B08_Solicitation_Attachment_4_Supplemental_SOW.docx

DOCX document 216 KB Posted

Attached to
ASIS - REHABILITATE MD DEVELOPED ZONE WATER SYSTEM
Solicitation number
140P4326R0008
Issued by

About this file

This is a Supplemental Statement of Work (SOW) for construction services at Assateague Island National Seashore in Berlin, Maryland, requiring rehabilitation of the Maryland Developed Zone water distribution system. The contractor must possess a minimum of five years' experience in horizontal boring of underground service water utilities, with the period of performance running from September 5, 2026, through May 31, 2027. All work must be completed by May 31, 2027. The scope includes providing all labor, supervision, materials, tools, supplies, transportation, licenses, permits, personal protective equipment, and professional services necessary for the water system rehabilitation. The base bid covers the complete scope per construction specifications and drawings, with two optional bid items: (1) procurement, delivery, construction, and installation of a precast concrete pumphouse building, and (2) installation of a water service line to the south beach parking area. Quotes will be provided on a government-supplied price schedule with a lump-sum format for all elements.

Contractor responsibilities include designating a qualified on-site superintendent and alternate superintendent with five years' verifiable experience and two years of supervisory experience in the relevant work, available during all operations and responsive to government communications within 72 hours. Required submittals include a bid bond of 20 percent, active SAM registration with UEI number, contractor's license, drawings/specifications for the pumphouse, performance and payment bond of 100 percent, certificate of insurance, subcontractor SF 1413 forms, schedule of values, waste management/spill prevention plan, site-specific safety plan, quality control plan, daily work logs, weekly certified payroll on WH-347, and weekly releases of claims DI-137. Construction operations are limited to 7:00 a.m. to 3:30 p.m. Eastern Time, Monday through Friday, excluding federal holidays. The contractor must comply with OSHA standards, provide comprehensive site-specific safety plans, implement erosion and sediment control measures, maintain a one-year warranty on all work, and assume full responsibility for any damages resulting from contractor operations, with all losses reported to the Contracting Officer's Representative within two hours of occurrence.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Park Service U.S. Department of the Interior

Northeast Region Assateague Island National Seashore Facility Management Division

TITLE: REHABILITATE MD DEVELOPED ZONE WATER DISTRIBUTION SYSTEM (SUPPLEMENTAL)

Project Location: 6633 Bayberry Drive, Berlin Maryland 21811

STATEMENT OF WORK FOR CONSTRUCTION SERVICES

1. GENERAL

Assateague Island National Seashore (ASIS), headquartered in Berlin, Maryland seeks a contractor with a minimum of 5 years’ experience in horizontal boring of underground service water utilities. Period of Performance on this contract shall take place between 9/5/2026, through 5/31/2027. All contract work shall be completed no later than May 31, 2027.

It is strongly recommended that the contractor’s visit and inspect the site during the pre-bid site visit to verify all estimated quantities, and existing conditions provided by the Government and to observe the complexities of conducting the scope of work. All quantities are provided as informational only. Contractors shall be responsible for verifying all measurements and acquiring all quantities to complete this requirement. Quotes will be broken down by using a government provided price schedule, which will provide a lump sum for all elements.

The term ‘Contractor’ herein, includes the prime contractor and all subordinate contractors employed on their behalf, and are subject to the same guidelines for this contract.

The term ‘Park” herein, refers to the National Park Service unit, Assateague Island National Seashore.

2. PURPOSE AND BACKGROUND

Assateague Island National Seashore operates continuously year-round and provides day use areas, ranger stations, hiking trails and campgrounds. These areas all need potable water to operate and provide the proper services for visitors to the park. The existing water infrastructure that provides potable water to the island is over two decades old and has been pieced together as fixes have occurred over the years leading to water pressure differences, varying water quality as well as increased downtime of water service. Due to these various factors, completely abandoning most of this existing water infrastructure and constructing and installing a new water utility has been determined to be the best method to remediate water distribution throughout the island. This new water system is set to be designed for future use of the park as well as ease of maintenance when issues do arise.

3. TASKS

Provide all labor, supervision, materials, tools, supplies, transportation, license, certificates, permits, personal protection equipment, professional services, and equipment incidental to and necessary to provide services, as specified in the SOW at Assateague Island National Seashore. The contractor shall know and understand the complexities and intricacies of work in the scope of work.

Requirements

3.1. Bids:

3.1.1. Base Bid:

3.1.1.1. Scope of work per Rehabilitate MD Developed Zone Water Distribution System Construction Specifications and Construction Drawings (Full Set and Cut Sheets)

3.1.2. Bid Option 1:

3.1.2.1. Procure, deliver, construct and install a precast concrete building with specification defined in attachment “Island Water Pumphouse General Specifications”

3.1.3. Bid Option 2:

3.1.3.1. Install, per final construction documents, water service line to south beach parking area (see cut sheet CU 310&311) labeled in light blue “FWS”

3.2. Project Specifications

Required (Not Limited To) Deliverables
Due
Contractor’s License Pertinent to Requirement
With quote package
Contractor’s Specialty License – If Applicable
With quote package
Bid Bond 20% on SF 24
With quote package
Active SAM Registration w/ UEI # Clearly Visible
With quote package
Drawings/Specifications/Layout For Island Pumphouse
With quote package
Written Designation of Superintendent and Alt Superintendent
14 Days After Award
Designated Superintendent & Alt. Superintendent Resumes
14 Days After Award
Performance and Payment Bond 100% on SF 25A
14 Days After Award
Certificate of Insurance
14 Days After Award
SF 1413 for all Subcontractors
14 Days After Award
Schedule of Values (SOV)
14 Days After Award
Waste Management/Spill Prevention Plan
21 Days After Award
Site Specific Safety Plan
21 Days After Award
Quality Control Plan
21 Days After Award
Daily Work Logs
Weekly
Certified Payroll on WH-347 w/Updated Schedule and SOV
Weekly
Release of Claims DI-137
Closeout/With Final Invoice
Warranty Letter
Closeout/With Final Invoice

4. SAFETY

4.1. The contractor shall comply with all pertinent provisions of the Occupational Safety and Health Administration (OSHA) Standards, 29 CFR 1910 and provide all necessary supervision, safety protection devices, and certified personal protective equipment (ANSI etc.), required for complete and safe operations on site in accordance with OSHA guidelines. All OSHA requirements may be obtained without cost to the general public at www.osha.gov. NPS will request from contractor any pertinent safety communication, certifications or required trainings for any employee(s) engaged in work that require such. Protective measures shall prevent injury to the public, Federal employees, contractors, visitors, Contractor’s employees, and damage to or contamination of surrounding property and/or the environment.

4.2. All tools/machinery/equipment/vehicles shall be safeguarded from the public. Tools/machinery/equipment/vehicles shall not be left unattended. All tools/equipment shall not be allowed to lie around except in the immediate work area. Any tools not in immediate use shall be staged or stowed in such manner so as not to create a hazard. The government and contractor will agree on delineating the work area around the project.

4.3. The Contracting Officer (CO) or Project Manager may include additional safety measures or procedures if determined necessary or required by other Federal, State, or local law, or park policy.

4.4. Contractor shall provide a comprehensive site-specific safety plan for approval before any work begins. An onsite qualified Safety Representative shall be identified including contact information.

4.5. Traffic Control (If Applicable):

4.5.1. The contractor is responsible for placing warning signs to warn the public of any work area or closed areas. Whether this is through signs, cones, flagger, labels or danger signals, the public or employees need to be fully aware of the risk associated with the contractor’s work.

4.5.2. Maintain open traffic on Park roads outside of the work closure to the greatest extent possible. Temporary traffic delays shall be kept to the minimum and only as necessary. Limit traffic impacts to 10 minutes maximum for each delay period, unless otherwise authorized by the COR.

4.6. Staging and Access:

4.6.1. All work, parking of vehicles, equipment, materials, and all other operations in connection with this contract shall be confined to the specified hours and stagging/work areas designated and approved in writing by the CO and/or COR.

4.6.2. Temporary stagging and storage locations shall be coordinated with the COR 14 calendar days in advance of work

4.6.3. No overnight parking in the park is authorized unless prior approval is requested and received in writing from the COR--NO EXCEPTIONS. Violators will be towed at the Contractor’s expense.

4.6.4. Confine on-site material and equipment for storage and laydown equipment in staging or storage areas or other areas specifically designated by the COR.

5. ENVIROMENTAL

5.1. The Contractor shall comply with Executive Order 13834, pertaining to Sustainability, work shall incorporate the following:

5.1.1. Reduce waste and implement recycling programs for construction and demolition materials whenever possible.

5.2. The Contractor shall comply with all Federal, State and Local government regulations pertaining to waste disposal, recycling and hazardous material use, storage, and disposal.

5.2.1. Materials and chemicals shall be stored, used, and disposed of in such a manner as to not endanger or threaten the environment and the health and safety of Park employees and visitors.

5.3. The Contractor shall have a Hazard Communication Program in place as required by 29 CFR 1910.1200 where Safety Data Sheets (SDS) / Technical Data Sheets shall be obtained by the contractor for all hazardous materials to be used in the performance of this contract. This plan shall be furnished to the NPS prior to the start of work. These SDS’s and an inventory of hazardous materials must be provided to the CO or COR prior to bringing the material on site. SDS shall be maintained at any jobsite where a substance requiring a SDS is being used. It shall also be available in any vehicle carrying such substance while in the Park. These SDS will be available to all employees of the Contractor, employees of the Park, concessionaires and the public when any member of these groups might come in contact with, or be exposed to, any substance requiring a SDS due to its hazardous status.

5.4. Hazardous waste must be re-claimed/captured for recycling by the contractor. Hazardous Waste Manifests shall be submitted prior to final invoice.

5.5. The park has both natural and man-made protected resources. It is the Contractor’s sole responsibility to ensure they are always protected during this project.

5.5.1. The Contractor is responsible for confirming with NPS Staff regarding the identification of these assets prior to the start of work or at any time any questionable or unforeseen items arises. Work shall stop until clarification by the NPS is made.

5.6. Work prescribed in the scope, stated or not, might require work in dangerous conditions including extreme temperatures and environmental conditions, tight or uneven spaces, exposed to chemicals/fumes.

5.7. Erosion, Waste and Sediment Control (If Applicable):

5.7.1. The Contractor is responsible for the design, installation, maintenance and removal of all erosion, waste, and sediment control devices in accordance with all local, state, and federal regulations having jurisdiction, as required for the project.

5.7.2. Prior to project start, submit proposed erosion, waste and sediment control plan for approval by the COR/CO/CS.

5.7.3. Install sediment/refuse barriers and other measures intended to trap sediment or refuse before land disturbance takes place.

5.7.4. Maintain all erosion and sediment control devices to assure continued performance of their intended function. Replace damaged and deteriorated control devices as needed.

5.7.5. During construction, stabilize or protect soil stockpiles, on-site borrow areas, and soil transporting with sediment trapping measures.

5.7.6. When approved by the COR, remove all temporary waste, erosion and sediment control measures within 30 days after final site stabilization or after the temporary measures are no longer needed.

6. CONTRACTORS RESPONSIBLITIES AND REQUIREMENTS

6.1. A written designation of a supervisor(s) and an alternate supervisor(s) with the same qualifications as the proposed supervisor will need to be submitted (see required submittals): The supervisor and/or alternate supervisor is required to be always present on-site during all operations to direct contract personnel and maintain operations. The on-site supervisor MUST:

6.1.1. Be fluent in the English language in order to effectively communicate with the contractor’s employees and/or subcontractors as well as the COR and other Government personnel.

6.1.2. Be available for phone calls during all working hours, and have the authority to stop all work for unsatisfactory performance as directed by the COR.

6.1.3. Possess 5-years verifiable experience and technical competence in work prescribed in 3.1 (Requirements) as well as 2-years supervisory experience, submitted as a resume.

6.1.4. Be responsible for controlling the quality of work and inspecting all completed work to ensure that correct performance requirements are met.

6.2. Communications:

6.2.1. The contractor and the government should always strive to keep open communications about the project. The government will expect the contractor to respond in a timely manner to any communications (e-mail, phone calls, text messages etc.), even if it is just an acknowledgment response.

6.2.2. Timely manner, is being defined as within 72 hours of any type of communication during hours of operation (see section 8)

6.2.3. If the main point of contact (POC) is unavailable (vacation, sick, field work etc.) they need to delegate authority to an alternate POC. There needs to always be a point of contact available in a timely manner during the entirety of the project whether site work is being conducted or not. For planned events where the main POC is unavailable, they need to notify the government within 48 hours of when an event will occur, and an updated delegation of authority.

6.3. The requirements set forth are intended to provide general guidelines for the services that shall be provided by the Contractor. The contractor needs to use their knowledge to understand the project scope and nuisances of work even if not stated in scope. All work performed by the contractor shall be performed in accordance with manufacturers specifications, guidelines and recommendations, industry standards, and commercial practices.

6.4. Provide sufficient trained, certified (up to date pertinent certifications), and experienced manpower and equipment to complete the project within the period of performance. The total daily productive man hour requirements and quantity of personnel necessary to performance of all services specified herein is the sole responsibility of the contractor and shall be quoted accordingly. Davis Bacon Wages shall be utilized.

6.5. Quality workmanship is required at the full performance level of specified work, beginning at the contract start date. The contractor shall be responsible for professional quality, technical accuracy, project coordination, equipment installation, training, disposal of existing equipment, and all other ancillary items required and provide all deliverables that meets the requirements of the NPS.

6.6. Contractor shall take into consideration the existing ancillary equipment, building support systems, and environment, as well as the potential presence of unknown structures, utilities, and ancillary infrastructure to provide a proposal that meets the project objectives.

6.7. Submittals:

6.7.1. The contractor shall maintain a daily work log by filling out completely with pictures, as applicable. The Daily Work Log Form will be provided to them by the Government. The daily work log or approved equivalent shall be submitted to the COR, courtesy copying the CS/CO via email after a week of work and or any time requested by the COR, CS/CO.

6.7.2. The contractor shall also note in the daily work log the presence of any damage or conditions that may affect the contractor ability to perform work. The contractor shall note and report to the COR any issues or problems that arise, which are within the statement of work.

6.8. Provide Submittals and implement them after approved by the CO/COR. A CM 16 Submittal Form shall be used as a cover sheet for every submittal and will be provided by the Government to the contractor at award. Multiple submittals may be listed on a single CM 16 submittal form.

6.9. Contractor will be required submit all pertinent manufacturer’s data for all equipment, components, and materials BEFORE install occurs. Pertinent data could include installation, operations and maintenance manuals, product data and warranty information. All data shall be annotated to show the specific material identification information, catalog number, type, color, and size of each item.

6.10. All work performed for the performance of this contract must carry a minimum one-year warranty from the date of final inspection.

6.11. Submit a construction schedule no later than 14-days after project award and update it as the project progresses to reflect the most current timeline (two-week look ahead). Include a revised Construction Work Schedule in all pencil copies and attached to all payment applications. Invoices shall be rejected if this document is not attached.

6.12. Contractor Employee Conduct:

6.12.1. The Contractor’s employees shall conduct themselves in a professional, orderly, and safe manner will on the job site. A contractor’s employee shall be subject to removal from the premises upon determination by the Contracting Officer that such action is in the best interests of the Government. Such removal from the job site or dismissal from the premises shall not relieve the Contractor of the requirement to provide sufficient personnel to perform the service as specified.

6.12.2. Rudeness, fighting, being under the influence of alcohol and/or drugs or bringing and/or consuming alcohol and/or drugs, gambling, soliciting, stealing, and any immoral or otherwise undesirable conduct shall not be permitted on the job site. Any employee engaging in such conduct shall be immediately removed from the job site.

6.12.3. Music being played/listened to at the job site shall be kept to a minimum and at the discretion of the COR to determine if it is appropriate for the work site.

6.13. Photographs, social media posts, online content, or any form of communication is strictly prohibited regarding all aspects of this requirement unless authorized in writing by the COR.

6.14. In instances where the contractor finds pre-existing conditions or damage to park resources that may reflect upon the quality of the work or cause undue liability, the contractor shall not start work until the contractor and COR have agreed on the responsibility for these pre-existing conditions.

7. GOVERNMENT PROVIDED INFORMATION

7.1. Forms:

7.1.1. CM-16 Submittal Form

7.1.2. Daily Work Log

7.2. Links to Pertinent Information Related to This Work:

Management - Assateague Island National Seashore (U.S. National Park Service) (nps.gov)

MUTCD

OSHA

Code of Federal Regulations (CFR)

ANSI

Federal, State and Local Environmental Laws, Regulations, and Policies

7.3. Attachments:

8. HOURS OF OPERATION

8.1. Construction operations shall be conducted between the hours of 7:00 am –3:30 pm ET, Monday – Friday, except when there’s a federal government holidays (Federal Holidays), local or national emergencies, administrative closings, or similar Government directed facility closings.

8.2. The contractor will be notified by the COR (7) business days in advance, if possible, for days there shall be no work conducted outside of regularly scheduled federal holidays.

8.3. All work outside of the designated performance hours are required to be requested three (3) business days in advance, in written form, by the Contractor to the Contracting Officer’s Representative (COR) for approval.

8.4. Access to the work site may be limited at times due to unforeseen weather and/or tidal events. The government will not be liable for any burdens associated with unforeseen circumstances.

9. ADDITIONAL APPLICABLE REGULATIONS AND POLICIES

9.1. All supplies, materials, equipment, processes, and tools are subject to the submittal process and approval by the COR/CO/CS. Supplies, materials, tools, processes, and equipment that doesn’t meet the project requirements set forth in this contract could be rejected. Contractor shall take this into consideration during the bidding process.

9.2. Only changes as approved in writing by the CO shall be deemed authorized. Any other form of changes performed under this contract that are unauthorized shall be the burden of the Contractor and shall be at no cost to the Government.

9.3. Damages and liability for any loss (tangible or intangible) during the performance of this contract caused by the contractors’ operations:

9.3.1. The contractor shall assume full responsibility for any and all damages or claims for damage resulting from injury to persons, property, or equipment, which might result from any work performed under this contract.

9.3.2. All damage resulting from such operations shall be repaired to its original condition to the satisfaction of the COR at no additional cost to the Government.

9.3.3. The contractor shall take all immediate actions necessary to prevent further damage.

9.3.4. All losses and/or damages shall be reported to the COR, within two (2) hours of any loss and/or damage being determined and before leaving the area loss occurred. Contractor shall provide a detailed written documentation of the loss and/or damage to the CO and COR within 24 hours of occurrence.

9.3.5. The contractor is responsible for all costs associated with reported damages and/or losses to persons, property or environment that occur because of the contractor’s negligence.

9.3.6. Liquidated damages, per FAR 11.5 – Liquidated Damages, may or may not apply to this contract, please refer to contracting documents for more information.

END OF STATEMENT OF WORK