B08 Solicitation_Attachment 1 - SOW for LIBO HVAC Replacements.pdf
PDF 4 MB Posted
- Attached to
- LIBO- Replacement of Multiple HVAC Systems Federal contract opportunity
- Solicitation number
- 140P6220Q0045
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6220Q0045.pdf | ||
| B08 Solicitation_Attachment 4 - Instructions for Submission of Quotation.pdf | ||
| B08 Solicitation_Attachment 2 - DoL SCA Wage Determination.pdf | ||
| B08 Solicitation_Attachment 3 - Tech Fin and PP Statement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 140P6220Q0045 ATTACHMENT 1 Page 1 of 44
Lincoln Boyhood National Memorial
Lincoln City, IN 47552
Replace HVAC Systems in 5 Park Units
PMIS: 231834, 231887, 245354, 237372, 239260,
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
April 2020
RFQ 140P6220Q0045 ATTACHMENT 1 Page 2 of 44
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 General Requirements
DIVISION 23
SECTION 235416.13 – GAS-FIRED FURNACES WITH COOLING
SECTION 238126 - DUCTLESS SPLIT-SYSTEM AIR-CONDITIONERS
SECTION 238123 - CURATORIAL STORAGE-ROOM SPLIT SYSTEM
SUBMITAL CHECKLIST and PHOTOGRAPHS
1. Appendix A: Photos
RFQ 140P6220Q0045 ATTACHMENT 1 Page 3 of 44
SECTION 01 10 00
DIVISION 1 GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: Lincoln Boyhood National Memorial is located in Lincoln City, IN. The National Park Service began operation of the location in the early 1960’s. The structures affiliated with this project remain intact and accessible. The HVAC systems within the structures will be replaced entirely with the exception of the existing, original heating/cooling duct systems.
1.2 Work Covered by the Contract Documents: see Division 23 Sections 235416.13, 238126, 238123
A. Project Location:
Lincoln Boyhood National Memorial 3027 E South Street Lincoln City, IN 47552
B. Work consists of: The project will consist of replacing 6 HVAC systems at the following locations: Quarters 2
Housing (Q-2), Quarters 4 Housing (Q-4), Maintenance Staff Office (MX), Administration Building (ADM), Curatorial Office Complex (CUR).
1. Unless specifically noted, all HVAC systems will be from the same manufacturer and whenever possible, the same model number. The installation and operation of all HVAC systems will be alike for ease of preventative, recurring, and corrective maintenance operations. Common accessories such as thermostats, air filters, and piping will be of the same manufacturer and model whenever possible. The contractor may offer different brands of heating and cooling units, but each component must be the same brand, i.e., furnaces will be the same manufacturer, cooling units will be the same manufacturer.
EXCEPTIONS: the “mini-split” heat pump unit to be installed in the Curatorial Office location need not be the same brand as the other locations. The mini-split unit will be of comparable quality to the existing unit and provide comparable AFUE (AFUE 96-98) and SEER (17 minimum) numbers as to all units. The ceiling mounted HVAC unit in the Curatorial Artifact Storage room will be comparable to the current model (Liebert) installed in the room. The unit must have automatic humidity and climate control features unique for the storage of historical artifacts. In addition to the climate control features, the unit must be ceiling mounted as floor space within the room is not available.
2. All current vent and duct systems will be utilized. Current wall or roof penetrations will be reutilized if possible. All Plenums and flexible duct connections will be replaced with new.
All cooling coil units to be replaced. All vent and duct systems will be professionally cleaned before installing new HVAC units. All units will have condensate filters installed in the condensate drain systems to remove toxic impurities entering into the sanitary sewer system or ground. Contractor will be responsible for all utility hook-ups (gas, electric, plumbing).
RFQ 140P6220Q0045 ATTACHMENT 1 Page 4 of 44
3. The requirements for replacement will be specified in the three Division 23 sections:
SECTION 235416.13 – GAS-FIRED FURNACES WITH COOLING
SECTION 238126 - DUCTLESS SPLIT-SYSTEM AIR-CONDITIONERS
SECTION 238123 - CURATORIAL STORAGE-ROOM SPLIT SYSTEM
C. All work will be performed under a single contract.
D. Period of Performance: Work shall be completed within approximately 87 calendar days of contract award. 40 days for shop drawings and material delivery and 40 days on site to substantial completion, 7 days for final completion. Due to COVID-19 considerations in 2020, the project start date will be determined by the CO in consultation with project COR. Estimated start date: mid-late summer 2020.
ITEM 2 - EXISTING UTILITIES
2.1 Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation if required.
A. All existing utility penetrations through roofs, walls, or foundations for HVAC electrical, gas, or drainage uses will be re-utilized as much as possible. Existing penetrations may be expanded to fit. New penetrations will be approved by the COR prior to work. All new, existing, or unused penetrations will be repaired to match or blend with current interior and exterior characteristics.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
2.3.1 Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2.3.2 Hours for Utility Shutdowns: Shutdowns shall not exceed 8 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/piro/learn/management/suptcompendium.htm
A. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
https://www.nps.gov/piro/learn/management/suptcompendium.htm
RFQ 140P6220Q0045 ATTACHMENT 1 Page 5 of 44
C. Pubic Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
Pubic Use of Site: This is a non- public use area, but contactor will need to be aware that the public may enter the site infrequently.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the Contracting Officer. Submit requests for work outside of the stated normal business hours to the Contracting Officer for approval at least 48 hours in advance of the work.
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction site limits and staging areas. Do not exceed portions of Project site beyond areas in which the HVAC replacement work will be conducted.
B. Limits: All work will be limited to a 25-foot perimeter around exterior of the proposed work site and within the limits of existing HAVC systems on the interior of the building.
C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
D. Security and Protection facilities installation:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. All materials, parts, and system components associated with HVAC system removal or installation should be hand carried or wheeled into the units with the least amount of landscape disturbance as possible. Contractor may be required to use landscape protection barriers such as plywood sheets or similar ground protection methods.
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project area as identified by the COR.
3.5 Preservation of Natural Features: N/A
3.6 Hauling Restrictions: Match State and County road requirements for all park work/access.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 6 of 44
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all hazardous rubbish. Do not allow rubbish to accumulate. Provide onsite containers for collection of rubbish and dispose of it at frequent intervals during progress of work.
B. Dispose of waste materials legally using dumpsters provided by the contractor.
C. During construction, recycle or salvage at least 50 percent of the non-hazardous materials from construction activities, where markets or recycling opportunities exist. To the greatest extent possible, provide products and materials that have a lesser or reduced effect on the environment considering raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, and/or disposal of the products. Contractor will provide proof of recycling with documentation such as weigh bills and/or receipts from approved recycling centers. Non-recycled materials will be disposed of in a legal manner in local approved landfills or waste facilities. Contractor will provide proof of non-recycled materials with documentation such as weigh bills and/or receipts from approved disposal centers.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO/COR.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
3.9 Photo Documentation:
All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days or as approved by COR.
A. Existing Condition Images: Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
B. Construction Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with enough overall field view to show location and then details.
2. Maintain organized index for photos with date, description, etc..
RFQ 140P6220Q0045 ATTACHMENT 1 Page 7 of 44
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
As a minimum, conduct one weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one day after the meeting.
A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).
B. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
i. Immediately report all spills of hazardous materials to the park.
ii. Maintain a spill emergency response kit.
iii. Train employees how to respond to a spill and use the emergency response kit.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract. (Block 11 of the SF 1442 or relevant section of the award document)
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids. All bidders will be held to have the same knowledge concerning the site and the on-ground conditions as if they had inspected the job site.
No change orders will be approved for work obvious during a site visit. Please see FAR 52.236-27 - Site Visit (Construction).
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, which may be used in the Construction Specifications or Special Provisions, refer to the organizations and specifications of the organizations may be found at the below https://www.nps.gov/orgs/1671/upload/NPS-Reference_Standards-Sect-01-42-00.pdf
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.
A. It is the Contractor's responsibility to provide hard hats and safety goggles to all those working on or visiting the site if requested. Contractor is expected to supply and use all standard PPE associated with HVAC replacement operations. All necessary personal protective equipment to be in good repair at all times.
7.2 Submittals:
A. Accident Prevention Program: At the preconstruction conference submit for approval an accident prevention program. The program shall include:
1. Name of responsible supervisor to carry out the program
2. First aid procedures https://www.nps.gov/orgs/1671/upload/NPS-Reference_Standards-Sect-01-42-00.pdf
RFQ 140P6220Q0045 ATTACHMENT 1 Page 8 of 44
3. Training, both initial and continuing
4. Planning for possible emergency situations
5. Contractor to identify nearest location of medical facility for emergencies
6. Recognition that work will be performed in remote areas with limited communication or cell phone coverage
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the Contracting Officer or designee as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Protective Equipment: It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources.
Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE: See FAR 52.236-26
ITEM 9 - SUBMITTALS
9.1 General Submittal Procedures:
A. General: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual specific sections.
A. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. All CM-16 transmittal forms will be submitted to the parks COR for review.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 9 of 44
B. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
C. Preconstruction Conference Submittal: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
1. Construction Schedule.
2. A comprehensive breakdown of the Schedule of Values.
3. Accident Prevention Plan (see section 7 of this document).
4. A list of Subcontractors for this project.
5. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
6. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
7. Quality Control Plan.
8. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
9. Contractors Commissioning Plan.
9.2 Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet.
A. Product Data: QUARTERS NUMBER 2 AND 4, ADMINISTRATION, MAINTENANCE OFFICE - FORCED AIR
HEATING AND COOLING SYSTEMS
B. Product Data: CURATORIAL STORAGE ROOM - SPLIT SYSTEM, HEATING AND COOLING SYSTEM
C. Product Data: CURATORIAL OFFICE - HEAT PUMP (MINI-SPLIT) SYSTEM, HEATING AND COOLING SYSTEM
D. Product Data: ALL UNITS - AC unit and condenser
E. Product Data: ALL UNITS - Intake and exhaust venting
F. For submittals specified above, forward submittals to Contracting Officer at least 15 days before need for approval
(depends on length of project).
G. After approving submittals, Contracting Officer will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: Refer to FAR 52.211-6 - If an item in this solicitation is identified as “brand name or equal” or lists more than 3 manufacturers, the purchase description reflects the characteristics and level of quality that will satisfy the Government’s needs. The salient physical, functional, or performance characteristics that “equal” products must meet are specified in the solicitation or relevant specification.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 10 of 44
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that Contractor:
1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
2. Will provide the same warranties for the proposed item as for the item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Progress Schedules: As soon as possible after Notice of Award and before beginning any work, submit Progress Schedule. Contracting Officer will review the Progress Schedule for format and content. . Submit one electronic copy of Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted. The following information must accompany submission of progress schedules prior to processing any pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values will be provided by the Contracting Officer.
ITEM 10 – TEMPORARY SERVICES
10.1 Fire Prevention and Protection:
A. Hazard Control: Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 11 of 44
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
11.3 Substantial Completion and Final Inspection: Submit written certification that project is substantially complete, and a final inspection must be requested to the Contracting Officer in writing. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. Submit written certification that project is substantially complete, and a final inspection must be requested to the
CO and COR in writing. The COR will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
B. If the work is determined to be substantially complete, following the final inspection, the COR will prepare a Punch List and issue a Letter of Substantial Completion.
C. If the work is not determined to be substantially complete following the final inspection, the Contracting Officer will notify Contractor in writing. Contractor shall request a new final inspection after completing the work. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
D. Contractor shall complete the Punch List within 30 calendar days, documented.
E. If Contracting Officer determines that the work is not substantially complete; he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
F. If Contractor completes all items of work on the Punch List and all contractually required items, Contracting Officer will issue Letter of final acceptance of work.
G. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for reinspection costs in accordance with the Inspection of Construction contract clause.
H. Disposition of any permits and warranties required by the specifications in this section.
11.4 Acceptance of the Work: After all deficiencies have been corrected, a Letter of Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of Substantial Completion.
B. Provide All Warranty information of products installed organized by Division. All contact information, extents and conditions shall be clearly noted as well as date of overall project Substantial Completion.
C. Information shall include operation and maintenance manuals for each warranted material.
End of Section
RFQ 140P6220Q0045 ATTACHMENT 1 Page 12 of 44
SECTION 235416.13
GAS FIRED FURNACE WITH COOLING
GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SCOPE OF WORK
A. Project Location: Lincoln Boyhood National Memorial, 3027 E South St, Lincoln City, IN 47552
B. Building(s) Name/Identifier: Section 235416.13 will consist of replacing 4 HVAC systems at the following locations: Quarters 2 Housing (Q-2), Quarters 4 Housing (Q-4), Maintenance Staff Office (MX), Administration Building (ADM).
1. See pictures of current HVAC to be replaced in Attachment 1, Work Site Locations. Exterior pictures of structures where work will be performed are included. Each unit where work will take place will be reviewed at the Pre-Installation Conference and during Contractor Site Visits.
C. Unless specifically noted, all HVAC systems will be from the same manufacturer and whenever possible, the same model number. Output BTU and tonnages may be the same for all 4 units. Recommended numbers are 80,000 BTU for heating and 3 ton condenser units for cooling (approx. 45,000 BTU cooling). The installation and operation of all HVAC systems will be alike for ease of preventative, recurring, and corrective maintenance operations. Common accessories such as thermostats, air filters, and piping will be of the same manufacturer and model whenever possible. The contractor may offer different brands of heating and cooling units, but each component must be the same brand, i.e., furnaces will be the same manufacturer, cooling units will be the same manufacturer. All systems will be of comparable quality to the existing unit and provide the following performance values: AFUE (AFUE 95-98) and SEER (17 minimum) for all units.
1. All current vent and duct systems will be utilized. Current wall or roof penetrations will be reutilized if possible. All Plenums and flexible duct connections will be replaced with new. All cooling coil units to be replaced. All vent and duct systems will be professionally cleaned before installing new HVAC units. All units will have condensate filters installed in the condensate drain systems to remove toxic impurities entering into the sanitary sewer system or ground. Contractor will be responsible for all utility hook-ups (gas, electric, plumbing).
D. The contractor will measure all structures before installation to determine proper sizing of all HVAC units and structures. The contractor will review all HVAC unit recommendations with the COR before beginning the project.
E. The contractor will fully demo one existing HVAC unit and accessories and install the new HVAC unit and accessories in the same structure or location before beginning another demo and installation in another structure. The COR will determine the order of demo/installation prior to the contractor beginning work.
Whenever possible, the contractor will re-use all piping wall and roof penetration holes. The COR will approve for re-use all exterior pads on a structure by structure basis. Pads to be replaced or re-used will be identified at the Pre-installation Conference.
F. Section Includes:
1. Gas-fired, condensing furnaces and accessories complete with controls.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 13 of 44
2. Air filters.
3. Condensing Units, Coils, and Refrigeration components.
G. Demolition Work Includes:
1. Removal of existing gas-fired furnaces and plenum, A/C coil, and condensing units.
2. Removal of natural gas or propane pipe back to the main point of connection. Valve and cap pipe if not reused.
3. Evacuate and removal of refrigeration piping completely. Disconnect and remove condensing unit power and control wiring back to the power and control panels.
4. Removal of concrete pad or roof structure supporting condensing unit if not reused.
5. Patch and repair of all wall, ceiling, and floor penetrations to match existing conditions.
6. Repair of existing ductwork and insulation at the point of connection for new equipment.
7. As described in Part 1 – General, Section 1.2 Scope of Work, sub-section E: The contractor will fully demo one existing HVAC unit and accessories and install the new HVAC unit and accessories in the same structure before beginning another demo and installation in another structure. The COR will determine the order of demo/installation prior to the contractor beginning work.
8. Contractor will remove and dispose of all equipment and materials that are replaced according to local/state/federal regulations. Contractor will supply proof that hazardous waste has been disposed of according to state and federal laws by providing receipts of disposal.
H. Additional work as described by the NPS Representative at a Pre-installation Conference conducted at the Project Location.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Product Data: Supply all product data as listed below. “Current” is listed to describe what us currently in the unit and will be removed. Contractor will use “New Minimum Requirements” for installation purposes.
2. For ease of installation and replacement/repair parts, it is highly recommended that one size of heating unit and one size of cooling unit be installed. The recommendation for these 4 units are: Heating - 80,000 BTU minimum AFUE 97%; Cooling – Minimum 17 SEER, 3 Ton Condenser unit.
3. Quarters 2 (Q-2) – DIMENSIONS: The structure is 36’ (L) X 30’ (W) X 8’ (H) with 2 floors (1080 SF per floor, 2160 SF total. Current: HEATING: Natural Gas, Upflow, 74,000 BTU, AFUE: 92%. COOLING: 3 ton exterior compressor unit, 12 SEER, 3 Ton, single phase 208/230V.
New minimum requirements: Furnace - 80,000 BTU, AFUE 97% min. Cooling – 45,000 BTU, SEER 17+, 3 ton condensing unit
(Q-2, Q-4, Adm, and MX may be the same size, type and model for complete HVAC system (recommended:
furnace: 80,000 BTU AFUE 97% and cooling: 3 Ton 17 SEER)
4. Quarters 4 (Q-4) – DIMENSIONS: The structure is a single story 60’ (L) X 25’ (W) X 8’ (H), 1500 SF.
Current: HEATING: Natural Gas, Upflow, 60,000 BTU AFUE 95%. COOLING: 2.5 ton exterior compressor unit, 13 SEER, single phase 208/230V.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 14 of 44
New minimum requirements: Furnace - 80,000 BTU, AFUE 97% min. Cooling – 45,000 BTU, SEER 17+, 3 ton condensing unit
(Q-2, Q-4, Adm, and MX may be the same size, type and model for complete HVAC system (recommended:
furnace: 80,000 BTU AFUE 97% and cooling: 3 Ton 17 SEER)
5. Administration (Adm) – DIMENSIONS: The structure is a single story 60’ (L) X 25’ (W) X 8’ (H), 1500 SF.
Current: HEATING: Natural Gas, Upflow, 60,000 BTU AFUE 95%. COOLING: 2.5 ton exterior compressor unit, 13 SEER, single phase 208/230V.
New minimum requirements: Furnace - 80,000 BTU, AFUE 97% min. Cooling – 45,000 BTU, SEER 17+, 3 ton condensing unit
(Q-2, Q-4, Adm, and MX may be the same size, type and model for complete HVAC system (recommended:
furnace: 80,000 BTU AFUE 97% and cooling: 3 Ton 17 SEER)
6. Maintenance (MX) – DIMENSIONS: The structure is a single story with attached semi-heated garage.
Office area 25’ (L) X 22’ (W) X 8’ (H), Garage 25’ (L) X 13.5’ (L) X 11’ (H), Total SF 890. Current: HEATING:
Natural Gas, Upflow, 65,000 BTU AFUE 80%. COOLING: 2.5 ton exterior compressor unit, 2.5 ton, 12 SEER, single phase 208/230V.
New minimum requirements: Furnace - 80,000 BTU, AFUE 97% min. Cooling – 45,000 BTU, SEER 17+, 3 ton condensing unit
(Q-2, Q-4, Adm, and MX may be the same size, type and model for complete HVAC system (recommended:
furnace: 80,000 BTU AFUE 97% and cooling: 3 Ton 17 SEER)
7. In addition to all maintenance plans and guides, the contractor will provide 30-60 minutes of on-site training per unit installed (6 training sessions total). The training will encompass, but is not limited to: unit start up and operations, preventative and recurring maintenance, troubleshooting, electronic component operations, and general knowledge applicable to each unit. The contractor will provide at least 1 qualified HVAC Technician, and the park may supply up to 3 persons per each training event.
B. Shop Drawings:
1. All material submittals shall clearly indicate proposed items, capacities, characteristics, and details in conformance with contract documents. The submittals will include definitions of abbreviations and explanations/descriptions of technical terminology.
2. Include details of equipment assemblies. Indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection.
3. Include diagrams for power, signal, and control wiring.
1.4 INFORMATIONAL SUBMITTALS
A. Sample Warranty: For special warranty.
1.5 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For each furnace to include in emergency, operation, and maintenance manuals.
1. Include the following:
a. Furnace and accessories complete with controls.
b. Air filter.
c. Condensing Unit, Coil, and Refrigeration components.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 15 of 44
1.6 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Disposable Air Filters: Furnish two complete sets per unit.
1.7 QUALITY ASSURANCE
A. ASHRAE Compliance: Applicable requirements in ASHRAE 62.1, Section 5 - "Systems and Equipment" and Section 7 - "Construction and Startup."
B. ASHRAE/IES 90.1 Compliance: Applicable requirements in ASHRAE/IES 90.1, Section 6 - "Heating, Ventilating, and Air-Conditioning."
C. Comply with NFPA 70.
1.8 WARRANTY
A. Special Warranty: Manufacturer agrees to repair or replace the following components of furnaces that fail in materials or workmanship within specified warranty period:
1. Warranty Period, Commencing on Date of Substantial Completion:
a. Furnace Heat Exchanger: 20 years.
b. Integrated Ignition and Blower Control Circuit Board: Five years.
c. Draft-Inducer Motor: Five years.
d. Refrigeration Compressors: 5 years.
e. Evaporator and Condenser Coils: Five years.
PRODUCTS
1.9 ASSEMBLY DESCRIPTION
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a qualified testing agency, and marked for intended location and application.
1.10 GAS-FIRED FURNACES, CONDENSING
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following or approved equal:
1. Bryant Heating & Cooling Systems; a unit of United Technologies Corp.
2. Carrier Corporation; a unit of United Technologies Corp.
3. Lennox Industries, Inc.; Lennox International.
4. Rheem Manufacturing Company; Heating and Cooling Products.
5. Ruud Air Conditioning Division.
6. Trane.
7. Goodman.
http://www.specagent.com/Lookup?ulid=10016 http://www.specagent.com/Lookup?uid=123457150152 http://www.specagent.com/Lookup?uid=123457150153 http://www.specagent.com/Lookup?uid=123457150159 http://www.specagent.com/Lookup?uid=123457150161 http://www.specagent.com/Lookup?uid=123457150162
RFQ 140P6220Q0045 ATTACHMENT 1 Page 16 of 44
8. Other Approved Equals.
B. Cabinet: Galvanized steel.
1. Cabinet interior around heat exchanger shall be factory-installed insulation.
2. Lift-out panels shall expose burners and all other items requiring access for maintenance.
3. Factory paint external cabinets in manufacturer's standard color.
4. Airstream Surfaces: Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1.
C. Fan: Centrifugal, factory balanced, resilient mounted, direct drive.
1. Special Motor Features, ECM: Electronically controlled motor (ECM) controlled by integrated furnace/blower control.
D. Type of Gas: Natural.
E. Heat Exchanger:
1. Primary: Stainless steel.
2. Secondary: Stainless steel
F. Burner:
1. Gas Valve: 100 percent safety modulating main gas valve, main shutoff valve, pressure regulator, safety pilot with electronic flame sensor, limit control, transformer, and combination ignition/fan timer control board.
2. Ignition: Electric pilot ignition, with hot-surface igniter or electric spark ignition.
G. Gas-Burner Safety Controls:
1. Electronic Flame Sensor: Prevents gas valve from opening until pilot flame is proven; stops gas flow on ignition failure.
2. Flame Rollout Switch: Installed on burner box; prevents burner operation.
3. Limit Control: Fixed stop at maximum permissible setting; de-energizes burner on excessive bonnet temperature; automatic reset.
H. Combustion-Air Inducer: Centrifugal fan with thermally protected motor and sleeve bearings pre-purges heat exchanger and vents combustion products; pressure switch prevents furnace operation if combustion-air inlet or flue outlet is blocked.
I. Furnace Controls: Solid-state board integrates ignition, heat, cooling, and fan speeds; adjustable fan-on and fan-off timing; terminals for connection to accessories; diagnostic light with viewport.
J. Accessories: Curatorial Archive Storage unit shall have an automatic humidity control unit installed with applicable thermostatic humidity sensor controls mounted according to manufacturer suggested SF guidelines for unit.
1. Combination Combustion-Air Intake and Vent: PVC plastic fitting to combine combustion-air inlet and vent through outside wall. All current roof or wall penetrations to be re-utilized if possible. Material to be used to comply with manufacturer suggested combustion-air intake and vent material.
2. CPVC Plastic Vent Materials:
RFQ 140P6220Q0045 ATTACHMENT 1 Page 17 of 44
a. CPVC Plastic Pipe: Schedule 40, complying with ASTM F441/F441M.
b. CPVC Plastic Fittings: Schedule 40, complying with ASTM F438, socket type.
c. CPVC Solvent Cement: ASTM F493.
3. PVC Plastic Vent Materials:
a. PVC Plastic Pipe: Schedule 40, complying with ASTM D1785.
b. PVC Plastic Fittings: Schedule 40, complying with ASTM D2466, socket type.
c. PVC Solvent Cement: ASTM D2564.
K. Capacities and Characteristics:
1. Airflow Configuration: Upflow
a. Q-2, Q-4, Adm, MX – Upflow
2. Gas:
a. Type: Natural
b. Venting Type: Power venter with combustion-air intake
c. Efficiency AFUE: ALL UNITS: 97% - 98% (97% Minimum) (see 1.4 Action Submittals, note 2)
d. Input BTU: Btu/h. Q-2: 80K, Q-4: 80K, ADM: 80K, MX: 80K (see 1.4 Action Submittals, note 2)
e. Heat Output BTU: Btu/h. Q-2: 76-78K, Q-4: 76-78K, ADM: 76-78K, MX: 76-78K (see 1.4 Action
Submittals, note 2)
f. Gas Connection Size: 1/2” n.p.s., or minimum required for new unit.
g. Combustion-Air Connection Inlet Size: 3” or minimum required for new unit.
h. Combustion-Air Inlet Material: PVC unless new units require specified type of combustion air inlet material.
i. Heat-Exchanger Condensate Drain Size: 3/4” n.p.s., unless new unit specifies alternate size.
j. Vent Connection Size: 3” unless new unit specifies alternate size.
k. Vent Material: PVC unless new units require specific type of vent material (see J 1, Combustion-Air
Intake and Vent).
3. Fan & Furnace Electrical Connection – all units to comply with manufacturer suggested installation size and types – see 1.3 Action Submittals for individual unit requirements:
a. Airflow: 1200 cfm
b. External Static Pressure: 0.5 inches wg.
c. Motor:
1) Size: 1/2 horsepower minimum or per new unit requirements
2) Speed: Variable.
d. Volts: 120.
e. Phase: Single.
f. Hertz: 60.
g. Full-Load Amperes (FLA): 7.9.
h. Maximum Overcurrent Protection (MOP): 15.
1.11 THERMOSTATS
A. Controls shall comply with requirements in ASHRAE/IES 90.1, Section 6 - "Heating, Ventilating, and Air Conditioning."
B. Solid-State Thermostat: Wall-mounted, programmable, microprocessor-based unit with automatic switching from heating to cooling, preferential rate control, seven-day programmability with minimum of four temperature presets per day, and battery backup protection against power failure for program settings. Thermostats will be compatible with all new heating and cooling units.
C. Control Wiring: Balanced twisted-pair cabling.
1. Description: Screened and shielded twisted pairs (F/FTP), No. 24 AWG, 100 ohms, four pair.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 18 of 44
2. Cable Jacket Color: Blue.
1.12 AIR FILTERS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following or approved equal for each HVAC system. Whenever possible, filter size and type should be the same for all systems:
1. Aprilaire; Research Products Corp.
2. Filtrete Home Filtration Products; a 3M brand.
3. General Filters, Inc.
4. Permatron Corporation.
B. Disposable Filters (complete filter will be disposed of) or Washable Filters (hard frame, filter can be cleaned and used numerous times): 2” thick fiberglass media with ASHRAE 52.2 MERV rating of 8 or higher, in constructed sheet metal filter frame.
1.13 REFRIGERATION COMPONENTS
A. General Refrigeration Component Requirements:
1. All refrigeration compressor, coils, and specialties shall be designed to operate with R-410A Refrigerant when possible.
2. Refrigeration components and cooling system to be by the same manufacturer as the furnace with published cooling performance data as an assembly.
3. Energy Efficiency: Equal to or greater than prescribed by ASHRAE/IES 90.1.
B. Refrigerant Coil: Copper tubes mechanically expanded into aluminum fins. Comply with AHRI 210/240. Match size with furnace. Include condensate drain pan with accessible drain outlet complying with ASHRAE 62.1.
1. Refrigerant Coil Enclosure: Steel, matching furnace width with access panel and flanges for integral mounting on furnace cabinet and galvanized sheet metal drain pan coated with black asphaltic base paint.
C. Refrigerant Line Kits: Annealed-copper suction and liquid lines factory cleaned, dried, pressurized with nitrogen, sealed, and with suction line insulated. Provide in standard lengths for installation without joints, except at equipment connections.
1. Flexible Elastomeric: Closed-cell, sponge- or expanded-rubber materials. Comply with ASTM C534/C534M, Type I, 1 inch (25 mm) thick.
D. Air-Cooled Compressor-Condenser Unit:
1. Casing: Steel, finished with baked enamel, with removable panels for access to controls, weep holes for water drainage, and mounting holes in base. Provide brass service valves, fittings, and gage ports on exterior of casing.
2. Compressor: Hermetically sealed scroll type.
a. Crankcase heater.
b. Vibration isolation mounts for compressor.
c. Compressor motor shall have thermal- and current-sensitive overload devices, start capacitor, relay, and contactor.
d. Two-speed compressor motors shall have manual-reset high-pressure switch and automatic-reset low-pressure switch.
e. Refrigerant: R-410A.
http://www.specagent.com/Lookup?ulid=9880 http://www.specagent.com/Lookup?uid=123457150124 http://www.specagent.com/Lookup?uid=123457150125 http://www.specagent.com/Lookup?uid=123457150126 http://www.specagent.com/Lookup?uid=123457150127
RFQ 140P6220Q0045 ATTACHMENT 1 Page 19 of 44
3. Refrigerant Coil: Copper tube, with mechanically bonded aluminum fins, complying with AHRI 210/240, and with liquid sub-cooler.
4. Fan: Aluminum-propeller type, directly connected to motor.
5. Motor: Permanently lubricated, with integral thermal-overload protection.
6. Low Ambient Kit: Permits operation down to 45 deg F (7 deg C).
7. Mounting Base: Polyethylene or Concrete – see 3.2, line f, “Installation”.
E. Capacities and Characteristics: Match all refrigerant coil and compressor-condenser unit capacities and characteristics to unit types to be installed, as noted in 1.3 Action Submittals.
1. Refrigerant Coil:
a. Total Cooling Capacity: Btu/h – see action submittal requirements
b. Condensate Drain Size: 3/4” n.p.s. or as manufacturer specified with new unit.
2. Compressor-Condenser Unit:
a. Cooling Energy Efficiency 17 SEER minimum
b. Volts: 208/230
c. Phase: Single
d. Hertz: 60
e. Minimum Circuit Ampacity (MCA): 12.0
f. Maximum Overcurrent Protection (MOP): 20
EXECUTION
1.14 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Examine factory-installed insulation before furnace installation. Reject units that are wet, moisture damaged, or mold damaged.
C. Examine roughing-in for gas and refrigerant piping systems to verify actual locations of piping connections before equipment installation. All existing wall or roof penetrations will be re-used if possible.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
1.15 INSTALLATION
A. Install gas-fired furnaces and associated fuel and vent features and systems according to NFPA 54.
B. Suspended Units: Suspend from structure using threaded rods, spring hangers, and building attachments.
Secure rods to unit hanger attachments. Adjust hangers so unit is level and plumb.
1. Install seismic restraints to limit movement of furnace by resisting code-required seismic acceleration. Refer to local/state building code instructions to confirm seismic requirements
C. Base-Mounted Units: Secure units to substrate. Provide optional bottom closure base if required by installation conditions.
1. Anchor furnace to substrate to resist code-required seismic acceleration. Refer to local/state building code instructions to confirm seismic requirements.
RFQ 140P6220Q0045 ATTACHMENT 1 Page 20 of 44
D. Controls: Install thermostats and humidistats at mounting height of 60 inches (1500 mm) above floor.
E. Wiring Method: Install control wiring in accessible ceiling spaces and in gypsum board partitions where unenclosed wiring method may be used. Conceal control wiring except in unfinished spaces.
F. Install ground-mounted, compressor-condenser components on 4-inch- (100-mm-) thick, reinforced concrete base; 4 inches (100 mm) larger on each side than unit OR install ground-mounted compressor-condenser components on polyethylene mounting base. Coordinate anchor installation with concrete base OR polyethylene mounting base. Mounting base material to be consistent with manufacturer suggested base units for each new unit installed. Contractor shall receive approval by COR before mounting base material is approved.
1.16 PIPING CONNECTIONS
A. Drawings indicate general arrangement of piping, fittings, and specialties. Connect gas piping with union or flange, a drip leg, and appliance connector valve.
B. Install piping adjacent to equipment to allow service and maintenance.
C. Vent and Combustion-Air Connection, Condensing, Gas-Fired Furnaces: Connect plastic piping vent material to furnace connections and extend outdoors. Terminate vent outdoors with a cap and in an arrangement that will protect against entry of birds, insects, and dirt/debris.
1. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.
2. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.
3. Plastic Piping Solvent-Cement Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following:
a. Comply with ASTM F402 for safe-handling practice of cleaners, primers, and solvent cements.
b. CPVC Piping: Join according to ASTM D2846/D2846M, Appendix.
c. PVC Pressure Piping: Join schedule number ASTM D1785 PVC pipe and PVC socket fittings according to ASTM D2672. Join other-than-schedule-number PVC pipe and socket fittings according to ASTM D2855.
4. Slope pipe vent back to furnace or to outside terminal. Vent drains to be installed according to local/state regulations and manufacturer suggested drain installations.
5. Vent and Combustion piping shall be sized according to manufacturer’s…