B08_-_Solicitation_(Attachment_Specifications).pdf
PDF 1014 KB Posted
- Attached to
- SD-GAVINS PT NFH-REHAB AQUARIUM ENTRANCE ROAD
- Solicitation number
- 140FGA25Q0030
About this file
This document is a comprehensive set of technical specifications for rehabilitating the aquarium entrance road at Gavins Point National Fish Hatchery in Yankton, South Dakota. The project involves completely removing and reconstructing the existing road, which currently has severe longitudinal and transverse cracking, distortion, potholes, and overall surface roughness. The specifications cover multiple technical divisions including site clearing, earthwork, soil stabilization, asphalt paving, gravel surfacing, pavement markings, and culvert installation.
Key project details include a planned start date after Labor Day (September 2, 2025), with specific requirements for site preparation, materials, and construction methods. The specifications mandate careful excavation, proper soil compaction, installation of geotextile for stabilization, placement of aggregate base courses, and asphalt paving with specific density and compaction standards. Environmental protection measures are emphasized, including erosion control, waste management, and protection of existing utilities and vegetation. The project will involve removing an estimated 80 feet of 30-inch diameter culvert and requires adherence to South Dakota Department of Transportation (SDDOT) standards throughout the construction process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES
DEPARTMENT OF THE INTERIOR
FISH AND WILDLIFE SERVICE
REGION 6 ENGINEERING
Lakewood, Colorado
REHABILITATE AQUARIUM ENTRANCE ROAD
GAVINS POINT NATIONAL FISH HATCHERY
YANKTON, YANKTON COUNTY, SOUTH DAKOTA
22-025
5/22/2025
DESCRIPTION/SPECIFICATIONS
FWS SPECIALIZED SPECIFICATIONS
REHABILITATE AQUARIUM ENTRANCE ROAD
AT
GAVINS POINT NATIONAL FISH HATCHERY
SPECIFICATION INDEX
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 011100 SUMMARY OF WORK
012900 PAYMENT PROCEDURES
013100 PROJECT MANAGEMENT AND COORDINATION
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013233 PHOTOGRAPHIC DOCUMENTATION
013300 SUBMITTAL PROCEDURES
013310 SUBMITTAL TEMPLATE
014000 QUALITY REQUIREMENTS
015000 TEMPORARY FACILITIES AND CONTROLS
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
DIVISION 2 – EXISTING CONDITIONS
SECTION 024113 SELECTIVE SITE DEMOLITION
DIVISION 31 - EARTHWORK
SECTION 311000 SITE CLEARING
312000 EARTH MOVING
313200 SOIL STABILIZATION
313215 EXCAVATION FILL COMPACTION
DIVISION 32 – EXTERIOR IMPROVEMENTS
SECTION 321216 ASPHALT PAVING
321500.1 GRAVEL SURFACING
321723 PAVEMENT MARKINGS
DIVISION 33 – UTILITIES
SECTION 334200 CULVERTS
END OF SECTION
SECTION 011000 - SUMMARY
GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Project background.
3. Work covered by Contract Documents.
4. Work under separate contracts.
5. Access to site.
6. Coordination with occupants.
7. Coordination with local utilities.
8. Work restrictions.
9. Permits and Fees.
10. Applicable codes, standards, and specifications.
11. Means and methods.
12. Safety.
13. Environmental Protection.
B. Related Requirements:
1. Section 015000-Temporary Facilities and Controls for limitations and procedures governing temporary use of Government's facilities.
1.2 PROJECT INFORMATION
A. Project Location: Gavin’s Point National Fish Hatchery, 31227 436th Avenue, Yankton, Yankton County, SD
B. Station Contact Information: Nick Starzl, Project Leader, 605-665-3352 .
1.3 PROJECT BACKGROUND
The Gavins Point NFH Aquarium Entrance Road has severe cracking, distortion, potholes and overall severe surface roughness, requiring rehabilitation.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Gavins Point NFH Aquarium Entrance Road has severe longitudinal cracking, severe transverse cracking, distortion, alligator cracking, potholes and overall severe surface roughness. The road needs to be completely removed and reconstructed.
1.5 WORK UNDER SEPARATE CONTRACTS
A. General: In the event there is work being performed under a separate contract the Contractor shall cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts.
Coordinate the Work of this Contract with work performed under separate contracts.
1.6 ACCESS TO SITE
A. All operations of the Contractor (including storage of materials) upon Government premises shall be confined to areas authorized or approved by the Contracting Officer.
B. Limit use of Project site areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to Aquarium north entrance road, see drawings.
2. Driveways, Walkways and Entrances: Keep driveways and loading areas, and entrances serving premises clear and available to Government, Government Representatives, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1.7 COORDINATION WITH OCCUPANTS
A. Full Government Occupancy: Government will occupy site and existing adjacent building(s) during entire construction period. Cooperate with Station Manager during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits at all times.
1. Notify Station Manager not less than 48 hours in advance of activities that will affect Station operations.
2. The Hatchery requires access at all times to 436th Avenue. Single lane access must be maintained throughout construction.
3. Work on the Entrance Road can begin after Labor Day (2 September 2025).
4. Aquarium public access will close after Labor Day (September 1st, 2025), at which time the parking lot can be used for contractor parking and storage.
1.8 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 4:00 p.m., Monday through Friday, unless otherwise indicated.
1. Work on weekends will be restricted to Contracting Officers approval and at the Station Managers discretion.
2. No work will take place over Federally observed holidays.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Station Manager not less than 48 hours in advance of proposed utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruptions to the Government.
1. Notify Station Manager not less than 48 hours in advance of proposed disruptive operations.
E. Nonsmoking Building: Smoking is not permitted within buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes.
1.9 COORDINATION WITH LOCAL UTILITIES
A. The Contractor shall be responsible for contracting and arranging with local utility for the termination, moving, or connection of utilities that serve existing buildings and ones that are planned to serve the new Work.
B. Local utilities that serve Gavins Point NFH, SD are:
1. Bon Homme Yankton Electric Association, Inc; P.O. Box 158, Tabor, SD 57063
2. Century Link (Telephone), P.O. Box 2956, Phoenix, AZ 85062
3. Midco Business (Internet), P.O. Box 5010, Sioux Falls, SD 57117
4. B-Y Water District, P.O. Box 248, Tabor, SD 57063
1.10 PERMITS AND FEES
A. The Contractor shall be responsible for obtaining all necessary local, State, and Federal permits and licenses, and payment of related fees, per the Contract Clauses.
1.11 APPLICABLE CODES, STANDARDS AND SPECIFICATIONS
A. All work shall comply with the codes and standards applicable to each type of work as listed in individual Sections of these Specifications.
B. Where a conflict occurs between a referenced document and the Project Specifications, the Project Specifications govern.
C. Where a conflict occurs between referenced documents, the document containing the most stringent requirements governs.
D. Where referenced documents are not specified by date, the document current at the bid opening applies.
E. Materials, applications, and tests specified by reference to published standards of society, association, code, or other published standards are included in the specifications as if written in their entirety.
F. Conform to all regulations and statutes of the State of South Dakota and to all Federal Regulations which apply.
1.12 MEANS AND METHODS
A. Means and methods of construction shall be such as the Contractor or subcontractors may choose;
subject, however, to the Contracting Officer's right to reject means and methods proposed which:
1. Constitute a hazard to the work, persons, or property.
2. Will not produce finished work in accordance with terms of the contract.
3. Are contrary to specified means or methods included in the contract.
B. The right to reject means and methods of the Contractor or subcontractor shall not be construed or interpreted as acceptance of control of means and methods by the Contracting Officer.
C. The Contracting Officer's approval of means and methods or failure to exercise right to reject means and methods shall not relieve the Contractor of the obligation to complete the work required by the contract.
D. Total responsibility for control of all means and methods lies with the Contractor for all work.
1.13 SAFETY
A. The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient flasher lights, flagmen, danger signals and signs, and shall take all necessary precautions for the protection of the work and the safety of the public. All ponds and water control structures shall remain accessible by vehicle. Roads closed to traffic shall be protected by effective barricades and shall be placed with acceptable warning signs. All barricades and obstructions shall be illuminated at night and all lights shall be kept burning from sunset until sunrise. Install appropriate traffic signs at crossroads and approaches to site as needed to direct affected public traffic. Specific signs and barricade requirements are detailed in the U.S. Department of Transportation, "Manual on Uniform Traffic Control Devices".
B. The Contractor shall assume full responsibility and liability for compliance with all applicable Federal, State, and local regulations pertaining to the protection of workers, visitors to the site, and persons occupying areas adjacent to the site, including the provisions of 29CFR1910 and 29CFR1926 of the Code of Federal Regulations. The Contractor shall hold harmless the Government for failure to comply with any applicable safety or health regulation on the part of himself, his employees, or his subcontractors.
C. Provide personal safety equipment and training commensurate with the hazards which may exist at the work site. The personal safety equipment and training shall be determined by a thorough hazard analysis of all work site areas. The safety program available at all work sites shall include a minimum of:
1. One nonfreezing-type fire extinguisher in each workshop and shed used for storage of materials at the work site. Place in location readily accessible to construction personnel.
2. A first aid kit for use of construction personnel commensurate with size of project with items necessary for first aid treatment of all injuries.
3. The Contractor shall conduct regular onsite safety inspections and all construction personnel shall receive a safety orientation.
4. Post telephone numbers of nearest hospital, ambulance service or flight for life, and fire station in conspicuous location. Advise all workers of location of telephone numbers.
1.14 ENVIRONMENTAL PROTECTION
A. The Contractor shall abate and control all environmental pollution arising from construction activities by complying with all applicable Federal, State, and local laws and regulations concerning environmental pollution control and abatement, as well as the specified requirements in this contract. Compliance with this requirement by subcontractors will be the responsibility of the Contractor.
B. Fossils and Artifacts
1. Should the Contractor discover any fossils or artifacts during construction operations, such objects shall become the property of the Government. The Contractor shall cease construction operations in the area of the "find," and immediately notify the station manager of such discovery. Construction operations may proceed in other areas not affected by this clause. Care shall be exercised by the Contractor not to damage fossils or artifacts uncovered during excavation operations.
2. Failure to comply with this requirement may be considered a violation of the Archeological Resources Protection Act of 1979 as amended. Destruction of historic and prehistoric sites and/or unauthorized collection of cultural materials can result in criminal and/or civil penalties. Penalties can include fines, prison sentences, and/or confiscation of equipment.
3. If the Contractor uses fill from a nongovernmental source to perform work that is required under this project, and a new borrow site is opened or an existing borrow area is expanded in order to obtain such materials, the Contractor shall assure that any new borrow area disturbance meet the requirements of Section 106 of the National Historic Preservation Act.
C. Abatement of Air Pollution
1. The Contractor shall comply with applicable Federal, State, and local laws and regulations concerning the prevention and control of air pollution.
2. Construction activities shall be performed in such a manner that air pollution will be held to a minimum.
3. Burning of materials, trees and brush, combustible construction materials, and rubbish will not be permitted. Construction debris shall be disposed of at a location designated by the Contracting Officer or hauled off the Station to an approved disposal site.
D. Prevention of Water Pollution
1. The Contractor is responsible for implementing the terms and requirements of the (insert state) storm water discharge permit, as issued to the State under the National Pollution Discharge Elimination System (NPDES) by the Environmental Protection Agency (EPA).
The Contractor shall apply for and execute all permits as required by the State of (insert state) regarding storm water discharge from the construction site. The Contractor shall submit to the Contracting Officer a copy of all permit applications and a copy of all approvals from the State. Allow the Government 10 days for review of the application package prior to submission.
2. During construction, the Contractor shall comply with all applicable Federal, State, and local laws and regulations concerning the control and abatement of water pollution.
3. The Contractor's construction activities shall be performed by methods that will prevent entrance or accidental spillage of solid matter, contaminants, debris, and other objectionable pollutants and wastes into streams, flowing or dry water-courses, lakes, ponds, and underground water sources. The Contractor shall dispose of all pollutants such as petroleum products, rubbish, cement, concrete, etc., and objectionable material at a jurisdictionally accepted waste management facility.
4. Sanitary facilities, such as chemical toilets shall be located far enough from wells, live streams, or ponds to prevent pollution of the water.
5. Dewatering work for structure foundations or earthwork operations adjacent to or encroaching on streams or watercourses shall be conducted in a manner that prevents muddy water and eroded materials from entering streams or watercourses. This shall be accomplished by construction of intercepting ditches, bypass channels, barriers, settling ponds, or other approved means. Excavated material shall not be placed in or adjacent to watercourses where it can be washed away by high water or storm runoff.
E. Prevention of site contamination
1. The purpose of this section is to prevent invasive species from being introduced to the project work sites. This includes both plant and animal species. Invasive species can have long last detrimental effects at project sites at US Fish and Wildlife Service lands.
2. Prior to entrance to the work site, all equipment brought on site will be thoroughly washed to remove dirt, seeds, and plant parts. Any equipment that has been any body of water within the past 30 days will be thoroughly cleaned with hot water greater than 140 degree F (typically the temperature found at commercial truck washes) and dried for a minimum of five days before being used at this project site. In addition, before transporting equipment from the project site all visible mud, plants and fish/animals will be removed, all water will be eliminated, and the equipment will be thoroughly cleaned. Anything that came in contact with water will be cleaned and dried following the above procedure.
F. Environmental Litigation: Time lost due to work stoppage because of failure of the Contractor to comply with these requirements may not be the subject of a claim for extension of time, for additional costs, or damages.
END OF SECTION 011000
SECTION 012900 – PAYMENT PROCEDURES
1.1 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
1.2 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Submit the schedule of values to Contracting Officer at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.
1.3 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by Contracting Officer.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Government and Contractor.
C. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. Schedule of values.
2. Contractor's construction schedule (preliminary if not final).
3. Submittal schedule (preliminary if not final).
D. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Written guarantees, warranties, and certificates.
3. Record (As-Built) Drawings
4. All test reports.
END OF SECTION 012900
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Coordination drawings.
2. Requests for Information (RFIs).
3. Project meetings.
1.2 DEFINITIONS
A. RFI: Request from Government, Owner, Construction Manager, or Contractor seeking information required by or clarifications of the Contract Documents.
1.3 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
1.4 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Provide a construction schedule noting demolition activities, construction activities, deliveries, payments, etc., as needed to convey coordination information to the Contacting Officer, Contacting Officer’s Representative (COR), Government Inspector as well as local staff.
2. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
3. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
4. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities as well as any activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the Schedule of Values (SOV).
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.5 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer’s Representative indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Review: The Government will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.
1.6 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. The Government will return RFIs as submitted to the Government by other entities controlled by Contractor with no response. RFI’s must come directly from the Contractor.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. RFI number, numbered sequentially.
6. RFI subject.
7. Specification Section number and title and related paragraphs, as appropriate.
8. Drawing number and detail references, as appropriate.
9. Field dimensions and conditions, as appropriate.
10. Contractor's suggested resolution. If Contractor's solution(s) have an impact the Contract
Time or the Contract Sum, Contractor shall state impact in the RFI.
11. Contractor's signature.
12. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. RFI Forms: AIA Document G716, or Software-generated form with substantially the same content as indicated above, acceptable to the Government.
D. The Governments Action: The Government will review each RFI, determine action required, and respond. Allow seven working days for the Government’s response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for coordination information already indicated in the Contract Documents.
d. Requests for adjustments in the Contract Time or the Contract Sum.
e. Requests for interpretation of designer's actions on submittals.
f. Incomplete RFIs or inaccurately prepared RFIs.
g. Request For Information submitted by a sub-contractor to the Contractor.
2. The Government’s action may include a request for additional information, in which case the time for response will date from time of receipt of additional information.
3. The Government’s action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal.
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Contacting Officer and COR in writing within 10 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly with not less than the following information:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Contacting Officer and COR.
4. RFI number including RFIs that were dropped and not submitted.
5. RFI description.
6. Date the RFI was submitted.
7. Date the Contacting Officer’s response was received.
F. On receipt of the Government’s action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify the Government within seven days if Contractor disagrees with response.
1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.
2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.
1.7 PROJECT MEETINGS
A. General: The construction contractor shall coordinate and schedule and conduct weekly construction progress meetings at the Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify the Facility Director, the Contracting officer and the COR of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including the Contracting Officer and the COR, Construction Manager, and other FWS personnel, within three days of the meeting.
B. Preconstruction Conference: The Contracting Officer will schedule a preconstruction conference before starting construction, at a time convenient to the Contracting Officer, COR, Hatchery POC, On-Site Government Inspector and Contractor.
1. Attendees: Authorized representatives of the Contracting Officer, Government Project Manager, COR, Hatchery staff and their consultants; Contractor and its superintendent;
major subcontractors; suppliers; and other concerned parties shall attend the conference.
Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Change Orders.
f. Procedures for RFIs.
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Preparation of record documents.
l. Use of the premises and existing building.
m. Work restrictions.
n. Working hours.
o. Owner's occupancy requirements.
p. Responsibility for temporary facilities and controls.
q. Procedures for moisture and mold control.
r. Procedures for disruptions and shutdowns.
s. Construction waste management and recycling.
t. Parking availability.
u. Office, work, and storage areas.
v. Equipment deliveries and priorities.
w. First aid.
x. Security.
y. Progress cleaning.
3. Minutes: The construction contractor shall be responsible for conducting meeting, recording minutes and distributing the meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise the Government of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility problems.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written instructions.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of authorities having jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: Conduct weekly construction progress meetings as directed by the Contracting officer and/or the COR.
1. Attendees: In addition to representatives of the Government, Construction Manager, and COR (as applicable), each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do
so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of proposal requests.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
18) Documentation of information for payment requests.
3. Minutes: The construction contractor shall be responsible for conducting meeting, recording minutes and distributing the meeting minutes.
a. Schedule Updating: Revise the construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
PRODUCTS (Not Used)
EXECUTION (Not Used)
END OF SECTION 013100
SECTION 013200 – CONSTRUCTION PROGRESS DOCUMENTATION
1.1 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's construction schedule.
2. Construction schedule updating reports.
3. Daily construction reports.
4. Site condition reports.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
1.3 INFORMATIONAL SUBMITTALS
A. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
1. Submit a working electronic copy of schedule, using software indicated, and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.
B. Construction Schedule Updating Reports: Submit with Applications for Payment.
1.4 COORDINATION
A. Coordinate Contractor's construction schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PRODUCTS
2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established from the Notice to Proceed to the date of completion.
B. Activities: Treat each story or separate area as a separate numbered activity for each main element of the Work. Comply with the following:
1. Activity Duration
2. Procurement Activities
3. Submittal Review Time
4. Punch List and Final Completion: Include not more than 15 days for completion of punch list items and final completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Work under More Than One Contract: Include a separate activity for each contract.
3. Work by Owner: Include a separate activity for each portion of the Work performed by
Owner.
4. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Uninterruptible services.
d. Partial occupancy before Substantial Completion.
e. Use of premises restrictions.
f. Provisions for future construction.
g. Seasonal variations.
h. Environmental control.
5. Work Stages: Indicate important stages of construction for each major portion of the Work.
6. Other Constraints
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion and the following interim milestones.
1. Insert milestones not indicated elsewhere.
END OF SECTION 013200
SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Preconstruction photographs.
2. Periodic construction photographs.
B. Related Requirements:
1. Section 017700-Closeout Procedures for submitting photographic documentation as Project Record Documents at Project closeout.
1.2 INFORMATIONAL SUBMITTALS
A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.
B. Digital Photographs: Submit unaltered, original, full-size image files within 5 days of taking photographs.
1. Digital Camera: Minimum sensor resolution of 8 megapixels.
2. Digital photographs to be submitted in the order in which they were taken with the photograph “name” as given by the device used to take to photo.
3. Identification: Provide the following information with each image description in file metadata tag:
a. Date and time photograph was taken
b. Unique photograph number
1.3 QUALITY ASSURANCE
A. Photographs to be clear, focused, level, have proper exposure settings (not over exposed or under exposed), and clearly show and document the subject matter. Detail photographs (close-ups) to be preceded by a larger overall view of the area being documented.
1.4 USAGE RIGHTS
A. If a professional photographer is used for this requirement, obtain and transfer copyright usage rights from photographer to Owner for unlimited reproduction of photographic documentation.
2.1 PHOTOGRAPHIC MEDIA
A. Digital Images: Provide images in JPG format, with minimum size of 8 megapixels.
EXECUTION
3.1 CONSTRUCTION PHOTOGRAPHS
A. Photographer: Engage a qualified photographer to take construction photographs. Photographer need not be a professional photographer, but an individual familiar with and able to produce clear, focused photographs of the subject area with good reference points.
B. General: Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.
1. Maintain key plan with each set of construction photographs that identifies each photographic location.
C. Digital Images: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
1. Date and Time: Include date and time in file name for each image.
2. Field Office Images: Maintain one set of images accessible in the field office at Project site, available at all times for reference. Identify images in the same manner as those submitted to the Government.
D. Preconstruction Photographs: Before commencement of excavation, commencement of demolition and starting construction, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Government.
1. Flag excavation areas before taking construction photographs.
2. Take minimum of 10 photographs, or as needed, to show existing conditions adjacent to property before starting the Work.
3. Take minimum of 10 photographs, or as needed, of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
E. Periodic Construction Photographs: Take photographs as needed to fully document the construction progress. Select vantage points to show status of construction and progress since last photographs were taken. Try to retake progress photos from the same vantage points when possible so as to show relative construction progress.
F. Final Completion Construction Photographs: Take color photographs after date of Substantial Completion for submission as Project Record Documents. The Government will inform photographer of desired vantage points.
G. Additional Photographs: The Government may request photographs in addition to periodic photographs specified as needed to verify progress or to verify work completion accuracy.
1. Three days' notice will be given, where feasible.
2. In emergency situations, take additional photographs within 24 hours of request.
3. Circumstances that could require additional photographs include, but are not limited to, the following:
a. Special events planned at Project site.
b. Immediate follow-up when on-site events result in construction damage or losses.
c. Photographs to be taken at fabrication locations away from Project site. These photographs are not subject to unit prices or unit-cost allowances.
d. Substantial Completion of a major phase or component of the Work.
e. Extra record photographs at time of final acceptance.
f. Owner's request for special publicity photographs.
H. Upon closeout of the project, all photos are to be provided on a CD-ROM or similar, and included in the Operation and Maintenance Manual. Photos shall be structured within folders for the date which the photo was taken. Folders shall be named as such: (Year)-(MNDY). For example, July 11, 2021 would be noted as 2021-0711.
END OF SECTION 013233
SECTION 013300 – SUBMITTAL PROCEDURES
1.1 SUMMARY
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Contracting Officer’s responsive action.
B. Informational Submittals: Written and graphic information and physical samples that do not require Contracting Officer responsive action. Submittals may be rejected for not complying with requirements.
1.3 ACTION SUBMITTALS
A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by the Government and additional time for handling and reviewing submittals required by those corrections.
1.4 SUBMITTAL ADMINISTRATIVE REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.
Time for review shall commence on Contracting Officer receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals. Submittals received after 1:00 PM will be considered to having arrived the following day.
1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Contracting Officer will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 10 working days for review of each resubmittal.
C. Paper Submittals: Place a permanent label or title block on each submittal item for identification.
1. Transmittal for Paper Submittals: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form.
a. Transmittal Form for Paper Submittals: Use FWS transmittal form. This form will be made available in either PDF or as a Word document.
D. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. Name file with submittal number or other unique identifier, including revision identifier.
a. File name shall use a sequential submittal number followed by station initials and Specification Section number (Submittal 001-(Item Name)-(CSI Number)).
Resubmittals shall include a numeric suffix after the submittal number (e.g., Submittal 001-R1-(Item Name)-(CSI Number)).
2. Transmittal Form for Electronic Submittals: Use FWS transmittal form. This form will be made available in either PDF or as a Word document.
E. Options: Identify options requiring selection by the Government.
F. Deviations: Identify deviations from the Contract Documents on submittals.
G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Contracting
Officer’s action stamp.
4. The contractor is allowed (2) resubmittals for any one item or group of related items for a total of (3) reviews of any given item or group of items. If at that time the contractor has not provided the required, requested information, the Government shall be allowed a credit for additional review time and associated costs.
H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
I. Use for Construction: Retain complete copies of submittals on project site. Use only final action submittals that are marked with approval notation from Contracting Officer’s action stamp.
2.1 SUBMITTAL PROCEDURES
A. General Electronic Submittal Procedure Requirements:
1. Submit electronic submittals via email as PDF electronic files.
2. PDF files shall be formatted as an 8.5x11 or 11x17 size “sheet” to allow readability and reduce file size.
3. Contracting Officer’s Representative, through the Contracting Officer, will return annotated file by e-mail and/or standard mail. Annotate and retain one copy of file as an electronic Project record document file.
B. General Paper Submittal Procedure Requirements:
1. Action Submittals: Submit four (4) paper copies of each submittal unless otherwise indicated. Contracting Officer’s Representative through the Contracting Officer will return three (3) copies.
2. Informational Submittals: Submit three (3) paper copies of each submittal unless otherwise indicated. Contracting Officer will not return copies.
3. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.
b. Provide a notarized statement on original paper copy certificates and certifications where indicated.
C. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment. Do not submit items of different CSI divisions together within a single submittal, they shall be submitted separately.
1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable to the item being submitted for approval. Submittals that are not clearly marked will be returned without review.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams showing factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on accompanying Shop
Drawings.
5. Submit Product Data before or concurrent with Samples.
6. Submit Product Data in the following format:
a. PDF electronic file.
b. Four (4) paper copies of Product Data unless otherwise indicated. Contracting
Officer’s Representative through the Contracting Officer will return two (2) copies.
D. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data unless submittal based on drawing files is otherwise permitted.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.
3. Submit Shop Drawings in the following format:
a. PDF electronic file formatted as an 11x17 “sheet” as a maximum size to allow readability and reduce file size.
b. Four (4) opaque copies of each submittal. Contracting Officer’s Representative through the Contracting Officer will retain two (2) copies; remainder will be returned.
E. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c…