60) days; all pricing of goods shall include FOB DESTINATION, all packing, handling, shipping charges and delivery to any point(s) within the City to a secure area of inside delivery; all prices of services shall include all expenses necessary to provide the service at the location specified.
10. ADDITIONAL TERMS & CONDITIONS: The City of DeLand reserves the right to reject offers containing terms or conditions contradictory to those requested in the invitation specifications.
11. TAXES: The City of DeLand is exempt from Federal Excise Taxes and all sales taxes.
Florida State Exemption Certificate No. 85-8013842706C-2.
INVITATION TO BID
AN EQUAL
OPPORTUNITY
EMPLOYER
X
12. DISCOUNTS: All discounts except those for prompt payment shall be considered in determining the lowest net cost for evaluation purposes.
13. MEETS SPECIFICATIONS: The offeror represents that all offers to this invitation shall meet or exceed the minimum requirements specified.
14. SAMPLES: When required, samples of products shall be furnished with response to the City at no charge. Samples may be tested and will not be returned to the offeror. The result of any and all testing shall be made available upon written request.
15. SILENCE OF SPECIFICATIONS: The apparent silence of these specifications or any supplemental specifications as to details or the omission from same of any detailed description concerning any point, shall be regarded as meaning that only the best commercial practices are to prevail and that only materials of first quality and correct type, size, and design are to be used. All workmanship shall be first quality. All interpretations of specifications shall be made upon the basis of this statement.
16. GOVERNING LAWS: Any agreement to purchase resulting from this invitation shall be governed by the laws, regulations, and ordinances of the State of Florida and the City of DeLand, Florida. Venue shall be non-jury in the circuit Court of Volusia County, Florida.
17. ASSIGNMENT: Any agreement to purchase issued pursuant to this invitation and award thereof and the monies which may become due hereunder are not assignable except with the prior written approval of the City.
18. CONTENT OF INVITATION/RESPONSE: The contents of this invitation, all terms, conditions, specifications, and requirements included herein and the accepted and awarded response thereto may be incorporated into an agreement to purchase and become legally binding. Any terms, conditions, specifications, and/or requirements specific to the item or service requested herein shall supersede the requirements of the ‘GENERAL
CONDITIONS AND INSTRUCTIONS”.
19. LIABILITY: the supplier/provider shall hold and save the City of DeLand, its officers, agents, and employees harmless against claims by third parties resulting from breach of contract or negligence by the supplier/provider.
20. PATENTS, COPYRIGHT, AND ROYALTIES: The supplier/provider, without exception, shall indemnify and save harmless the City of DeLand, its officers, agents and employees from liability of any nature or kind, including cost and expenses for or on account of any copyrighted, registered, patented, or unpatented invention, process, or article manufactured or used in the provision of goods and/or services, including use by the City of DeLand. If the supplier/provider uses any design, device, or materials covered by letters, patent, copyright, or registration, it is mutually agreed and understood without exception that the quoted price shall include all royalties or costs arising from the use of such design, device, or materials in any way involved.
21. TRAINING: Unless otherwise specified suppliers/providers may be required at the convenience of and at no expense to the City to provide training to City personnel in the operation and maintenance of any item purchased as a result of this invitation.
22. ACCEPTANCE: Products purchased as a result of this invitation may be tested for compliance with specifications. Items delivered not conforming to specifications may be rejected and returned at bidder’s expense. Those items and items not delivered by the delivery date specified in accepted offer and/or purchase order may be purchased on the open market. Any increase in cost may be charged against the bidder.
23. SAFETY WARRANTY: Any awarded supplier/provider including dealers, distributors, and/or manufacturers shall be responsible for having complied with all Federal, State, and local standards, regulations, and laws concerning the product or service specified, and the use hereof, applicable and effective on the date of manufacture or use or date in service including safety and environmental standards as apply to both private industry and governmental agencies.
24. WARRANTY: The offeror agrees that, unless otherwise specified, the product and/or service furnished as a result of this invitation and award thereto shall be covered by the most favorable commercial warranty the offeror gives to any customer for comparable quantities of such products and/or services and that the right and remedies provided herein are in addition to and do not limit any rights afforded to the City of DeLand by any other provision of the invitation/offer.
25. AWARD: As the best interest of the City may require, the city reserves the right to make award(s) by individual item, group of items, all or none, or a combination thereof; on a geographical basis and/or on a Citywide basis with one or more supplier(s) or provider(s);
to reject any and all offers or waive any irregularity or technicality in offers received.
Offerors are cautioned to make no assumptions unless their offer has been evaluated as being responsive. Any or all award(s) made as a result of this invitation shall conform to applicable ordinances of the City of DeLand, Florida.
26. VIOLATIONS: any violation of any of the stipulations, terms, and/or conditions listed and/or included herein may result in the offeror/bidder being disqualified from doing business with the City for a period of time to be determined on a case-by-case basis.
27. PRICING: For purposes of this Invitation and evaluation of responses hereto the following shall apply: unit prices shall prevail over extended prices; written matter shall prevail over typed matters; numbers spelled in word form shall prevail over Arabic numerals (“one” over “1”). When not inconsistent with context words used in the present tense include the future, words in the plural number include the singular number, and words in the singular number include the plural number. The word “shall” is always mandatory and not merely directory.
28. INSURANCE: Vendor/Contractor shall defend, indemnify and hold harmless the city of DeLand from and against any and all liability, losses, damages, claims, demands, expenses, fees, fines, penalties, suits, proceedings, actions, and costs of actions (including attorneys’ fees), of whatsoever kind or nature arising out of or in any way arising out of the agreement or any act or omission of Vendor/Contractor or its agents, servants, employees, independent contractors, customers, patrons or invitees, unless such claims are as a result of the City’s sole negligence.
The Vendor/Contractor shall secure and maintain, at its own expense at all times during the term of this contract, a comprehensive public liability insurance policy issued by a responsible insurance company, and in a form acceptable to the City, protecting and insuring against all of the following: claims, demands, damages, fees, fines, penalties, suits, proceedings, actions, and costs of actions, etc., coverage limits of not less than $1,000,000 for bodily injury to or death to one or more person(s), and $1,000,000 for damage to any property, or a combined single limit of $2,000,000 for any occurrence of bodily injury to persons or damage to property, which insurance shall be issued on the occurrence basis. This policy shall name the City of DeLand as additionally insured.
The Vendor/Contractor shall secure and maintain, at its own expense at all times during the term of this contract an automobile liability coverage policy with a minimum of a $1,000,000 combined single limit per occurrence.
The Vendor/Contractor shall secure and maintain, at its own expense at all times during the term of this contract, Worker’s compensation Insurance covering all the persons employed by the Vendor/Contractor in connection with this contract. Worker’s Compensation shall be the Statutory Limits.
The Vendor/Contractor shall not commence work under this contract until he has obtained all insurance required and submitted proof thereof to the City’s Risk Manager for approval. Certificates shall provide for thirty (30) day cancellation notice to the City.
Referenced Certificate to be mailed to Risk Manager, City of DeLand, 120 South Florida Avenue, DeLand, Florida, 32720-5481.
The Vendor/Contractor shall either cover any sub-contractors on its policy or require the sub-contractors to conform to all requirement for insurance contained herein.
Vendor/Contractor agrees that the City of DeLand will make no payments pursuant to the terms of the contract until all required proof or evidence of insurance has been provided to the City’s Risk Manager.
29. DEFINITIONS:
CITY – The term “City” herein refers to the City of DeLand, Florida, and its duly authorized representatives.
OFFEROR - The term “offeror” used herein refers to any dealer, manufacturer, representative, distributor, or business organization submitting an offer to the City in response to this invitation.
BIDDER – The term “bidder” used herein refers to any dealer, manufacturer, representative, distributor, or business organization that will be or has been awarded a contract and/or purchase order pursuant to the terms and conditions of the invitation and accepted offer.
30. PUBLIC ENTITY CRIMES INFORMATION STATEMENT: A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted vendor list.
31. PERMITS: Contractor shall be responsible for payment of all applicable permit fees.
32. PAYMENT: Payment will be made in accordance with Local Government Prompt Payment Act (Florida Statutes 218.70 – 218.80). A City of DeLand VISA Purchasing Card will be used to pay for services or goods you provide, unless you are not currently VISA capable. Ability to accept VISA will not be considered in determining “lowest and best responsible bidder”. If you are not currently VISA capable, invoices submitted by the first of the month will be paid with the regularly scheduled accounts payable run for that month unless stated otherwise.
33. PERFORMANCE BOND: Upon award the successful bidder will also be required to furnish and pay for a satisfactory contract 100% Performance and Construction Bond to be recorded by the vendor, with the Clerk of the Circuit Court, Volusia County, Florida, to enter into a contract for services with the City of DeLand. The recorded document shall be returned to the City of DeLand, City Clerk’s Office, 120 south Florida Avenue, DeLand, FL, 32720
34. AVAILABILITY OF FUNDS: A contract shall be deemed executory only to the extent of appropriations available to each department for the purchase of such articles. The City’s extended obligation on these contracts which envision extended funding, through successive fiscal periods shall be contingent upon actual appropriations for the following fiscal year.
THE CITY OF DELAND RESERVES THE RIGHT TO REJECT ANY OR ALL
OFFERS, TO WAIVE INFORMALITIES, AND TO ACCEPT ALL OR ANY
PART OF ANY OFFER AS MAY BE DEEMED TO BE IN THE BEST INTEREST
OF THE CITY.
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1— Defined Terms
Article 2— Bidding Documents
Article 3— Qualifications of Bidders
Article 4— Pre-Bid Conference
Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 6— Bidder’s Representations and Certifications
Article 7— Interpretations and Addenda
Article 8— Bid Security
Article 9— Contract Times
Article 10— Substitute and “Or Equal” Items
Article 11— Subcontractors, Suppliers, and Others
Article 12— Preparation of Bid
Article 13— Basis of Bid
Article 14— Submittal of Bid
Article 15— Modification and Withdrawal of Bid
Article 16— Opening of Bids
Article 17— Bids to Remain Subject to Acceptance
Article 18— Evaluation of Bids and Award of Contract
Article 19— Bonds and Insurance
Article 20— Signing of Agreement
Article 21— Sales and Use Taxes
Article 22— Contracts to Be Assigned
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
TOC Page 1 of 1
ARTICLE 1—DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.
2.04 Bidder may register as a plan holder and obtain complete sets of Bidding Documents, in the number and format stated in the Advertisement or invitation to bid, from the Issuing Office.
Bidders may rely that sets of Bidding Documents obtained from the Issuing Office are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.
2.05 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination. Those prospective bidders that obtain an electronic (digital) copy of the Bidding Documents from a plan room are encouraged to register as plan holders from the Bidding Documents Website or Issuing Office. Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
2.06 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above.
However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
C. After the Contract is awarded, the Owner will provide or direct the Engineer to provide for the use of the Contractor documents that were developed by Engineer as part of the Project design process, as Electronic Documents in native file formats.
1. Electronic Documents that are available in native file format include:
a. Drawings and Specifications
2. Release of such documents will be solely for the convenience of the Contractor. No such document is a Contract Document.
3. Unless the Contract Documents explicitly identify that such information will be available to the Successful Bidder (Contractor), nothing herein will create an obligation on the part of the Owner or Engineer to provide or create such information, and the Contractor is not entitled to rely on the availability of such information in the preparation of its Bid or pricing of the Work. In all cases, the Contractor shall take appropriate measures to verify that any electronic/digital information provided in Electronic Documents is appropriate and adequate for the Contractor’s specific purposes.
4. In no case will the Contractor be entitled to additional compensation or time for completion due to any differences between the actual Contract Documents and any related document in native file format.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within
10 days of Owner’s request, Bidder must submit the following information:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
3.02 Prospective Bidders must submit required information regarding their qualifications at time of bid submittal. Owner will review the submitted information to determine which contractors are qualified to bid on the Work. Owner will issue an Addendum listing those contractors that Owner has determined to be qualified to construct the project. Bids will only be accepted from listed contractors. The information that each prospective Bidder must submit to seek prequalification includes the following:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Prospective Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
3.03 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.
C. Bidder’s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
3.04 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.05 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A pre-bid conference will be conducted for this Project.
4.03 A mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Proposals will not be accepted from Bidders who do not attend the conference. It is each Bidder’s responsibility to sign in at the pre-bid conference to verify its participation. Bidders must sign in using the name of the organization that will be submitting a Bid. A list of qualified Bidders that attended the pre-bid conference and are eligible to submit a Bid for this Project will be issued in an Addendum.
4.04 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.
c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
4. Geotechnical Baseline Report/Geotechnical Data Report: The Bidding Documents contain a Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR).
a. As set forth in the Supplementary Conditions, the GBR describes certain select subsurface conditions that are anticipated to be encountered by Contractor during construction in specified locations (“Baseline Conditions”). The GBR is a Contract Document.
b. The Baseline Conditions in the GBR are intended to reduce uncertainty and the degree of contingency in submitted Bids. However, Bidders cannot rely solely on the Baseline Conditions. Bids should be based on a comprehensive approach that includes an independent review and analysis of the GBR, all other Contract Documents, Technical Data, other available information, and observable surface conditions. Not all potential subsurface conditions are baselined.
c. Nothing in the GBR is intended to relieve Bidders of the responsibility to make their own determinations regarding construction costs, bidding strategies, and Bid prices, nor of the responsibility to select and be responsible for the means, methods, techniques, sequences, and procedures of construction, and for safety precautions and programs incident thereto.
d. As set forth in the Supplementary Conditions, the GDR is a Contract Document containing data prepared by or for the Owner in support of the GBR.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
5.03 Other Site-related Documents
A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:
1. As Coordinated with the City of DeLand.
Owner will make copies of these other Site-related documents available to any Bidder on request.
B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.
C. The other Site-related documents are not part of the Contract Documents.
D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.
E. No other Site-related documents are available.
5.04 Site Visit and Testing by Bidders
A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.
B. A Site visit is scheduled following the pre-bid conference. Maps to the Site will be available at the pre-Bid conference.
C. A Site visit is scheduled for (will be decided in pre-construction meeting). Maps to the Site will be made available upon request.
D. Bidders visiting the Site are required to arrange their own transportation to the Site.
E. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site: Ray Bahrami, City Engineer, 1102 South Amelia Avenue, DeLand, Florida 32724. Bidder must conduct the required Site visit during normal working hours.
F. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
G. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, H. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
I. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
5.05 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.
5.06 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents by 5: 00 P.M. on Thursday, May 14th, 2026. Contact information and submittal procedures for such questions are as follows:
A. Corey McMillen, Purchasing Manager, 120 South Florida Avenue, DeLand, Florida 32720.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five percent (5%) of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9—CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.
9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
9.03 Submitted bid prices are to be held and remain valid through 10/1/2026.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
10.02 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders.
Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs.
The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders. Bidders cannot rely upon approvals made in any other manner.
10.03 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within ten days after Bid opening:
A. [List key categories of the Work. Depending on the Project this might include electrical, fire protection, major equipment items].
11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.
Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, bid item, alternate, adjustment unit price item, and unit price item listed therein. All bid submissions should include a digital copy (USB).
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 81/2 inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.
12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
12.06 A Bid by an individual must show the Bidder’s name and official address.
12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.08 All names must be printed in ink below the signatures.
12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Lump Sum
A. Bidders must submit a Bid on a lump sum basis as set forth in the Bid Form.
13.02 Base Bid with Alternates
A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.
The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.
13.03 Sectional Bids
A. Bidders may submit a Bid on any individual section or any combination of sections, as set forth in the Bid Form.
B. Submission of a Bid on any section signifies Bidder’s willingness to enter into a Contract for that section alone at the price offered.
C. If Bidder submits Bids on individual sections and a Bid based on a combination of those sections, such combined Bid need not be the sum of the Bids on the individual sections.
D. Bidders offering a Bid on one or more sections must be capable of completing the Work covered by those sections within the time period stated in the Agreement.
13.04 Cost-Plus-Fee Bids
A. Bidders must submit a Bid on the Contractor’s fee, which must be in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .