This is a Statement of Work for an HVAC, insulation, and electrical upgrade project at the Magney Housing Unit located at 23209 St. Croix Trail North, Scandia, Minnesota, operated by the St. Croix National Scenic Riverway under the National Park Service. The project encompasses three primary scopes of work with a 90-calendar-day completion requirement from the Notice to Proceed, with all onsite work occurring after October 5, 2026.
The first scope involves installing a new three-head mini-split HVAC system, requiring furnishing and installation of one outdoor heat pump unit (Mitsubishi MXZ-3D24NL or equivalent) with 22,000 BTU cooling and 25,000 BTU heating capacity at 208/230V single phase, plus three indoor wall-mounted air handling units (one Mitsubishi MSZ-GX06NL or equivalent in each bedroom, and one MSZ-GX12NL or equivalent in the living room). Installation includes refrigerant line sets, control wiring, condensate drainage, mounting hardware, a dedicated 208-230V 60Hz electrical circuit with disconnect, system charging, startup testing, and owner orientation. The second scope requires installation of a new bathroom exhaust fan (Broan BELS8 or equivalent, 80 CFM with humidity sensor) powered by a new 15-amp circuit from the upgraded electrical panel, including 4-inch ventilation ductwork vented to exterior with backdraft damper. The third scope mandates replacing the existing Square D XO 100-amp electrical service panel with a new 150-amp NQ Circuit Breaker Panelboard from Schneider Electric, Eaton, or Siemens, featuring 26 minimum spaces, bolt-on breakers matching existing branch circuit amperages, a dedicated 50-amp breaker for HVAC power, exterior disconnect within 10 feet of the heat pump unit compliant with NEC 440.14, and compliance with 2026 National Electric Code requirements. The work also includes removing all existing attic fiberglass insulation and replacing it with closed-cell spray foam insulation achieving R-50 rating applied to the ceiling flat, with proper ventilation baffle maintenance, sealed air leaks, and third-party electrical inspection by a state-licensed commercial inspection agency prior to final COR inspection. All work must comply with 2026 NEC and 2024 International Building, Existing Building, Fire, Plumbing, Mechanical, Wildland Urban Interface, Fuel Gas, and Energy Conservation Codes.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Solicitation_-_Bid_Schedule.xlsx | XLSX spreadsheet | |
| Sol_140P6426Q0064.pdf | ||
| B08_Solicitation_-_Tech_Questionnaire_-_HVAC_Replacement.docx | DOCX document | |
| B08_Solicitation_-_DOL_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
St. Croix National Scenic Riverway 401 North Hamilton Street, St. Croix Falls WI 54024
Upgrade HVAC, Insulation, and Electrical at Magney Housing Unit
PMIS 350854
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
2026-02-16
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 07 – THERMAL and MOISTURE PROTECTION Section 07 21 27 Enclosed Cavity Foam Insulation
DIVISION 23 HVAC
Section 23 34 50 Bathroom Exhaust Fans Section 23 81 26 Ductless Split System Air Conditioner
DIVISION 26 ELECTRICAL
Section 26 05 50 Wiring Methods
SITE PLAN – APPENDIX A
PHOTOGRAPHS – APPENDIX B
DRAWINGS – APPENDIX C
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The Magney housing unit is a 2-bedroom 1-bathroom house roughly 1200sqft. The house was acquired by the NPS in 1977 and is currently utilized as a housing unit. The home is a poured concrete and block structure with LP smart siding and standing seam steel roofing. The building is in good general condition but requires some updates. Currently the house utilizes two window mount AC units for air conditioning. These units require installation and removal every year, are 10 plus years old, and allow rodent and insect intrusion. The current attic fiberglass batten insulation is inadequate and smashed down from access traffic, this results in loss of building efficiency. The electrical panel is believed to be original at least 49 years old and needs to be replaced to meet building codes and remove safety concerns. There is currently no bathroom fan/ventilation. This results in mold and mildew issues and complaints by tenants.
1.2 Work Covered by the Contract Documents:
A. Project Location: 23209 St. Croix Trail North, Scandia MN 55073
B. Work consists of:
A) Install New 3-Head Mini-Split HVAC System
a. Contractor to confirm equipment locations, structural conditions, electrical capacity, condensate routing, and verify heating and cooling load calculations.
B) Equipment & Materials
a. Furnish and install one high-efficiency outdoor heat pump unit, Mitsubishi MXZ-
3D24NL or equivalent
i. 22,000BTU Cooling capacity
ii. 25,000BTU Heating capacity
iii. 208/230V single phase
iv. Install outdoor unit a minimum 18” above ground level and to all other manufacture standards. Refer to Appendix B and C.
b. Furnish and install three indoor wall mounted air handling units.
i. One (1) ½ ton Mitsubishi MSZ-GX06NL or equivalent.
ii. 5,500BTU Cooling capacity
iii. 6,250 BTU Heating capacity
iv. Wall Mounted in Bedroom A on North wall. Refer to Appendix B and C.
v. One (1) ½ ton Mitsubishi MSZ-GX06NL or equivalent.
vi. 5,500BTU Cooling capacity
vii. 6,250 BTU Heating capacity
viii. Wall Mounted in Bedroom B on North wall. Refer to Appendix B and C.
Page | 4
ix. One (1) 1 ton Mitsubishi MSZ-GX12NL or equivalent.
x. 11,000BTU Cooling capacity
xi. 12,500 BTU Heating capacity
xii. Wall Mounted in Living room on North wall. Refer to Appendix B and C.
c. Provide refrigerant line sets, control wiring, condensate drain lines, mounting brackets, and vibration isolation pads.
C) Installation
a. Install outdoor heat pump on approved pad or wall bracket with proper clearances.
b. Mount three indoor units securely and level per manufacturer specifications.
c. Run refrigerant lines, electrical wiring, and condensate drains between indoor and outdoor units.
d. Penetrations sealed and flashed to prevent water intrusion.
e. Install New dedicated 208-230V 60Hz electrical circuit and disconnect as required by manufacturer specifications.
D) Commissioning
a. Charge system with refrigerant.
b. Startup system and test all operating modes.
c. Balance airflow and verify proper operation of each indoor unit.
d. Provide owner orientation and manufacturer documentation.
2. Install New Bathroom Exhaust Fan A) Pre-Installation
a. Provide power from new 15000amp panel board installed in the utility room as part of this scope of work. A new 15A circuit is to be provided unless the Contractor can demonstrate total load for bathroom electrical, inclusive of lighting and receptacles can incorporate exhaust fan on same circuit.
b. Provide new 4” ventilation duct from fan to exterior of the house including vent terminal. Reference appendix B and C.
c. Identify fan location with COR to ensure optimal moisture removal.
B)
a. Install new, 80CFM bathroom exhaust fan with light and Humidity Sensor. Broan BELS8 or equivalent.
i. 80 CFM
ii. LED light
iii. 120v 21W
iv. 1.5 Sones
v. Built in Humidity Sensor
b. Connect fan to new electrical circuit with switch.
c. Install insulated ductwork vented to the exterior with backdraft damper.
d. Seal all duct connections to prevent air leakage.
C) Testing
a. Test fan operation, airflow, and noise levels.
b. Confirm proper exterior exhaust and damper operation.
Page | 5
3. Replace existing Square D XO 100 amps electrical service panel.
A) Provide 150 amp NQ Circuit Breaker Panelboard as manufactured by Schneider
Electric, or equal from approved manufacturers.
a. Approved Manufactures
i. Eaton
ii. Siemens
iii. Schneider
b. Size 150 amp, Minimum 26 spaces
c. Provide panelboard with Bolt-on breakers
d. Provide new breakers to match existing branch circuits amperage
e. Provide electrical service required to operate the new HVAC system. Per the basis of design units specified in 1.2 B., provide at a minimum the following:
i. Dedicated exterior electrical disconnect to the heat pump unit which complies with NEC 440.14 and located within 10-feet (indirect sight from the unit).
ii. All wiring and conduit to route power back to service panel meeting NEC.
iii. Provide and install dedicated 50amp breaker for 208/230V single phase power needs.
iv. Submit all necessary electrical component requirements based on the
HVAC unit make and model proposed by the Contractor to confirm or identify differences from the basis of design for COR approval.
f. Ensure that grounding electrode system and grounding electrode conductor are reinstalled to meet 2026 National Electric Code requirements. Existing system meets requirements.
g. Contractor to verify available fault current from utility in sizing AIC rating of main breaker in 150-amp panelboard.
B) Combine the Range and Dryer sub breakers into the new panel.
C) Modify existing conduits to accommodate new panel board enclosures. Coordinate with
COR.
4. Remove existing attic insulation and re-insulate with closed cell foam insulation.
A) Remove all existing insulation.
a. Insulation must be collected in a way that does not contaminate in or around the structure. All waste collected must be properly disposed of off of NPS property.
b. Inspect attic for air leaks and moisture issues. Seal penetrations (top plates, electrical boxes, duct penetrations) to reduce air infiltration.
c. Ensure proper ventilation paths are maintained.
B) Install new closed cell spray foam insulation.
a. Install new spray foam insulation to achieve an R-50 rating.
b. Installation of foam will be on the flat of the ceiling.
c. Evenly distribute insulation to avoid gaps or compression.
Page | 6
d. Install baffles where necessary to maintain airflow at eaves.
C) Final Verification
a. Verify insulation depth and coverage meets or exceeds R-50 requirement.
b. Remove debris and leave attic in clean condition.
C. Contractor to provide third-party inspection of electrical work through commercial inspection agency prior to final inspection by COR.
a. Third party inspection agency to be licensed by the state. Provide verification to COR prior to inspections.
b. Since this is on Federal land, no local permits are required.
c. Inspector to confirm that all work complies with requirements of 2026 National Electric
Code.
D. Contractor to follow all applicable codes.
E. Applicable Codes:
a. 2026 National Electric Code
b. 2024 International Building Code
c. 2024 International Existing Building Code
d. 2024 International Fire Code
e. 2024 International Plumbing Code
f. 2024 International Mechanical Code
g. 2024 International Wildland Urban Interface Code
h. 2024 International Fuel Gas Code
i. 2024 International Energy Conservation Code
F. All work will be performed under a single contract.
G. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed. All onsite work must be performed after 10/05/2026.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts are projected beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
Page | 7
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50 foot radius of discovery and notify the Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure or structures involved in this project are not historic.
C. There is no excavation required for this project.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative (COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
Page | 8
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/sacn/learn/compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communication including land and/or cell phone numbers (note some areas of work have limited-service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. Project location is a employee housing unit. Contractor shall conduct operations to ensure tenants access to their housing at all times.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
8am - 4pm., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year’s Day Inauguration Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
• Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 9
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork, and clearing of vegetation, to:
1. 10 feet beyond building perimeter
Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Sanitary Operations:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment is free of soil, seeds, vegetative matter, or other debris that could
Page | 10 contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant protection is not required for this project.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Not required.
6. Hot Work Permit: Not Required
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area shown in appendix A below may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features:
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site.
Coordinate with COR for approved dumpster locations prior to commencing construction.
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
Page | 11
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated. Contractor will maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR. Contractor will maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied:
1. N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
Page | 12
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
a) Coordinate with COR prior to execution
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Page | 13
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 14
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
Page | 15
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
Page | 16
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
Page | 17
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final
Page | 18 inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line-Item No. Contract Line-Item No. CLIN 010 Items, HVAC, Bathroom Fan, and Electrical panel replacement.
1. This item consists of Contract Line-Item No. CLIN 010 Items, HVAC, Bathroom Fan, and Electrical panel replacement..
2. Payment will be made per the contract and percentage of completion level.
B. Contract Line-Item No. Contract Line-Item No. CLIN 020 Insulate the attic with spray foam.
Include removal of existing attic insulation.
Page | 19
1. This item consists of Contract Line-Item No. CLIN 020 Insulate the attic with spray foam.
Include removal of existing attic insulation.
2. Payment will be made per the contract and percentage of completion level.
END OF SECTION
Page | 20
Appendix A Site Plan
Page | 21
Appendix B Project Photos
Page | 22
Page | 23
Page | 24
Page | 25
Page | 26
Page | 27
Page | 28
Appendix C Project Drawings
PRODUCT DESCRIPTION
Basic Use: CertaSpray® Closed Cell Foam is a two-component closed cell spray foam with a zero-ozone-depleting blowing agent.
When CertaSpray A-side is mixed with CertaSpray B-side closed cell under pressure in a 1:1 volumetric ratio, they react and expand into a medium-density closed cell foam with an in-place core density of nominal 2.0 pcf.
Benefits: CertaSpray Closed Cell Foam provides thermal insulation for the interior or exterior of the building while also reducing air and water vapor infiltration through the building envelope.
Applications: The closed cell 2-pcf foam can be spray-applied into open wall cavities, perimeter joists, cathedral ceilings, garage ceilings, attics, exterior walls and crawlspaces. When covered by a 15-minute prescriptive thermal barrier, thickness is not limited. Product must be finished according to local code, and must be applied by a qualified applicator.
Composition and Materials: CertaSpray Closed Cell Foam is a medium-density, MDI-based polyurethane thermoset foam.
LIMITATIONS
Foam Plastic Insulation: CertaSpray Closed Cell Foam is defined by the building codes as a foam plastic insulation.
Thermal Barrier: Many building codes require that foam plastic insulation be covered with an approved 15-minute thermal barrier. Consult local building code officials to ensure the application meets local building codes and regulations.
Vapor Retarder: CertaSpray Closed Cell Foam meets the performance requirement for a Class II vapor retarder at 1" thickness. Check local building code for climate-specific vapor retarder requirements.
Lighting Fixtures: The National Electrical Code prohibits installation of any insulation over or within 3" (76 mm) of recessed light fixtures unless approved insulated ceiling (IC) light fixtures are used.
Maximum Use Temperature: CertaSpray foam should not be in contact with equipment or materials that have operating temperatures greater than 180°F.
All application surfaces must be free of oil, grease, dust and debris. Surface must be dried prior to application of spray foam. Do not apply this product when the dew point is within 5°F of the air temperature, or when the substrate moisture content is greater than 18%. Excess humidity may cause poor adhesion and result in product failure.
To avoid overspray, product should not be applied when conditions are windy.
Product Name CertainTeed CertaSpray® Closed Cell Foam
Manufacturer CertainTeed Corporation
Address 20 Moores Road Malvern, PA 19355
Phone 800-233-8990
Website www.certainteed.com/insulation
TECHNICAL DATA
Applicable Standards
• �ASTM C1029, Type I and Type II
• ICC-ES, AC–377 (ESR-3758)
• 2012 International Residential Code (IRC) Section R316
• 2012 International Building Code (IBC) Section 2603
• �2012 International Energy Conservation Code (IECC) Section R 303
• NFPA 285 (2012 IBC Types I & II Construction)
• �For use in dwellings under the IRC and Type I, II, III, IV and V constructions under the IBC
• AC-377 Appendix X (Attic & Crawl Spaces)
CertaSpray® Closed Cell Foam SPOT: PMS 300 & PMS 425
Specification Sheet
CHEMICAL PROPERTIES
CERTASPRAY A CERTASPRAY B
Viscosity at 25ºC, cps
150-250 Summer = 800 Winter = 500
Extreme Winter = 400
Specific Gravity at 25ºC, g/ml
1.23 1.14
Prior to application, substrate temperature must reach:
Summer Blend: 10ºC (50ºF) Winter Blend: -4ºC (25ºF) Extreme Winter Blend: -12ºC (10ºF)
The final product yield is dependent on spray conditions and spray techniques.
Finished product should not be left exposed to UV for more than 2 weeks or the product could degrade.
Typical End Use Properties: The thermal performance values are achieved at the thickness specified when installed as recommended.
CAUTION: CertainTeed recommends that you consult an HVAC expert and comply with guidelines established by applicable building codes prior to using any closed or open cell spray foam insulation product in an attic retrofit application. If not installed correctly, adding spray foam to a vented attic may significantly impair the performance of the HVAC system and may cause other damage to the building. CertainTeed will not assume any liability or responsibility for any personal injury or property damage occurring as a result of the improper installation of spray foam insulation that is not in accordance with the instructions accompanying the product, that is not in conformance with any applicable building codes or that is contrary to the advice given by a duly qualified HVAC expert.
INSTALLATION
FIRE PERFORMANCE*
TEST METHOD RESULT
Flame Spread Index, 4"
ASTM E84 < 25
Smoke Index, 4" ASTM E84 < 450
Attic Vertical Walls
ACC 377
Appendix X < 11.5"
* �The results of the test method may not be indicative of real-life fire performance. All plastic insulation must be separated from the interior building by an approved thermal barrier of 1/2" gypsum wallboard or equivalent thermal barrier material as required by the building code.
HANDLING AND STORAGE
Storage: It is recommended that the CertaSpray A and CertaSpray B drums should be stored between 55-80°F. Keep containers tightly closed and store in a dry, well-ventilated area protected from freezing, rain, direct sunlight and excess heat. The storage life of B-side is up to 6 months and A-side up to 6 months when stored according to the recommended conditions.
Handling: When opening the drums, loosen the cap slowly to release pressure in the drum. Do not ingest. Avoid contact with eyes, skin and clothing. Avoid breathing aerosols, vapor or mist. Wash skin thoroughly after handling.
The Safety Data Sheet (SDS) for CertaSpray A and CertaSpray B closed cell must be read before using this product.
HEALTH AND SAFETY
The health and safety information in this data sheet does not contain sufficient detail for safe handling in all cases. For detailed safety and health information refer to the SDS for this product.
AVAILABILITY AND COST
Distributed and sold throughout the United States. For availability and cost contact your local Territory Manager, contractor or distributor, or call CertainTeed Sales Support Group at 800-233-8990.
WARRANTY
Refer to CertainTeed’s Lifetime Limited Warranty for CertaSpray Foam Insulation (30-50-012).
MAINTENANCE
No maintenance required.
TECHNICAL SERVICES
Technical assistance can be obtained either from your local CertainTeed sales representative, or by calling CertainTeed Sales Support Group at 800-233-8990.
www.certainteed.com/insulation
Code No. 30-50-011, © 05/16 CertainTeed Corporation.
CertainTeed Corporation 20 Moores Road Malvern, PA 19355
BLACK
ASK ABOUT OUR OTHER CERTAINTEED PRODUCTS AND SYSTEMS:
ROOFING • SIDING • TRIM • DECKING • RAILING • FENCE
GYPSUM • CEILINGS • INSULATION
Professional: 800-233-8990 Consumer: 800-782-8777 www.certainteed.com/insulation
THERMAL PERFORMANCE
THICKNESS AGED R-VALUE**
in. mm R 1 25 6.5
1.5 38 9.8
2 51 13
2.5 64 17
3 76 20
3.1 79 21
3.25 83 22
3.5 89 23
4 102 27
4.5 114 30
5 127 33
5.5 140 37
6 152 40
7.5 191 50
8.5 216 56
10 254 66
11.5 292 76
12 305 80
RECOMMENDED
PROCESSING CONDITIONS
VALUE
Winter and Summer, ºF Extreme Winter, ºF
110 – 135 120 – 135
Hose Temperature, ºF < 135
Pressure, psi 1100 – 1500
A/B Volumetric Ratio 1/1
Cream Time**, sec 1 – 2
Tack Free Time**,sec 4 – 8
Maximum Thickness Per Pass, Inches
3.25
Maximum Installation Thickness, Inches
See application section
**�Tested in accordance with ASTM C518 and/or C177 at 75°F (24°C) mean temperature. Aged 90 days at 140°F.
PHYSICAL AND MECHANICAL PROPERTIES
PROPERTY ASTM METHOD VALUE
Core Density, pcf D1622 nominal 2.0 pcf
Closed Cell Content, % D6226 > 90%
Compressive Strength, psi D1621 > 25
Tensile Strength, psi D1623 57
Water Absorption, % by volume D2842 < 3%
Dimensional Stability, 70°C/97% RH, vol. %, 7 days D2126 < 15%
Water Vapor Transmission (Permeability), perm-inch E96
1.00 @ 1"
0.50 @ 2"
0.33 @ 3"
0.25 @ 4"
0.20 @ 5"
0.17 @ 6"
Air Permeability, at 1" thickness, L/s/m2 E283 0.013
Fungi Resistance C1338 Pass, with no growth
The typical properties were obtained on samples produced with a Gusmer/Graco H25 spray machine using an air-purged Fusion spray gun. The foam was sprayed at a thickness of approximately 4", in two passes of 2" each.