B08_Solicitation_(Attach_1_Specifications).pdf

PDF 2 MB Posted

Attached to
WICR VC ROOF REPLACEMENT Federal contract opportunity
Solicitation number
140P6224Q0010
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document is a set of project specifications for replacing the roof on the library addition and sealing walls at the Wilson's Creek National Battlefield Visitor Center in Republic, Missouri. The project involves removing and replacing approximately 8,760 square feet of the existing TPO roofing system, repairing 16 roof penetrations, installing 700 linear feet of new metal flashing, and sealing approximately 9,483 square feet of exterior concrete walls. The work must be completed within 90 calendar days of the notice to proceed. Key requirements include using a 60-mil TPO roofing system with a 20-year warranty, meeting wind uplift and fire resistance standards, and maintaining the building in a weather-tight condition during construction. Submittals such as shop drawings, product data, samples, and safety plans are required. The project is being procured through Solicitation 140P6224Q0010 issued by the Department of the Interior National Park Service Midwest Region.

View the file

Other files for this federal contract opportunity

Other files attached to WICR VC ROOF REPLACEMENT, newest first.
File Type Posted
Sol_140P6224Q0010_Amd_0001.pdf PDF
B08_Solicitation_(Attach_8_Question_Answer)_0001.pdf PDF
B08_Solicitation_(Attach_7_Site_Visit_Sign_in_Roster)_0001.pdf PDF
Sol_140P6224Q0010.pdf PDF
B08_Solicitation_(Attach_4_PPQ).doc DOC document
B08_Solicitation_(Attach_3_Technical_Questionnaire).docx DOCX document
B08_Solicitation_(Attach_5_Price_Schedule).xlsx XLSX spreadsheet
B08_Solicitation_(Attach_2_Wage_Det_(MO20240075_Rev_1)).pdf PDF
B08_Solicitation_(Attach_6_Limitations_on_Subcontracting_Report).xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Div. 1 V. 2023-11-11 Page | 1

Wilson’s Creek National Battlefield

Republic Missouri

Replace Roof on Library Addition and Install New Flashing and Seal Walls of Both Library Addition and Visitor Center

PMIS 329307

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

1/23/2024

Page | 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 - Division 01 Short Form General Requirements Page 3

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 075423 - Thermoplastic-Polyolefin (TPO) Roofing Page 18

EXHIBITS

Exhibit A: Existing TPO Roof Page 26

Exhibit B: Roof Penetrations Page 27

Exhibit C: Site Maps and Location Page 30

Exhibit D: Example Products Page 33

Exhibit E: Example of Purposed Ridge Cap Flashing Page 35

Exhibit F: Specifications for Securock Page 36

Page | 3

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: Wilson’s Creek National Battlefield is a civil war battlefield located in SW Missouri.

The main Visitor Center is composed of two sides the Visitor Center side and the Library Addition with a adjoining vestibule in between. The Visitor Center side was built in 1982 and is mainly composed of preformed concrete walls and roof, with a TPO style roof covering. The Library

Addition and Vestibule were built in 2002 and is also composed of preformed concrete walls and a steel pan roof deck, with TPO style roof.

1.2 Work Covered by the Contract Documents:

A. Project Location: The Visitor Center and Library Addition is located at 6424 West Fr 182, Republic, Missouri 65738 in Greene County. (See Exhibit C)

Work consists of: This project will replace a 20-year-old, approximately 8,760 square feet, of failing TPO roof system on Library Addition and Vestibule. Repair 16 penetrations, remove and filled from the deck up including insulation. The new TPO 60 mil will be mechanically attached with 3/8” underlayment over the existing Library and vestibule roofs. The TPO will be extended over the parapet walls on the Library with a new flashing cap to protect the top of the walls. Install approximately 700 LF of flashing on all parapet walls on the Library and Visitor Center roofs.

Also repair all existing externally exposed cracks in exterior walls of the Library, vestibule and

Visitor Center that are larger than 1/8 inch in width. They will be cleaned of excess and loose debris, and filled with Quikrete Concrete Repair (See Exhibit D) or similar product approved by the COR. Estimate 32 hours of labor and $1000 of sealant material to accomplish this task. After all cracks have been sealed in the exterior walls of will be sealed with a concrete sealer.

It is the intent of the park to keep this building open during construction and must always remain weathertight at all times.

Provide labor, equipment, and materials to remove and fill 16 existing roof penetrations, (See

Exhibit B) replace approximately 8,760 square feet of existing TPO style roofing, (See Exhibit A) install approximately 700 LF of new flashing (See Exhibit E) and seal approximately 9483 square feet of concrete walls. The existing roof over the Library Addition has 16 roof penetrations (See

Exhibit B) that will be filled to decrease the likelihood of roof leaks in sensitive areas and will also improve the integrity of the building envelope. These covers, sky lights, and vents will be removed and any penetrating bracing extending above the steel deck will be removed and brought down to deck level, a 18 gauge steel patch will be installed to the existing steel deck to insure a stable platform, insulation will be installed to match existing surrounding insulation board and a waterproof barrier TPO patch will be installed over the existing hole and adhered to existing

TPO roof. Contractor will only be responsible for removing what portions of the penetrations that is above the steel deck. Contractor will coordinate with the COR to schedule with the NPS who will remove any connections from the steel deck down into the building and remaining utilities below the steel deck. Once all penetrations have been filled and sealed, approximately 8,760

Page | 4 square feet of new 3/8” Securoc gypsum-fiber roof board substrate will be fastened through the existing TPO roof to the metal deck using manufactured recommended fasteners and pattern.

Once the new substrate has been installed, a new 60 mil mechanically fastened TPO style roof will be laid over the entire Library Addition and Vestibule roof surface, according to manufactures specifications. Along the gutter edge there will be a new 24-gauge drip edge installed with

4inches under the TPO roof and two inches down into the gutter with a drip edge. Manufacture specified cover tape or welded TPO patch will be installed back over the drip edge to insure a watertight seal. Along the three other sides of the building that have a parapet style wall, the new

TPO will be extended up over the top of the existing parapet wall and terminated four inches down on the outside of the wall and will be fully adhered to the retaining wall using a manufacture recommended membrane adhesive. The HVAC of the building will need to remain in operation at all times to control temperature and humidity within the building. Contractor will be required to work around existing HVAC ductwork that is currently on the roof. The support feet can be removed for laying the new TPO roofing material, but ductwork must stay connected. If ductwork needs to be temporarily disconnected to install new flashing this will need to be approved and monitored by COR. (See Exhibit A) Any variation from this must be approved by the COR. All remaining roof penetrations that were not removed, will have manufactured recommended flashing installed and sealed according to manufactured specification. Next approximately 700 liner feet of new 24-gauge metal parapet cap will be installed along the upper portion of the concrete wall of the Library and Visitor Center to protect the top of the wall from future damage.

(See Exhibit E) The parapet cap will be factory coated with Kynar style bronze finish or similar product, to match the existing metal flashing on the front of the building. Color to be approved by

COR through submittal process. The parapet cap will extend down four inches or whatever length necessary to completely cover the TPO membrane, on the outside of the parapet wall and be fastened with blind fasteners, so that no screws are shown on the exterior of the building. The parapet cap will extend down four inches on the inner wall totally encapsulating the top of the wall and be screwed to the parapet wall according to manufactured specifications (See Exhibit E) for example photos. On the ends the parapet cap will be molded and secure or preformed end caps will be installed to insure a watertight barrier. If top cap is put on in sections, it will overlap at least

2” on all planes and be sealed with manufactured recommended sealer in between sections. or a similar like product approved by COR. Repair all existing externally exposed cracks in exterior walls of the Library, vestibule and Visitor Center that are larger than 1/8 inch in width. They will be cleaned of excess and loose debris, and filled with Quikrete Concrete Repair (See Exhibit D) or similar product approved by the COR. Finally, seal all exterior exposed concrete walls of the

Library and Visitor Center. which are approximately 9483 square feet of both building’s exterior walls will be sealed with a water based penetrating sealer with low VOC and low sheen to not change the appearance of the walls.

B. All work will be performed under a single contract.

C. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.

a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical

Page | 5 average weather patterns, contractor shall provide documentation in request for additional days.

1.3 Existing Condition Protections:

A. Preservation of Historical and Archeological Fabric:

i. The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the

Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.

iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.

iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting

Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

v. The Contractor agrees to include this language within all subcontracts.

ITEM 2 – PROTECTING EXISTING UTILITIES

2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative

(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.

Page | 6

B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park

Service, and applicable park rules and regulations prescribed by the Park Superintendent.

https://www.nps.gov/wicr/learn/management/superintendent-s-compendium.htm

A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited-service coverage), email and in case of emergency 24-hour contact options for duration of time operations.

B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting

Officer.

C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of

7:30 a.m. to 4 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day http://www.nps.gov/wicr/learn/management/superintendent-s-compendium.htm

Page | 7

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding

Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal

Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Contractor will be required to store materials and operated within the designated areas. Any variation of this would have to be approved by the COR in advance. Rear entrance and parking area must remain open at all times. If need arises that this cannot happen, notification to the COR must happen in advance. (See Exhibit C) for detailed pictures of work area and site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances. All supplies will be delivered to the rear of the building using the entrance off Missouri State Highway ZZ (See Exhibit C) unless approved by the COR.

C. Do Not disturb site outside of noted disturbance area, including earthwork, and clearing of vegetation, to

1. 15 feet beyond building perimeter and designated storage areas.

Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction if needed. Contractor shall remediate soil compaction as directed to do so by the

CO/COR. Contractor will be responsible for any damaged done to surrounding sidewalks, grass areas, HVAC equipment, or any other NPS property.

D. Utilities

1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.

3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

4. Waste Operation:

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

Page | 8

a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan. (See Exhibit C)

b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate dumpster within staging area as shown on site plan or coordinated with COR. (See Exhibit C)

E. Security and Protection facilities:

1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.

Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

3. Tree and Plant Protection: N/A.

4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

5. Temporary Enclosures: Provide temporary enclosures such as snow fence as required for protection of construction in progress and completed, from access by visitors or staff, other construction operations, and similar activities.

6. Hot Work Permit: N/A

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area noted on the plans / aerial map. (See Exhibit C) Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the

COR. Security of the materials and equipment on site is the Contractor’s responsibility.

3.5 Preservation of Natural Features: N/A.

3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.

3.7 Housekeeping:

Page | 9

A. Keep project neat, orderly, and in a safe condition at all times.

1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Occupancy Requirements for Buildings:

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

3.9 Photo Documentation:

A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

B. Existing Condition Images:

1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

C. Construction Progress Images:

Page | 10

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

D. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc..

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety:

B. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

C. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

D. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR, and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics Management

A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.

B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.

C. Repetitive and/or intermittent, high-level noise: N/A

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926

Page | 11

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS

Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National

Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample

JHA template may be provided upon request.

5. Planning for possible emergency situations, such as tornados, cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies.

7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute

"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

https://www.nps.gov/orgs/1671/do-business-with-us.htm

Page | 12

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times. At a minimum, maintain four sets of PPE including hard hats and all other Accident Prevention Plan required equipment.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park

Service Emergency Dispatch.

ITEM 8 - PRECONSTRUCTION CONFERENCE

8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

Page | 13

9.1 General Contracting Submittal Procedures:

A. General: Prepare and submit submittals required by individual Technical Specification

Sections. Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR

B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the

Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.

Work shall not commence until written Notice to Proceed has been issued. Contracting

Officer will notify Contractor of tentative date for the Pre-Construction Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Quality Control Plan.

8. Temporary Enclosure Prevention Plan. This plan will be submitted to COR prior to construction to ensure building always remains weathertight in case of unforeseen weather.

9. Recycled Materials Plan This plan will be submitted to COR prior to construction to ensure all materials and waste that can be, will be recycled. Following construction, a recycled materials report will be turned into COR with approximate weight or cubic yards recycled.

9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

Page | 14

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.

C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.

Paint samples shall be actual paint finish drawdown for all project colors.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the

Contractor. If submittals are not approved, Contracting Officer will return all copies to

Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.

Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that General Contractor:

1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.

2. Will meet or exceed warranties for the proposed item specified.

3. Has determined that the proposed item is compatible with interfacing items.

Page | 15

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the

Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.

9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.

Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of

Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this

Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

Page | 16

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting

Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

B. If the work is not determined to be complete following the final inspection, the Contracting

Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the

CO.

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of

Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

11.5 Warranties

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS

12.1 Summary

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.

Page | 17

B. If no contract line item exists for a portion of the work, include the costs in a related item.

12.2 List of Contract Line Items

A. Contract Line-Item No.010 - Replace TPO Roof on Visitor Center and Vestibule

1. This item consists of removing and filling 16 roof penetrations in Visitor Center roof and replacing approximately 8760 square feet of 60 mil TPO style roofing on Visitor Center and Vestibule.

2. Payment will be made per the contract and percentage of completion level.

B. Contract Line-Item No. 020 – Install New Flashing on Visitor Center and Museum

1. This item consists of installing approximately 700 liner feet of 24-gauge top cap style flashing along the top of the parapet walls of both the Visitor Center and the Museum.

C. Contract Line-Item No. 030 – Seal all exterior walls of Visitor Center and Museum

1. This item consists of filling all cracks over 1/8 inch in the walls of both the Visitor Center and Museum with a concrete filler and then sealing approximately 9483 square feet of walls in both buildings with a concrete sealer.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

WICR PMIS NUMBER 329307 1/23/2024

Div 7 THERMOPLASTIC-POLYOLEFIN (TPO) ROOFING 075423-1 Page | 18 MasterSpec Short Form Copyright 2018 AIA

SECTION 075423 - THERMOPLASTIC-POLYOLEFIN (TPO) ROOFING

PART 2 - GENERAL

2.1 SUMMARY

A. Section Includes:

1. Adhered thermoplastic polyolefin (TPO) roofing system.

2. Mechanically fastened, thermoplastic polyolefin (TPO) roofing system.

3. Loosely laid and ballasted, thermoplastic polyolefin (TPO) roofing system.

4. Substrate board.

5. Cover board.

2.2 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Wilson’s Creek National Battlefield Visitor

Center Multipurpose Room located at 6424 W Fr 182 Republic Mo. 65738.

2.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Roof system component fasteners, include copy of FM Approvals' RoofNav listing.

B. Shop Drawings: Include roof plans, sections, details, and attachments to other work, including the following:

1. Base flashings and membrane termination details.

2. Flashing details at penetrations.

3. Roof plan showing orientation roof membrane, fastening spacings, and patterns for mechanically fastened roofing system.

4. Tie-in with adjoining air barrier.

C. Samples: For the following products:

1. Roof membrane and flashings material, thickness, and color required.

2. Ridge cap material, thickness, and color required.

3. Concrete filler and sealer required.

Page | 19 MasterSpec Short Form

D. Wind Uplift Resistance Submittal: For roofing system, indicating compliance with wind uplift performance requirements.

2.4 INFORMATIONAL SUBMITTALS

A. Manufacturer Certificates:

1. Performance Requirement Certificate: Signed by roof membrane manufacturer, certifying that roofing system complies with requirements specified in "Performance Requirements"

Article.

a. Submit evidence of compliance with performance requirements.

2. Special Warranty Certificate: Signed by roof membrane manufacturer, certifying that all materials supplied under this Section are acceptable for special warranty.

B. Product Test Reports: For roof membrane and insulation, for tests performed by a qualified testing agency, indicating compliance with specified requirements.

C. Research reports.

D. Field Test Reports:

1. Concrete internal relative humidity test reports.

2. Fastener-pullout test results and manufacturer's revised requirements for fastener patterns.

E. Field quality-control reports.

F. Sample warranties.

2.5 CLOSEOUT SUBMITTALS

A. Maintenance data.

B. Certified statement from existing roof membrane manufacturer stating that existing roof warranty has not been affected by Work performed under this Section.

C. All warranty information related to this project.

2.6 QUALITY ASSURANCE

A. Manufacturer Qualifications: A qualified manufacturer that is UL listed or listed in FM

Approvals' RoofNav for roofing system identical to that used for this Project.

Page | 20 MasterSpec Short Form

B. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer's product and that is eligible to receive manufacturer's special warranty. Contractor must have at least 10 years’ experience with this product.

2.7 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of roofing system that fail in materials or workmanship within specified warranty period.

1. Warranty Period: 20 years from date of Substantial Completion.

PART 3 - PRODUCTS

3.1 PERFORMANCE REQUIREMENTS

A. Accelerated Weathering: Roof membrane shall withstand 2000 hours of exposure when tested according to ASTM G152, ASTM G154, or ASTM G155.

B. Impact Resistance: Roof membrane shall resist impact damage when tested according to

ASTM D3746, ASTM D4272, or the "Resistance to Foot Traffic Test" in FM Approvals 4470.

C. Wind Uplift Resistance: Design roofing system to resist the following wind uplift pressures when tested according to FM Approvals 4474, UL 580, or UL 1897: For detailed Zones and lbf/sqft.

(See Exhibit F)

1. Zone 1 (Roof Area Field Prime): 14 lbf/sq. ft. / Zone 1 (Field Perimeter): 25 lbf/sq. ft.

2. Zone 2 (Roof Area Perimeter): 33 lbf/sq. ft

3. Zone 3 (Roof Area Corners): 45 lbf/ sq.ft.

D. FM Approvals' RoofNav Listing: Roof membrane, base flashings, and component materials shall comply with requirements in FM Approvals 4450 or FM Approvals 4470 as part of a roofing system and shall be listed in FM Approvals' RoofNav for Class 1 or noncombustible construction, as applicable. Identify materials with FM Approvals Certification markings.

1. Fire/Windstorm Classification: Class 1A-90.

2. Hail-Resistance Rating: SH.

E. ENERGY STAR Listing: Roofing system shall be listed on the DOE's ENERGY STAR "Roof

Products Qualified Product List" for low slope roof products.

F. Energy Performance: Roofing system shall have an initial solar reflectance of not less than 0.70 and an emissivity of not less than 0.75 when tested according to CRRC-1.

Page | 21 MasterSpec Short Form

G. Exterior Fire-Test Exposure: ASTM E108 or UL 790, Class A; for application and roof slopes indicated; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

H. Fire-Resistance Ratings: Comply with fire-resistance-rated assembly designs indicated. Identify products with appropriate markings of applicable testing agency.

3.2 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING

A. TPO Sheet: ASTM D6878/D6878M, internally fabric- or scrim-reinforced, TPO sheet.

1. Thickness: 60 mils nominal.

2. Exposed Face Color: White.

3.3 AUXILIARY ROOFING MATERIALS

A. General: Auxiliary materials recommended by roofing system manufacturer for intended use and compatible with other roofing components.

1. Adhesive and Sealants: Comply with VOC limits of authorities having jurisdiction.

B. Sheet Flashing: Manufacturer's standard unreinforced TPO sheet flashing, 60 mils thick, minimum, of same color as TPO sheet.

C. Prefabricated Pipe Flashings: As recommended by roof membrane manufacturer.

D. Bonding Adhesive: Manufacturer's standard.

E. Metal Termination Bars: Manufacturer's standard, predrilled stainless steel or aluminum bars, approximately 1 by 1/8 inch thick; with anchors.

F. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Approvals 4470, designed for fastening roofing components to substrate, and acceptable to roofing system manufacturer.

G. Ridge Cap: Factory-coated 24-gauge preformed metal. Blind fasteners in outside and screwed with matching screws on inside. Color will be bronze to match exterior metal on building.

H. Miscellaneous Accessories: Provide pourable sealers, preformed cone and vent sheet flashings, preformed inside and outside corner sheet flashings, T-joint covers, lap sealants, termination reglets, and other accessories.

Page | 22 MasterSpec Short Form

3.4 SUBSTRATE BOARDS

A. Substrate Board: USG Securock Brand High-Performance Roof gypsum board. (See Exhibit D)

1. Thickness: 3/8 inch.

B. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Approvals 4470, designed for fastening substrate board to roof deck.

PART 4 - EXECUTION

4.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

1. Verify that minimum concrete drying period recommended by roofing system manufacturer has passed.

2. Verify that concrete substrate is visibly dry and free of moisture, and that minimum concrete internal relative humidity is not more than 75 percent, or as recommended by roofing system manufacturer, when tested according to ASTM F2170.

a. Test Frequency: One test probe per each 1000 sq. ft., or portion thereof, of roof deck, with not less than three tests probes.

b. Submit test reports within 24 hours after performing tests.

3. Verify that concrete-curing compounds that will impair adhesion of roofing components to roof deck have…