This document is a solicitation for road maintenance services at Pine Bluff Arsenal. The U.S. Army Contracting Command - Rock Island is seeking a firm-fixed-price contract to repair damaged pavement, patch potholes, and overlay a parking lot. The work must be completed within 30 days of notice to proceed and will be inspected upon completion at the installation. Quotes are due by August 28, 2023. A site visit will be held prior to the deadline. The solicitation is set aside for small businesses and has an estimated value of $45 million. It includes a statement of work outlining the repair requirements, environmental and security compliance terms, and clauses for insurance, disputes, and protests.

View the file

Other files for this federal contract opportunity

Other files attached to Pine Bluff Arsenal Road Maintenance, newest first.
File Type Posted
W519TC-23-Q-2331-0003 Released.pdf PDF
Parking Lot Map.pdf PDF
B08 - W519TC-23-Q-2331 Amendment 01 SF30.pdf PDF
B08 - W519TC-23-Q-2331 Amendment 01 - Site Visit.pdf PDF
B08 - Attachment 001 - PRICE MATRIX.XLSX XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W519TC23Q2331 21-Jul-2023

b. TELEPHONE NUMBER

309-782-4997

8. OFFER DUE DATE/LOCAL TIME

09:00 AM 28 Aug 2023

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W519TC9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

GREG BROWN

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

ARMY CONTRACTING COMMAND - ROCK ISLAND

3055 RODMAN AVE

ROCK ISLAND IL 61299

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$45,000,000

NAICS:

237310

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF18

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W519TC23Q2331

Section SF 30 - BLOCK 14 CONTINUATION PAGE

RFQ W519TC-23-Q-2331

The U.S. Army Contracting Command – Rock Island (ACC-RI) is contemplating award of a Firm-Fixed-Price (FFP) purchase order contract to repair damaged pavement on the roads and parking areas around the Pass and ID center, as well as overlay the southeast parking lot located at Pine Bluff Arsenal (PBA). The requirements shall be completed in accordance with and meet all requirements of the Statement of Work (SOW), and specifications contained in this solicitation.

1. This is a combined synopsis and solicitation prepared in accordance with the format in Federal Acquisition Regulation (FAR) Part 13 – Simplified Acquisition Procedures, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; a quote is requested, and a written solicitation will not be issued. This is a total small business set-aside solicitation, in accordance with authorization provided at Federal Acquisition Regulation 19.502-2 – Total small business set-asides.

2. This combined synopsis and solicitation was prepared in accordance with the format in FAR Part 13 – Simplified Acquisition Procedures, therefore progress payments will not be authorized in accordance with FAR 32.003.

3. This solicitation document, and incorporated provisions and clauses are those in effect through Federal Acquisition Circular (FAC) 2023-04, effective 02JUN2023, and Defense Federal Acquisition Regulation Supplement (DFARS) DPN 20230609, effective 09JUN2023. The complete text of any of the provisions and clauses may be accessed in full text at www.acquisition.gov.

4. The corresponding NAICS code is 237310; the small business size standard is $39,500,000.00; and the Product Service Code (PSC) is

Z2LB.

5. The road maintenance being requested via this RFQ shall meet all requirements included in the Statement of Work (SOW).

6. Vendor will perform work required under this solicitation via FOB Destination at Pine Bluff Arsenal, postal address:

10020 Kabrich Circle Pine Bluff, Arkansas

71602-9500

Inspection and Acceptance will occur at Destination.

7. Period of Performance: The vendor shall complete all requirements within 30 days from Notice to Proceed (NTP) issuance.

8. A Site Visit will be held prior to the closing date of this solicitation. An amendment to the solicitation will be posted at SAM.GOV providing the date and details of the site visit, and instructions to gain access to Pine Bluff Arsenal.

9. The following attachment is associated with this solicitation:

Attachment 001: Price Matrix

10. Quote shall be received no later than Monday, August 28, 2023, at 9:00 a.m. central time. Quote shall be submitted electronically to the points of contact listed below.

11. This is not a firm commitment on the part of the Government and does not constitute an order.

12. The points of contact for this action are:

Contract Specialist: Mr. Greg Brown at greg.j.brown.civ@army.mil, Contracting Officer: Mr. John Fotos at john.g.fotos.civ@army.mil.

Section SF 1449 - CONTINUATION SHEET

INSTRUCTIONS TO OFFERORS

1. Quote submission package shall consist of the information listed below and remain valid for a period of 60 days after the United States Government’s submission deadline.

a. A price quote in Microsoft Excel, i.e. ATTACHMENT 001, that includes:

i. Company CAGE code and Unique Entity ID;

ii. Contact information (i.e. name, phone number, and email address) for duly authorized company representative with the authority to offer and sign contracts on behalf of the company;

iii. Proposed prices to complete the road maintenance requirements located at Pine Bluff Arsenal (PBA) in accordance with the Statement of Work (SOW), and specifications contained in this solicitation.

b. Technical Acceptability – It is the Offerors responsibility to ensure the quote contains sufficient technical data and product literature to demonstrate the proposed solution meets or exceeds the stated requirements. At a minimum, Offeror shall provide:

- Proof of ability to meet bonding and insurance requirements in accordance with FAR 52.228-5, Insurance-Work on a Government Installation, FAR 52.228-15, Performance and Payment Bonds- Construction, and the Local Directive entitled, Required Insurance, as contained in this solicitation

- Proof of verifiable experience performing road work similar to the requirements detailed in the SOW. Examples of verifiable experience include but are not limited to: a basic description of the companies background and expertise, examples detailing the kinds of road maintenance the company is capable of performing, and/or summaries of previous road maintenance requirements completed.

c. Signed acknowledgement of the solicitation and any subsequent solicitation amendments (if any amendments have been issued by the Government).

d. Completed FAR provisions and clauses included in this attachment as necessary.

e. Quoter must be registered in the System for Award Management (SAM) database to be eligible to receive a Government contract. SAM is to be used for all of the following: (i) contractor registration (formerly CCR), (ii) representations and certifications (formerly ORCA), and (iii) exclusions (formerly EPLS). If quoter has current representations and certifications in the System for Award Management (SAM) database, quoter shall submit their SAM representations and certifications.

The United States Government (USG) will hold a Site Visit prior to the closing date of the solicitation. An amendment to this solicitation will be posted at SAM.gov providing the date and details of the site visit, and instructions to gain access to Pine Bluff Arsenal.

(a) The Government anticipates awarding a single firm-fixed-price purchase order resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

- Compliance with the terms of the solicitation.

- PRICE. The Lowest Price Technically Acceptable (LPTA) proposed price will be evaluated to ensure the price is fair and reasonable using procedures at FAR 13.106-3, prior to award.

- TECHNICAL ACCEPTABILITY: Only quotes that are found to be technically acceptable will be considered for award.

(b) Options. The Government will not evaluate options as part of this solicitation.

(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

STATEMENT OF WORK

Statement of Work

1. The Pine Bluff Arsenal (PBA) requires repairs to damaged pavement on the roads and parking areas around the Pass and ID center as well as an overlay of the south east parking lot. Contractor shall complete all work for this action will be no later than October 1, 2023. The following material quantities are approximations based on measurements of the affected areas.

2. Work to be completed in this delivery order is as follows:

a. ACHM Patching of Existing Asphalt Roadways in the following locations: A Street (pot holes) 2.5 tons, SE Parking Lot (pot holes). Total ACHM Patching of Existing Asphalt Roadways = 37 tons.

b. SE parking lot to be overlaid after existing holes have been repaired. Work will include: 132.5 Gal. of tack coat and 182.5 tons of ACHM Surface Course (PG 64-22 0.5)

3. Asphaltic patching shall conform to the provisions of Section 415 – Asphalt Concrete Hot Mix Patching of Existing Roadways and all referenced sections therein of the Arkansas State Highway and Transportation Department “Standard Specifications for Highway Construction”, except as specified herein. Reference hereinafter to the Arkansas State Highway and Transportation Department “Standard Specifications for Highway Construction” will be by the basic designation “Standard Specifications”. The words “Chief Engineer” or “Engineer” in the Standard Specification shall be interpreted to mean “Contracting Officer”.

4. Prime and Tack Coat shall conform to the provisions of Section 401- Prime and Tack Coats and Emulsified Asphalt in Base Course and all referenced sections therein of the Arkansas State Highway and Transportation Department “Standard Specifications for Highway Construction”, except as specified herein. Reference hereinafter to the Arkansas State Highway and Transportation Department “Standard Specifications for Highway Construction” will be by the basic designation “Standard Specifications”. The words “Chief Engineer” or “Engineer” in the Standard Specification shall be interpreted to mean “Contracting Officer”.

5. Asphalt Surface Course shall conform to the provisions of Section 407- Asphalt Concrete Hot Mix Surface Course and all referenced sections therein of the Arkansas State Highway and Transportation Department “Standard Specifications for Highway Construction”, except as specified herein. Reference hereinafter to the Arkansas State Highway and Transportation Department “Standard Specifications for Highway Construction” will be by the basic designation “Standard Specifications”. The words “Chief Engineer” or “Engineer” in the Standard Specification shall be interpreted to mean “Contracting Officer”.

6. The point of contact for this issue is Jesse Ward in the Engineering, Plans, and Services Division at (870) 540- 3239.

OPSEC REQUIREMENTS:

1. Contractor and all associated sub‐contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

2. Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (TSDB) (Army Directive 2014‐05/AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3. The contractor and all associated sub‐contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the Contracting Officer Representative (COR). This training shall be completed within 10 calendar days of contract award and within 20 calendar days of new employees commencing performance with the results reported to the COR NLT 20 calendar days after contract award.

Environmental Requirements:

1. Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the COR.

2. Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide(https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for-Sustainable- Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials; recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.

3. Compliance with License and Certification Requirements: Contractor shall obtain all license and certification required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.

4. Notification of Federal and State Regulators: Contractor shall immediately notify the COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.

5. Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation.

Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.

6. Reporting Noncompliance: Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR.

7. Verification of National Environmental Policy Act Documents: Contractor shall obtain from the COR, a copy of AMC's National Environmental Policy Act Policy and 32 CFR 651 which addresses actions to be taken by contractor. These documents include but is not limited to the analysis-associated decision document of an Environmental Impact Statement and Record of Decision; Environmental Assessment and Finding of No Significant Impact or Notice to Proceed; or Record of Environmental Consideration on the proposed contract actions prior to commencement of such actions.

8. Conformance with Environmental Management System: Contractor shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of contamination, or can negatively impact the natural and/or human environment.

9. Competency Training for Contractor Personnel: Contractor shall not allow personnel to perform any activities and/or tasks on AMC installations without proper and adequate qualifications or job competency training. In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.

10. Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste generated, which cannot be recycled to an approved and permitted off-post disposal facility.

10.1 Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.

10.2 Prior to removing any waste from the installation for disposal, the Contractor shall coordinate with the installation Qualified Recycling Program (QRP) Manager, Designated Government Representative (DGR), and COR to arrange for recyclable materials to be removed and diverted from the waste stream.

10.3 Submit in writing the quantities of waste removed and recycled to the DGR and/or COR on a monthly basis. The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled, and the quantities of materials disposed/recycled by weight

10.4 The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.

10.5 The Contractor shall make maximum effort to reduce and prevent waste.

11. Generation of Hazardous Waste: Contractor shall contact the COR to obtain technical assistance from the Environmental Office for assisting with achieving and maintaining compliance with hazardous waste requirements. Contractor shall properly profile all waste generated as part of this contract to determine if any waste is hazardous waste as defined by 40 CFR. The Contractor shall properly package the hazardous waste and complete the hazardous waste manifest, prior to removing any hazardous waste from the installation. The contractor shall remove all hazardous waste generated by contract activities from the installation, to an approved off-post permitted hazardous waste disposal facility. The DGR shall assist contractors with profiling their waste upon request.

12. Use of Hazardous Materials: Contractor shall submit to the COR a hazardous material inventory.

The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from COR.

13. Prevention of Storm Water Pollution: The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimum control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as applicable to the Pollutant Discharge Elimination System general permit requirements. Applicable permits include

1. The installation’s Small Municipal Separate Storm Sewer System (MS4) Permit;

2. The Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activities

(MSGP); and

3. All Construction Activity Storm Water permits minimum control measures include, but not limited to:

Public Education and Outreach on Storm Water Impacts Public Involvement and Participation Illicit Discharge Detection and Elimination Construction Site Storm Water Run-off Control Post Construction Storm Water Management in New Development and Redevelopment

Pollution Prevention/Good Housekeeping for Municipal Operations Contractors will comply with the MSGP permit when the activity is identified as a permitted industrial activity. BMPs include, but are not limited to:

o Practicing spill prevention and good housekeeping.

o Installing and managing erosion and sediment control.

o Meeting the requirements of the MS4 permit.

Contractors will obtain permit coverage for construction activities disturbing over one acre of land (total acreage is cumulative across all portions of the project). BMPs include, but are not limited to:

o Preparing and implementing a site-specific Storm Water Pollution Prevention Plan (SWPPP) as outlined in the permit and prior to any soil disturbance.

o Installing and managing erosion and sediment control.

o Make available, upon request, permit associated documentation.

o Practicing spill prevention and good housekeeping.

o Meeting the requirements of the MS4 permit.

o Schedule inspections and provide corrective actions for noted deficiencies.

14. Storm Water Management Low Impact Design/Development (LID): The Contractor shall perform, track, participate, implement, and comply with Section 438 of the Energy Independence and Security Act;

Executive Order13514; and the DOA memorandum (2010) for full implementation of low impact design/development (LID) techniques to restore predevelopment hydrology to the maximum extent technically feasible for both new and renovation construction projects regardless of size. In support of LID, Contractors will adhere to installation landscape codes and the guidance found in the Installation Design Guide concerning Low Impact Design/Development for storm water management. The following LID practices include, but are not limited to:

Restoring predevelopment hydrology to the maximum extent technically feasible;

Promoting natural removal of pollutants such as nutrients, oil and grease, and sediments from storm water;

Managing rainfall at the point where it falls;

Meeting the requirements of the MS4 permit.

Important Note: Utilization of permanent retention/detention ponds is prohibited without authorization from the Installation Planning Division.

15. Use of Pesticides: Contractor shall submit the type and quantity of regulated pesticides to be applied, the application purpose, and location to the COR for approval 10 working days prior to the initial application. The Contractor shall submit the actual quantities applied (DD1532 or equivalent) to the COR within 2 working days (48 hours) after each approved application. The Contractor shall utilize Integrated Pest Management (IPM) technology and procedures in strict compliance with all applicable Federal, State, Army, and installation regulations, to include the installation's integrated pest management plan. Pesticide applicators shall be certified and licensed in accordance with the State where work is being performed and/or Department of Defense regulations. The Contractor shall provide evidence of personnel licenses and certifications to the COR prior to the initial application of pesticides. Only those pesticides registered with the US Environmental Protection Agency (EPA) and approved by Army Materiel Command Pest Management Consultant shall be utilized and then only in strict accordance with product labeling. The installation reserves the right to prohibit and limit the amount and type of pesticides used.

16. Protection of Work Site Resources: Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, the Contractor shall coordinate harvesting of saleable timber with the COR. Contractor shall notify the COR if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6inches in diameter unless permission has been granted in writing by the COR.

17. Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders and contract the COR and secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).

18. Protection of Sensitive Areas: Contractor shall comply with all installation designated sensitive and/or off-limit area restrictions. Sensitive areas are generally demarked indicating what activities (e.g., driving, digging, foot traffic) are prohibited. The Contractor shall also adhere to the following installation sensitive areas requirements

18.1 Cultural Resources Sites: Do not excavate, remove, damage, or otherwise deface any archeological resource located on public lands.

18.2 Endangered Species Habitats: Do not initiate any action that may disturb, endanger, or damage to any degree the habitat of a threatened and endangered species.

18.3 Wetlands: Do not excavate or take any action that could fill or damage any wetland unless working under a project specific Corps of Engineers 404 permit. Wetlands include streams, riparian areas, bogs, marshes, and swamps.

19. Corrective Action for Noncompliance: Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the COR, take immediate corrective action.

Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.

20. Noise: Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times. Pile-driving operations shall be coordinated through the COR.

21. Mercury: Mercury is prohibited, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited. Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed. Immediately report to the COR instances of breakage or mercury spillage. Clean mercury spill area to the satisfaction of the Contracting Officer. Cleanup of a mercury spill shall not be recycled and shall be managed as a hazardous waste for disposal.

22. Universal Waste / e-Waste Management: Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.

23. Pollution Prevention / Hazardous Waste Minimization: Minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for supporting waste minimization goals.

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab and Other Covered Entities

NOV 2021

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-26 Covered Telecommunications Equipment or Services-- Representation.

OCT 2020

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

NOV 2021

52.219-1 Small Business Program Representations MAR 2023 52.219-6 Notice Of Total Small Business Set-Aside NOV 2020 52.219-8 Utilization of Small Business Concerns OCT 2022 52.219-28 Post-Award Small Business Program Rerepresentation MAR 2023 52.222-3 Convict Labor JUN 2003 52.222-19 Child Labor -- Cooperation with Authorities and Remedies DEC 2022 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment JUN 2020 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-22 Previous Contracts And Compliance Reports FEB 1999 52.222-23 Notice of Requirement for Affirmative Action to Ensure

Equal Employment Opportunity for Construction

FEB 1999

52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-40 Notification of Employee Rights Under the National Labor

Relations Act

DEC 2010

52.222-41 Service Contract Labor Standards AUG 2018 52.222-42 Statement Of Equivalent Rates For Federal Hires MAY 2014 52.222-43 Fair Labor Standards Act And Service Contract Labor

Standards - Price Adjustment (Multiple Year And Option Contracts)

AUG 2018

52.222-50 Combating Trafficking in Persons NOV 2021 52.222-54 Employment Eligibility Verification MAY 2022 52.222-55 Minimum Wages for Contractor Workers Under Executive

Order 14026

JAN 2022

52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

JUN 2020

52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.225-18 Place of Manufacture AUG 2018 52.225-25 Prohibition on Contracting with Entities Engaging in Certain

Activities or Transactions Relating to Iran-- Representation and Certifications.

JUN 2020

52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-15 Performance and Payment Bonds--Construction JUN 2020 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.232-34 Payment By Electronic Funds Transfer--Other Than System for Award Management

JUL 2013

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

MAR 2023

52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-12 Cleaning Up APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.239-1 Privacy or Security Safeguards AUG 1996 52.252-1 Solicitation Provisions Incorporated By Reference FEB 1998

52.252-2 Clauses Incorporated By Reference FEB 1998 52.252-5 Authorized Deviations In Provisions NOV 2020 52.252-6 Authorized Deviations In Clauses NOV 2020 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors JAN 2023 252.204-7015 Notice of Authorized Disclosure of Information for Litigation

Support

JAN 2023

252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation

DEC 2019

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation

MAY 2021

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2023

252.204-7022 Expediting Contract Closeout MAY 2021 252.211-7003 Item Unique Identification and Valuation JAN 2023 252.225-7055 Representation Regarding Business Operations with the

Maduro Regime

MAY 2022

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports

DEC 2018

252.232-7010 Levies on Contract Payments DEC 2006 252.246-7003 Notification of Potential Safety Issues JAN 2023 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for

Military Operations

OCT 2010

CLAUSES INCORPORATED BY FULL TEXT

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 million, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

2 in 1 Invoice

(Contracting Officer: Insert either “Invoice 2in1” or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC HQ0303

Issue By DoDAAC W519TC

Admin DoDAAC** W519TC

Inspect By DoDAAC W41G26

Ship To Code ____

Ship From Code ____

Mark For Code ____

Service Approver (DoDAAC) W519TC

Service Acceptor (DoDAAC) W519TC

Accept at Other DoDAAC ____

LPO DoDAAC ____

DCAA Auditor DoDAAC ____

Other DoDAAC(s) ____

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

Upon invoice submission, send email notification to Contract Specialist Greg Brown @ greg.j.brown.civ@army.mil, and Contracting Officer John Fotos @ john.g.fotos.civ@army.mil

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

ADDITIONAL INFORMATION

INSPECTION AND ACCEPTANCE (PBA) (AUG 90) (4306I):

Inspection and acceptance will be at destination, unless otherwise provided herein. Until delivery and acceptance, and after any rejections, risk of loss will be on the contractor, unless loss results from negligence of the United States Government.

UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT PERSONNEL

(PBA) (AUG 90) (4417).

a. The contractor will not accept any instructions by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the designated Contracting Officer's Representative (COR) acting within the limits of his authority. Contracting Officer's Representative will be so designated in writing to the contractor and the scope of his authority will be set forth therein.

b. No information, other than that which may be contained in an authorized modification to this purchase instrument duly issued by the Contracting Officer, may be considered a valid obligation.

Information received from any other person employed by the U.S. Government will not be considered grounds for deviation from any stipulation of this purchase instrument or referenced drawings and/or specifications.

(End)

REQUIRED INSURANCE

Pursuant to paragraph (a) of FAR Clause 52.228-5, "Insurance – Work on a Government Installation", or FAR Clause 52.228-7, "Insurance – Liability to Third Persons", the Contractor shall procure and maintain the following insurance during the entire period of performance under this contract:

TYPE AMOUNT

Worker’s Compensation As required by Law

Employer’s Liability Minimum liability limit $100,000

General Liability Minimum bodily injury limits, $500,000 per occurrence

Automobile Liability Minimum liability of $200,000 per person, $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage

Aircraft Public and Coverage required when contract performance involves us of aircraft:

Passenger Liability Minimum liability of $200,000 per person, $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Passenger liability shall be at least $200,000 multiplied by the number of seats or number of passengers, whichever is greater.

Vessel Collision Liability Coverage required when contract performance involves use of vessels:

Minimum liability of $5,000,000 or the market value of the property being shipped by vessel, whichever is greater

AMC-LEVEL PROTEST PROGRAM

If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible Contracting Officer. However, you can also protest to Headquarters, AMC.

The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with General Accounting Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. To be timely, protests must be filed within the periods specified in FAR 33.103. Send protests (other than protests to the Contracting Officer) to:

Headquarters U.S. Army Materiel Command Office of Command Counsel-Deputy Command Counsel 4400 Martin Road Rm: A6SE040.001 Redstone Arsenal, AL 35898-5000 Fax: (256) 450-8840 e-mail: usarmy.redstone.usamc.mbx.protests@mail.mil

The AMC-level protest procedures are found at:

http://www.amc.army.mil/Connect/Legal-Resources/

If Internet access is not available, contact the Contracting Officer or HQ, AMC Office of Command Counsel to obtain the AMC-Level Protest Procedures.

EMPLOYEE IDENTIFICATION

The contractor shall be responsible for providing positive identification of employees as required by the Security Office at Pine Bluff Arsenal. Prior to beginning work or receiving a notice to proceed, the contractor shall identify with the Pine Bluff Contracting Division and Security Office points of contact who shall be responsible for identifying employees, subcontractors, vendors and delivery personnel. One identified point of contact shall personally accompany any contractor personnel, subcontractors, vendors, or delivery personnel to be badged to the Security Office. Employees or other personnel arriving without an identified point of contact will not be badged. Any delays caused by improper identification of employees shall be at the contractor's expense and no time extensions shall be allowed for such delays.

DISMISSALS

The Contracting Officer may require the contractor to suspend or dismiss from work any employee or employees whose retention is deemed to be not in the public interest, because of the misconduct of the employee or for reasons of security, subject, however, to appeal under the provisions of Articles entitled "Disputes" for reinstatement of such employees.