About this file
This is a price sheet for the Westside Interceptor ARV (Air Release Valve) Replacements project in Florida. The project encompasses the replacement of four air release valves at specified locations: 1205 S Woodland (ARV 1), 1208 S Woodland (ARV 2), Adelle & New Hampshire Ave (ARV 3), and 710 W New Hampshire Ave (ARV 4). Each ARV replacement involves installation of stainless steel saddle or tie-in connections to existing valves, corporation stops, 2-inch green poly piping with compression adapters, stainless steel ball valves, green ARV enclosures, removal and cleaning of existing components, backfill operations, and manhole work. ARV 3 requires special attention with four tanker units for waste management due to site-specific flow conditions. The project includes associated work such as asphalt patching at ARV 2, sidewalk replacement at ARV 3, and closure of 18-inch FM isolation valves to control sewer flow during saddle replacements.
All four items are listed with a unit quantity of one and zero unit costs, resulting in a total project cost of $0.00 on this price sheet submission. Work designated for completion by others includes asphalt patching, sidewalk replacement, and supply of four new 2-inch D-025 ARVs by the city. The contractor is responsible for obtaining and installing a check valve at ARV 3 to backdrain the sewer into the wet well to prevent sewer spillage, with potential night work required depending on flow rates and project completion timeline. Tanker placement will occur at the closest lift station to the ARV work site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B2609Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| B-26-09 Price Sheet | ||||
| Item | Item Description | Qty | Unit Cost | Extended Cost |
| 1 | ARV 1: (1205 S Woodland) 18" x 2" SS saddle / Corp stop / 2" green poly / comp adapter / 2" SS ball valve under ARV / Green ARV enclosure / remove R&C / clean fill / backfill MH / no tanker needed here | 1 | $0.00 | |
| 2 | ARV 2: (1208 S Woodland) Tie to exisitng valve / Corp stop / 2" green poly / comp adapter / 2" SS ball valve under ARV / green ARV enclosure / remove R&C / clean fill / backfill MH / no tankers needed here | 1 | $0.00 | |
| 3 | ARV 3: (Adelle & New Hampshire Ave) 18" x 2" SS saddle / Corp stop / 2" green poly / comp adapter / 2" SS ball valve under ARV / Green ARV enclosure / remove R&C / clean fill / backfill MH / 4 tankers needed here | 1 | $0.00 | |
| 4 | ARV 4: (710 W New Hampshire Ave) Tie to exisitng valve / Corp stop / 2" green poly / comp adapter / 2" SS ball valve under ARV / green ARV enclosure / remove R&C / clean fill / backfill MH | 1 | $0.00 | |
| Total | $0.00 | |||
| Work By Others | ||||
| • Asphalt patch at ARV 2 | ||||
| • Sidewalk replacement at ARV 3 | ||||
| • City to supply (4) new 2" D-025 ARVs | ||||
| • Closing of 18" FM isolation valves to control sewer flow during saddle replacements | ||||
| Note: ARV 3 tankers will be placed at he closest lift sation to the ARV work. A check valve eill need to be picked up to backdrain the sewer into the wet well to eliminate any sewer spill at the ARV replacement site. This may need to be night work depending on the flows and the time needed to complete |