B08_Solicitation_-_Att_2_-_Drawings.pdf
PDF 3 MB Posted
- Attached to
- ARPO - Replace DP-2 Panel and Restore Power Federal contract opportunity
- Solicitation number
- 140P6025Q0040
About this file
These are electrical construction drawings for the Arkansas Post National Monument Panel DP-2 Replacement project. The project involves removing the existing electrical panel DP-2 and replacing it with a new exterior-mounted NEMA 3R panel, with two primary scopes of work: the base bid and a bid additive. The base bid requires removing the existing panel, installing a new panel with 800A rated main circuit breaker, routing and reconnecting existing electrical feeds, and intercepting the fire alarm service. The bid additive involves restoring power to a previously severed 1-inch conduit by core drilling the exterior wall, installing a new junction box, and reconnecting the conduit. The project specifications include detailed requirements for electrical work, wall penetrations, conduit installation, and equipment mounting, with strict adherence to the 2023 National Electrical Code and UL standards. The work is located at the Arkansas Post National Monument in Gillette, Arkansas, and requires careful coordination with National Park Service staff to minimize power disruptions and maintain critical systems.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6025Q0040_Amd_0001.pdf | ||
| B12_MISC_QA_Doc_0001.docx | DOCX document | |
| Sol_140P6025Q0040.pdf | ||
| B08_Solicitation_-_Att_1_-_Specifications.docx | DOCX document | |
| B08_Solicitation_-_Att_4_-_PPQ.doc | DOC document | |
| B08_Solicitation_-_Att_3_-_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BASE BID AND BID ADDITIVE:
BASE BID: PROVIDE ALL MATERIALS, EQUIPMENT, AND LABOR TO REMOVE EXISTING BRANCH ELECTRICAL PANEL DP-2
AND REPLACE WITH NEW EXTERIOR MOUNTED BRANCH PANEL DP-2 WITHIN A NEMA 3R PANEL. ROUTE AND
RECONNECT ELECTRICAL FEEDS TO NEW PANEL. ADDITIONALLY, INTERCEPT ELECTRICAL SERVICE FROM FIRE
ALARM JUNCTION BOX AND ROUTE BY SURFACE MOUNTED CONDUIT DIRECT TO NEW PANEL DP-2 PER THE
DESIGN PARAMETER NOTED ON SHEETS E0.1 AND E1.1.
BID ADDITIVE 1: PROVIDE ALL MATERIALS, EQUIPMENT, AND LABOR TO RESTORE POWER FROM A PREVIOUSLY SEVERED 1"
CONDUIT EMBEDDED WITHIN GROUT FILL OF EXTERIOR WALL BY CORE DRILLING TO INTERCEPT SEVERED
CONDUIT, INSTALL NEW WALL MOUNTED JUNCTION BOX, AND CONDUIT TO PROVIDE RECONNECTION PER THE
DESIGN PARAMETERS NOTED ON SHEET E1.2.
AutoCAD SHX Text
ROCK
AutoCAD SHX Text
LITTLE
AutoCAD SHX Text
ARKANSAS
AutoCAD SHX Text Agate Fossil Beds NM
AutoCAD SHX Text Apostle Islands NL
AutoCAD SHX Text Arkansas Post NMEN
AutoCAD SHX Text Badlands NP
AutoCAD SHX Text Brown v. Board of Education NHS
AutoCAD SHX Text Buffalo NR
AutoCAD SHX Text Cuyahoga Valley NRA
AutoCAD SHX Text Dayton Aviation Heritage NHP
AutoCAD SHX Text Effigy Mounds NM
AutoCAD SHX Text Fort Larned NHS
AutoCAD SHX Text Fort Scott NHS
AutoCAD SHX Text Fort Smith NHS
AutoCAD SHX Text Fort Union Nat. Trading Post NHS
AutoCAD SHX Text George Rogers Clark NHP
AutoCAD SHX Text George Washington Carver NM
AutoCAD SHX Text Grand Portage NM
AutoCAD SHX Text Harry S Truman NHS
AutoCAD SHX Text Herbert Hoover NHS
AutoCAD SHX Text Homestead NM of America
AutoCAD SHX Text Hopewell Culture NHP
AutoCAD SHX Text Hot Springs NP
AutoCAD SHX Text Indiana Dunes NL
AutoCAD SHX Text Isle Royale NP
AutoCAD SHX Text James A Garfield NHS
AutoCAD SHX Text Jefferson NEM
AutoCAD SHX Text Jewel Cave NM
AutoCAD SHX Text Keweenaw NHP
AutoCAD SHX Text Knife River Indian Villages NHS
AutoCAD SHX Text Lincoln Boyhood NMEM
AutoCAD SHX Text Mississippi NRRA
AutoCAD SHX Text Missouri NRR
AutoCAD SHX Text Mount Rushmore NMEM
AutoCAD SHX Text Niobrara NSR
AutoCAD SHX Text Ozark NSR
AutoCAD SHX Text Pea Ridge NMP
AutoCAD SHX Text Perry's Victory IPM
AutoCAD SHX Text Pictured Rocks NL
AutoCAD SHX Text Pipestone NM
AutoCAD SHX Text Saint Croix NSR
AutoCAD SHX Text Scotts Bluff NM
AutoCAD SHX Text Sleeping Bear Dunes NL
AutoCAD SHX Text Theodore Roosevelt NP
AutoCAD SHX Text Ulysses S Grant NHS
AutoCAD SHX Text Voyageurs NP
AutoCAD SHX Text William Howard Taft NHS
AutoCAD SHX Text Wilson's Creek NB
AutoCAD SHX Text Wind Cave NP
AutoCAD SHX Text
FORT SMITH
AutoCAD SHX Text
MEMPHIS
AutoCAD SHX Text
OKLAHOMA
AutoCAD SHX Text
MISSISSIPPI
AutoCAD SHX Text
LOUISANA
AutoCAD SHX Text
WEST VIRGINIA
AutoCAD SHX Text
PENNSYLVANIA
AutoCAD SHX Text
NEBRASKA
AutoCAD SHX Text
KANSAS
AutoCAD SHX Text
IOWA
AutoCAD SHX Text
MISSOURI
AutoCAD SHX Text
OHIO
AutoCAD SHX Text
MICHIGAN
AutoCAD SHX Text
WISCONSIN
AutoCAD SHX Text
MINNESOTA
AutoCAD SHX Text
INDIANA
AutoCAD SHX Text
TOLEDO
AutoCAD SHX Text
ST. LOUIS
AutoCAD SHX Text
KANSAS CITY
AutoCAD SHX Text
DULUTH
AutoCAD SHX Text
CLEVELAND
AutoCAD SHX Text
CINCINNATI
AutoCAD SHX Text
MILWAUKEE
AutoCAD SHX Text
LINCOLN
AutoCAD SHX Text
TOPEKA
AutoCAD SHX Text
JEFFERSON CITY
AutoCAD SHX Text
INDIANAPOLIS
AutoCAD SHX Text
COLUMBUS
AutoCAD SHX Text
LANSING
AutoCAD SHX Text
MADISON
AutoCAD SHX Text
ST. PAUL
AutoCAD SHX Text
DES MOINES
AutoCAD SHX Text
BISMARCK
AutoCAD SHX Text
NORTH DAKOTA
AutoCAD SHX Text
SOUTH DAKOTA
AutoCAD SHX Text
PIERRE
AutoCAD SHX Text
ILLINOIS
AutoCAD SHX Text
SPRINGFIELD
AutoCAD SHX Text
DAYTON
AutoCAD SHX Text
DETROIT
AutoCAD SHX Text
MINNEAPOLIS
AutoCAD SHX Text
AKRON
AutoCAD SHX Text
FORT WAYNE
AutoCAD SHX Text
CHICAGO
AutoCAD SHX Text
SIOUX FALLS
AutoCAD SHX Text
ROCHESTER
AutoCAD SHX Text
GREEN BAY
AutoCAD SHX Text
OKLAHOMA CITY
AutoCAD SHX Text
ST. LOUIS
AutoCAD SHX Text
OKLAHOMA
AutoCAD SHX Text
TENNESEE
AutoCAD SHX Text
KENTUCKY
AutoCAD SHX Text
COLORADO
AutoCAD SHX Text
WYOMING
AutoCAD SHX Text
MONTANA
AutoCAD SHX Text
SASKATCHEWAN
AutoCAD SHX Text
MANITOBA
AutoCAD SHX Text
ONTARIO
AutoCAD SHX Text
ONTARIO
AutoCAD SHX Text
OMAHA
AutoCAD SHX Text
CHEYENNE
AutoCAD SHX Text
SPRINGFIELD
AutoCAD SHX Text
PEORIA
AutoCAD SHX Text
DENVER
AutoCAD SHX Text
TO HIGHWAY 165 S VIA COUNTY ROAD 169
AutoCAD SHX Text
VISITOR CENTER
AutoCAD SHX Text
PARKING LOT
AutoCAD SHX Text P O S T
AutoCAD SHX Text L A K E
AutoCAD SHX Text
ALLIGATOR
AutoCAD SHX Text
SLOUGH
AutoCAD SHX Text P O S T B A Y O U
AutoCAD SHX Text
ELECTRICAL PANEL DP-2 REPLACEMENT
AutoCAD SHX Text
BASIC DATA:
AutoCAD SHX Text
STATE
AutoCAD SHX Text
NATIONAL PARK SERVICE
AutoCAD SHX Text
INTERIOR REGIONS 3, 4, AND 5
AutoCAD SHX Text
REGION
AutoCAD SHX Text
COUNTY
AutoCAD SHX Text
DEPARTMENT OF THE INTERIOR
AutoCAD SHX Text
UNITED STATES
AutoCAD SHX Text
LOCATION WITHIN PARK
AutoCAD SHX Text
NAME OF PARK
AutoCAD SHX Text
TITLE OF DRAWING
AutoCAD SHX Text
COVER
AutoCAD SHX Text
VISITOR CENTER
AutoCAD SHX Text 80021
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
ARKANSAS
AutoCAD SHX Text
ARKANSAS
AutoCAD SHX Text
OF
AutoCAD SHX Text
PKG.
AutoCAD SHX Text
NO.
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
CONSTRUCTION DRAWINGS
AutoCAD SHX Text
QUALITY DESIGN CERTIFICATION
AutoCAD SHX Text
OR
AutoCAD SHX Text
OR
AutoCAD SHX Text Development (Title I)
AutoCAD SHX Text Prepared in Accordance with Design
AutoCAD SHX Text by Design Development (Title I)
AutoCAD SHX Text Construction Drawing Not Preceded
AutoCAD SHX Text Approved by Superintendent on
AutoCAD SHX Text Variance from Design Development (Title I)
AutoCAD SHX Text Project Manager
AutoCAD SHX Text Drawing No.
AutoCAD SHX Text Date
AutoCAD SHX Text Date
AutoCAD SHX Text Sheet
AutoCAD SHX Text Mark
AutoCAD SHX Text
REVISION
AutoCAD SHX Text Date
AutoCAD SHX Text Initial
AutoCAD SHX Text
PMIS - 274253D
AutoCAD SHX Text C:\Users\tbentley\Desktop\ARPO VC Electrical DP-2\ARPO 274253D_VC Panel DP-2_COVER.dwg
AutoCAD SHX Text
MWR
AutoCAD SHX Text
PROJECT AREA
AutoCAD SHX Text
AutoCAD SHX Text
ARKANSAS POST NATIONAL MEMORIAL
AutoCAD SHX Text
ARKANSAS POST NATIONAL MONUMENT
AutoCAD SHX Text SHEEET SUBSHEET SHEET TITLE SUBSHEET SHEET TITLE SHEET TITLE SHEET TITLE 1 COVER COVER 2 E0.1 GENERAL NOTES - ELECTRICAL REMOVALS E0.1 GENERAL NOTES - ELECTRICAL REMOVALS GENERAL NOTES - ELECTRICAL REMOVALS 3 E1.1 NEW ELECTRICAL WORK E1.1 NEW ELECTRICAL WORK NEW ELECTRICAL WORK 4 E1.2 BID ADDITIVE 01E1.2 BID ADDITIVE 01BID ADDITIVE 01
AutoCAD SHX Text
SHEET INDEX
AutoCAD SHX Text 4/15/2025
AutoCAD SHX Text
REGIONAL MAP PROJECT LOCATION
AutoCAD SHX Text
ARKANSAS COUNTY
AutoCAD SHX Text
ARKANSAS
AutoCAD SHX Text
VICINITY MAP
AutoCAD SHX Text
PARK MAP
MECHANICAL
WOMEN'S
RESTROOM
OFFICE
THEATER
VISITOR CENTER / MUSEUM
MEN'S
RESTROOM
EXTERIOR
SERVICE
CORRAL
EXHIBIT
SPACE
EXHIBIT
SPACE
EXHIBIT
SPACE
OFFICE
OFFICE
OFFICE
OFFICE
BREAK ROOM
E1.0
ELECTRICAL
SUB PANELS
FED FROM
PANEL DP-2
L1 L2 L3
ELECTRICAL
SUB PANEL
FED FROM
PANEL DP-2
L4
DP-2
GENERAL NOTES:
1. ALL CONSTRUCTION SHALL BE IN CONFORMANCE WITH THESE PLANS, REFERENCED
STANDARDS AND SPECIFICATIONS, AND GENERAL CONDITIONS IN THE CONTRACT.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR DETERMINATION OF ALL FINAL QUANTITIES
AND METHODS IN ORDER TO CONDUCT THE WORK PRIOR TO SUBMITTING THEIR BID.
3. PROVIDE ALL SUBCONTRACTORS WITH ALL THE NECESSARY CONSTRUCTION DOCUMENT
SHEETS AND INFORMATION APPLICABLE TO THEIR AREA OF WORK AS WELL AS WORK
INFLUENCED BY OR INFLUENCES WORK BY OTHER TRADES.
4. ENSURE THAT ALL REQUIRED COORDINATION IS DONE BEFORE BEGINNING ANY
CONSTRUCTION. IT IS THE CONTRACTOR'S RESPONSIBILITY TO OBTAIN ALL REQUIRED
AUTHORIZATION FROM CONTRACTING OFFICER AND REPRESENTATIVE, PARK STAFF POINT
OF CONTACT, AND FULLY ACKNOWLEDGE PRIOR TO COMMENCING WORK ON SITE.
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MEETING ALL INSPECTION CRITERIA AND
SCHEDULES.
6. ALL PROPERTY DAMAGED BY CONSTRUCTION ACTIVITIES SHALL BE RESTORED TO A
CONDITION EQUAL TO OR BETTER THAN EXISTING AT THE CONTRACTORS EXPENSE. THIS
PERTAINS TO CONSTRUCTED ELEMENTS, AS OWNED BY NPS, OR OTHER ENTITY. PHOTO
DOCUMENT EXISTING CONDITIONS AND REVIEW WITH PARK CONTRACTING OFFICER
REPRESENTATIVE (COR) TO AVOID MIS-IDENTIFICATION OF PRE-EXISTING DAMAGE AS
CONSTRUCTION ACTIVITY CAUSED.
7. ALL WORK AND ALL MATERIALS FURNISHED SHALL BE IN CONFORMITY WITH THE
REQUIREMENTS IN THE CONTRACT DOCUMENTS.
8. THE SPECIFICATIONS, NOTES AND PLANS CALL ATTENTION TO CERTAIN REQUIRED
FEATURES OF THE CONSTRUCTION BUT DO NOT IMPLY TO COVER ALL MEANS AND
METHODS OF CONSTRUCTION.
9. ALL WORK SHALL BE ACCOMPLISHED TO THE HIGHEST QUALITY CRAFTSMANSHIP
INDUSTRY STANDARDS FOR EACH RESPECTIVE TRADE.
10. ALL WORK SHALL BE ACCOMPLISHED IN STRICT ACCORDANCE WITH ALL APPLICABLE
LOCAL, STATE, AND FEDERAL CODES AND REGULATIONS.
11. APPARENT ERRORS, DISCREPANCIES OR OMISSIONS ON THE DRAWINGS SHALL BE
BROUGHT TO THE CONTRACTING OFFICER'S ATTENTION AS SOON AS THE DISCREPANCY
OR OMISSION IS FOUND. CONTRACTOR SHALL NOT PROCEED WITH WORK AT THE
DISCREPANCY OR OMISSION PRIOR TO RECEIVING DIRECTION FROM THE COR.
12. ALL COMMUNICATION REQUESTING CLARIFICATION, DIRECTION AND OR REQUEST FOR
INFORMATION (RFI) SHALL BE IN WRITTEN FORM. SUBMIT ALL COMMUNICATION REQUESTS
TO COR AND ONLY WRITTEN RESPONSES FROM THE CO OR COR WILL BE CONSIDERED
APPROVED/AUTHORIZED.
13. THE GOVERNMENT WILL NOT BE RESPONSIBLE TO PAY FOR ANY UN-APPROVED MATERIALS
NOR MATERIALS NOT INCORPORATED INTO THE SCOPE OF THE PROJECT WORK.
14. AFTER COMPLETION OF CONSTRUCTION, PERFORM SITE CLEANUP OPERATION TO REMOVE
ALL TRASH, DEBRIS, EXCESS MATERIALS AND EQUIPMENT FROM THE PARK. IT SHALL BE THE
CONTRACTOR'S RESPONSIBILITY TO SHOW THE PROJECT SITE CLEAN FOR FINAL
ACCEPTANCE. ALL TRASH AND DEBRIS SHALL BE LAWFULLY DISPOSED OF.
15. CONTINUOUS ACCESS SHALL BE MAINTAINED FOR THE SURROUNDING AREAS DURING
CONSTRUCTION OF THE PROPOSED WORK. NPS STAFF RESERVE THE RIGHT TO PROCEED
WITH INDEPENDENT WORK ACTIVITY IN CLOSE PROXIMIITY AT THE SAME TIME THE
CONTRACTOR IS PERFORMING THE WORK OF THE CONTRACT; HOWEVER, CONFLICT WITH
IMPEDING PROGRESS SHALL BE AVOIDED.
MCB: Main Circuit Breaker LOCK: Lockable Circuit Breaker GFI: GFCI Circuit Breaker MLO: Main Lug Only FCB: Feeder Circuit Breaker MCCB: Molded Case Circuit Breaker Legend: Notes:
Total Est. Demand Current (80% Rated): 0 A
Continuous Current @ 125%: 0 A Non-Cont. Current @ 100%: 0 A
Total Est. Demand Current (100% Rated): 0 A Total Est. Demand: 0 VA
Load Classification Connected Load Demand Factor Estimated Demand Panel Totals
Total Amps: 0 A 0 A 0 A Total Load: 0 VA 0 VA 0 VA
31 Space -- -- 0 0 -- -- Space 32 29 Space -- -- 0 0 -- -- Space 30 27 -- -- -- 0 0 -- -- Space 28 25 (E) LTG - Plaza Pole 20 A 2 0 0 -- -- Space 26 23 -- -- -- 0 0 -- -- -- 24 21 (E) LTG - Parking Lot 20 A 2 0 0 2 150 A (E) L4 22 19 -- -- -- 0 0 -- -- -- 20 17 (E) L3 150 A 2 0 0 2 225 A (E) L2 18 15 -- -- -- 0 0 -- -- -- 16 13 (E) L1 225 A 2 0 0 2 90 A Spare 14 11 -- -- -- 0 0 -- -- -- 12 9 Spare 90 A 2 0 0 2 40 A Spare 10 7 -- -- -- 0 0 -- -- -- 8 5 Spare 40 A 2 0 0 2 30 A Spare 6 3 -- -- -- 0 0 -- -- -- 4 1 Spare HP-1 20 A 2 0 0 2 20 A Spare 2
CKT Circuit Description Trip P A B C P Trip Circuit Description CKT
Mounting: Wires: 3 FCB / MCB Rating: 800 A Supply From: MDP Phases: 1 MLO / MCB: MCB
Location: MECHANICAL 104 Volts: 120/240 A.I.C. Rating:
Extg Branch Panel:DP2 TO BE REMOVED
REPRESENTATIONAL PHOTOGRAPHS:
THE FOLLOWING PHOTOGRAPHS ARE PROVIDED FOR THE CONVENIENCE OF THE CONTRACTOR ONLY AND DO NOT ALLEVIATE THE CONTRACTOR'S
RESPONSIBILITY TO FAMILIARIZE THEMSELVES WITH THE SITE PRIOR TO SUBMITTING THEIR BID. THESE PHOTOS DO NOT CAPTURE THE TOTALITY OF THE
PROJECT AREA; HOWEVER THEY PROVIDE A REPRESENTATIONAL EXAMPLE OF THE EXISTING ELECTRICAL PANEL, ASSOCIATED INTERIOR SPACES AND
THE LOCATION FOR INSTALLATION OF THE NEW PANEL.
EXISTING PANEL DP-2 TO BE REMOVED AND RE-ROUTE
ELECTRICAL SERVICES TO EXTERIOR MOUNT NEW PANEL.
NEW PANEL DP-2 IN NEMA 3R ENCLOSURE TO BE WALL MOUNTED BETWEEN LOUVER
AND DOOR DIRECTLY OPPOSING EXISTING DP-2 WITHIN THE MECHANICAL ROOM.
VISITOR CENTER PLAN
3/32" = 1'-0"
POWER DISRUPTION AND TEMPORARY POWER COORDINATION NOTES:
1. IT IS CRITICAL THAT THE CONTRACTOR COORDINATE WITH THE COR A MINIMUM OF 72
HOURS IN ADVANCE OF ANY PLANNED DISRUPTION IN POWER THROUGHOUT THE ENTIRE
CONSTRUCTION CONTRACT. THE PARK AND COR RESERVE THE RIGHT TO DENY A POWER
DISRUPTION IF THERE IS A SIGNIFICANT CAUSE TO OPERATIONS AND REQUIRE THE
CONTRACTOR TO SCHEDULE AROUND PARK KNOWN TIMES OF AVOIDANCE.
2. THE CONTRACTOR SHALL PROVIDE TEMPORARY POWER CONNECTIONS TO RETAIN
ELECTRICITY TO CRITICAL SYSTEMS WHICH WILL INCLUDE MATTERS OF FIRE, SECURITY AND
LIFE SAFETY MATTERS IF DISRUPTION IS TO CONTINUE BEYOND DAILY OPERATION HOURS
WHEN PARK STAFF ARE AVAILABLE TO MONITOR. THIS INCLUDES THE FIRE ALARM AND
SECURITY SYSTEM OPERATING WITHIN THE VISITOR CENTER.
3. THE CONTRACTOR SHALL SCHEDULE SEQUENCING OF DISCONNECTING SERVICE FROM
EXISTING PANEL DP-2 AND ENGAGING NEW PANEL DP-2 AS A CONTINUOUS EFFORT ON
CONSECUTIVE DAYS IN ORDER TO MINIMIZE DURATION OF DISRUPTION.
4. THE CONTRACTOR SHALL NOT BE ALLOWED TO COMMENCE WITH DISCONNECTION OF
EXITING ELECTRICAL SERVICE TO EXISTING PANEL DP-2 UNTIL ALL MATERIALS AND
EQUIPMENT ARE IN THE POSSESSION OF THE CONTRACTOR FOR INSTALLATION OF NEW
PANEL DP-2.
ELECTRICAL REMOVAL SCOPE OF WORK NOTES:
1. REMOVE EXISTING PANEL BOARD DP-2 (800A, 120/240V, 1 PHASE) AND LAWFULLY
DISPOSE OFF OFF SITE.
2. LIMIT CUTTING OF LINES IN ORDER TO RETAIN DP-2 SERVICE FEEDER AND SIX (6) EXISTING
BRANCH CIRCUITS BEING TWO (2) - 150/2P, TWO (2) - 225A/2P, AND TWO (2) 20A/2P
WHICH ARE TO BE EXTENDED TO NEW PANEL.
3. EXISTING WIREWAY BENEATH EXISTING PANEL DP-2 MAY REMAIN AND BE INCORPORATED
IN RE-DIRECTING ALL SERVICE FEEDS THROUGH THE EXTERIOR WALL TO NEW PANEL DP-2.
SURFACE
22 KAIC
AutoCAD SHX Text
PARK 411 PROJECT 80021
AutoCAD SHX Text
PMIS NO.
AutoCAD SHX Text 274253D
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF 4
AutoCAD SHX Text
ARKANSAS POST NATIONAL MONUMENT GILLETE, ARKANSAS
AutoCAD SHX Text
DATE:
AutoCAD SHX Text 04/15/2025
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
SUBSHEET
AutoCAD SHX Text
DESIGNER:
AutoCAD SHX Text
CADD:
AutoCAD SHX Text
TECH REVIEW:
AutoCAD SHX Text
TLB
AutoCAD SHX Text
TLB
AutoCAD SHX Text
TLB
AutoCAD SHX Text
INITIAL
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
DATE
AutoCAD SHX Text E0.1
AutoCAD SHX Text
GENERAL NOTES ELECTRICAL REMOVALS
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text APPROXIMATE LOCATION OF STRUCTURAL GROUT FILLED CORE WITHIN WALL (ESTIMATED 16" FROM EAST EDGE OF LOUVER
EXISTING WIREWAY BENEATH EXISTING PANEL DP-2 WHICH MAY REMAIN FOR DIRECTING WIRING TO NEW PANEL DP-2
DP-3 (E)
DP-2 (E)
(FOR
REMOVAL)
DP-2
(NEW)
AIR
HANDLER
THRU-WALL
LOUVER
MECHANICAL
ROOM FIRE
ALARM
PANEL
FIRE ALARM
JUNCTION
BOX ABOVE
LOUVER
FIRE
ALARM
JUNCTION
BOX 2
FIRE
ALARM
JUNCTION
BOX 1
T
FIRST FLOOR
SECOND FLOOR
UTILITY
TRANSFORMER MDP
LIFT STATION
DP1
TRANSFORMER
PAD
HVAC PAD MAIN BUILDING
DP2 PANEL
'L1'
PANEL
'L2'
PANEL
'L3'
PANEL
'L4'
DP3
ACCU #1
OUTDOOR
EXISTING 3 SETS (3-300KCMIL AND 1-1/OG)
EXISTING WIREWAY
EXISTING 3-#4 / 0 AND 1#4G
EXISTING 3-#1 / 0 AND #6G
ENLARGED ELECTRICAL PLAN
NEW ELECTRICAL NOTES:
1. ALL WORK SHALL COMPLY WITH THE 2023 NATIONAL ELECTRICAL CODE
2. ALL EQUIPMENT SHALL BE UL LABELED AND LISTED FOR THE PURPOSE. MATERIAL SHALL BE NEW
AND SHALL CONFORM TO THE APPLICABLE STANDARD OR STANDARDS WHERE SUCH HAVE BEEN
ESTABLISHED FOR THE PARTICULAR MATERIAL ON QUESTION.
3. CONTRACTOR SHALL DISCONNECT AND REMOVE EXISTING PANELBOARD DP-2. RETAIN DP-2
SERVICE FEEDER (800A/2P) AND SIX EXISTING BRANCH CIRCUITS (TWO 225A/2P, TWO 150A/2P AND
TWO 20A/2P) FOR EXTENSION TO NEW PANEL. EXISTING CONDUIT THAT IS NO LONGER IN USE
SHALL BE REMOVED WITH PLUGS PROVIDED FOR EXISTING HOLES.
4. NEW PANELBOARD SHALL UTILIZE BOLT-ON CIRCUIT BREAKERS WITH AN 800A RATED MAIN CIRCUIT
BREAKER. ALL BREAKERS SHALL BE FULLY RATED FOR 22 KAIC, SERIES RATED BREAKERS ARE NOT
ACCEPTABLE. PANEL ENCLOSURE SHALL BE NEMA 3R RATED AND PROVIDE END AND SIDE GUTTER
CLEARANCES AS REQUIRED BY THE NEC. ALL LUGS SHALL BE UL LISTED FOR COPPER CONDUCTORS.
ALL BUSSING SHALL BE COPPER. MULTIPLE POLE CIRCUIT BREAKERS SHALL BE PROVIDED WITH A
SINGLE HANDLE. PROVIDE CIRCUIT BREAKERS WITH TRIP RATING AND POLES AS INDICATED ON
DRAWINGS. PROVIDE CIRCUIT BREAKER LOCK FOR TWO 20/A/1P CIRCUIT BREAKERS FOR FIRE
ALARM CONNECTION.
5. CONDUCTORS SHALL BE EXTENDED TO NEW PANEL LOCATION AND SHALL BE COPPER, 600V,
RATED FOR WET LOCATIONS AND MATCH THE INSULATION TYPE OF THE EXISTING CONDUCTORS.
CONDUCTOR SPLICING SHALL BE MADE WITHIN EXISTING WIREWAY. SPLICES SHALL BE MADE WITH
SPLIT BOLT CONNECTORS TAPED WITH #88 PLASTIC ELECTRICAL TAPE OR WITH IDEAL TYPE GP OR GT
TAP CONNECTORS WITH INSULATING COVER OR CRIMPING SLEEVE (OR EQUAL).
6. CONDUIT SHALL BE RIGID GALVANIZED STEEL WHERE EXPOSED TO EXTERIOR OF BUILDING.
ELECTRICAL METALLIC TUBING MAY BE USED ON THE INTERIOR WITH SET SCREW FITTINGS. ATTACH
RIGID CONDUIT TO SHEET METAL ENCLOSURES WITH TWO BONDING TYPE LOCK NUTS AND
INSULATED BUSHING. CONDUIT BODIES OR JUNCTION BOXES MAY BE USED TO EXTEND CIRCUITS
AND SHALL BE COMPATIBLE WITH THE CONDUIT.
7. CONDUITS THROUGH EXTERIOR WALL SHALL BE SEALED WITH FIBER AND INSULATING ELECTRICAL
PUTTY TO PREVENT ENTRANCE OF MOISTURE. WHERE EXTERIOR WALL IS FIRE RATED, CONDUIT
SEALS SHALL COMPLY WITH NEC 300.21.
8. PROVIDE ELECTRICAL SAFETY ARC FLASH WARNING LABEL COMPLYING WITH NEC 110.16.
9. EXTEND A #2/O BARE COPPER GROUND FROM GROUND BUS TO EXISTING GROUNDING ROD.
10. PROVIDE AN ENGRAVED BAKELITE TYPE NAMEPLATE WITH 5/16” HIGH LETTERS FOR DP-2
INCLUDING VOLTAGE, PHASE AND EQUIPMENT PANEL IS SERVED FROM.
11. PANEL DP-2 IS SERVED FROM SWBD DP-1 AND IS NOT A SERVICE ENTRANCE RATED PANEL. PROVIDE
A DIRECTORY THAT THIS IS ONE OF TWO SERVICES IN BUILDING AND DENOTE BOTH LOCATIONS PER
NEC 230.2.
12. PANELBOARD SHALL BE PROVIDED WITH BRANCH CIRCUIT SERVED, SHALL BE PLACED IN THE FRAME
UNDER CLEAR PLASTIC COVER.
POWER RISER DIAGRAM
2" = 1'-0"
NO SCALE
REF. NOTES ( ):X
1 NEW ELECTRICAL SERVICE EQUIPMENT. CONNECT GROUND TO EXISTING
BUILDING SERVICE GROUND BY EXTENDING A #2/O BARE COPPER
GROUDN FROM GROUND BUS TO EXISTING GROUND ROD. LABEL AS
SECOND SERVICE AND ADD
SERVICE LABEL TO DP-2.
MCB: Main Circuit Breaker LOCK: Lockable Circuit Breaker GFI: GFCI Circuit Breaker MLO: Main Lug Only FCB: Feeder Circuit Breaker MCCB: Molded Case Circuit Breaker Legend: Notes:
Total Est. Demand Current (80% Rated): 0 A
Continuous Current @ 125%: 0 A Non-Cont. Current @ 100%: 0 A
Total Est. Demand Current (100% Rated): 0 A Total Est. Demand: 0 VA
Load Classification Connected Load Demand Factor Estimated Demand Panel Totals
Total Amps: 0 A 0 A 0 A Total Load: 0 VA 0 VA 0 VA
31 Space -- -- 0 0 -- -- Space 32 29 Space -- -- 0 0 -- -- Space 30 27 -- -- -- 0 0 -- -- Space 28 25 (E) LTG - Plaza Pole 20 A 2 0 0 -- -- Space 26 23 -- -- -- 0 0 -- -- -- 24 21 (E) LTG - Parking Lot 20 A 2 0 0 2 150 A (E) L4 22 19 -- -- -- 0 0 -- -- -- 20 17 (E) L3 150 A 2 0 0 2 225 A (E) L2 18 15 -- -- -- 0 0 -- -- -- 16 13 (E) L1 225 A 2 0 0 2 20 A Spare 14 11 -- -- 0 0 -- -- -- 12 9 0 0 2 200 A Spare 10 7 Space -- -- 0 0 -- -- -- 8 5 0 0 2 100 A Spare 6 3 Spare with Lock - On 20A 1 0 0 1 20 A 4 1 Spare 20 A 1 0 0 1 20 A Spare 2
CKT Circuit Description Trip P A B C P Trip Circuit Description CKT
Mounting: Wires: 3 FCB / MCB Rating: 800 A Supply From: MDP Phases: 1 MLO / MCB: MCB
Location: Exterior Wall Outside Mechanical Room 104 Volts: 120/240 A.I.C. Rating:
New Branch Panel:DP2
WALL PENETRATION AND PANEL MOUNTING NOTES:
1. THERE IS AN EXISTING STRUCTURAL GROUT FILLED CORE LOCATED WITHIN THE WALL DIRECTLY
ADJACENT TO PANEL DP-2 LOCATION. PER THE ORIGINAL CONSTRUCTION DRAWINGS OF THE BUILDING, THE FILLED CORE SHOULD BE 2'-0" WIDE CENTERED ON THE CONCRETE ROOF/CEILING BEAM VISIBLE
WITHIN THE MECHANICAL ROOM.
2. THE CONTRACTOR SHALL TEMPORARILY MARK ON THE WALL (CHALK, TAPE, OR OTHER COR APPROVED
METHOD) THE ANTICIPATED LINE OF THE GROUTED CORE PRIOR TO MARKING OUT PROPOSED
LOCATION OF THRU-WALL CORE DRILL PENETRATIONS TO FEED NEW CONDUIT TO NEW PANEL DP-2.
REVIEW THE PROPOSED PENETRATION LOCATIONS AND HOLE SIZES WITH COR AND RECEIVE WRITTEN
APPROVAL BEFORE PROCEEDING TO CORE DRILL INTO THE WALL.
3. BASED ON THE EXISTING CONSTRUCTION DRAWINGS AND EXPERIENCED DURING INSTALLATION OF THE
HVAC WALL LOUVER BY SEPARATE CONTRACT, THE CONTRACTOR SHOULD ENCOUNTER A WALL THAT IS
4" CONCRETE MASONRY UNIT - 4" RIGID STYROFOAM INSULATION CORE - 4" FACE BRICK. IF THE
CONTRACTOR ENCOUNTERS ANYTHING WITHIN THIS WALL OTHER THAN WHAT IS DESCRIBED HERE, THEY
SHALL STOP WORK IMMEDIATELY AND NOTIFY THE COR. DO NOT CONTINUE WITH WORK UNTIL A
DIRECTION IS PROVIDED BY THE CO/COR IN WRITING.
4. IT IS ANTICIPATED THAT THE SIZE AND QUANTITY OF THRU-WALL CORE-DRILLED HOLE PENETRATIONS
REQUIRED ARE AS FOLLOWS:
- TWO (2) 3" CONDUITS FOR PANEL FEEDER
- FOUR (4) 2" CONDUITS FOR EXISITING PANELBOARDS
- ONE (1) 1" TO WIREWAY BELOW EXISTING DP-2 ON THE INTERIOR OF THE MECHANICAL ROOM.
IF THE CONTRACTOR REQUIRES ANY ADDITIONAL THRU-WALL PENETRATIONS IN ORDER TO CONDUCT
THE WORK, THEY SHALL PROVIDE A WRITTEN SUBMITTAL TO THE COR AS WELL AS FIELD MARK ON THE
WALL IN ORDER TO RECEIVE APPROVAL OR RE-DIRECTION FROM THE COR IN WRITING.
5. SIZE OF NEMA 3R ENCLOSURE TO BE DETERMINED BY REQUIRED INTERIOR CLEAR SPACE DIMENSIONS
AND MAXIMUM EXTERIOR DIMENSIONS, AND ANTICIPATED CONSTRUCTION PER COORDINATION WITH
APPROVED PRODUCT MANUFACTURER. THE CONTRACTOR SHALL SUBMIT ALL SIZE AND ENCLOSURE
MANUFACTURER SHOP DRAWINGS AND SPECIFICATIONS TO CO FOR DETERMINATION OF APPROVAL
PRIOR TO ORDERING EQUIPMENT TO DEMONSTRATE ENCLOSURE AND PANELBOARD ARE DIRECTLY
COMPATIBLE.
6. ALL ENCLOSURES SHALL BE FABRICATED TO MEET DIMENSIONAL REQUIREMENTS . ALL ENCLOSURES
SHALL BE UL TESTED AND LISTED AS NEMA 3R.
7. SOME VARIATIONS TO COMPONENTS OF ENCLOSURE ARE ANTICIPATED TO VARY BY MANUFACTURER.
ANY MINOR VARIATIONS IN SIZE AND CONSTRUCTION WILL BE REVIEWED AS PART OF SUBMITTAL
PROCESS.
8. MANUFACTURER SHALL PROVIDE SHALLOW 1-5/8" X 13/16" STAINLESS STEEL UNISTRUT CHANNEL ALONG
BACK OF SURFACE MOUNTED ENCLOSURES FOR MEANS OF SURFACE MOUNTING TO WALLS.
9. ALL CONDUIT UTILIZED INTO AND OUT OF CONDUIT ENTRY POINTS SHALL BE LIQUID-TIGHT CONDUIT.
FOR ENTRY POINTS THAT PROVIDED SHARED ENTRY FOR BRANCH CIRCUITS, E.C. SHALL SEAL ENTRY POINT
WITH LISTED SEALING COMPOUND SUCH THAT WATERPROOF SEAL INTO NEMA 3R ENCLOSURE IS
MAINTAINED.
10 EQUIPMENT SHALL BE MOUNTED TO BACK-PAN WITH UNISTRUT MOUNTING SUPPORTS, DEPTHS
COORDINATED AS REQUIRED FOR EQUIPMENT FACES TO BE FLUSH AND ALIGNED WITH FRONT OF
NEMA 3R ENCLOSURES TO ENSURE FULL COMPLIANCE WITH NEC ARTICLES APPLICABLE. REQUIRED
WORKING CLEARANCES ARE ACHIEVED WHEN DOOR IS OPEN (90 DEGREES).
11. THE CONTRACTOR SHALL SUBMIT TO THE CO FOR DETERMINATION OF APPROVAL ALL PROPOSED
METHODS OF MOUNTING THE PANEL TO THE EXTERIOR FACE OF THE BUILDING. THE SUBMITTAL SHALL
INCLUDE IDENTIFYING WEIGHT OF EQUIPMENT (PANELBOARD, ENCLOSURE, AND ESTIMATED CIRCUIT
TOTAL GROSS WEIGHT), MATERIALS, MEANS AND METHODS PROPOSED COMPATIBLE WITH THE
APPROVED PANELBOARD AND ENCLOSURE MANUFACTURER.
12. THE CONTRACTOR SHALL MINIMIZE IMPACT TO THE VISITOR CENTER BUILDING AND WALL FACE IN
MANNER OF MOUNTING PANELBOARD AND ENCLOSURE WHILE SUFFICIENTLY CARRYING THE WEIGHT
OF THE EQUIPMENT. ANY THROUGH-WALL PENETRATIONS TO BOLT AND BEAR THE EQUIPMENT
THORUGH TO THE INSIDE FACE OF CMU DUE TO STRENGTH LIMITATIONS IN FACE BRICK TO CARRY THE
LOADS SHALL BE INDICATED. ANY PROPOSED EXTENSION OF UNISTRUT OR LIKE MATERIAL TO TOUCH OR
EMBED IN GROUND MUST DEMONSTRATE SOIL TYPES, BONDING, AND NUETRAL GROUNDING OF
MOUNTING MATERIALS WILL BE PROVIDED.
FIRE ALARM ELECTRICAL PHOTOS
SURFACE - NEMA 3R
22 KAIC
Spare with Lock - On
Space
Space Space
AutoCAD SHX Text
PARK 411 PROJECT 80021
AutoCAD SHX Text
PMIS NO.
AutoCAD SHX Text 274253D
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF 4
AutoCAD SHX Text
ARKANSAS POST NATIONAL MONUMENT GILLETE, ARKANSAS
AutoCAD SHX Text
DATE:
AutoCAD SHX Text 04/15/2025
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
SUBSHEET
AutoCAD SHX Text
DESIGNER:
AutoCAD SHX Text
CADD:
AutoCAD SHX Text
TECH REVIEW:
AutoCAD SHX Text
TLB
AutoCAD SHX Text
TLB
AutoCAD SHX Text
TLB
AutoCAD SHX Text
INITIAL
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
DATE
AutoCAD SHX Text E1.1
AutoCAD SHX Text
NEW ELECTRICAL WORK
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text APPROXIMATE LOCATION OF STRUCTURAL GROUT FILLED CORE WITHIN WALL (ESTIMATED 16" FROM EAST EDGE OF LOUVER
AutoCAD SHX Text INTERCEPT AND RE-ROUTE ELECTRICAL SERVICE FROM FIRE PANEL JUNCTION BOXES 1 AND 2 EXISTING WALL MOUNTED AND LABELED TO ROUTE TO SUB PANEL LP-1. RE-DIRECT SERVICE ALONG WALL BY JUNCTION BOX AND CONDUIT TO NEW PANEL DP-2 DEDICATED CIRCUITS WITH LOCK OUT COVERS MEETING NFPA AND NEC CODES.
AutoCAD SHX Text
FIRE ALARM PANEL ON EAST WALL (DIRECTLY ACROSS FROM PANEL DP-2)
AutoCAD SHX Text
CONDUIT TO JUNCTION BOX 2
AutoCAD SHX Text
(2) CONDUIT TO JUNCTION BOX 1
AutoCAD SHX Text EXISTING JUNCTION BOX (ABOVE MECHANICAL LOUVER) LABELED FIRE ALARM HOUSING SENSOR WIRES LEADING TO POINTS THROUGHOUT BUILDING. CONFIRM ROUTING OF CONDUIT FROM FIRE ALARM PANEL TO THIS JUNCTION
4" STEEL COLUMN
MECHANICAL
WOMEN'S
RESTROOM
MEN'S
RESTROOM
ELECTRICAL
SUB PANELS
FED FROM
PANEL DP-2
L1 L2 L3
ENLARGED ELECTRICAL PLAN - BID ADDITIVE
NEW ELECTRICAL NOTES:
1. AS A RESULT OF THE INSTALLATION OF THE MECHANICAL LOUVER LOCATED ADJACENT RIGHT OF
THE EXISTING ELECTRICAL PANEL DP-2, A ONE-INCH GALVANIZED ELECTRICAL CONDUIT WAS
SEVERED. THE CONDUIT ENDS WERE FLUSH CUT AND REMAIN ENCAPSULATED WITHIN A GROUT
CORE FILLED CAVITY OF THE EXTERIOR WALL ABOVE THE LOUVER AND WITHIN THE GROUT FILLED
4" CMU BLOCK CORE OF THE INSIDE FACE OF THE WALL BELOW THE LOUVER.
2. WITHIN THE CONDUIT THERE IS AN ESTIMATED 10 WIRES WHICH HAVE BEEN SEVERED. THESE
INCLUDE SERVICE TO SEVERAL DUPLEX OUTLETS WITHIN THE MECHANICAL ROOM , THE SOUTHERN
PORTION OF THE VISITOR CENTER, AND THE FIRE ALARM SYSTEM LOCATED WITHIN THE
MECHANICAL ROOM. THE FIRE ALARM SYSTEM HAS BEEN TEMPORARILY RE-ROUTED TO ANOTHER
JUNCTION BOX AND IS TO BE DIRECT WIRED FROM ALARM JUNCTION BOXES BACK TO NEW PANEL
DP-2 AS BASE SCOPE OF SERVICES.
3. IN COORDINATION WITH THE PARK STAFF AND BY CONTRACTOR DETERMINED METHODS,
DETERMINE TO THE GREATEST REASONABLE EXTENT THE OUTLETS AND SERVICES THAT ARE
CURRENTLY INOPERABLE DUE TO THE SEVERED CONDUIT (PARK TO HAVE IDENTIFIED AND
CONFIRMATION OF CIRCUITS IDENTIFIED AS SERVING THE INOPERABLE OUTLETS AND SERVICES. BY
PARK STAFF EXPLORATION, IT IS BELIEVED CIRCUIT #40 IN PANEL LP-1 IS WHAT WAS SEVERED.
4. IN ORDER TO RESTORE POWER TO SERVICE WITHIN THE SEVERED CONDUIT THAT IS TO BE FED FROM
PANEL DP-2, THE SCOPE OF WORK UNDER BID ADDITIVE 1 IS AS FOLLOWS:
4.1. THE CONTRACTOR SHALL CORE DRILL INTO THE EXISTING WALL BELOW THE MECHANICAL
LOUVER AS MEANS TO INTERCEPT THE EXISTING CONDUIT AND SEVERED WIRES. CORE
DRILLING SHALL BE EXPLORATORY WITH SMALLEST BIT NECESSARY TO LOCATE THE
CONDUIT. PHOTOS AND INPUT FROM STAFF TO ZERO IN ON WHERE THE CONDUIT IS
LOCATED. ALL DRILLED EXPLORATORY HOLES NOT RESULTING IN THE LOCATION OF THE
CONDUIT SHALL BE GROUT FILLED.
4.2. ONCE LOCATED, THE CONTRACTOR SHALL SUBMIT A PROPOSED MEANS OF RESTORING BY
CONTINUATION OF POWER BACK TO SUB-PANEL L-1 TO THE COR/CO FOR EVALUATION
AND WRITTEN APPROVAL BACK TO THE CONTRACTOR PRIOR TO COMMENCING WITH THE
WORK. CONSIDERED MEANS MAY INCLUDE BUT ARE NOT LIMITED TO:
4.2.1. INSTALL A JUNCTION BOX AT THE POINT OF INTERCEPTING THE CONDUIT IN THE
WALL BENEATH THE MECHANICAL LOUVER OPENING AND ROUTE NEW CONDUIT
AND WIRING DIRECTLY TO SUBPANEL L-1 IN THE ADJACENT ROOM.
4.2.2. BY SCANNING OR OTHER MEANS OF LOCATING STEEL CONDUIT WITHIN A WALL,
CHOSE TO INTERCEPT THE CONDUIT ABOVE THE MECHANICAL LOUVER, BUT NOT
WITHIN THE GROUTED CORE OF THE WALL, AND INSTALL SURFACE WALL MOUNTED
JUNCTION BOX AND ROUTE CONDUIT AROUND THE PERIMETER OF THE
MECHANICAL LOUVER AND RESTORE THE LOOP TO NEW JUNCTION BOX BELOW
LOUVER INSTALLED BY CONTRACTOR (AS DESCRIBED IN 4.2.1 ABOVE).
5. ALL WORK SHALL COMPLY WITH THE 2023 NATIONAL ELECTRICAL CODE
6. ALL EQUIPMENT SHALL BE UL LABELED AND LISTED FOR THE PURPOSE. MATERIAL SHALL BE NEW
AND SHALL CONFORM TO THE APPLICABLE STANDARD OR STANDARDS WHERE SUCH HAVE BEEN
ESTABLISHED FOR THE PARTICULAR MATERIAL ON QUESTION.
7. ELECTRICAL METALLIC TUBING MAY BE USED ON THE INTERIOR WITH SET SCREW FITTINGS. ATTACH
RIGID CONDUIT TO SHEET METAL ENCLOSURES WITH TWO BONDING TYPE LOCK NUTS AND
INSULATED BUSHING. CONDUIT BODIES OR JUNCTION BOXES MAY BE USED TO EXTEND CIRCUITS
AND SHALL BE COMPATIBLE WITH THE CONDUIT.
2" = 1'-0"
MECHANICAL ROOM LOOKING WEST
SEVERED CONDUIT BELOW MECHANICAL LOUVER SEVERED CONDUIT ABOVE MECHANICAL LOUVER
STEEL LINTEL HEADER
REPRESENTATIVE PHOTOS
1979 ORIGINAL CONSTRUCTION POWER FLOOR PLAN
AutoCAD SHX Text
PARK 411 PROJECT 80021
AutoCAD SHX Text
PMIS NO.
AutoCAD SHX Text 274253D
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF 4
AutoCAD SHX Text
ARKANSAS POST NATIONAL MONUMENT GILLETE, ARKANSAS
AutoCAD SHX Text
DATE:
AutoCAD SHX Text 04/15/2025
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
SUBSHEET
AutoCAD SHX Text
DESIGNER:
AutoCAD SHX Text
CADD:
AutoCAD SHX Text
TECH REVIEW:
AutoCAD SHX Text
TLB
AutoCAD SHX Text
TLB
AutoCAD SHX Text
TLB
AutoCAD SHX Text
INITIAL
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
DATE
AutoCAD SHX Text E1.2
AutoCAD SHX Text
NEW ELECTRICAL WORK BID ADDITIVE 1
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text APPROXIMATE LOCATION OF CONDUIT THAT WAS SEVERED THAT IS TO RESTORE CONNECTION TO SUB-PANEL L-1
AutoCAD SHX Text SUB-PANEL L-1 - SCOPE OF WORK TO RESTORE CONNECTION RESULTING FROM SEVERED CONDUIT IN MECHANICAL ROOM LOUVER OPENING
AutoCAD SHX Text
MECHANICAL RETURN AIR PLINTH
AutoCAD SHX Text
CONDUIT WITHIN GROUT FILLED 4" CMU BLOCK
AutoCAD SHX Text CONDUIT WITHIN GROUT FILLED 4" CORE OF WALL WITHIN HEADER CUT (NOTE, RIGID INSULATION SHOWN IN CORE WHERE GROUT TERMINATES)
AutoCAD SHX Text
MECHANICAL PLINTH AT WEST END OF MECHANICAL ROOM
AutoCAD SHX Text NOTE, STEEL LINTEL INSTALLED TO CARRY HEADER OF LOUVER OPENING. FURTHER CONCEALS SEVERED CONDUIT
AutoCAD SHX Text
NEW ELECTRICAL BRANCH PANEL DP-2 INSTALLED UNDER BASE SCOPE OF SERVICES
EXISTING POWER PLAN FROM 1979 CONSTRUCTION DOCUMENTS PROVIDED FOR THE CONTRACTOR CONVENIENCE. NO ASSURANCE OF EXISTING CONDITIONS AT THE TIME OF THIS CONTRACT ARE SAME. THIS GRAPHIC IS FOR POINT OF REFERENCE ONLY.
| Sheets and Views |
| C00 |
| ARPO 274253D_VC Panel DP-2_E0.1.pdf |
| Sheets and Views |
| L0 |
| ARPO 274253D_VC Panel DP-2_E1.1.pdf |
| Sheets and Views |
| L0 |
| ARPO 274253D_VC Panel DP-2_E1.2.pdf |
| Sheets and Views |
| L0 |
| ARPO 274253D_VC Panel DP-2_E1.1.pdf |
| Sheets and Views |
| L0 |
File details come from the government source that posted it. Updated .