This solicitation requests construction services for a Bureau of Indian Affairs office relocation and renovation project for the U.S. Geological Survey in Reston, Virginia. The solicitation is set aside 100% for Indian Small Business Economic Enterprises. Offerors must provide firm-fixed pricing in accordance with the line item requirements, which include construction services for Room 1D and optional services for Room 2D. The period of performance is 365 days from notice to proceed, with an optional 365-day extension. The total value is between $1-5 million. Offerors must attend a mandatory site visit on August 24, 2022 and submit all required documentation and security forms in order to gain access. The closing date for offers is September 15, 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QandA_0001.xlsx | XLSX spreadsheet | |
| Attachment_M_Green_Tag_0001.xlsx | XLSX spreadsheet | |
| Sol_140G0122R0020_Amd_0001.pdf | ||
| Attachment_N_Red_Tag_0001.xlsx | XLSX spreadsheet | |
| Attachment_J_-__Site_Visit_Security_Document.docx | DOCX document | |
| Attachment_H_-_Bid_Bond_SF_24.pdf | ||
| Attachment_C_-_Payrolls_(WH-347).pdf | ||
| Attachment_K_SOW_1D301_Renovation.pdf | ||
| Attachment_F_-_Performance_Bond_SF_25.pdf | ||
| Attachment_E_-_DOL_Wage_Determination.pdf | ||
| Attachment_L_SOW_2D100_Renovation.pdf | ||
| Attachment_I_-_Past_Performance_Information.docx | DOCX document | |
| Attachment_D_-_Certification_for_Payment_(construction).pdf | ||
| Attachment_A_-_Release_of_Claims.doc | DOC document | |
| Sol_140G0122R0020.pdf | ||
| Attachment_G_-_Payment_Bond_SF_25A.pdf | ||
| Attachment_B_-_Nondisclosure_Agreement.doc | DOC document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
USGS NATIONAL ACQUISITION BRANCH
205 NATIONAL CENTER
12201 SUNRISE VALLEY DRIVE
RESTON VA 20192
GNB
Terrence Hardy 7036487377
1x 08/16/2022
140G0122R0020
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
365 0 calendar days and complete it within ________________ ________________ calendar days after receiving
09/15/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USGS NATIONAL ACQUISITION BRANCH
205 NATIONAL CENTER
12201 SUNRISE VALLEY DRIVE
RESTON VA 20192
GNB
Terrence Hardy
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 62
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140G0122R0020
Provide Firm-Fixed pricing in accordance with the line items below.
Construction services will be performed at the
U.S. Geological Survey National Building, Reston, Virginia. In accordance with the Instruction to
Vendors, Statement of Work (SOW), Davis-Bacon
Wage Determination Number VA20220178 dated
07/08/2022, Attachments, Terms and Conditions, and Applicable Clauses.
This is a Indian Small Business Economic
Enterprise (ISBEE) Set-a-Side.
Site Visit Details:
Date: 08/24/2022
Time: 11:00 A.M. Eastern Time (ED)
Location: U.S. Geological Survey, National
Building
12201 Sunrise Valley Drive, Reston, VA 20192
Valid Government-issued identification is required to enter the building. Please use the
Visitor's Entrance at the prescribed time only.
Vendors must provide the attached completed security document and a business license copy prior to the site visit in order to gain access to the building.
All vendors interested in attending the site visit shall send a confirmation email to:
Terrence Hardy: trhardy@usgs.gov
Site Visit confirmation email shall include:
-Company Name
-Number of Attendees
-Names of Attendees
-Attachment 1: Completed Security Document
-Attachment 2: Copy of Business License
*Prime contractor is responsible for ensuring all subcontractors are present during the site visit.*
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 62
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140G0122R0020
Disclosure of Magnitude in accordance with FAR
36.204: Between $1,000,000 and $5,000,000.
Delivery: 365 Days After Notice to Proceed
Delivery Location Code: 0006366957
USGS Office of Management Services
MS 210
12201 Sunrise Valley Drive
Reston VA 20192 US
00001 Firm Fixed Price. Room 1D. Provide a labor, 1 LS equipment, tools, materials, supervision to perform BIA Relocation / Renovation Project in accordance with the attached statement of work.
Product/Service Code: Z2AA
Product/Service Description: REPAIR OR ALTERATION
OF OFFICE BUILDINGS
01001 Optional CLIN. Firm Fixed Price. Room 2D. Provide 1 LS a labor, equipment, tools, materials, supervision to perform BIA Relocation / Renovation Project in accordance with the attached statement of work.
Period of performance is 365 days after issuance of NTP.
Optional CLIN may be exercised up to 365 days after base contract award.
(Option Line Item)
365 Days After Award
Product/Service Code: Z2AA
Product/Service Description: REPAIR OR ALTERATION
OF OFFICE BUILDINGS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SECTION B – SUPPLIES, SERVICES AND PRICES
B.1 Purpose
The purpose of this contract is to obtain Construction Services: Bureau of Indian Affairs (BIA) Office Move / Renovation for the U.S. Geological Survey (USGS) in Reston, Virginia.
B.2 Contract Type and Services
This is a Firm-Fixed Price contract. The USGS will issue a Firm Fixed Price (FFP) contract for the BIA Office Move / Renovation Project.
This RFQ is 100% set aside for Indian Small Business Economic Enterprise (ISBEE).
B.3 Pricing
Provide a Firm Fixed Price for the BIA Office Move / Renovation Project rendered on the Open Market under NAICS Code: 236220 Commercial and Institutional Building.
END OF SECTION B
Solicitation No. 140G0122R0020
SECTION C -- DESCRIPTIONS AND SPECIFICATIONS – STATEMENT OF WORK
SEE ATTACHMENTS K & L
END OF SECTION C
SECTION D – PACKAKING AND MARKING
D.1 GS0501 Packaging and Marking - Commercial Practice July 2001
(a) Preservation, packaging, and marking for all items delivered hereunder shall be in accordance with standard commercial practice and adequate to insure acceptance by common carrier and safe arrival at destination.
(b) All containers shall be plainly marked on or adjacent to the exterior shipping label to show the contract number, task order number, description of contents, and contractor's name.
D.2 Delivery Addresses for Deliverables
The delivery address of any deliverables specified under this contract will be to:
USGS National Building 12221 Sunrise Valley Dr Reston, VA 20192
D.3 Product Delivery - Storage-Handling
The Contractor shall arrange for deliveries of all materials to be delivered directly to the point of installation.
The Contractor shall be responsible for receiving deliveries on site at USGS and shall reconcile bills of lading for deliveries of contractor-furnished materials for the contracted project. Government personnel will not be responsible for reconciling bills of lading for contractor-furnished materials delivered to the USGS for a Contractor. The Contractor shall furnish a Contractor point-of-contact to vendors for receipt of material deliveries. The Contractor shall not provide the names of Government personnel to vendors as the point-of-contact for deliveries. The Contractor shall be responsible for scheduling and tracking the deliveries of all contractor-furnished materials for the project.
END OF SECTION D
SECTION E -- INSPECTION AND ACCEPTANCE
E.1 52.252-02 CLAUSES INCORPORATED BY REFERENCE
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:
http://www.acquisition.gov/far/
Clause Title Date 52.236-5 Material and Workmanship April 1984 52.246-02 Inspection of Supplies--Fixed Price August 1996 52.246-04 Inspection of Services--Fixed-Price August 1996 52.246-12 Inspection of Construction August 1996 52.546-13 Inspection – Dismantling, Demolition, or Removal of
Improvements August 1996
E.2 GS0701 INSPECTION -- SUPPLIES AND SERVICES JULY 2001
(a) The Inspection of Supplies clause incorporated above applies to the following contract line-item number(s):
Line item 0001 and 1001
(b) The Inspection of Services clause incorporated above applies to the following contract line-item number(s):
Line item 0001 and 1001
E.3 GS0715 PLACE OF INSPECTION JULY 2001
Government inspection of delivered items will be performed at destination by the COR or a Government authorized inspector.
E.4 FINAL INSPECTION AND ACCEPTANCE
Upon completion of the contracted work, the Contractor shall notify the COR. The COR will schedule an inspection of the work site and will perform the inspection at the site to determine if all work performed by the Contractor meets the requirements of the Statement of Work, Specifications and Drawings. The Contractor shall be present at the site during final inspection by the COR. The Date of Acceptance of the work by the Government will be determined by the Government after the final inspection has been performed.
E.5 INSPECTION BY REGULATORY AUTHORITIES
(a) This project is subject to inspection by the following authorities:
USGS Contracting Officer's Representative (COR) or authorized designee
(b) During performance of the work stated herein, the COR or authorized designee will perform on-site progress inspections of the work. These inspections will occur at any time during the course of the contract, at the discretion of the COR or authorized designee. Progress inspections will be performed by the COR or authorized designee to determine if the Contractor is making reasonable progress toward completing the work in order to meet the scheduled delivery date as set forth in the contract, and to ensure that the Contractor is performing the work in accordance with the technical requirements.
(c) The Contractor shall notify the Contracting Officer when inspections take place. Written decision as to action to be taken as a result of inspections will be made in conjunction with the CO and COR.
E.6 GS0721 INSPECTION AND ACCEPTANCE PERIOD JULY 2001
(a) It is anticipated that inspection and acceptance shall be completed by USGS personnel within 7 days after delivery of all completed deliverables by the contractor, at which time the contractor will be informed of any deficiencies or of final payment approval.
(b) Accordingly, subparagraph (a)(5)(i) of the clause FAR 52.232-25, Prompt Payment, is hereby modified to increase the constructive acceptance period to 7 days. If the Government subsequently rejects the items, and repair or replacement cannot be effected within the contract delivery date, the contractor may request that the contract delivery date be extended one day for each day the Government required for inspection in excess of the above allotted inspection period.
END OF SECTION E
SECTION F -- DELIVERIES OR PERFORMANCE
F.1 52.252-02 CLAUSES INCORPORATED BY REFERENCE
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be
52.211-13 Time Extensions September 2000 52.242-14 Suspension of Work April 1984
F.2 52.211-10 Commencement, Prosecution, and Completion of Work
April 1984
The Contractor shall be required to (a) commence work under this contract within 1 business days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 days from date of award unless the other options are exercised. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
F.3 GS0905 PLACE OF PERFORMANCE JULY 2001
Services to be provided hereunder shall be performed at the following location(s):
USGS National Building 12221 Sunrise Valley Dr Reston, VA 20192
F.4 GS0910 PERIOD OF PERFORMANCE JULY 2001
The period of performance of the resulting Contract will be date of award through twelve (12) months unless the additional options are exercised.
F.5 GS0916 PERIOD FOR EXERCISE OF OPTION TO EXTEND
SERVICES
JULY 2001
For the purposes described in FAR 37.111, the Government may exercise the option to extend the contract under the clause 52.217-8, Option to Extend Services, by written notice issued to the Contractor prior to the expiration of the initial contract period or any option period, including any previous extensions under this clause. When such date falls on the last day of a fiscal year, notification must be provided within 7 days after funds are appropriated and available for the new fiscal year.
F.6 GS0919 LEGAL HOLIDAYS JANUARY 2002
The following legal holidays are observed by this Government agency:
New Year’s Day January 01 Martin Luther King’s Birthday 3rd Monday in January Presidents Day 3rd Monday in February Memorial Day Last Monday in May
Juneteenth June 19 Independence Day July 04 Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veterans Day November 11 Thanksgiving Day 4th Thursday in November Christmas Eve December 24 Christmas Day December 25
When a holiday falls on Saturday or Sunday, it is observed on the adjacent Friday or Monday, respectively.
In addition to the holidays listed above, the contractor agrees to observe leave days or closures designated by Federal Statute, Executive Order, or Presidential Proclamation.
F.7 GS0924 UNSCHEDULED CLOSURES JULY 2001
(a) The USGS facility where contractor employees are working may occasionally have unscheduled closures in which federal employees are dismissed on administrative leave (such as for inclement weather, holiday early closings, power outages, or other emergencies). In these cases, the Contracting Officer or COR will advise the contractor whether any of the contractor's activities are considered critical and require continued performance. In most cases, the Contractor employees not performing critical tasks will not be allowed to remain in the facility after federal employees are dismissed.
(b) If the contractor opts to treat these nonproductive hours as paid leave, these hours are billable at the established contract rates. The total number of hours billed on such days may not exceed the number scheduled for affected employees and may not include overtime hours.
(c) Paragraph (b) does not apply, and nonproductive hours are not billable as direct hours worked where the contractor's accounting system normally treats leave of the type used as an indirect or fringe benefit pool expense.
F.8 GS0925 UNSCHEDULED CLOSURES - FIXED PRICE MARCH 2003
(a) The USGS facility where contractor employees are working may occasionally be closed temporarily and federal employees dismissed, such as for inclement weather, holiday early closings, power outages, or other emergencies. In these cases, the Contracting Officer or COR will advise the contractor whether any of the contractor's activities on Government facilities are considered critical and require continued performance. In most cases, the Contractor will be required to dismiss employees at Government facilities who are performing noncritical tasks after federal employees are dismissed.
(b) If the unscheduled closure causes an increase in the cost of contract performance or if any contract term or condition is affected by the closure, the Contractor may request an adjustment pursuant to Clause FAR 52.242-17 Government Delay of Work.
(c) Contractor performance at locations that are not affected by the unscheduled closure will not be subject to this clause.
F.9 TIME OF WORK PERFORMANCE
The Contractor shall perform the work during normal business hours Monday thru Friday, 7:30 am CT to 4:30 pm CT, except for legal holidays and as pre-authorized by COR. Any work required outside the normal business hours requires a fort- eight hour (48) written notice to the COR for approval in advance of working.
F.10 SCHEDULE OF CONSTRUCTION
Within two (2) weeks from the Notice to Proceed, the Contractor shall submit to the COR a written Schedule of Construction for the project. The Schedule shall indicate the anticipated dates that the Contractor will be on site and when specific tasks/services under the scope are to be performed and completed by. When preparing the Schedule, the Contractor shall consider lead times for material procurement, and any other factor affecting start/end times of component construction. The Contractor shall notify the COR immediately if any anticipated on-site date is expected to change from the original schedule and a revised schedule submitted. The Contractor shall be responsible for determining the labor staffing levels needed to complete the project by the established delivery date.
F.11 PRE-CONSTRUCTION MEETING
After Contract award, and prior to start of construction, the Contractor shall participate in a pre-construction meeting scheduled by the Contracting Officer's Representative (COR). The Contractor, at a minimum, shall have the project manager and field superintendent available on site for a pre-construction meeting, prior to the commencement of work for this contract. The meeting is normally scheduled by the COR within 5 days after contract award.
F.12 SUBMITTALS
The Contractor shall submit the "Product Submittals" to the COR for approval within ten (10) calendar days after receipt of the notice to proceed. For submittals that are not known at time of award, these product submittals shall be submitted to the COR throughout the performance period as required in order to have all work completed by the defined period of performance end date. Contractor shall provide submittals and give a reasonable timeframe for the Government to review and respond to submittals and still allow the contractor to carry out the deliverables of the Contract.
END OF SECTION F
SECTION G -- CONTRACT ADMINISTRATION DATA
G.1 GS1101 CONTRACT ADMINISTRATION OFFICE JULY 2001
(a) This contract will be administered by:
United States Geological Survey Terrence Hardy, Contracting Officer trhardy@usgs.gov, 703-648-7377 12201 Sunrise Valley Drive Reston VA 20192
(b) Written communications to the Administrative Contracting Officer shall make reference to the contract number and shall be mailed to the above address.
G.2 1452.201-70 AUTHORITIES AND DELEGATIONS SEPTEMBER 2011
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause.
A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.3 GS1125 SCHEDULE OF PRICES (CONSTRUCTION) JULY 2001
In accordance with the clause FAR 52.232-05, Payments under Fixed-Price Construction Contracts, the contractor shall, within 10 days after date of award, submit to the Contracting Officer for approval, a Schedule of Prices. This schedule shall consist of a detailed breakdown of the contract price, segregated under each of the significant construction categories. It shall state the quantities for each of the various types of work, the unit prices, and extended totals.
Subcontractors who may be involved in more than one category of work must provide the same breakout data for each category. The submission of the required data shall not otherwise affect the contract terms.
G.4 PAYROLLS
The Contractor is required to submit copies of all payrolls to the Contracting Officer weekly for each task underway. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors weekly. This information may be submitted in any form. The optional form (WH-347) may be used, see clause 52.222-8 under Section I.
G.5 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (September 2011)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Internet Payment Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
Send a copy of the final invoice.
The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in CCR) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the original contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the contracting officer.
G.6 UNILATERAL DEOBLIGATION OF UNEXPENDED FUNDS MAY 2013
Contracting Officers may de-obligate unexpended balances with a unilateral administrative modification when all the following applies:
(a) The following clause is included in the award, either initially or subsequently by bilateral modification:
The contract shall submit all invoices under the award no later than 90 calendar days after the period of performance has expired, unless a request for extension has been submitted to the Contracting Officer. After 120 days has passed since the expiration of the period of performance, the government reserves the right to issue a unilateral modification deobligating any unexpended funds, and to initiate closeout procedures.
(b) The Contracting Officer has contacted the cognizant program official to confirm that all work is complete and deliverables received and accepted.
(c) The Contracting Officer has determined that the vendor has invoiced and been paid all amounts due under the award.
(d) All addition close procedures will be initiated as appropriate.
G.7 Technical Liaison-Technical Direction (Jul 2018)
(a) The performance required herein shall be subject to the technical direction of the Technical Liaison (TL) as identified below. As used herein, "technical direction" is defined as direction to the contractor that fills in details, suggests possible lines of approach, or otherwise supplements the scope of the work set forth herein and shall not constitute a new assignment, and does not supersede or modify any article or clause of this contract.
(b) The Technical Liaison is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government. Only a warranted Contracting Officer is authorized to obligate funds on this or any other contract action.
(c) The contractor shall immediately notify the Contracting Officer in writing if the Technical Liaison has taken an action (or fails to take action) or issues direction (written or oral) that the contractor considers exceeding the above limitations.
(d) The Technical Liaison assigned for this contract is:
TBD
(e) Only the Contracting Officer may designate a different Technical Liaison.
END OF SECTION G
SECTION H -- SPECIAL CONTRACT REQUIREMENTS
H.1 52.252-02 CLAUSES INCORPORATED BY REFERENCE
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be
52.202-01 Definitions June 2020
H.2 GS0340 ENVIRONMENTALLY PREFERABLE
BUILDING PRODUCTS AND MATERIALS
MAY 2008
(a) The contractor shall use environmentally preferable products and materials where economically feasible.
Environmentally preferable products have a lesser or reduced effect on human health and the environment when compared to other products and services that serve the same purpose.
(b) Refer to EPA's environmentally preferable products web site, www.epa.gov/opptintr/epp. In general, environmentally preferable products and materials do one or more of the following –
(1) Contain recycled material, are biobased, or have other positive environmental attributes;
(2) Minimize the consumption of resources, energy, or water;
(3) Prevent the creation of solid waste, air pollution, or water pollution;
(4) Promote the use of non-toxic substances and avoid toxic materials or processes.
(c) See FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts, for related bio-based product requirements.
(d) See FAR 52.223-17, Affirmative Procurement of EPA-designated Items in Service and Construction Contracts, for related recycled content requirements.
(e) If this contract includes janitorial services, the contractor specifically must -
(1) use the following recycled content products - towels, tissue products, and plastic trash can liners, and
(2) use biobased and/or environmentally preferable cleaning products.
H.3 GS0342 HAZARDOUS MATERIAL IDENTIFICATION MAY 2008
(a) In accordance with clause FAR 52.223-3, Hazardous Material Identification and Material Safety Data, Alternate I, the contractor shall provide Materials Safety Data Sheets (MSDS) for the following products prior to their use under this contract: adhesives, caulking, sealants, insulating materials, fireproofing or fire-stopping materials, paints, carpets, floor and wall patching or leveling materials, lubricants, clear finish for wood surfaces, janitorial cleaning products, pesticides, rodenticides, and herbicides.
(b) The Government reserves the right to review such products at any time. The Contracting Officer may eliminate from permitted use under this contract products with significant quantities of toxic, flammable, corrosive or carcinogenic material and products with potential for harmful chemical emissions.
H.4 GS0343 ENERGY EFFICIENT PRODUCTS MAY 2008
(a) When acquiring energy-using products, the contractor shall purchase ENERGY STAR® or other energy-efficient items listed on the Department of Energy’s Federal Energy Management Program (FEMP) Product Energy Efficiency Recommendations product list. This clause applies to any power-consuming equipment to be installed or used in USGS facilities, whether title to the equipment will pass to the Government or be retained by the Contractor.
(b) For products that consume power in a standby mode (as listed on FEMP’s Standby Power Devices product listing), the contractor shall -
1) Purchase items which meet FEMP’s standby power wattage recommendation or document the reason for not purchasing such items; or
(2) If FEMP has listed a product without a corresponding wattage recommendation, purchase items which use no more than one watt in their standby power consuming mode. When it is impracticable to meet the one watt requirement, purchase items with the lowest standby wattage practicable.
(c) The requirements of this clause do not apply if (1) no compliant product’s utility and performance can meet the contractor’s need or contract specifications, (2) compliance would not be life-cycle cost-effective, or (3) compliant solutions are otherwise not available.
(d) Information is available via the Internet about - ENERGY STAR® at http://www.energystar.gov/; and FEMP at http://www.eere.energy.gov/femp/procurement.
H.5 GS0346 CONSTRUCTION WASTE MANAGEMENT MAY 2008
(a) Items and material existing in the space or to be removed from the space during the demolition phase are eligible for reuse in the construction phase of the project. The reuse of items and materials is preferable to recycling them; however, items considered for reuse must be in refurbishable condition, and must meet the quality standards set forth by the Government in this solicitation/contract. In the absence of definitive quality standards, the contractor is to ensure that the quality of the item(s) in question will meet or exceed accepted industry or trade standards for first quality commercial grade applications. Before use, the contractor shall submit a reuse plan to the Contracting Officer. The Government will not pay for existing fixtures and other existing improvements accepted in place.
(b) Recycling construction waste means providing all services necessary to furnish construction materials or wastes to organizations which will employ these materials or wastes in the production of new materials. Recycling includes required labor and equipment necessary to separate individual materials from the assemblies of which they form a part.
(c) The Offeror shall maintain a recycling program to dispose of or recycle construction waste in compliance with this clause. The program must cover the following requirements.
(1) The contractor will provide continuous facilities for the recycling of incidental construction waste during initial construction.
(2) Products may be excluded from the recycling program when the small quantity of material involved, the extraordinarily complex nature of the waste disposal method, or prohibitive expense for recycling would represent a genuine hardship.
(3) Records of construction materials recycled shall be maintained and accessible to the Contracting Officer.
Records shall include materials recycled or landfilled, quantity, date, and identification of hazardous wastes.
(d) As a minimum, the contractor will recycle lighting and associated support system, carpet and carpet pad, hardware, drywall, and electrical components during both the demolition and construction phases of the project, subject to economic evaluation and feasibility.
(e) If any waste materials encountered during the demolition or construction phase are found to contain lead, asbestos, PCBs (such as fluorescent lamp ballasts), or other harmful substances, they are to be handled and removed in accordance with State and Federal laws and requirements concerning hazardous waste.
(f) The requirements of paragraphs (b) through (d) of this clause do not apply when no construction recycling and salvage operation is reasonably available in the locality where work is to be performed.
H.6 GS0347 INDOOR AIR QUALITY DURING
CONSTRUCTION
(a) Items and material existing in the space or to be removed from the space during the demolition phase are eligible for reuse in the construction phase of the project. The reuse of items and materials is preferable to recycling them; however, items considered for reuse must be in refurbishable condition, and must meet the quality standards set forth by the Government in this solicitation/contract. In the absence of definitive quality standards, the contractor is to ensure that the quality of the item(s) in question will meet or exceed accepted industry or trade standards for first quality commercial grade applications. Before use, the contractor shall submit a reuse plan to the Contracting Officer. The Government will not pay for existing fixtures and other existing improvements accepted in place.
(b) Recycling construction waste means providing all services necessary to furnish construction materials or wastes to organizations which will employ these materials or wastes in the production of new materials. Recycling includes required labor and equipment necessary to separate individual materials from the assemblies of which they form a part.
(c) The Offeror shall maintain a recycling program to dispose of or recycle construction waste in compliance with this clause. The program must cover the following requirements.
(1) The contractor will provide continuous facilities for the recycling of incidental construction waste during initial construction.
(2) Products may be excluded from the recycling program when the small quantity of material involved, the extraordinarily complex nature of the waste disposal method, or prohibitive expense for recycling would represent a genuine hardship.
(3) Records of construction materials recycled shall be maintained and accessible to the Contracting Officer.
Records shall include materials recycled or landfilled, quantity, date, and identification of hazardous wastes.
(d) As a minimum, the contractor will recycle lighting and associated support system, carpet and carpet pad, hardware, drywall, and electrical components during both the demolition and construction phases of the project, subject to economic evaluation and feasibility.
(e) If any waste materials encountered during the demolition or construction phase are found to contain lead, asbestos, PCBs (such as fluorescent lamp ballasts), or other harmful substances, they are to be handled and removed in accordance with State and Federal laws and requirements concerning hazardous waste.
(f) The requirements of paragraphs (b) through (d) of this clause do not apply when no construction recycling and salvage operation is reasonably available in the locality where work is to be performed.
H.7 GS0348 ENVIRONMENTAL REQUIREMENTS -
SELECTED CONSTRUCTION MATERIALS
(a) Asbestos
No asbestos-containing fireproofing or insulation on building structures, acoustical treatment, molded or wet-applied ceiling or wall finishes/decorations, or pipe and boiler insulation (including duct, tank, etc.) will be permitted in new materials provided by the contractor under this contract.
(b) Lighting: Interior and Parking
(1) Modern diffused, fluorescent fixtures using solid state octron ballasts with energy efficient lamps (T-8 or better) and electronic ballasts shall be provided if new fixtures are to be used. Fixtures shall be capable of producing and maintaining a uniform lighting level of 50-foot candles at working surface height throughout the space. In addition, restroom lighting shall be 30 foot candles measured at counter height and 20 foot-candles measured at the floor in enclosed corridors.
(2) Exterior parking areas, vehicle driveways, pedestrian walkways and building perimeter shall have a minimum of 1 foot-candle measured at the ground of illumination and be designed based on Illumination Engineering Society standards. Exterior lighting and indoor parking shall be sufficient to accommodate security monitoring (i.e., closed circuit television camera). Indoors parking shall have a minimum of 10 foot-candles measured at the floor and be designed based on Illumination Engineering Society standards.
(3) The contractor shall provide occupancy sensors and/or scheduling controls through building automation system to reduce the hours the lights are on when the space is unoccupied. Daylight dimming controls shall be used in atriums or other space where daylight can contribute to energy savings.
(4) Lighting shall be controlled by occupancy sensors arranged to control open areas, individual offices, conference rooms, toilet rooms, and all other programmed spaces or rooms within the facility to be constructed, remodeled, or maintained hereunder. The control system shall provide an optimal mix of infrared and ultrasonic sensors suitable for the configuration and type of space. Occupancy sensors shall be located so that they have a clear view of the room or area they are monitoring. No more than 1,000 BOMA Usable Square Feet of open space shall be controlled by one occupancy sensor. All occupancy sensors shall have manual switches to override the light control with an adjustable timer to control the amount of time the lighting is manually activated. Such switches shall be located by door openings in accordance with the Americans With Disabilities Act Accessibility Guidelines and the Uniform Federal Accessibility Standards.
(c) Potable Water Supply
Solder and flux in joining potable water supply piping shall not contain more than 0.2 percent lead and domestic water pipes or pipefittings shall not contain more than 8 percent lead. In addition, the contractor is to meet standards set forth in EPA's in "Drinking Water Standards for Schools, and Non-Residential Buildings", A Publication 812-B-94-002, April 1994.
(d) Wood Products
(1) For all new installations of wood products, the contractor is encouraged to use independently certified forest products. For information on certification and certified wood products, see web sites for the Forest Stewardship Council or the Certified Forest Products Council at www.fscus.org/ and www.certifiedwood.org/.
(2) New installations of wood products used under this contract must not contain wood from endangered wood species, as listed by the Convention on International Trade and Endangered Species (CITES). The list of species can be found at www.certifiedwood.org/Resources/CITES/ CITESContent.html.
(3) Particle board, strawboard and plywood materials shall comply with HUD Standards for VOC emissions (particleboard: 0.2 ppm of formaldehyde, plywood: 0.3 ppm of formaldehyde).
(e) Adhesives and Sealants
All adhesives employed on this project (including, but not limited to, adhesives for carpet, carpet tile, plastic laminate, wallcoverings, wood adhesive, or sealants) shall be those with the lowest possible Volatile Organic Compound (VOC) content below 20 g/L. and which meet the requirements of the manufacturer of the products adhered or involved. The contractor shall use adhesives and sealants with no formaldehyde or heavy metals.
(f) Insulation - Thermal, Acoustic, and HVAC
(1) All insulation products shall contain recovered materials as required by EPA's Comprehensive Procurement Guideline and related recycled content recommendations.
(2) No insulation installed with this project shall be material manufactured using chlorofluorocarbons (CFCs), nor shall CFCs be used in the installation of the product.
(3) All insulation containing fibrous materials exposed to air flow must be rated for that exposure or encapsulated.
(4) Insulating properties for all materials must meet or exceed applicable industry standards. Polystyrene products shall meet ASTM C578-91.
(g) Floor Covering
All Floor covering must meet EPA and OSHA environmental health and safety requirements. In addition, the indoor air standard for 4-phenylcyclohexene (4-PC) appears as follows: to protect against induction of multiple chemical sensitivity
- .005PPB; to protect against acute irritant effects - 01.7 PPB. Testing will be required on the finished flooring to establish a product content standard for 4-PC that will assure compliance with the indoor air standard.
H.8
GS1306
PERFORMANCE AND PAYMENT BONDS MAY 2003
The offeror to whom award is made shall deliver good and sufficient performance and payment bonds (Standard Forms 25 and 25A) to the Contacting Officer, at the address shown in clause G1101 and via email, within 10 calendar days after receipt of award. Bonds must be furnished in the following amounts: Performance bond - 100% of the total contract amount, payment bonds - 100% of the total contract amount
H.9 GS1310 ORGANIZATIONAL CONFLICTS OF INTEREST--GENERAL JULY 2001
(a) The term "organizational conflict of interest" means a situation where a contractor has interests, either due to its other activities or its relationships with other organizations, which place it in a position that may be unsatisfactory or unfavorable (i) from the Government's standpoint in being able to secure impartial, technically sound, objective assistance and advice from the contractor, or in securing the advantages of adequate competition in its procurement; or (ii) from industry's standpoint in that unfair competitive advantages may accrue to the contractor in question.
(b) The contractor agrees that, if after award he discovers an organizational conflict of interest with respect to this contract, he shall make an immediate and full disclosure in writing to the Contracting Officer, which shall include a description of the action which the contractor has taken or proposes to take to avoid, eliminate, or neutralize the conflict.
The Government may, however, terminate the contract for the convenience of the Government if it would be in the best interests of the Government.
(c) In the event that the contractor was aware of organizational conflict of interest prior to the award of this contract and failed to disclose the conflict to the Contracting Officer, the Government may terminate the contract at no cost to the Government.
H.10 GS1326 INDEMNITY JULY 2001
The contractor herein is "an independent contractor" and shall obtain all necessary insurance to protect himself from liability arising out of this contract.
The contractor hereby agrees to indemnify and hold the Government harmless in connection with, any loss or liability from damage to or destruction of property or from injuries to or death of persons (including the agents and employees of both parties) if such damage, destruction, injury or death arises out of, or is caused by performance of work under this contract, unless such damage, destruction, injury or death is caused solely by the active negligence of the Government, its agents or employees. The contractor agrees to include this clause, appropriately modified, in all subcontracts to be performed under this contract.
H.11 GS1330 KEY PERSONNEL JULY 2001
(a) The Contractor shall assign to this contract the following key personnel to the identified positions/functions:
Position/Function Name
(Offeror must fill in names of proposed key personnel, as presented in the technical proposal.)
(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes must possess qualifications comparable to the original key person, as well as satisfying any minimum standards set forth elsewhere in the solicitation/contract. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.
(End Clause)
H.12 GS1338 NOTICE TO THE GOVERNMENT OF DELAYS (JUL 2001) (MODIFIED)
(a) In the event the Contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or any date, or whenever the Contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately notify the Contracting Officer and the Contracting Officer’s Representative, in writing, giving pertinent details, provided that this data shall be informational only in character and that this provision shall not be construed as a waiver by the Government of any delivery schedule or date or of any rights or remedies provided by law or under this contract.
(b) If the Contractor fails to respond in a timely manner to any portion of this contract, delay will be attributed to the Contractor. Although the period of performance may change due to the delay, the price may be subject to a downward adjustment.
(c) If the Government delays performance of this contract, the period of performance and/or price may be revised upon mutual agreement between the Government and the Contractor.
H.13 GS1348 ACCIDENT REPORTING APRIL 2003
If an accident occurs on Government-controlled facilities, a report must be provided to the Contracting Officer’s Representative and the Contracting Officer within 48 hours. An accident is defined as an event which causes injury, illness, or loss or damage to Government-owned or private property. The contractor will cooperate with any ensuing Government accident investigation.
H.14 GS1350 SUPERVISION OF CONTRACTOR'S EMPLOYEES JULY 2007
(a) Personnel assigned to render services under this contract shall at all times be employees of the Contractor (or a subcontractor) and under the direction and control of the Contractor.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .