B08_Solicitation_140L4324Q0127_Fence_Retrofitting_for_Wildlife.pdf

PDF 18 MB Posted

Attached to
FENCE RETROFITTING FOR WILDLIFE Federal contract opportunity
Solicitation number
140L4324Q0127
Issued by
Department of the Interior Bureau of Land Management Oregon-Washington

About this file

This document is a Solicitation for FENCE RETROFITTING FOR WILDLIFE, Solicitation Number 140L4324Q0127, issued by the Department of the Interior Bureau of Land Management Oregon-Washington.

The solicitation is seeking vendors to provide fence retrofitting services to enhance wildlife passage and reduce wildlife-vehicle collisions along designated roadways in the Oregon-Washington region. Key requirements include supplying and installing various fence modifications such as jump-outs, vehicle reflectors, and wildlife passage openings. The period of performance is 12 months from the date of award. Pricing is to be submitted on a firm-fixed-price basis. This is a small business set-aside procurement. The response deadline is September 30, 2022, and the anticipated award date is November 15, 2022. No information is provided about incumbent contractors.

View the file

Other files for this federal contract opportunity

Other files attached to FENCE RETROFITTING FOR WILDLIFE, newest first.
File Type Posted
Sol_140L4324Q0127_Amd_0001.pdf PDF
B09_Amend0001_140L4324Q0127_FenceRetrofitingForWildlife_0001.pdf PDF
Sol_140L4324Q0127.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER, 1. SOLICITATION NO. 2. TYPE OF SOLICITATION r3. DATE ISSUED PAGE OF PAGES

□ ���:�g�

D F<g':k1D

ANDAWARD 140L4324Q0127

(Construction, Alteration, or Repair) □ NEGOTIATED IRFPl 07/02/2024 REQUEST FOR PROPOSAL

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

LHA

BLM OR-ST OFC PROC MGMT BR(OR952 )

1220 SW 3rd Avenue, 12th Floor

PORTLAND OR 97 204

9. FOR

INFORMATION CAL

5. REQUISITION/PURCHASE REQUEST NO.

0040651851

8. ADDRESS OFFER TO

6. PROJECT NO.

Susanne Clark, Contract Specialist susanneclark@blm.gov blm_or_so 952_mail@blm.gov

SOLICITATION

NOTE: In sealed bid solicitations "offer'' and "offeror" mean "bid" and "bidder."

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Tille, identifying no., date)

1 I

Fence Retrofitting for Wildlife for the ELM-Lakeview District Office, Oregon

11. The Contractor shall begin performance within calendar days and complete it within 4 Q calendar days after receiving

□ award, ["] notice to proceed. The performance period is ["]mandatory □negotiable. (See 52 . 211-10, Atl I and Section B_)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES� indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

ll<lYES □ NO

a. Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by

12b. CALENDAR DAYS

1430 (hour) local time

08/01/2024 (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due .

b. An offer guarantee D is, i"J is not required.

c. All offers are subject to Iha (1) work requirements, and (2) other provisions and clauses incorporated in Iha solicitation in full taxi or by reference.

d. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected .

NSN 7540-01-155-3212 STANDARD FORM 1442 (Rev. 12/2022) Prescribed by GSA

FAR(48 CFR) 53.236-1 (d) x

Company Name:____________________________________________

Company POC:_____________________________________________

Email Address:______________________________________________

Phone Number:_____________________________________________

SAM UEI No.:_______________________________________________

The magnitude of this construction project is between $25,000 and $100,000.

See Clause 52.228-13 Alternative Payment Protections

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

17. The offerer agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

AMOUNTS

► I

18. The offerer agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and dale of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER {Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

Continued.

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY

BLM OR-ST OFC PROC

1220 SW 3rd Avenue, PORTLAND OR 97204

D 10 U.S.C. 3204(a} D 41 U.S.C. 3304(a}

CODE I LHA 27. PAYMENT WILL BE MADE BY

MGMT BR(OR952)

12th Floor

CONTRACT/NG OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

□ 28. NEGOTIATED AGREEMENT (Contraclor is required to sign this document 029.AWARD (Contraclor is not required to sign this document.) Your offer on this and retum copies to issuing office.) Contractor agrees to furnish solicitation is hereby accepted as to the items listed. This award consummates the and deliver all items or perform all work requirements identified on this form and contract, which consists of (a) the Government solicitation and your offer, and (b) any continuation sheets for the consideration stated in this contract. The rights this contract award. No further contractual document is necessary.

and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and soecifications incomorated bv reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN {Type or prinQ 31a. NAME OF CONTRACTING OFFICER {Type or print)

Fortunato Sapida Jr

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

STANDARD FORM 1442 (REV. 1212022) BACK

CONTINUATION SHEET

EFERENCE NO. OF DOCUMENT BEING CONTINUED

140L4324Q0127

NAME OF OFFEROR OR CONTRACTOR

ITEM NO. SUPPLIES/SERVICES

(A) (B)

Delivery: 09/30/2025

Delivery Location Code: 0004276558

BLM-OR LAKEVIEW DISTRICT OFFICE*

1301 SOUTH G STREET

LAKEVIEW OR 97630 US

Period of Performance: 08/10/2024 to 09/30/2025

00010 Fence retrofitting/repair for wildlife

Product/Service Code: Z2PZ

Product/Service Description: REPAIR OR ALTERATION

OF OTHER NON-BUILDING FACILITIES

NSN 7540-01-152-8067

QUANTITY UNIT UNIT PRICE

(C) (D) (E)

PAGE

OF

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFRl 53.110

Fence Retrofitting for Wildlife BLM-Lakeview District Office, Oregon

SOLICITATION NO. 140L4324Q0127

Section Title Part I—The Schedule

A Solicitation/contract form B Bid schedule C Specifications/Drawings D Packaging and marking E Inspection and acceptance F Deliveries or performance G Contract administration data H Special contract requirements

Part II—Contract Clauses I Contract clauses

Part III—List of Documents, Exhibits, and Other Attachments

J List of attachments Part IV—Representations and Instructions

K Representations, certifications, and other statements of offerors

L Instructions, conditions, and notices to offerors M Evaluation factors for award

SOLICITATION NO. 140L4324Q0127

SECTION B – BID SCHEDULE

This requirement is for one (1) Firm Fixed Price Construction contract for Fence Retrofitting for Wildlife for the BLM-Lakeview District Office, Oregon.

Price Schedule

Item Description Estimate Quantities

Unit Unit Price Total

1 Base

Maintain and Modify fence to meet wildlife standards.

Estimated days for completion of Base: 10 – 20 days

9.34 Mile $ $

TOTAL FOR BASE

2 Option 1 for increased quantities.

Maintain and Modify fence to meet wildlife standards.

Estimated days for completion of Option 1: 5 – 10 days

4.94 Mile $ $

3 Option 2 for increased quantities.

Estimated days for completion of Option 2: 5 – 10 days

5.36 Mile $ $

TOTAL FOR OPTIONS $

TOTAL FOR BASE AND ALL OPTIONS $

PERFORMANCE PERIOD: See clause 52.211-10, Alt I in Contract Clauses Section and Price Schedule (Section B).

THIS SOLICITATION IS SET ASIDE FOR SMALL BUSINESS CONCERNS.

(End of Section B)

SOLICITATION NO. 140L4324Q0127

SECTION C – SPECIFICATIONS/DRAWINGS

STATEMENT OF WORK

1. Description of Work:

Background: The Lakeview District of the Bureau of Land Management (BLM) is located within the range of pronghorn (Antilocapra americana) and other big game species such as mule deer (Odocoileus hemionus). Pronghorn typically crawl under fences, instead of jumping them; therefore, they require adequate space between the ground and lower wire to pass under the fence safely and easily during their daily movements and seasonal migrations. Additionally, loose fence wire poses a significant risk to wildlife, livestock, and humans. Many miles of fence on the Lakeview District do not comply with the recommended standards for ease of big game passage.

Purpose: The purpose of this project is to modify and improve existing fences to comply with recommended standards for pronghorn and other big game. Alteration of fences to these standards will minimize injury to big game and other wildlife and help mitigate human made barriers to herd passage.

Objective: Modify and/or repair 9.34 miles of existing fence (with an additional 10.3 miles as options; Figure 1-6; Photos 1-23) to meet standards for wildlife, with an emphasis on pronghorn. Most of these miles are currently in decent condition, but need the bottom wire replaced. The contractor will be responsible for making sure the entire fence meets the standards for wildlife.

Timelines for completion are discussed below.

2. Project Locations:

The project is on lands administered by the Lakeview District BLM within Lake County and Harney County, Oregon.

See attached maps (Figures 1-6) and table of legal locations.

Legal Locations, Segment Length and Condition:

Segment Township

Range Section

County Current Condition Figure

Photos

Miles

Base Segment 1

T38S R28E

Sections 09, 16-18

Lake

3 strands, all t-posts with rock jack and t-post bracing; some leaning t-posts; replacement of t-posts estimated to be minimal, <10; brush cleared from fence as needed to re-string bottom with smooth / remove bottom barbed wire; bottom barbed wire needs replaced with smooth

Figure 1-3

Photos 1-13

5.28

SOLICITATION NO. 140L4324Q0127

Base Segment 2

T38S R28E

Section

Lake

4 strands, all t-posts with wooden post bracing in good condition; second from top wire is smooth

(old electric fence wire), can be re-used and placed on bottom if in good condition; brush cleared from fence as needed to re-string bottom with smooth / remove bottom barbed wire; bottom barbed wire needs replaced with smooth

Figure 1-2; 4 Photos 14-17

0.29

Base Segment 3

T38S R28E

Sections 13-15;

T38S R29E

Sections 18-19

Lake and

Harney

3 strands, all t-posts with wooden post bracing in good condition; replacement of t-posts estimated to be minimal, <10; any available smooth wire

(old electric fence) can be re-used and placed on bottom if in good condition; brush cleared from fence as needed to re-string bottom with smooth / remove bottom barbed wire; bottom barbed wire needs replaced with smooth

Figure 1-2; 4 Photos 18-23

3.77

Option 1

T40S R27E

Sections 04, 05 08, 17, 20, 21, 29;

T39S R27E

Section

Lake

3-4 strands, all t-posts; about half has sagging barbed wire, overall considered in semi-functional condition; bottom barbed wire needs replaced with smooth

Figure 1, 5 4.94

Option 2

T39S R26E

Sections 25, 26, 35; T40S R26E 02, 11, 14, 15

Lake

3-4 strands; some portions of sagging barbed wire and leaning t-posts, overall considered in good condition; bottom barbed wire needs replaced with smooth

Figure 1, 6 5.36

Access:

Base: Preferred route is via Beatys Butte Road off Highway 140. Access will be discussed during the Prework Conference. Area closures, project activities, or weather may temporarily preclude access to some field areas. Historical weather conditions that preclude work have been accounted for and included in the performance period.

Option 1 and Option 2: Preferred route is via Highway 140. Access will be discussed during the Prework Conference. Area closures, project activities, or weather may temporarily preclude access to some field areas. Historical weather conditions that preclude work have been accounted for and included in the performance period.

SOLICITATION NO. 140L4324Q0127

3. Specific Requirements:

• Notify BLM at least 7 days in advance of work location plans so permittees can also be notified of fence work.

• Section of fence undertaken each day shall be completed the same day it is started, to avoid cattle trespass.

• Replace bottom barbed fence wire with smooth (barbless) wire and place 16”-18” above the ground.

• If bottom wire is already smooth, but too low, raise to 16”-18” above the ground.

• Ensure all fence wires are tight.

• Replace existing bent / damaged T-posts as needed, at current spacing.

• Replaced existing stays that were removed / damaged during wire replacement, at current spacing.

• Repair rock jacks / corner braces as needed.

• Ensure any wire gates within the identified altered sections meet the same specifications regarding smooth wire, height, and tautness.

• If marked with flight diverters for sage grouse, leave marked.

• Keep same number of strands as fence currently has.

• Clear brush on fence as needed to remove the bottom barbed wire / replace the bottom wire with smooth

• Haul away and properly dispose of damaged / waste wire, T-posts, wood posts, stays, and fence staples.

• Notify BLM at least 7 days in advance of proposed mowing along fence lines so biologist can inspect area for milkweed plants.

• Work shall be implemented when roads are dry or frozen to minimize potential damage to roads and other resources.

• Contractor shall clean any vehicles prior to entering or leaving a site, in order to minimize the potential risk of spreading noxious weeds/invasive non-native species.

• Contractor shall follow all fire restrictions put in place by South Central Oregon Fire

Management Partnership https://scofmp.org/restrictions.shtml https://scofmp.org/restrictions.shtml

SOLICITATION NO. 140L4324Q0127

4. Contractor Furnished Items:

• T-post wire Clips

• Fence staples

• Stays

• Barbed wire for rebuild sections

• Rolls of smooth wire to replace the bottom wire of the fence

• Metal T-Posts to be used to support the fence, however any T-posts in good condition may be reused for the project.

• All equipment and supplies needed roll up old wire.

• All equipment needed to roll out new wire for bottom wire

SOLICITATION NO. 140L4324Q0127

5. Government Furnished Items:

• Geo-reference digital maps and paper maps with the project location and best access.

6. Deliverables:

Performance will include completion of 9.34 miles (Base), and/or 4.94 miles (Option 1), and/or 5.36 miles (Option 2) of fence alteration meeting the specific requirements above.

7. Inspection and Acceptance:

The BLM will require regular status updates from the Contractor. BLM may visit the field at any time or may request an update on miles of accomplishment. The Contractor shall submit a weekly progress report to the BLM so the BLM can begin inspecting the completed sections. Work will be accepted when the deliverables have been satisfactorily met and all requirements in the statement of work and contract.igure 1. Overview of contracted options

SOLICITATION NO. 140L4324Q0127

Figure 2. Overview of Base

SOLICITATION NO. 140L4324Q0127

Figure 3. West Section of Base

SOLICITATION NO. 140L4324Q0127

Figure 4. East Section of Base

SOLICITATION NO. 140L4324Q0127

Figure 5. Option 1

SOLICITATION NO. 140L4324Q0127

Figure 6. Option 2

SOLICITATION NO. 140L4324Q0127

Photo 1. Base Segment 1

Photo 2. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 3. Base Segment 1

SOLICITATION NO. 140L4324Q0127

SOLICITATION NO. 140L4324Q0127

Photo 4. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 5. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 6. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 7. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 8. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 9. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 10. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 11. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 12. Base Segment 1

SOLICITATION NO. 140L4324Q0127

Photo 13. Base Segment 1

Photo 14. Base Segment 2

SOLICITATION NO. 140L4324Q0127

Photo 15. Base Segment 2

SOLICITATION NO. 140L4324Q0127

Photo 16. Base Segment 2

SOLICITATION NO. 140L4324Q0127

Photo 17. Base Segment 2

SOLICITATION NO. 140L4324Q0127

Photo 18. Base Segment 3

SOLICITATION NO. 140L4324Q0127

Photo 19. Base Segment 3

SOLICITATION NO. 140L4324Q0127

Photo 20. Base Segment 3

SOLICITATION NO. 140L4324Q0127

Photo 21. Base Segment 3

Solicitation No. 140L4324Q0127

Fence Retrofitting for Wildlife

Photo 22. Base Segment 3

Fence Retrofitting for Wildlife

Photo 23. Base Segment 3

Fence Retrofitting for Wildlife BLM-Lakeview District Office, Oregon

(End of Statement of Work)

CONSTRUCTION SPILL PROVISIONS:

PART 2: PRODUCTS

A. Spark Arresters: Shall meet the requirements of the State of Oregon’s regulations.

PART 3: EXECUTION

3.01 HAZARDOUS MATERIAL CONTAINMENT/CLEANUP

A. During contractor operations on lands managed by the BLM, in event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, the Contractor shall immediately implement the SPCC plan as referenced herein and notify the on-site Government Contract Representative (COR or PI). The Government Representative will initiate the District’s Hazardous Materials Contingency Plan and/or Spill Containment Plan reporting requirements. The Government Representative will remain on scene until relieved by the District Hazardous Materials Management Coordinator (HMMC) or his/her representative.

SOLICITATION NO. 140L4324Q0127

B. Spill Prevention, Control, and Countermeasure Plan (SPCC): The Contractor shall develop an SPCC Plan as defined under 40 CFR Part 112. The SPCC Plan will be reviewed and accepted by the Contracting Officer prior to initiating project work. The SPCC Plan shall, as a minimum, contain the following information:

1. Response Priorities

2. Contractor Representative in Charge

3. Duties of Contractor Personnel

4. Contractor Emergency Response Procedures

5. Contents of Spill Containment Kit (SCK)

6. Spill Response Diagram

Upon request, an example of a SPCC may be obtained from the _________ District Environmental Protection Specialist for Hazardous Materials.

C. Spill Containment Kit (SCK): The Contractor shall have a SCK, as described in the SPCC, on-site during any operation and provide training to employees on how components of the SCK are used. The SCK must be designed for use with petroleum products, and must contain, as a minimum, the following items:

1. Two Bales (4 Booms/Bale, of 8" dia. X 10’ length Oil-only Absorbent Booms)

2. Two Bales (100 Pads/Bale, of Oil-only Absorbent Pads, minimum of 17"x19"x1/4")

3. One Oil-only Absorbent Sweep (minimum of 18" dia. X 100' length)

4. One Floating On-Water Containment Boom (minimum 18” width x 100’ length) (only required for in-stream or riparian work within 50 feet or less of a waterway.)

5. Gloves (PVC and Latex), Goggles, and Garbage Bags sufficient to contain soiled absorbents.

D. The Contractor shall implement the Emergency Response Actions described in the SPCC plan. Those actions include, but are not limited to, immediate action to protect employee health and safety, immediate action to stop the flow of product from the equipment, removal of equipment from the waterway if required and/or possible, deployment of the absorbent booms and pads downstream from the equipment, and any other immediate action as specified by Federal and/or State On-Scene Coordinators or his/her representative. The Contractor shall be responsible for cleanup/removal and proper disposal of contaminated materials from the site.

E. If the HMMC determines that additional resources are needed, the HMMC will implement the District’s Hazardous Materials Contingency Plan and the District Spill Containment Plan. The Contractor may be responsible for any or all costs associated with this level of effort. The amount of actual damage will be deducted by the Government from the amount due the Contractor prior to final payment.

(End of Section C)

SOLICITATION NO. 140L4324Q0127

SECTION D – PACKAGING AND MARKING

Section Does Not Apply

(End of Section D)

SOLICITATION NO. 140L4324Q0127

SECTION E – INSPECTION AND ACCEPTANCE

The following clauses are incorporated by reference:

52.246-12 INSPECTION OF CONSTRUCTION AUG 1996

See Paragraph #7 of Statement of Work.

(End of Section E)

SOLICITATION NO. 140L4324Q0127

SECTION F – DELIVERIES OR PERFORMANCE

F.1.0 PERIOD OF PERFORMANCE

See clause 52.211-10, Alt I in Contract Clauses section and and Price Schedule (Section B).

F.2.0 PROGRESS PLAN

At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.

(End of Section F)

Period of performance starts approximately 08/10/2024. All work must be completed by 09/30/2025. See the price schedule for expected number of days to complete the base, option 1 and option 2.

SOLICITATION NO. 140L4324Q0127

SECTION G – CONTRACT ADMINISTRATION DATA

The following local clauses are provided in full text:

CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (JULY 2010)

(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR42.15.

(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available for Government use in evaluating past performance as part of a source selection action.

(c) We request that you furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.

(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/. The CPARS User Manual, registration for On Line Training for Contractor Representatives, and a practice application may be found at this site.

(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official's narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1 - 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating ''No comment" in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment." Your response is due within 30 calendar days after receipt of the CPAR.

(f) The following guidelines apply concerning your use of the past performance evaluation:

(1) Protect the evaluation as "source selection information." After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.

(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

https://www.cpars.gov/ https://www.cpars.gov/ https://www.cpars.gov/ https://www.cpars.gov/

SOLICITATION NO. 140L4324Q0127

(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.

(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30- day review period.

(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of clause)

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)

(APR 2013)

Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).

“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Products or Commercial Services included in commercial item contracts. The IPP website address is:

https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Invoice billed according to contract line items and rates.

2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.

3. If the partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.

4. If final payment is billed, the last invoice shall state “FINAL”.

5. Contractor’s Release of Claims shall be submitted with the final invoice.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contract (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

(End of Section G) https://www.ipp.gov/ mailto:ippgroup@bos.frb.org

SOLICITATION NO. 140L4324Q0127

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1.0 BONDS

When a financial protection is covered by an individual surety, the Contractor shall mail Standard Form 28 Affidavit of Individual Surety in original, wet signature form to:

Bureau of Land Management Oregon State Office ATTN: Branch of Procurement Management [Contractor insert Contract no.] P.O. Box 2965 Portland, OR 97208

Where authorized, bonds covered by United States bonds or notes, certified cashier’s checks, bank drafts or money orders, mail to the above address using ATTN: CBS Lead [Contractor insert Contract no.].

H.2.0 ACCESS

In the event of a site/facility closure, the Contractor shall not perform or make deliveries to the site/facility until it is reopened by the Government, unless otherwise instructed by the Contracting Officer or their designated representative.

H.3.0 WORK HOURS

Unless otherwise specified in Section C, Specifications, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be done on Saturday, Sunday, or Federal holidays unless authorized by the COR.

H.4.0 ENVIRONMENTAL INTERRUPTION OF WORK

H.4.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work where the Contractor proceeds during unsafe adverse weather or site conditions, and/or fire danger. Historical average days of severe weather have been included in the performance period. The Contractor will not be entitled to additional contract time or compensation for any such suspensions except when unusually severe weather or unforeseen conditions exist.

H.4.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, or Federal candidate (Category 1 and 2), sensitive or state listed species, identified under BLM Manual 6840, are discovered to be present in or adjacent to the project area.

H.5.0 DRAWINGS

H.5.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size.

Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. The Contractor may request full-size drawings from the Contracting Officer.

H.6.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA

H.6.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.

H.6.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.

SOLICITATION NO. 140L4324Q0127

H.6.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in the Contract Clauses Section of this contract.

H.6.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.

H.7.0 SUBSTITUTION – PROCESSION OF WORK

Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the quotation accepted. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.

H.8.0 ENVIRONMENTAL IMPACT

All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ);

the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

H.9.0 HAZARDOUS MATERIALS

Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.

Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR

1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

H.10.0 GREEN PROCUREMENT REQUIREMENTS

In the performance of this service or construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, if applicable:

SOLICITATION NO. 140L4324Q0127

• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.

• USDA Biobased product listings published at www.biopreferred.gov.

• Energy Star® product listings published at www.energystar.gov/products.

• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories

Contractor shall comply with all reporting requirements stated in the applicable clause(s):

• 52.223-1 Biobased Product Certification

• 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

• 52.223-4 Recovered Material Certification

• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items

• 52.223-15 Energy Efficiency in Energy Consuming Products

• 52.223-17 Affirmative Procurement of EPA Designated Items in Service and Construction Contracts

H.11.0 UNAUTHORIZED PERSONNEL

The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

H.12.0 CONSTRUCTION WAGE RATES APPLICABLE TO TRUCK DRIVERS

29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon Act.

H.13.0 FIRE DANGER SEASON

If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR and outlined in the attachment at the end of this section.

Special Contract Requirements:

FIRE REQUIREMENTS PROCEDURES OUTLINE

This outline covers the fire protection requirements of a contractor or private party who performs service or construction contracts on BLM land. In western Oregon, the BLM allows Oregon Forest Law (ORS) and Oregon Administrative Rules (OAR) to apply to these operations on BLM lands rather than develop similar rules applicable only to BLM lands.

1. CLOSED FIRE SEASON

The closed fire season means that fire season has been declared. ORS 477.505 gives the State Forester the authority to establish the fire season. The authority has been delegated to the District Foresters around the state who issue public notices through the newspapers and radio when fire season will be closed for their individual districts.

http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories

SOLICITATION NO. 140L4324Q0127

Closed fire season depends upon the drying of forest fuels, rainfall, and time of year. During the closed fire season, the following requirements must be met:

• Fire tools must be on site;

• Fire extinguisher must be in all vehicles;

• Chainsaws must have a .023-inch mesh screen installed in the exhaust;

• Only unmodified saws are to be used in the forest;

• Approved spark arresters must be on all internal combustion engines;

• Watchman service must be provided for 3 hrs after shutdown of power equipment for the day;

• No smoking is permitted while working or traveling through any operations area in the forest;

• No use of explosives is permitted unless approved by the State Forester's representative;

• Permits to burn are required unless waived by a representative of the State Forester.

• Permits to operate power-driven machinery shall be obtained by the Contractor prior to commencing operations unless waived by a representative of the State Forester (ORS 47.625).

Changes or modifications to the above requirements are possible depending upon changes in State of Oregon law and requirements of the State Districts and Protective Associations.

2. FIRE PRECAUTION LEVELS

There are 4 fire precaution levels that begin with level 1 at the start of the closed fire season and can go through level 4 if conditions warrant. The fire precaution levels restrict certain forest operations as the fire danger increases.

It is the responsibility of the individual operating on forest land to know the precaution level for the day and take the correct fire precautions. There are no precaution levels prior to the closed fire season. Each fire precaution level requires adherence to the restrictions applicable to all lower levels in addition to the limits placed by that level.

Level 1 is the lowest level of fire danger usually occurring early in the season and perhaps again after significant rainfall during the season. All requirements listed above apply. Waivers may be issued by the State Districts or Protective Associations and these MUST be approved by the BLM. Waivers will only be considered if the conditions on the work site are not as severe as predicted. The requirements for fire tools on site, screens installed in saws, and fire extinguishers with saws will not be waived.

Level 2 is the partial hootowl where saws can operate from first light in the morning until 1:00 p.m. in the afternoon.

From 1:00 p.m. until the end of the day saws are to be shut down. Waivers for operating beyond the 1:00 p.m.

shutdown will be evaluated on a site-by-site basis.

Level 3 is the partial shutdown of all forest industrial operations and shuts down contractor operations with few exceptions. Waivers may be issued on a site-by-site basis.

Level 4 is the general shutdown of all contractor operations. Waivers will not be issued. Landowners are permitted entry into their lands.

ORS. 477.066 requires that an operator on forest land take immediate action to control and extinguish a fire on forest land. The contractor shall take this action and notify the BLM and the nearest State of Oregon District office immediately.

OAR. 629-43-030 requires watchmen to be:

• Physically capable and experienced in operating any firefighting equipment on site.

• On duty for 3 hours after the shutdown of the last power-driven equipment for the day.

• Furnished adequate facilities for transportation and communications in order to summon assistance if needed.

• Patrolling and visually inspecting all sites where work was done during the day.

SOLICITATION NO. 140L4324Q0127

3. FIRE TOOLS REQUIRED DURING CLOSED FIRE SEASON

The operator/contractor shall furnish fire tools to all personnel on site using the following combinations.

NUMBER OF PERSONNEL_______________________________

1- 4 5 6 7 8 9 10 11 12 13 14

KIND OF TOOLS NUMBER OF TOOLS REQUIRED_________________________

Pulaskis 1 1 1 1 1 1 2 2 2 2 2

Shovels 2 2 2 3 3 3 3 4 4 5 5

Hazel hoes 1 2 3 3 4 5 5 5 6 6 6

In addition to the above handtools, the operator/contractor must provide a backpack pump can filled with water located with the tool box in a readily available area.

All shovels are to be size 0 or larger, long handled. All tools shall be sharp and ready for service. Fire extinguishers as follows:

For chainsaws - 8 oz. capacity by weight.

For vehicles - UL rating of at least 4 BC.

4. ADDITIONAL WATER SUPPLY

Contractor shall comply with ORS 477.615 during fire season when inside or within one-eighth of one mile of a state forest protection district and furnish additional water supply and equipment for use in fire suppression in conformity with the rules promulgated by the Oregon State Forester, when directed by the Oregon State Forester in writing. When required, all water supply and equipment components shall be maintained and ready for immediate use.

During fire season when operating a stationary internal combustion engine inside or within one eighth of one mile of a state forest protection district, Contractor shall comply with ORS 477.650 and provide a water supply, with equipment for its use in fire suppression for each engine, in conformity with the rules promulgated by the Oregon State Forester. All water supply and equipment components shall be maintained and ready for immediate use.

(End of Special Contract Requirements)

(End of Section H)

SOLICITATION NO. 140L4324Q0127

SECTION I – CONTRACT CLAUSES

The following provision is incorporated by reference:

Clause Title Date

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017

The following clauses are incorporated by reference:

Clause Title Date

52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL

CONFIDENTIALITY AGREEMENTS OR STATEMENTS

JAN 2017

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER

SUBCONTRACT AWARDS

JUN 2020

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018

52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE AUG 2020

52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,

AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB

COVERED ENTITIES

DEC 2023

52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN

TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES

OR EQUIPMENT

NOV 2021

52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION JUN 2023

52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT

ORDERS—PROHIBITION

DEC 2023

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN

SUBCONTRACTING WITH CONTRACTORS DEBARRED,

SUSPENDED, OR PROPOSED FOR DEBARMENT

NOV 2021

52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC

CORPORATIONS

NOV 2015

52.211-13 TIME EXTENSIONS SEPT 2000

52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE NOV 2020

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION FEB 2024

52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS AUG 2018

52.222-7 WITHHOLDING OF FUNDS MAY 2014

52.222-8 PAYROLLS AND BASIC RECORDS AUG 2018

52.222-9 APPRENTICES AND TRAINEES JULY 2005

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988

52.222-11 SUBCONTRACTS (LABOR STANDARDS) MAY 2014

52.222-12 CONTRACT TERMINATION – DEBARMENT MAY 2014

52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE

REQUIREMENTS AND RELATED REGULATIONS

MAY 2014

52.222-14 DISPUTES CONCERNING LABOR STANDARDS FEB 1988

52.222-15 CERTIFICATION OF ELIGIBILITY MAY 2014

52.222-20 CONTRACTS FOR MATERIALS, SUPPLIES, ARTICLES AND

EQUIPMENT EXCEEDING $15,000

MAY 2014

52.222-3 CONVICT LABOR JUNE 2003

52.222-21 PROHIBITION OF SEGREGATED FACILITIES APR 2015

52.222-26 EQUAL OPPORTUNITY SEP 2016

52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR

CONSTRUCTION

APR 2015

52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES JUL 2014

52.222-50 COMBATING TRAFFICKING IN PERSONS NOV 2021

SOLICITATION NO. 140L4324Q0127

52.222-55 MINIMUMM WAGES FOR CONTRACTOR WORKERS UNDER

EXECUTIVE ORDER 14026

JAN 2022

52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 JAN 2020

52.223-6 DRUG-FREE WORKPLACE MAY 2001

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES FEB 2021

52.227-1 AUTHORIZATION AND CONSENT DEC 2007

52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND

COPYRIGHT INFRINGEMENT

DEC 2007

52.227-17 RIGHTS IN DATA – SPECIAL WORKS DEC 2007

52.228-2 ADDITIONAL BOND SECURITY OCT 1997

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS MAY 2014

52.232-17 INTEREST MAY 2014

52.232-23 ASSIGNMENT OF CLAIMS MAY 2014

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS JAN 2017

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR

AWARD MANAGEMENT

OCT 2018

52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS

SUBCONTRACTORS

MAR 2023

52.233-1 DISPUTES MAY 2014

52.233-1 DISPUTES – ALTERNATE I DEC 1991

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM OCT 2004

52.236-2 DIFFERING SITE CONDITIONS APR 1984

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984

52.236-5 MATERIAL AND WORKMANSHIP APR 1984

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984

52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991

52.236-8 OTHER CONTRACTS APR 1984

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,

EQUIPMENT, UTILITIES, AND IMPROVEMENTS

APR 1984

52.236-10 OPERATIONS AND STORAGE AREAS APR 1984

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984

52.236-12 CLEANING UP APR 1984

52.236-13 ACCIDENT PREVENTION NOV 1991

52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984

52.236-17 LAYOUT OF WORK APR 1984

52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995

52.242-14 SUSPENSION OF WORK APR 1984

52.243-5 CHANGES AND CHANGED CONDITIONS APR 1984

52.244-6 SUBCONTRACTS FOR COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES

FEB 2024

52.246-21 WARRANTY OF CONSTRUCTION MAR 1994

52.248-3 VALUE ENGINEERING - CONSTRUCTION OCT 2020

52.249-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT

(FIXED-PRICE)

APR 2012

52.253-1 COMPUTER GENERATED FORMS JAN 1991

SOLICITATION NO. 140L4324Q0127

The following clauses are provided in full text:

52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO

SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services—Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications-Commercial Products or Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.

(a) Definitions. As used in this provision—

Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition.

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub.

L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to—

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such…