This Statement of Work (SOW) details the replacement of upstairs window frames for nine nearly identical two-story residential houses operated by the U.S. Fish and Wildlife Service's Yukon Delta National Wildlife Refuge in Bethel, Alaska. The project requires removing existing window frames, assessing and repairing potential water damage in rough openings, and installing new tilt-turn style fiberglass window frames with specific performance requirements, including Energy Star compliance, low U-factor (≤0.22), and specific solar heat gain coefficient (SHGC) specifications.
The work is scheduled to be completed between May 15 and September 30, 2026, with contractors required to provide their own tools, transportation, and ladders. Key deliverables include product submittals, emergency egress compliance documentation, field assessment reports, and a comprehensive closeout package. The project encompasses nine residential addresses in Bethel, with each location requiring upstairs window frame removal, potential water damage repair, and installation of new window frames fitted with glass panes. Contractors must be licensed, experienced in remote Alaska work, and prepared to handle potential additional repair work discovered during window frame removal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U. S. Fish and Wildlife Service, Yukon Delta National Wildlife Refuge, Bethel, AK 99559
STATEMENT OF WORK (SOW)
Window Frames FY26
December 3, 2025
1. General:
1.1 Overview:
Yukon Delta National Wildlife Refuge operates multiple residential structures for employees in Bethel, AK. Our headquarters building is at 807 Chief Eddie Hoffman HWY, Bethel, AK 99559. Our Refuge maintains nine (9) nearly identical two-story houses on pilings. The window frames and matching windowpanes on the top floor of all houses have been identified to be replaced. Bethel is approximately 800 air miles west of Anchorage, Alaska. Bethel has no road access and can only be reached by air or sea. The project sites are accessible by vehicle. We are seeking bids to complete the work described in this Statement of Work.
1.2 Purpose/End Application:
Our Refuge maintains nine (9) nearly identical two-story houses on pilings. The floorplans are the same, just swapped/flipped pending location (see attachment). The windows throughout these quarters are tilt-turn style frames and were manufactured by Alaska Window in Fairbanks.
Unfortunately, that company is out of business now. Many of the window frames are starting to break down over years of use and replacement parts are no longer available. Moisture seepage has caused rust and corrosion on ferrous and non-ferrous surfaces and components of the frames. We are interested in having new window frames and window panes and mechanical fixtures for windows on the top floors of the nine (9) quarters. These new windows frames shall have replaceable window panes and a support market for replacement components and hardware. They will need to be replaced with like window frames and window panes as what is removed (i.e., the same side tilts/turns). Windowsills shall also be replaced on all windows frames from wood to a solid waterproof material such as Corian® or vinyl.
We have strong concerns about how the windows could have been installed originally due to moisture seepage we have observed. Once an old window frame is removed, a thorough inspection of the surrounding flashing and water impermeability layer (vapor barrier) is needed. If any damage is found in the flashing, vapor barrier, or wood framing around the windows, the damage will need to be repaired prior to the installation of the new window frame. In that case, new flashing, vapor barrios, and installation materials will need to be used. These additional costs are will not be in the base bid and will be assessed while on site. It is also worth noting that we wish to maintain the vinyl siding on the houses currently and extra care will be needed when removing and reinstalling window frames not to damage exterior siding. If damage occurs, the contractor shall repair damage caused.
1.3 Contractor Qualifications:
1.3.1 General contractors and specialty subcontractors shall be licensed and well qualified to perform the work consistent with the Contract Documents. We may reasonably object to
Contractor's proposed selection of workers and business entities. We prefer Contractors and Subcontractors that have worked in remote Alaska (e.g., Bethel) so we know they understand logistics and potential complexity with completing contracts here. If damage is found at the window rough openings, additional skilled labor (e.g., licensed
Mechanical Contractor) might be necessary and would be assessed and quoted beyond the original bid.
1.3.2 Provide documentation of current state certification of General Contractors and any additional skilled laborers required to fulfill the contract.
1.4 Other: Structural drawings and photos are attached or included as figures below.
2. Place of Performance and Period of Performance (POP)
2.1 Adress of work:
Yukon Delta NWR Headquarters
PO Box 346
807 Chief Eddie Hoffman HWY
Bethel, AK 99559
Quarters address Comments
9453 Ayaginar
Drive
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
Nengqerralria
Drive
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
156 Blackberry
Drive
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
150 Blackberry
Drive
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
805 Chief Eddie
Hoffman Hwy
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
815 Chief Eddie
Hoffman Hwy
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
1725 Wildlife
Lane
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
1727 Wildlife
Lane
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
1729 Wildlife
Lane
Upstairs window frames to be replaced with new tilt-turn style window frames fitted with new window panes.
2.1.1 Bethel is approximately 800 air miles west of Anchorage, Alaska. Bethel has no road access and can only be reached by air or sea. The project sites are accessible by vehicle.
2.2 Period of Performance (POP): All work shall be completed between 15 May 2026 and 30
September 2026, totaling 138 days, and shall occur only during non-frozen months. The contractor is required to submit bonds and Initial Project Schedule no later than 10 calendar days before issuance of the Notice to Proceed (NTP).
2.3 Normal duty hours are Monday through Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information. Additional communication between the Contractor and the Lead Maintenance Worker and/or Assistant Refuge Manager will be required for entry into occupied residences. Work related to this contract shall be conducted during normal duty hours. Empty rough openings are to be avoided outside of normal duty hours.
2.4 Non-duty hours include weeknights, weekends, and Government holidays: Work could occur during non-duty hours (i.e., weekends) at select residences at the approval of the Lead
Maintenance Worker and/or the Assistant Refuge Manager.
3. Scope
3.1 Remove upstairs window frames in nine (9) nearly identical 2-story housing units. Assess rough openings for water damage. Lead Maintenance Worker and/or Assistant Refuge Manager will also assess rough openings for water damage. If damage is found, damage shall be repaired, up to replacing damaged structural framing and then rough openings will be made watertight before installation of new window frames. Repair costs needed for found structural damage will be quoted and discussed on site, beyond the bid for this SOW.
3.2 Remove and replace upstairs window frames and panes in nine (9) nearly identical 2-story housing units with windows that meet and exceed the following requirements:
3.2.1 Number of Panes: 3
3.2.2 Glass: MSG Low-E (with Argon Gas)
3.2.3 Frame: Insulated, fiberglass
3.2.4 U-factor: ≤ 0.22
3.2.5 SHGC: 0.26-0.40
3.2.6 VT: 0.41-0.50
3.2.7 Standards: Energy Star and 2012 IECC compliant
3.3 Replace existing window frames in-kind (same size, same tilt/turn directionality). See detailed EXCEPTION below. Operable windows shall be tilt-and-turn style windows that open to the inside (in-swing). An example replacement window frame brand could be REHAU. All windowsills are to be replaced with a solid waterproof material such as Corian®. Color options shall be provided to the Lead Maintenance Worker and/or the Assistant Refuge Manager prior to ordering.
3.4 The number and approximate sizes for window frames for all units combined are listed below;
however, the contractor is responsible for confirming window dimensions. See attachment
One (1) listed - Window Frames Photos and below are for reference only. Note that the structural drawing Window Schedule has the kitchen window as “c”. This does not appear to be correct, and that the rough opening matches “a” for the kitchens. Number and approximate size of windows (width x height):
3.4.1 45x windows: 55 ½” x 47 ½”. Figure 1
3.4.2 9x master bedroom windows: 83 ¾” x 47 ½”. Figure 2
3.4.3 9x living room windows: 103 ½” x 47 ½”. Figure 3
3.4.4 9x kitchen windows: 27” x 40”. Figure 4
3.5 EXCEPTION: Verify that one window in each bedroom meets requirements for emergency egress. New opening must be at least 20”Wide x 24”High and 5.7 cu.ft. clear opening minimum, height of sill above floor ≤ 44”, and comply with NFPA 101, 24.2.2.3. Provide all incidentals for a fully finished replacement.
3.6 Install properly to seal tightly within frames and to building structure.
3.7 Re-trim exterior and interior of windows with new trim to match existing. Repair and/or re-install any damaged exterior vinyl siding that occurred during the installation process.
3.8 Contractor is responsible for disposing of the removed window frames and window panes. The
Bethel dump might require payment that shall be the responsibility of the contractor.
3.9 Storage, handling, and installation
3.9.1 Store products in conformance with the manufacturer's instruction. Store under cover in manufacturer's unopened packaging with identification labels or markings intact until ready for installation.
3.9.2 Fully support products in storage and prevent from contact with the ground until ready for installation.
3.9.3 Store products in a protected area and protect against exposure to sun, rain, water, dirt, mud, and other residue that may affect performance. Cover stored products with breathable protective wraps.
3.9.4 Install all products in accordance with manufacturer’s recommended installation procedures. Do not install products under environmental conditions outside manufacturer’s absolute limits.
4. Deliverables)
4.1 Deliverables required: All deliverables to be complete by the end of the POP.
4.1.1 Deliverables Summary Table
Deliverable Description Due Date Submission To
Initial Project
Schedule
Detailed Work schedule from NTP through 30 Sep 2026
Within 10 business days of NTP
COR, CS, Contracting
Officer & Refuge
Product
Submittals
Specs and materials (frames, panes, sills, etc.) for approval
Before material ordering
COR / Assistant Refuge
Manager
Emergency
Compliance
Documentation for one bedroom window per unit meeting egress code
Before window installation
COR, CS, CO , Refuge
Office
Field Assessment
Report
Report of any moisture or structural damage found post-frame removal
Within 1 business day of each discovery
Assistant Refuge
Manager and
Contracting Officer
Change Order
Proposals
Cost proposals for any damage repairs outside base bid
ASAP upon damage discovery COR and Refuge
Completed
Installations
Confirmation of new windows, specs met, trim/siding repaired
Before the day of each residence work
COR and Assistant
Refuge Manager
Final Inspection
Sign-off
Walkthrough/inspection checklist signed off by Government
End of POP or rolling per unit COR / Refuge
Warranty
Documentation
Manufacturer and installer warranty info for all materials and workmanship
Within closeout packet COR/Refuge
Closeout Report
Summary of work performed, all approvals, photos, warranty, and lessons learned
Final two (2) week of POP
COR and Contracting
Specialist
4.1.2 Initial Project Schedule within 10 days of Notice To Proceed (NTP)
4.1.3 Product submittal Log
Submittal Content Format Approval Authority
Window Product
Specifications
Energy rating, U-factor, SHGC, dimensions, material
COR and Assistant Refuge
Manager
Sill Material Options Samples or catalog images (e.g., Corian®/vinyl) PDF/photos
COR and Assistant Refuge
Manager
Emergency Egress
Compliance
Cut-sheets, dimensions, code compliance certificate
COR and Assistant Refuge
Assistant Refuge Manager
Trim & Siding Interior and exterior trim material, Photos/specs COR and Assistant Refuge
Submittal Content Format Approval Authority
Material Match siding repair Manager
4.1.4 Completed construction in accordance with the approved design documents.
4.1.5 Closeout Items (e.g., warranty information)
5. Government-Furnished Equipment (GFE) / Government-Furnished Information
(GFI)
5.1 Government-furnished equipment (GPE) and Government- furnished information
(GFI):
5.1.1 The Contractor shall provide their own tools and hardware. Storage of new window frames will be allowed in in the garages of the houses for the installations as well as a vacant FWS-operated garage at 228 Blackberry
Drive, Bethel, AK 99559. These garages are equipped with a single car bay door for access.
5.1.2 In addition to the Availability and Use of Utility Services clause Federal Acquisition
Regulation (FAR) 52.236-14, the Contractor shall furnish all temporary facilities and utilities needed including: heat, light, power, water, telephone, sanitary facilities, job offices, material handling equipment, temporary construction aids, and storage enclosures. If suitable USFWS water, electric, or other utility is present at the site, it may be used for construction purposes at no cost, only if it does not adversely impact the operations of the station and field station agrees to permit use. The Contractor shall provide and remove any temporary connections required.
5.1.3 It is encouraged that the Contractor participates in a site visit to assess work outlined in the SOW and to identify appropriate tools and hardware prior to work occurring.
5.2 Identify any limitations:
5.2.1 There are several hardware stores in Bethel, AK, though their supply and stock might not be adequate to fulfill the scope of this contract. Contractor is responsible for their tools and all hardware to complete this contract. The contractor will need a ladder to access the exterior of the windows. The refuge will not provide a ladder.
5.2.2 The Contractor will be required to travel to all residences on their own, therefore it is strongly advised that they rent a vehicle. Renting a vehicle might not be necessary due to available taxi services in Bethel. Regardless, no GPE, such as a vehicle or transportation between sites will be available to the Contractor from the Government.
6. Evaluation and Acceptance
6.1 The rough openings of each window need to be inspected by the Lead Maintenance Worker and/or the
Assistant Refuge Manager to assess moisture damage before new window frames are installed. This inspection will be required to assure that any damage is addressed. Any location with moisture damage will need to have the flashing and water barriers pulled back to assess full damage.
6.2 The work shall be done in accordance with all applicable federal, state and local codes including the most current edition of the IBC, National Electrical Code (NEC), NFPA 101 Life Safety Code, ADA/ABA, and any other applicable disciplines of the International Code Council, as well as with accepted general industry standards.
6.3 The work shall be accepted when all the work is completed as described here within and in accordance with any contract documents. Work will be inspected to assure compliance with the contract documents, but quality control and adherence to all contract requirements is the responsibility of the contractor, as further described in CFR 52.246-12, “Inspection of Construction”.
6.4 The Contractor’s work will be evaluated by the Lead Maintenance Worker and/or the Assistant
Refuge Manager. Work shall be completed in a clean and professional manner. Refuse/trash shall be cleaned up after completion of work at each residence. Communication from
Contractor on when work is completed at residences is required for final inspection at each residence and tenant coordination to access the next residence.
7. Quality Assurance/Quality Control (QAQC):
7.1 The Contractor’s work will be evaluated by the COR with the Lead Maintenance Worker and the Assistant Refuge Manager within the POP. Work shall be completed in a clean and professional manner and performed up to code. Refuse/trash shall be cleaned up after completion of work at each residence. If work is found to be faulty beyond the POP the
Contractor shall be held responsible for repairing their mistake, up to returning the site at the cost of the Contractor (see contract language beyond the Scope of Work). Photos, video, and/or clear documentation of failures or mistakes would be provided by the Lead Maintenance
Worker and/or the Assistant Refuge Manager via the Contracting Officer.
7.2 Identify and detail measures for assessing quality control and acceptance:
Quarters address Comments
9453 Ayaginar
Drive
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
Nengqerralria
Drive
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
Blackberry
Drive
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
Blackberry
Drive
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
805 Chief
Eddie
Hoffman Hwy
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
815 Chief
Eddie
Hoffman Hwy
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
1725 Wildlife
Lane
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
1727 Wildlife
Lane
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
1729 Wildlife
Lane
All upstairs window frame removal. Rough openings assessed for water damage and repaired if needed. New tilt-turn style window frame installed and fitted with glass.
8. Closeout Package Requirements
1. Final QA/QC checklists for each unit
2. Photos of each installed window (interior/exterior)
3. Warranty certificates (frames, panes, sills, labor)
4. Any change order approvals
5. Final invoice (linked to completed deliverables)
6. Summary memo of project lessons learned