This statement of work outlines the requirements for maintaining a tidal station in Glacier Bay National Park, Alaska. The National Park Service seeks a contractor to conduct annual scheduled maintenance of the station's radar water level measurement system, global navigation satellite system antenna, and data transmission equipment. The contractor must inspect and clean components, conduct geodetic leveling, replace batteries, and ensure continuous public data availability. Additional tasks include assessing water levels calculated from GNSS reflectometry compared to tidal station measurements and preparing related reports. The base period of performance is September 2023 through July 2024 with options to renew for up to four additional years. The contractor must visit the station within 11.5-12.5 months of the previous maintenance and deliver preliminary documentation within 15 days and final documentation within 60 days. The solicitation number for this opportunity is 140P9723Q0078.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
National Park Service
Glacier Bay Natural Resources
Statement of Work for the
Glacier Bay Tidal Station Maintenance in Glacier Bay, Alaska
5/15/2023
TABLE OF CONTENTS
1.0 General
2.0 Specific Requirements/Tasks
3.0 Delivery or Deliverables
4.0 Meetings
5.0 Required Travel and Other Direct Costs (ODCs)
6.0 Government Furnished Property/Equipment/Information
7.0 Special Instructions
8.0 Glossary of Abbreviations and Acronyms
Statement of Work (SOW)
1.0 General
1.1 Background
The mission of the National Park Service is to maintain resources unimpaired for future generations. A mission of Glacier Bay National Park is to be a source of scientific investigation into the retreat of Glaciers within Glacier Bay. This service acquisition provides the maintenance on a key piece of equipment that provides reference condition information for multiple studies and serves as a data provision for a key NWLON (National Water Level Observation Network) gap within the larger Alaskan NWLON network.
Glacier Bay National Park and the National Oceanic and Atmospheric Administration developed a 5-year agreement to install a NOAA tide station at the Bartlett Cove Fuel Dock in Glacier Bay National Park. As a part of the Agreement the National Park Service agreed to ensure maintenance of the instrumentation was conducted to maintain the station to NOAA NWLON standards and ensure that the data was made available to NOAA. To accomplish this task the NPS has decided to pursue a maintenance agreement with an appropriate entity capable of providing tide station maintenance, ensuring data availability, and providing a backup assessment of tidal data through reflectometry analysis from the associated permanent GNSS fixture at the site.
1.2 Objective
The objective of this service contract is to provide appropriate maintenance, ensure public data availability, and assess and evaluate the operational performance of the NWLON station installed at the docks near the headquarters of Glacier Bay National Park in Glacier Bay.
1.3 Scope of Work
This scope of work requires that the contractor provide personnel, expertise, equipment (except GFE), supplies, transportation, tools, materials, travel, and other non-personal services necessary to operate and maintain the Glacier Bay tidal stations. The maintenance terms are defined below. All activities under this task shall be done in accordance with (1) NWLON standards as specified in the latest published copy of the Standing Project Instructions (SPI) for the Coastal and Great Lakes Water Level Stations.
The water level sensors deployed at the station are required to operate continuously.
The GLBA tidal station consists of a Radar water level measurement system that is installed with a clear, unobstructed view of the water surface. There is a GOES satellite antenna for data transmission. Also included are a GNSS antenna, and data transmission and storage devices.
Scheduled maintenance station visits are covered by this SOW:
● Scheduled Maintenance (SM) – Activities performed on an annual basis at each station to maintain system integrity and confirm vertical stability.
The Contractor shall comply with all applicable state and Federal safety and health standards and regulations applicable to this work, including, but not limited to, the Occupational Safety and Health Act, 29 U.S.C § 651 et seq. When the Contractor relies on subcontractors in executing this work, the Contractor has sole responsibility for ensuring the subcontractors are qualified, appropriately trained and outfitted, and that the subcontractors comply with all applicable safety and health standards and regulations.
The Contractor shall adhere to the delivery schedule for SM and deliverables specified in this SOW and as confirmed during the scheduling planning meeting. Any changes or modifications to the schedule for any type of maintenance visit or deliverable must be reviewed and agreed to in advance by the Government.
If a station experiences an equipment failure within 72 hours immediately following any type of Contractor maintenance visit, and this failure is attributed to the Contractor’s performance, the Contractor shall be responsible for returning to the station and remedying the issue at the Contractor’s expense.
If, upon arrival at the site, the Contractor discovers any issue, failure, damage or situation that might lie outside the scope listed in this document, the Contractor shall immediately notify COR. The COR and the Contractor will attempt to make a joint determination of the situation. Depending on the circumstances, the COR may request a resource estimate for the Contractor to perform additional work if warranted. The CO will issue any final decision regarding the plan to proceed.
Contractor shall ensure that data being collected by the Tide station are transmitted and made publicly available to ensure NPS and NOAA CO-OPS both have access to the data in as close to real time as possible.
Contractor shall take data from the GNSS antenna (CORS site GLBX https://www.ngs.noaa.gov/cgi-cors/corsage.prl?site=GLBX) and assess the efficacy of using it for reflectometry for tidal heights and water levels of the station. The GNSS and tidal station data will be compared to determine the accuracy of the GNSS reflectometry information relative to known tidal heights.
https://www.ngs.noaa.gov/cgi-cors/corsage.prl?site=GLBX
1.4 Period of Performance
The initial base period of performance is estimated 9/1/2023 – 7/31/2024, with the first maintenance service required between 9/1/2023 – 12/31/2023. Additional option years of maintenance may be conducted provided funding availability for the work. Each additional option year has a one-month window from 11.5 – 12.5 months from the date of the previous maintenance to be conducted – with Deviations from that approved by the COR or other approved NPS Technical Representative.
Periods of Performance Table
Period Period Date Range
Base Period 9/1/2023 - 7/30/2024
Option 1 8/1/2024 - 7/30/2025
Option 2 8/1/2025 - 7/30/2026
Option 3 8/1/2026 - 7/30/2027
Option 4 8/1/2027 - 7/30/2028
1.5 Place of Performance
This service work will primarily take place at the dock near the Headquarters of Glacier Bay National Park in Glacier Bay, Alaska. Some of the data management and assessment work will be performed in an office setting at the Contractor’s office.
2.0 Specific Requirements/Tasks
In order to successfully execute this SOW, the Contractor shall:
Contact the park Technical Representative to determine the timing of the maintenance visit.
Arrange for secure and appropriate storage of all spare components, to serve as a staging area for field operations. The Contractor may work with the park to determine if appropriate facilities are available; however, if none are available, contractor will be responsible.
Furnish all vehicles, vessels, equipment, tools, materials, and supplies necessary to perform the tasks specified in this SOW.
Conduct all work in accordance with standard CO-OPS practices, unless otherwise specified.
Use CO-OPS standard forms where applicable for maintenance service records.
Otherwise, contractor is responsible for maintaining all records and transmitting those to NPS COR to document maintenance performed.
Staff each field team with the appropriate number of qualified personnel to accomplish the tasks specified in this SOW. This includes all professional, technical, and support personnel, along with their travel and transportation expenses to and from the place of performance.
Provide quick initial and follow-up response support as required to rapidly diagnose problems and thus minimize system downtime.
Schedule maintenance activities and ensure that they are conducted according to CO- OPS specifications to minimize downtime.
To the extent the Contractor relies on subcontractors in executing this work, the Contractor shall have sole responsibility for ensuring the subcontractors are qualified, appropriately trained and outfitted, and that the subcontractors comply with all applicable contract terms and conditions to include but not limited to safety and health standards and regulations.
Interact, in a professional manner, with individuals present at the dock site which may include, but are not limited to, federal agency personnel and the general public.
Contractors should be cautious of creating the impression that they represent NPS, NOAA or CO-OPS during required interactions with the afore mentioned entities.
2.1 Scheduled Maintenance
2.1.1 The tasks required to perform Scheduled Maintenance of water level measurement stations are detailed in Appendix F of the Next Generation Water Level Measurement System Site Design, Preparation, and Installation Manual and in the SPI. Requirements provided in the most recent version of the Project Instructions (PI) take precedence over requirements provided in this SOW.
If options are included, the Contractor shall perform a twelve-month Scheduled Maintenance (SM) within 11.5-12.5 months of the previous SM.
During each SM visit the Contractor shall:
Develop the Scheduled Maintenance checklist and provide to the COR for each annual inspection. The completed Scheduled Maintenance checklist shall be submitted as one of the deliverables.
Inspect and clean all above-water components of the station (e.g., enclosures, locks, antennas, solar panels, stands, mounts, poles and standoffs; conduit, cables, and connectors).
The Contractor shall repair and replace above-water components as necessary.
Immediately notify the Park Technical Representative (TR) and COR (if possible) if the Contractor observes any issue, failure, damage, or situation that could be beyond the scope of the task. The TR, COR, and the Contractor will jointly discuss potential solutions. The Park TR and COR will determine the course of action. Depending on the circumstances, the COR may request a resource estimate for the Contractor to perform additional work. The CO will issue any final decision regarding the plan to proceed.
Run geodetic levels between the benchmarks and the sensor leveling point(s) at all water level stations to ensure stability of the sensor(s) per the User’s Guide for Electronic Levels with Translev and Windesc, the User’s Guide to Vertical Control and Geodetic Leveling for CO-OPS Observing Systems, and the most recent PI.
Verify the elevations of all orifices installed for primary pressure gauges via steel tape measurement from the orifice zero to the orifice leveling point(s) and via leveling from PBM to the orifice leveling point.
Conduct static GNSS observations on the benchmark specified in the PI, if not specified then the most stable benchmark that meets the GPS visibility requirements for quality observations if required in the most recent PI. Publish and submit the GPS solution (email), OPUS published datasheet results and photos with either the preliminary or final documentation. The benchmark used for GPS observations must be included in the geodetic level run performed.
Replace all expired batteries in all DCPs and top side electronics with approved replacements, per Engineering Bulletin 10-002: Standardized Battery Type for CO-OPS Stations. Batteries shall be labeled with the installation date, shall be load tested annually, and shall be replaced every four years per the Standing PI.
The Contractor shall dispose of all used batteries in compliance with all federal, state, and local regulations.
Requirements specified in the Section 2.7 “Station Maintenance Requirements” and Section 2.7.1 “Additional Requirements for NOAA Sentinels” of the Standing Project Instructions for Coastal and Great Lakes Water Level Stations are also applicable for all maintenance activities.
If the Contractor cannot complete all Scheduled Maintenance requirements during a planned site visit, the Contractor shall return and complete all requirements within 15 days of the beginning of the original station visit.
Following each water level station visit, the Contractor shall:
Complete and submit the Preliminary Station Documentation within fifteen (15) working days of inspection (see Section 6.2.1 Preliminary Station Documentation).
Complete and submit a final SM documentation package within sixty (60) working days of SM.
Communicate any issues that may need major maintenance promptly to the COR and Park TR.
Include photos and drawings as needed.
2.2 Data Availability
2.2.1 Contractor shall ensure that data being collected by the Tidal station is easily available for immediate access. Data must be able to be accessed by NOAA CO-OPS and NPS staff via a publicly available web location.
Data is required to be continuously provided to NOAA CO-OPS for further processing. If notified of a failure Contractor will initiate contact with the Park TR and/or COR to determine appropriate pathways to resolve the situation. If the work falls outside of the scope of this contract, the Park TR and COR will determine the course of action.
Depending on the circumstances, the COR may request a resource estimate for the Contractor to perform additional work. The CO will issue any final decision regarding the plan to proceed.
2.3 Reflectometry
2.3.1 Contractor shall use the data collected by the GNSS antenna to conduct reflectometry assessments of water level height. These data shall be compared to time tied tidal station data to analyze and assess efficacy of reflectometry at this location for water level assessments.
Based on the results of these data, contractor shall prepare a report evaluating the use of reflectometry at the Glacier Bay tidal station, and submit this report to the COR.
3.0 Delivery or Deliverables
3.1.1 Preliminary Station Documentation for the Water Level Station
The Contractor shall complete and submit by email the Preliminary Site Report within fifteen (15) working days of station maintenance which contains, at a minimum the following:
● The date and time,
● Activities performed,
● The serial numbers of all the equipment,
● The leveling abstracts, if levels were performed as part of the visit,
● The sensor and datum offsets, or the accepted orifice offset
● GOES transmission parameters
Payment of 30% of the contract cost provided upon delivery of the Report.
3.1.2 Final Documentation for Scheduled Maintenance for Water Level Stations
The Contractor is required to submit a Final documentation package including final eSite Report to CO-OPS within sixty (60) working days of SM. The final documentation must include what is required by CO-OPS as described in the Standing Project Instructions and outlined below. All station documentation files shall be submitted in digital format. If the file size of the combined package of station maintenance documentation is greater than the allowed file size, the contractor shall arrange an alternate means of submitting the documentation package with the COR.
The standard water level station documentation package includes the following:
1) Transmittal letter (PDF format)
2) Water Level Station Site Report or Tide Station Report
3) Sensor test worksheet (PDF format)
4) Sensor elevation drawing (PDF format) showing sea floor, pier elevation, sensor leveling point, and sensor elevation, if the sensor is mounted vertically
5) Bench mark Diagram (PDF format) – Large-scale bench mark location sketch of the station site showing the relative location of the water level gauge, bench marks, and major reference objects found in the bench mark descriptions. The bench mark diagram shall include an arrow indicating north direction. – PDF format).
6) Bench mark descriptions with GPS coordinates (d/m/s.s format) (electronic file)
7) “Station to Reach” statement in Microsoft Word format
8) Digital photographs of each bench mark disk (four views); (JPEG format).
9) Levels (electronic files) including leveling equipment information and field notes of precise leveling, if applicable
10) Abstract of precise leveling (electronic format)
11) Datum offset computation worksheet or Staff/Gauge difference worksheet as appropriate, showing how sensor “zero” measurement point is referenced to the bench marks
12) Staff to gauge observations, if applicable (Microsoft Excel format)
13) Calibration certificates for leveling rods, if applicable (PDF format)
14) Calibration records for sensors, if applicable (PDF format)
15) Other information as appropriate, or as specified in the contract (PDF format)
16) Water level data download in specified format
17) GPS Deliverables - the OPUS published datasheet and 4 photos of the GPSBM in electronic format for each observation session as described in the User’s Guide for GPS Observations at Tide and Water Level Bench Marks
18) Scheduled Maintenance (AI) checklist
The Contractor shall retain a copy of all completed reports, which may be made available to CO-OPS upon request.
Payment of 60% of the Contract cost provided upon delivery of the Report.
3.1.3 The contractor is required to submit an assessment and analysis of reflectometry of the station GNSS antenna. The reflectometry shall include an assessment of the calculated water levels from reflectometry relative to the measured water levels from the tidal station data. This report shall at a minimum include the average differences, graphical representations, and an appropriate assessment of the variances associated with the two measurements over at least a 1 year time period. The report may include any other information that the contractor, using their professional judgement, determines may be relevant in helping to understand the utility of using reflectometry as a measurement of water level in Alaska. Raw data shall also be included with the report in electronic form.
Payment of 10% of the contract cost provided upon delivery of the Report.
Notice to contractors:
All information and data related to this project that the contractor gathers or obtains shall be both protected from unauthorized release and considered the property of the government. The contracting officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract.
Press releases, marketing material, or any other printed or electronic documentation related to this project, must not be publicized without the written approval of the contracting officer.]
4.0 Meetings
4.1. Post-award Kickoff Meeting
Within 15 business days of contract award, the Government will conduct a post-award kickoff meeting either via telecommunications or in person in Anchorage (specific date and time to be mutually agreed upon).
4.2. Other Meetings
Additional meetings may be necessary to determine additional site maintenance visits if option years are added. No other meetings are anticipated; however, at the contractors request additional meetings may be established to address issues or concerns that may arise in relation to the contract.
5.0 Required Travel and Other Direct Costs (ODCs)
Travel to Glacier Bay National Park Headquarters in Gustavus, AK for the duration of time necessary to conduct the maintenance will be required for will be required for this contract.
6.0 Government Furnished Property/Equipment/Information
No government furnished property is anticipated as needed for this project. If government furnished property becomes necessary to complete these tasks, a meeting with the COR may be required.
7.0 Special Instructions
No special instructions are required for this contract.
8.0 Glossary of Abbreviations and Acronyms
CO – Contracting Officer CO-OPS – Center for Operational Oceanographic Products and Services COR – Contracting Officer Representative GLBA – Glacier Bay National Park GNSS – Global Navigation Satellite System GPS – Geographic Positioning System GFE – Government Furnished Equipment NOAA – National Oceanic and Atmospheric Administration NPS – National Park Service NWLON – National Water Level Observation Network OPUS – Online Positioning User Service Park TR – Park Technical Representative
SM – Scheduled Maintenance