About this file

This document contains a submittal list template for use in managing construction submittals and estimating review time for a project to repair a rock wall at Whittington Creek for the National Park Service Midwest Region. The template includes sections for identifying the project, listing submittal requirements by specification section and paragraph, and estimating review hours by discipline for action submittals. Review estimates would be used to negotiate the submittal review portion of an architect/engineer's construction services task order. The template also provides guidance on its use during the construction documents and construction phases for submittal tracking and assigning review responsibilities between the construction management representative and architect/engineer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Submittal List with Review Estimate Instructions
National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
DESIGN SERVICES (Construction Documents (CD) Phase)
Responsible Party: Design Architect/Engineer (A/E)
1Enter Park Acronym, Project Management Information System (PMIS) Number, and Project Title.
2Record construction submittal requirements. Complete Specification Section, Paragraph Number, and Description sections. Insert additional rows as required for sections containing multiple submittals.
3In Requirements section, enter X for submittal requirements where applicable. Insert additional columns as needed under Informational or Action. Refer to Specification Section 01 33 23 for clarification. (Action submittals require Government resposive action and Informational submittals do not.) Division 1 Specifications submittals are Information submittals.
4Attach black and white version to Specification Section 01 33 23 in project manual. Delete instructional note on top of page.
CONSTRUCTION SERVICES (Construction Phase)
Responsible Party: Construction Contracting Officer Representative (COR)
1Use Submittal List submitted with Final Construction Documents. Copy/paste submittal information into Submittal List with Review Estimate Template. If amendments issued, adjust submittal requirements as necessary.
2Attach this template to Architect/Engineer (A/E) Construction Services Scope of Services.
3Use Review Estimate to estimate time required for Architect/Engineer to accomplish Action submittal reviews. Enter estimated whole or partial number of hours per discipline.
4Add discipline heading column as required.
5Use total number of hours per discipline at bottom of template and apply hourly rates listed in Indefinite Delivery/Indefinite Quantity (IDIQ) contract (using appropriate option period rates) to formulate Government estimate for submittal reviews.
6Use information from this template to negotiate submittal review portion of Architect/Engineer Construction Services task order.
7Provide template to Construction Management Representative (CMR) to show submittals they are responsible for and submittals to be forwarded to the Architect/Engineer. All Informational submittals will be reviewed by Construction Management Representative.
Responsible Party: Architect/Engineer (A/E)
1Indicate level of effort required for each Action submittal review by entering number of whole or partial hours for each discipline under Architect/Engineer Review Time section.
2All Informational submittals will be reviewed by Construction Management Representative (CMR).
3Use total number of hours per discipline at bottom of template and apply hourly rates listed in Indefinite Delivery/Indefinite Quantity (IDIQ) contract (using appropriate option period rates) to formulate estimate.
4Use this estimate to negotiate submittals review portion of Architect/Engineer Construction Services portion of the task order.

&8&K01+024Submittal List with Review Estimate Instructions | National Park Service (NPS) - Denver Service Center (DSC) &8&K01+024page &P of &N

Template

Submittal List with Review Estimate Template
National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
SUBMITTAL LISTACTION SUBMITTAL
REVIEW ESTIMATE
Park Acronym/Project Management Information System (PMIS) Number:(Complete this portion for Architect / Engineer (A/E)
Project Title:construction service task order negotiation.)
SUBMITTALREQUIREMENTSARCHITECT / ENGINEER REVIEW TIME
(Indicate with X)(Indicate in whole or partial hours.)
INFORMATIONALACTION
SPECIFICATION SECTIONPARAGRAPH NUMBERDESCRIPTIONCERTIFICATIONS OR LABORATORY TESTSREPORTS OR CALCULATIONS
OR PLANMANUFACTURER DATA
AND INSTRUCTIONSOTHERSAMPLESSHOP DRAWINGSMANUFACTURER DATA
AND INSTRUCTIONSOTHERARCHITECTCIVIL ENGINEERSTRUCTURAL ENGINEERMECHANICAL ENGINEERELECTRICAL ENGINEERPROJECT MANAGER COORDINATIONLANDSCAPE ARCHITECT
01 10 009.1.CGENERAL REQUIRMENTS
Preconstruction Conference Submittal:
Letter designating Project SuperintendentX
Construction ScheduleX
Schedule of ValuesX
Accident Prevention (Safety) PlanX
list of SubcontractorsX
statements from subcontractors...compliance...X
Quality Control PlanX
Waste Management PlanX
Water Control PlanX
List of Required Construction PermitsX
3137191.4BouldersXX
3137191.4Grout Mix DesignX
3137191.4Fly AshX
3137191.4AdmixturesX
3137191.4Bonding AgentX
3137191.4Curing CompoundX
3137191.6Grout Batch TicketX
3137193.1Water Control PlanX
3137193.1Grout Strength Test ResultsX
3292001.4Certification of Grass SeedX
3292001.4Turf Maintenance RecommendationsX
C014Ground Protection MatsX
C03CFilter SocksX

Total: 0 0 0 0 0 0 0