B1619 Reno A6 RFI Form.pdf

PDF 63 KB Posted

Attached to
Building 1619 Renovation at NAS JRB Fort Worth
Solicitation number
FA667522R0006
Issued by

About this file

This document contains a federal contract opportunity solicitation for building renovation services. The Air Force is seeking to renovate an existing building at Naval Air Station Joint Reserve Base Fort Worth to create space for security forces and investigative offices. The building will be fully gutted and renovated to be fully accessible, with work including demolition, mechanical, electrical, plumbing, and waste removal. A mandatory site visit will be held on June 29th, with proposals due by July 22nd. The contract is set aside for small businesses as a firm fixed price contract between $3-6 million. The NAICS code is 236220 and businesses must be registered in SAM to be eligible for award. The renovation schedule will be determined at time of award.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION / CLARIFICATION FORM

FOR CONTRACTOR USE ONLY

CONTRACT NO: RFI NUMBER: DATE (MM/DD/YY)

SUBJECT: DRAWING REFERENCE / DETAIL:

ATTACHMENT SENT UNDER SEPARATE

COVER(__)

RESPONSE NEEDED BY:

REQUEST:

PROPOSED SOLUTION (If applicable):

TO(Contracting Officer): 301 CONF/PK FROM (Contractor):

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

REQUEST FOR INFORMATION / CLARIFICATION FORM

FOR GOVERNMENT USE ONLY

FROM CONTRACTING

TO:

For Evaluation and Action

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

RFI RESPONSE / CLARIFICATION (refer to page 2)

RFI RESPONSE / CLARIFICATION:-

Government to complete following sections:

TO:(AF Contracting Office)

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

TO:(Contractor)

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

CONTRACTOR REVIEW

After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO

Reviewer:

DATE (MM/DD/YY) TYPE OR PRINT NAME AND TITLE SIGNATURE:

*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.

TOContractor:
Reviewer:
Text1:
Text2: 001
Date3_af_date:
Text4:
Text5:
Check Box6: Off
Date7_af_date:
Text9:
Text10:
Text11:
Text12:
Date13_af_date:
Text14:
Text16:
Date17_af_date:
Text18:
Text20:
Date21_af_date:
Text22:
Date24_af_date:
Text25:
Check Box27: Off
Check Box28: Off
Check Box29: Off
Check Box30: Off
Date31_af_date:
Text32: