B08_Solicitation_140L4326R0007_ESR_2026_Fence_Perm_Repair_Temp_Const_ver3-20-26.pdf
PDF 886 KB Posted
- Attached to
- ESR 2026 Fence Perm Repair Temp Const
- Solicitation number
- 140L4326R0007
About this file
This is a Request for Proposal (RFP) for a firm fixed-price construction contract to repair and construct fencing at the BLM Vale District Office in Malheur County, Oregon. The solicitation number is 140L4326R0007, issued March 20, 2026, with proposals due April 20, 2026 at 1430 PT. This is a service-disabled veteran-owned small business (SDVOSB) set-aside with an estimated project value between $500,000 and $1,000,000. The contractor must begin work within 10 calendar days of receiving notice to proceed and complete all work within 242 calendar days. Performance and payment bonds equal to 100 percent of the original contract price are required, with a bid guarantee of 20 percent of the bid price or $3,000,000, whichever is less. The contract is subject to Davis-Bacon wage requirements, prevailing wage standards, and Executive Order 14026 minimum wage requirements of $15.00 per hour.
The scope of work encompasses permanent fence repairs and temporary fence construction and removal across five fire-damaged areas: Little John Fire (7.85 miles), Rock Creek Fire (26.73 miles), Butte Fire (4.88 miles), Cow Valley Fire (5.67 miles), and Willowcreek Fire (6.8 miles). Work includes repairs to 3-4 wire barbed and smooth wire fencing, installation of T-posts, H-braces, rock jacks, stays, wire gates, and rock cribs, with completion dates of July 15, 2026 for temporary fence construction, September 30, 2026 for temporary fence removal, and December 31, 2026 for permanent fence repairs. Evaluation is based on a lowest-price technically acceptable (LPTA) approach, with one technical evaluation factor—relevant experience demonstrating at least three but no more than four similar fence projects completed as a prime contractor within six years—and price. Offerors must demonstrate knowledge of local market conditions, weather, and transportation complexities in the Oregon area. Proposals must be submitted electronically via email with separate technical and price proposals, and offerors are strongly encouraged to attend organized site visits scheduled for March 31 and April 1, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER, 1. SOLICITATION NO. 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF
AND AWARD 140L4326R0007 □ SEALED BID (IFB) INVITATION FDR BID
(Construction, Alteration, or Repair) [81 NEGOTIATED (RFP) REQUEST FOR PROPOSAL 03/20/2026 1
IMPORTANT - The "offer" section on the reverse must be fully completed by offerer.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6 . PROJECT NO.
7. ISSUED BY CODE I LHA 8. ADDRESS OFFER TO
BLM OR-ST OFC PROC MGMT BR(OR952) Susanne Clark, Contract Specialist at:
1220 SW 3rd Avenue, 12th Floor susanneclark@blm.gov and cc' PORTLAND OR 97204 blm_or_so_952_mail@blm.gov
9. FOR ►
I
a. NAME
INFORMATION CALL Susanne Clark I
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
5038086494
SOLICITATION
NOTE: In sealed bid solicitations "offer'' and "offerer" mean "bid and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
ESR 2026 Fence Perm Repair Temp Const for the BLM Vale District Office, Oregon
THIS SOLICITATION IS A SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS SET ASIDE.
IAW FAR 36.204 the magnitude of this project is between $500,000 and $1,000,000.
Company Name:
Company Point of Contact:
Email:
Phone:
SAM UEI:
11. The contractor shall begin performance within 10 calendar days and complete it within 2 4 2 calendar days after receiving
D award, (81 notice to proceed. This performance period is [81 mandatory D negotiable. (See Clause 52 • 211-10
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
[8)YES □ No
13. ADDITIONAL SOLICITATION REQUIREMENTS:
12b. CALENDAR DAYS
a. Sealed offers in original and __ 1 __ copies to perform the work required are due at the place specified in Item 8 by __ 1_4_3_0 __ (hour) local time 04/20/2026 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
b. An offer guarantee D is, [81 is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
PAGES
d. Offers providing less than __ 6 _0 __ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA- FAR (48 CFR) 53.236-1(d)
X susanneclark Pencil
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
AMOUNTS ►
18. The offerer agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
Continued ...
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
26. ADMINISTERED BY I LHA
BLM OR-ST OFC PROC MGMT BR(OR952)
1220 SW 3rd Avenue, 12th Floor
PORTLAND OR 97204
I ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
□ 10 U.S.C. 3204(a) ( □ 41 U.S.C. 3304(a) (
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
□ 28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return 1 copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
30b. SIGNATURE 30c. DATE
D 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
31a. NAME OF CONTRACTING OFFICER (Type or print)
Joy R. Menguita 31b. UNITED STATES OF AMERICA 31c. DATE
BY
STANDARD FORM 1442 (REV. 12/2022) BACK
REFERENCE NO. OF DOCUMENT BEING CONTINUED
CONTINUATION SHEET
140L4326R0007
NAME OF OFFEROR OR CONTRACTOR
ITEM NO. SUPPLIES/SERVICES
(A) (B)
00001
Product/Service Code: YlPZ
Product/Service Description: CONSTRUCTION OF
OTHER NON-BUILDING FACILITIES
NSN 7540-01-152-8067
QUANTITY UNIT
(C) (D)
PAGES
UNIT PRICE AMOUNT
(E) (F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
Fence Perm Repair Temp Const
ESR 2026 Fence Perm Repair Temp Const SOLICITATION NO. 140L4326R0007 BLM Vale District Office, Oregon Page 4 of 62
Section Title Part I—The Schedule
A Solicitation/contract form B Bid schedule C Specifications/Drawings D Packaging and marking E Inspection and acceptance F Deliveries or performance G Contract administration data H Special contract requirements
Part II—Contract Clauses I Contract clauses
Part III—List of Documents, Exhibits, and Other Attachments
J List of attachments Part IV—Representations and Instructions
K Representations, certifications, and other statements of offerors
L Instructions, conditions, and notices to offerors M Evaluation factors for award
BLM Vale District Office, Oregon Page 5 of 62
SECTION B – BID SCHEDULE
This requirement is for one (1) Firm Fixed Price Construction contract for ESR 2026 Fence Perm Repair Temp Const in multiple locations for the BLM Vale District Office in Malheur County, Oregon.
A unit price and extended amount must be set forth for each individual item shown here as well as the total for each fire area. Offers that do not reflect individual unit prices and a total for all items under each fire may be considered non-responsive and may not be considered for award.
PRICING SCHEDULE:
Item No.
Description – Permanent Fence Repair – Little John Fire – 7.85 miles
Estimated Quantity
Units Unit Price
Total Amount
1 3 or 4-wire (2-3 Barbed, 1 Smooth) Fence Repair 41,448 Feet $ $
2 Estimated T-Posts 518 Each $ $
3 Barbed Wire Roll 5820 Feet $ $
4 Smooth Wire Roll 2910 Feet $ $
5 H-Brace 32 Each $ $
6 Rock Jack 32 Each $ $
7 Barbed Wire Gate (4-wire) 12 Each $ $
8 Rock Crib 16 Each $ $
9 Stays 520 Each $ $
Subtotal $
Item No.
Description – Permanent Fence Repair – Rock Creek Fire – 26.73 miles
Estimated Quantity
Units Unit Price
Total Amount
10 3 or 4-wire (2-3 Barbed, 1 Smooth) Fence Repair 141,113 Feet $ $
11 Estimated T-Posts 1,764 Each $ $
12 Barbed Wire Roll 19,454 Feet $ $
13 Smooth Wire Roll 14,550 Feet $ $
14 H-Brace 106 Each $ $
15 Rock Jack 54 Each $ $
BLM Vale District Office, Oregon Page 6 of 62
16 Barbed Wire Gate (4-wire) 36 Each $ $
17 Rock Crib 54 Each $ $
18 Stays 2,125 Each $ $
Description – Temporary Fence Construction – Butte Fire – 4.88 miles
Estimated Quantity
Units Unit Price
Total Amount
19 3-wire (3 Barbed, 1 Smooth) Fence Install 25,766 Feet $ $
20 Estimated T-Posts 859 Each $ $
21 Barbed Wire Roll 51,533 Feet $ $
22 Smooth Wire Roll 25,766 Feet $ $
23 Easy Fence Panel 39 Each $ $
24 Barbed Wire Gate (4-wire) 4 Each $ $
Description – Temporary Fence Construction – Cow Valley Fire – 5.67 miles
Estimated Quantity
Units Unit Price
Total Amount
25 3-wire (3 Barbed, 1 Smooth) Fence Install 29,938 Feet $ $
26 Estimated T-Posts 998 Each $ $
27 Barbed Wire Roll 59,875 Feet $ $
28 Smooth Wire Roll 29,938 Feet $ $
29 Easy Fence Panel Kit 28 Each $ $
30 Barbed Wire Gate (4-wire) 6 Each $ $
BLM Vale District Office, Oregon Page 7 of 62
Description – Temporary Fence Removal – Willowcreek Fire – 6.8 miles
Estimated Quantity
Units Unit Price
Total Amount
31 3-wire (2 Barbed, 1 Smooth) Fence Removal 35,904 Feet $ $
Total Offer - $______________________________
PERFORMANCE PERIOD: See clause 52.211-10
ESTIMATED END DATE:
Temporary Fence Construction Completion Date: 07/15/2026 Temporary Fence Removal Completion Date: 09/30/2026 Permanent Fence Repair Completion Date: 12/31/2026
PERFORMANCE TIME: Estimated 242 Calendar Days
THIS SOLICITATION IS A SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS SET ASIDE.
(End of Section B)
BLM Vale District Office, Oregon Page 8 of 62
SECTION C –SPECIFICATIONS/DRAWINGS
See Description/Specification attachments:
1. Attachment 1, Section C, Statement of Work and Drawings – 23 pages
2. Attachment 2, Section C, Fencing Standards – 57 pages
3. Attachment 3, Section C, FY26 ESR Fires Fence Contract Log (Excel)
BLM Vale District Office, Oregon Page 9 of 62
CONSTRUCTION SPILL PROVISIONS:
PART 2: PRODUCTS
A. Spark Arresters: Shall meet the requirements of the State of Oregon’s regulations.
PART 3: EXECUTION
3.01 HAZARDOUS MATERIAL CONTAINMENT/CLEANUP
A. During contractor operations on lands managed by the BLM, in event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, the Contractor shall immediately implement the SPCC plan as referenced herein and notify the on-site Government Contract Representative (COR or PI). The Government Representative will initiate the District’s Hazardous Materials Contingency Plan and/or Spill Containment Plan reporting requirements. The Government Representative will remain on scene until relieved by the District Hazardous Materials Management Coordinator (HMMC) or his/her representative.
B. Spill Prevention, Control, and Countermeasure Plan (SPCC): The Contractor shall develop an SPCC Plan as defined under 40 CFR Part 112. The SPCC Plan will be reviewed and accepted by the Contracting Officer prior to initiating project work. The SPCC Plan shall, as a minimum, contain the following information:
1. Response Priorities
2. Contractor Representative in Charge
3. Duties of Contractor Personnel
4. Contractor Emergency Response Procedures
5. Contents of Spill Containment Kit (SCK)
6. Spill Response Diagram
Upon request, an example of a SPCC may be obtained from the _________ District Environmental Protection Specialist for Hazardous Materials.
C. Spill Containment Kit (SCK): The Contractor shall have a SCK, as described in the SPCC, on-site during any operation and provide training to employees on how components of the SCK are used. The SCK must be designed for use with petroleum products, and must contain, as a minimum, the following items:
1. Two Bales (4 Booms/Bale, of 8" dia. X 10’ length Oil-only Absorbent Booms)
2. Two Bales (100 Pads/Bale, of Oil-only Absorbent Pads, minimum of 17"x19"x1/4")
3. One Oil-only Absorbent Sweep (minimum of 18" dia. X 100' length)
4. One Floating On-Water Containment Boom (minimum 18” width x 100’ length) (only required for in-stream or riparian work within 50 feet or less of a waterway.)
5. Gloves (PVC and Latex), Goggles, and Garbage Bags sufficient to contain soiled absorbents.
D. The Contractor shall implement the Emergency Response Actions described in the SPCC plan. Those actions include, but are not limited to, immediate action to protect employee health and safety, immediate action to stop the
BLM Vale District Office, Oregon Page 10 of 62 flow of product from the equipment, removal of equipment from the waterway if required and/or possible, deployment of the absorbent booms and pads downstream from the equipment, and any other immediate action as specified by Federal and/or State On-Scene Coordinators or his/her representative. The Contractor shall be responsible for cleanup/removal and proper disposal of contaminated materials from the site.
E. If the HMMC determines that additional resources are needed, the HMMC will implement the District’s Hazardous Materials Contingency Plan and the District Spill Containment Plan. The Contractor may be responsible for any or all costs associated with this level of effort. The amount of actual damage will be deducted by the Government from the amount due the Contractor prior to final payment.
(End of Section C)
BLM Vale District Office, Oregon Page 11 of 62
SECTION D – PACKAGING AND MARKING
Section Does Not Apply
(End of Section D)
BLM Vale District Office, Oregon Page 12 of 62
SECTION E – INSPECTION AND ACCEPTANCE
The following clauses are incorporated by reference:
52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
(End of Section E)
BLM Vale District Office, Oregon Page 13 of 62
SECTION F – DELIVERIES OR PERFORMANCE
F.1.0 PERIOD OF PERFORMANCE
See clause 52.211-10 in Contract Clauses section.
F.2.0 PROGRESS PLAN
At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.
(End of Section F)
BLM Vale District Office, Oregon Page 14 of 62
SECTION G – CONTRACT ADMINISTRATION DATA
The following local clauses are provided in full text:
CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (JULY 2010)
(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR42.15.
(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available for Government use in evaluating past performance as part of a source selection action.
(c) We request that you furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/. The CPARS User Manual, registration for On Line Training for Contractor Representatives, and a practice application may be found at this site.
(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official's narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1 - 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating ''No comment" in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment." Your response is due within 30 calendar days after receipt of the CPAR.
(f) The following guidelines apply concerning your use of the past performance evaluation:
(1) Protect the evaluation as "source selection information." After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.
https://www.cpars.gov/
BLM Vale District Office, Oregon Page 15 of 62
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.
(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30- day review period.
(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of clause)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)
(FEB 2021)
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).
“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Products or Commercial Services included in commercial products or commercial services contracts.
The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice billed according to contract line items and rates.
2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.
3. If partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.
4. If final payment is billed, the last invoice shall state “FINAL”.
5. Contractor’s Release of Claims shall be submitted with the final invoice.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contract (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 – 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
(End of Section G) https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov
BLM Vale District Office, Oregon Page 16 of 62
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1.0 BONDS
When a financial protection is covered by an individual surety, the Contractor shall email the signed Standard Form 28 Affidavit of Individual Surety to the contracting office using the instructions in Section L below.
Where authorized, bonds covered by United States bonds or notes, certified cashier’s checks, bank drafts or money orders must be mailed to the below address using ATTN: CBS Lead [Contractor insert Contract no.]
Bureau of Land Management Oregon State Office ATTN: Branch of Procurement Management [Contractor insert Contract no.] P.O. Box 2965 Portland, OR 97208
H.2.0 ACCESS
In the event of a site/facility closure, the Contractor shall not perform or make deliveries to the site/facility until it is reopened by the Government, unless otherwise instructed by the Contracting Officer or their designated representative.
H.3.0 WORK HOURS
Unless otherwise specified in Section C, Specifications, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be done on Saturday, Sunday, or Federal holidays unless authorized by the COR.
H.4.0 ENVIRONMENTAL INTERRUPTION OF WORK
H.4.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work where the Contractor proceeds during unsafe adverse weather or site conditions, and/or fire danger. Historical average days of severe weather have been included in the performance period. The Contractor will not be entitled to additional contract time or compensation for any such suspensions except when unusually severe weather or unforeseen conditions exist.
H.4.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, or Federal candidate (Category 1 and 2), sensitive or state listed species, identified under BLM Manual 6840, are discovered to be present in or adjacent to the project area.
H.5.0 DRAWINGS
H.5.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size.
Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. The Contractor may request full-size drawings from the Contracting Officer.
H.6.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
H.6.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.
BLM Vale District Office, Oregon Page 17 of 62
H.6.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.
H.6.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in the Contract Clauses Section of this contract.
H.6.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.
H.7.0 SUBSTITUTION – PROCESSION OF WORK
Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the quotation accepted. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.
H.8.0 ENVIRONMENTAL IMPACT
All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ);
the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.
H.9.0 HAZARDOUS MATERIALS
Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.
Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR
1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
BLM Vale District Office, Oregon Page 18 of 62
H.10.0 GREEN PROCUREMENT REQUIREMENTS
In the performance of this service or construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, if applicable:
• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.
• USDA Biobased product listings published at www.biopreferred.gov.
• Energy Star® product listings published at www.energystar.gov/products.
• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories
Contractor shall comply with all reporting requirements stated in the applicable clause(s):
• 52.223-1 Biobased Product Certification
• 52.223-2 Reporting of Biobased Products under Service and Construction Contracts
• 52.223-4 Recovered Material Certification
• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items
H.11.0 UNAUTHORIZED PERSONNEL
The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
H.12.0 CONSTRUCTION WAGE RATES APPLICABLE TO TRUCK DRIVERS
29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon Act.
H.13.0 FIRE DANGER SEASON
If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state and local laws relating to fire prevention and with all special conditions of work as directed by the COR and outlined in the attachment at the end of this section.
H.14.0 SUBMITTALS
H.14.1 LIABILITY INSURANCE
In accordance with clause 1452.228-70, upon contract award submit a copy of an acceptable insurance certificate to the Contracting Officer prior to beginning the work by sending it to blm_or_so_952_mail@blm.gov and susanneclark@blm.gov.
The following clause is provided in full text:
http://www.epa.gov/cpg/products.htm http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories
BLM Vale District Office, Oregon Page 19 of 62
FIRE REQUIREMENTS PROCEDURES OUTLINE FOR OREGON, Dec 2013
This outline covers the fire protection requirements of a contractor or private party who performs service or construction contracts on BLM land. In western Oregon, the BLM allows Oregon Forest Law (ORS) and Oregon Administrative Rules (OAR) to apply to these operations on BLM lands rather than develop similar rules applicable only to BLM lands.
1. CLOSED FIRE SEASON
The closed fire season means that fire season has been declared. ORS 477.505 gives the State Forester the authority to establish the fire season. The authority has been delegated to the District Foresters around the state who issue public notices through the newspapers and radio when fire season will be closed for their individual districts.
Closed fire season depends upon the drying of forest fuels, rainfall, and time of year. During the closed fire season, the following requirements must be met:
• Fire tools must be on site;
• Fire extinguisher must be in all vehicles;
• Chainsaws must have a .023-inch mesh screen installed in the exhaust;
• Only unmodified saws are to be used in the forest;
• Approved spark arresters must be on all internal combustion engines;
• Watchman service must be provided for 3 hrs after shutdown of power equipment for the day;
• No smoking is permitted while working or traveling through any operations area in the forest;
• No use of explosives is permitted unless approved by the State Forester's representative;
• Permits to burn are required unless waived by a representative of the State Forester.
• Permits to operate power-driven machinery shall be obtained by the Contractor prior to commencing operations unless waived by a representative of the State Forester (ORS 47.625).
Changes or modifications to the above requirements are possible depending upon changes in State of Oregon law and requirements of the State Districts and Protective Associations.
2. FIRE PRECAUTION LEVELS
There are 4 fire precaution levels that begin with level 1 at the start of the closed fire season and can go through level 4 if conditions warrant. The fire precaution levels restrict certain forest operations as the fire danger increases.
It is the responsibility of the individual operating on forest land to know the precaution level for the day and take the correct fire precautions. There are no precaution levels prior to the closed fire season. Each fire precaution level requires adherence to the restrictions applicable to all lower levels in addition to the limits placed by that level.
Level 1 is the lowest level of fire danger usually occurring early in the season and perhaps again after significant rainfall during the season. All requirements listed above apply. Waivers may be issued by the State Districts or Protective Associations and these MUST be approved by the BLM. Waivers will only be considered if the conditions on the work site are not as severe as predicted. The requirements for fire tools on site, screens installed in saws, and fire extinguishers with saws will not be waived.
Level 2 is the partial hootowl where saws can operate from first light in the morning until 1:00 p.m. in the afternoon.
From 1:00 p.m. until the end of the day saws are to be shut down. Waivers for operating beyond the 1:00 p.m.
shutdown will be evaluated on a site-by-site basis.
Level 3 is the partial shutdown of all forest industrial operations and shuts down contractor operations with few exceptions. Waivers may be issued on a site-by-site basis.
Level 4 is the general shutdown of all contractor operations. Waivers will not be issued. Landowners are permitted entry into their lands.
ORS. 477.066 requires that an operator on forest land take immediate action to control and extinguish a fire on forest land. The contractor shall take this action and notify the BLM and the nearest State of Oregon District office immediately.
BLM Vale District Office, Oregon Page 20 of 62
OAR. 629-43-030 requires watchmen to be:
• Physically capable and experienced in operating any firefighting equipment on site.
• On duty for 3 hours after the shutdown of the last power-driven equipment for the day.
• Furnished adequate facilities for transportation and communications in order to summon assistance if needed.
• Patrolling and visually inspecting all sites where work was done during the day.
3. FIRE TOOLS REQUIRED DURING CLOSED FIRE SEASON
The operator/contractor shall furnish fire tools to all personnel on site using the following combinations.
NUMBER OF PERSONNEL_______________________________
1- 4 5 6 7 8 9 10 11 12 13 14
KIND OF TOOLS NUMBER OF TOOLS REQUIRED_________________________
Pulaskis 1 1 1 1 1 1 2 2 2 2 2
Shovels 2 2 2 3 3 3 3 4 4 5 5
Hazel hoes 1 2 3 3 4 5 5 5 6 6 6
In addition to the above handtools, the operator/contractor must provide a backpack pump can filled with water located with the tool box in a readily available area.
All shovels are to be size 0 or larger, long handled. All tools shall be sharp and ready for service. Fire extinguishers as follows:
For chainsaws - 8 oz. capacity by weight.
For vehicles - UL rating of at least 4 BC.
4. ADDITIONAL WATER SUPPLY
Contractor shall comply with ORS 477.615 during fire season when inside or within one-eighth of one mile of a state forest protection district and furnish additional water supply and equipment for use in fire suppression in conformity with the rules promulgated by the Oregon State Forester, when directed by the Oregon State Forester in writing. When required, all water supply and equipment components shall be maintained and ready for immediate use.
During fire season when operating a stationary internal combustion engine inside or within one eighth of one mile of a state forest protection district, Contractor shall comply with ORS 477.650 and provide a water supply, with equipment for its use in fire suppression for each engine, in conformity with the rules promulgated by the Oregon State Forester. All water supply and equipment components shall be maintained and ready for immediate use.
(End of Section H)
BLM Vale District Office, Oregon Page 21 of 62
SECTION I – CONTRACT CLAUSES
The following clauses are incorporated by reference:
Clause Title Date
52.202-1 DEFINITIONS NOV 2013
52.203-3 GRATUITIES APR 1984
52.203-5 COVENANT AGAINST CONTINGENT FEES MAY 2014
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE
GOVERNMENT
NOV 2021
52.203-7 ANTI-KICKBACK PROCEDURES MAY 2014
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR
ILLEGAL OR IMPROPER ACTIVITY
MAY 2014
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER
ACTIVITY
MAY 2014
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL
TRANSACTIONS
OCT 2010
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND
REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER
RIGHTS
APR 2014
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL
CONFIDENTIALITY AGREEMENTS OR STATEMENTS
JAN 2017
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER
SUBCONTRACT AWARDS
JUN 2020
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE AUG 2020
52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,
AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB
COVERED ENTITIES
DEC 2023
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN
TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES
OR EQUIPMENT
AUG 2020
52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION JUN 2023
52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT
ORDERS—PROHIBITION
DEC 2023
52.209-6 PROTECTING THE GOVERNMENT’S INTERESTS WHEN
SUBCONTRACTING WITH CONTRACTORS DEBARRED,
SUSPENDED, PROPOSED FOR DEBARMENT, OR VOLUNTARILY
EXCLUDED
JAN 2025
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS
OCT 2018
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC
CORPORATIONS
NOV 2015
52.211-13 TIME EXTENSIONS SEPT 2000
52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984
52.215-2 AUDIT AND RECORDS – NEGOTIATION OCT 2010
52.215-14 INTEGRITY OF UNIT PRICES NOV 2021
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS JAN 2025
52.219-27 NOTICE OF SET-ASIDE FOR, OR SOLE-SOURCE AWARD TO,
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS
(SDVOSB) CONCERNS ELIGIBLE UNDER THE SDVOSB PROGRAM
FEB 2024
52.219-28 POSTAWARD SMALL BUSINESS REREPRESENTATION JAN 2025
52.222-3 CONVICT LABOR JUNE 2003
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS – MAY 2018
BLM Vale District Office, Oregon Page 22 of 62
OVERTIME COMPENSATION
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS AUG 2018
52.222-7 WITHHOLDING OF FUNDS MAY 2014
52.222-8 PAYROLLS AND BASIC RECORDS JUL 2021
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988
52.222-11 SUBCONTRACTS (LABOR STANDARDS) MAY 2014
52.222-12 CONTRACT TERMINATION-DEBARMENT MAY 2014
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE
REQUIREMENTS AND RELATED REGULATIONS
MAY 2014
52.222-14 DISPUTES CONCERNING LABOR STANDARDS FEB 1988
52.222-15 CERTIFICATION OF ELIGIBILITY MAY 2014
52.222-35 EQUAL OPPORTUNITY FOR VETERANS OCT 2015
52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES JUL 2014
52.222-37 EMPLOYMENT REPORTS ON VETERANS FEB 2016
52.222-40 NOTICE OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR
RELATIONS ACT
DEC 2010
52.222-50 COMBATING TRAFFICKING IN PERSONS OCT 2025
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION JAN 2025
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 JAN 2022
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES FEB 2021
52.227-1 AUTHORIZATION AND CONSENT DEC 2007
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND
COPYRIGHT INFRINGEMENT
DEC 2007
52.227-4 PATENT INDEMNITY -- CONSTRUCTION CONTRACTS DEC 2007
52.227-17 RIGHTS IN DATA - SPECIAL WORKS DEC 2007
52.228-2 ADDITIONAL BOND SECURITY OCT 1997
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS MAY 2014
52.228-14 IRREVOCABLE LETTER OF CREDIT MAY 2014
52.229-3 FEDERAL, STATE, AND LOCAL TAXES APR 2003
52.230-2 COST ACCOUNTING STANDARDS OCT 2015
52.232-5 PAYMENTS UNDER FIXED - PRICE CONSTRUCTION CONTRACTS MAY 2014
52.232-17 INTEREST MAY 2014
52.232-23 ASSIGNMENT OF CLAIMS MAY 2014
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS JAN 2017
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR
AWARD MANAGEMENT
OCT 2018
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS
MAR 2023
52.233-1 DISPUTES MAY 2014
52.233-1 DISPUTES – ALTERNATE I DEC 1991
52.233-3 PROTEST AFTER AWARD AUG 1996
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM OCT 2004
52.236-2 DIFFERING SITE CONDITIONS APR 1984
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984
52.236-5 MATERIAL AND WORKMANSHIP APR 1984
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984
52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991
52.236-8 OTHER CONTRACTS APR 1984
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,
EQUIPMENT, UTILITIES, AND IMPROVEMENTS
APR 1984
52.236-10 OPERATIONS AND STORAGE AREAS APR 1984
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984
BLM Vale District Office, Oregon Page 23 of 62
52.236-12 CLEANING UP APR 1984
52.236-13 ACCIDENT PREVENTION NOV 1991
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984
52.236-17 LAYOUT OF WORK APR 1984
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1997
52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995
52.240-1 PROHIBITION ON UNMANNED AIRCRAFT SYSTEMS
MANUFACTURED OR ASSEMBLED BY AMERICAN SECURITY
DRONE ACT-COVERED FOREIGN ENTITIES
NOV 2024
52.242-13 BANKRUPTCY JUL 1995
52.242-14 SUSPENSION OF WORK APR 1984
52.243-4 CHANGES JUN 2007
52.244-5 COMPETITION IN SUBCONTRACTING DEC 1996
52.246-21 WARRANTY OF CONSTRUCTION MAR 1994
52.248-3 VALUE ENGINEERING - CONSTRUCTION OCT 2025
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
(FIXED-PRICE)
APR 2012
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
(FIXED-PRICE) – ALTERNATE I
SEP 1996
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) APR 1984
52.253-1 COMPUTER GENERATED FORMS JAN 1991
The following clauses are provided in full text:
52.204-14 – SERVICE CONTRACT REPORTING REQUIREMENTS (JAN 2014)
(a) Definition.
“First-tier subcontract” means a subcontract awarded directly by the Contractor for the purpose of acquiring supplies or services (including construction) for performance of a prime contract. It does not include the Contractor’s supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a Contractor’s general and administrative expenses or indirect costs.
(b) The Contractor shall report, in accordance with paragraphs (c) and (d) of this clause, annually by October 31, for services performed under this contract during the preceding Government fiscal year (October 1-September 30).
(c) The Contractor shall report the following information:
(1) Contract number and, as applicable, order number.
(2) The total dollar amount invoiced for services performed during the previous Government fiscal year under the contract.
(3) The number of Contractor direct labor hours expended on the services performed during the previous Government fiscal year.
(4) Data reported by subcontractors under paragraph (f) of this clause.
(d) The information required in paragraph (c) of this clause shall be submitted via the internet at www.sam.gov. (See SAM User Guide). If the Contractor fails to submit the report in a timely manner, the contracting officer will http://www.sam.gov/
BLM Vale District Office, Oregon Page 24 of 62 exercise appropriate contractual remedies. In addition, the Contracting Officer will make the Contractor’s failure to comply with the reporting requirements a part of the Contractor’s performance information under FAR subpart 42.15.
(e) Agencies will review Contractor reported information for reasonableness and consistency with available contract information. In the event the agency believes that revisions to the Contractor reported information are warranted, the agency will notify the Contractor no later than November 15. By November 30, the Contractor shall revise the report or document its rationale for the agency.
(f)
(1) The Contractor shall require each first-tier subcontractor providing services under this contract, with subcontract(s) each valued at or above the thresholds set forth in 4.1703(a)(2), to provide the following detailed information to the Contractor in sufficient time to submit the report:
(i) Subcontract number (including subcontractor name and DUNS number); and
(ii) The number of first-tier subcontractor direct-labor hours expended on the services performed during the previous Government fiscal year.
(2) The Contractor shall advise the subcontractor that the information will be made available to the public as required by section 743 of Division C of the Consolidated Appropriations Act, 2010.
(End of Clause)
52.211-10 – COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 242 days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
52.219-14 - LIMITATIONS ON SUBCONTRACTING (OCT 2022 DEVIATION)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status);
and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
BLM Vale District Office, Oregon Page 25 of 62
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or
19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees to the following requirements in the performance of a contract assigned a North American Industry Classification System (NAICS) code applicable to this contract:
(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.
(i) The following services may be excluded from the 50 percent limitation:
(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases.
(B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts
BLM Vale District Office, Oregon Page 26 of 62 will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.
(3) General…