This document is a set of technical specifications for the NBHMA West Entrance Parking Lot Asphalting project for the Roseburg BLM District in Oregon. The project involves comprehensive site preparation and paving work, including site grading, aggregate surfacing, asphalt concrete paving, and pavement marking at 6100 N Bank Rd, Roseburg, OR.
The specifications detail precise requirements for materials and execution, including ODOT Class C Hot Mix Asphalt Concrete (½" dense, Level 3), aggregate surfacing meeting AASHTO standards, and specific compaction and placement techniques. The project scope includes approximately 420 linear feet of 4" striping, four directional arrows, two handicap accessible symbols, and nine rubber parking stop curbs (eight existing, one new). Environmental considerations include temperature and moisture restrictions for paving, and a requirement for a Spill Prevention, Control, and Countermeasure Plan. Payment will be made on a lump sum and per-unit basis for different project components, with specific measurement and quality control requirements throughout the construction process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No.
PART VI – SPECIFICATIONS
NBHMA WEST ENTRANCE
PARKING LOT ASPHALTING
ROSEBURG BLM DISTRICT
GENERAL INFORMATION AND REQUIREMENTS SECTION 001009
TESTING LABORATORY SERVICES SECTION 001410
MOBILIZATION SECTION 001505
SITE GRADING SECTION 002213
AGGREGATE SURFACING SECTION 002233
ASPHALT CONCRETE PAVING SECTION 002551
PAVEMENT MARKING SECTION 002765
DIVISION 1 SECTION 001009
GENERAL REQUIREMENTS GENERAL INFORMATION AND REQUIREMENTS
001009-1
PART 1: GENERAL
1.01 SUMMARY:
A. Description of work: Furnishing all labor, equipment, and materials necessary to complete the work specified within these specifications and as shown on the drawings. Work includes grading, compacting, aggregate base course placement, asphalt placement, aggregate surfacing, parking block placement, and striping parking stalls.
B. Location: Work under this contract is located in Douglas County, Oregon. The work location is 6100 N Bank Rd, Roseburg, OR 97470, and shown on the drawings. GPS coordinates Latitude 43°19’10.9914” N, Longitude 123°15’14.868” W.
C. Access: Access to the work site is via State roads, County roads, and Bureau of
Land Management (BLM) roads.
D. Directions to work location: See Work Location Map.
1.02 REFERENCES:
Referenced Specifications/Standards with Abbreviations and/or Acronyms:
Where the following acronyms are used in these specifications or on the drawings, they are to be as meaning the same as the respective expressions represented. All abbreviations for use on drawings are in accordance with ASMEY 1.1(Abbreviations for Use on Drawings and in Text). All references used shall be the latest edition, which is in effect at time of bid. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor from the following:
AASHTO American Association of State Highway and Transportation Officials 444 North Capital Street, N. W., Suite 225 Washington, DC 20001
ASTM American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103-1187
CFR Code of Federal Regulations Superintendent of Documents Government Printing Office Washington, DC 20402
MUTCD Manual on Uniform Traffic Control
001009-2
Devices for Streets and Highways Superintendent of Documents Government Printing Office Washington, DC 20402
OSHA Occupational Safety and Health Administration’s Standards U. S. Department of Labor Occupational Safety and Health Administration Denver Area Office 333 West Colfax Avenue Denver, CO 80204
1.03 DEFINITIONS:
Approvals: Approvals of the submittal is an indication that the Contractor’s Submittal has been reviewed and that there are no objections, except as noted.
Approvals of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer’s attention in writing. After approval of an item, the Contractor may submit a substitute for approval when approved item cannot be purchased or delivered in time to avoid delay in completion of the project.
1.04 SUBMITTALS:
A. Scope: Requirements include administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Design Computations, and other submittals. Submittals shall include, but are not excluded to, the following lists:
A-1 SHOP DRAWINGS AND CONTROL PLANS
The following submittals of shop drawings and control plans are required for this project:
Title: Section: Govt. Response Time:
Spill Prevention, Control, and Countermeasure Plan
001009 7 calendar days
A-2 TESTING SERVICES AND LABORATORIES
The following submittals of certifications or licenses for testing services or laboratories shall be required for this project:
Title: Section: Govt. Response Time:
None
001009-3
A-3 MATERIAL CERTIFICATIONS AND TESTING REPORTS
The following material certificates and testing reports shall be submitted on this project:
Title: Section: Govt. Response Time:
Percent Wear, AASHTO T96 002551 7 calendar days Coarse and Aggregate Durability Index, AASHTO T210
002551 7 calendar days
Sand Equivalent (Alternative Method) Number 2, AASHTO T176
002551 7 calendar days
Density of Bituminous Concrete in Place by Nuclear Methods, ASTM D2950
002551 7 calendar days
A-4 CERTIFICATES OF CONFORMANCE
The following certificates of conformance shall be submitted on this project:
Title: Section: Govt. Response Time:
Hot Mix Asphalt Concrete (HMAC) Level 3 002551 7 calendar days Pavement Marking 002765 7 calendar days
Submittal Schedule: Submit a schedule for all submittal requirements, coordinated with the construction schedule and considering the Government Response times listed.
B. General Requirements:
1. Refer to specifications for submittals required.
2. Allow at least 5 working days for review of submittals.
3. Submittals shall be delivered to the Contracting Officer’s Representative.
C. Identification of Submittals: Identify each submittal by including the following information:
1. Name and address of submitter, plus name and telephone number of the individual to contact for additional information.
2. Name of project as it appears in these specifications.
3. Contract number and specification section number to which the submittal applies.
4. Whether this is an original submittal or re-submittal.
5. Each submittal shall clearly state the manufacturer's name and address, trade name, product, identification numbers etc., and shall state that the product meets all specification requirements of the contract. Each applicable specification shall be individually addressed by the submittal.
001009-4
1.05 CERTIFICATES OF CONFORMANCE:
A. Requirements:
1. The contracting officer may permit use of materials, when accompanied by certificates of conformance, prior to sampling and or testing.
2. Materials used on the basis of a certificate of conformance may be sampled and tested by the contracting officer.
3. Installation of materials on the basis of certificates of conformance shall not relieve the contractor of responsibility for incorporating materials which conform to the requirements of the drawings and specifications.
4. Material not conforming to those requirements will be subject to rejection, whether in place or not.
5. Certificates of conformance shall be submitted according to the specifications.
B. Format: Certificates of conformance shall conform to the following:
1. The certificate shall state the manufacturer and that the named product conforms to the contract requirements.
2. Additional information, including: name of testing agency, dates of tests, test results, and test methods, shall be provided by the contractor if required by the contract.
3. The certificate of conformance shall specifically identify the product covered by the certification.
4. Products or materials shall be identifiable in the field.
1.06 QUALITY CONTROL:
A. Codes and standards: The work shall comply with codes and standards applicable to each type of work and these specifications. This contract incorporates materials, applications, and tests by reference. By reference, a document is attached hereunto and made part hereof.
B. Conflict: When a conflict occurs between reference documents and project specifications, the project specifications shall govern. When a conflict occurs between the project drawings and project specifications, the project specifications shall govern.
C. Measurements: Where approved manufacture’s diagrams and shop drawings give specific measurements or rough-in dimensions for equipment, these dimensions shall take precedence over dimensions indicated on the drawings.
D. Materials: Prior to ordering materials, verify dimensions and functions of material proposed for use. Be certain the material is compatible with the structural and
001009-5 architectural features of work, avoids conflicts and that it will fit the project requirements.
1.07 DELIVERY, STORAGE, AND HANDLING:
A. Delivery: The contractor shall be responsible for loading, delivery and unloading of all government and contractor furnished material to the job site. The contractor shall protect all materials from damage while in transit to the site. Materials must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.
B. Storage:
1. The contractor shall be responsible for storage of contractor furnished materials.
2. The contractor shall be responsible for storage of government furnished materials, once accepted by the contractor. A signed receipt for government property constitutes acceptance of such property by the signee.
3. Storage of materials shall comply with the manufacturer's instructions.
4. The contractor shall provide access to the storage area(s) for inspection and handling.
C. Handling: The contractor shall load and unload products in such a manner that protects them from damage.
D. Comply with all legal and/or posted load restrictions when hauling materials and equipment on public, private, and government roads to and from the projects.
1.08 PROJECT/SITE CONDITIONS:
A. Site Specific Requirements:
1. The contractor shall take special care to ensure that the work area, work practices, and all equipment are safe and secure at all times to protect all adjacent landowners, the public and Government employees from potential hazards.
2. The contractor shall stage equipment within the work area limits shown on the drawings.
B. Noxious Weed Seed: The contractor shall, prior to initial mobilization into the contract area, steam clean or pressure wash all equipment used in the contract area or on BLM property under this contract. This wash requirement excludes contractor pickups and transport vehicles, low boy trucks delivering equipment, dump trucks and others delivering rock or materials to the contract area. This wash shall remove all soil material that may contain weed seeds from the equipment. The contracting officer or his/her representative must visually inspect
001009-6 and verbally approve the cleaning before the equipment is used in the contract area. Any equipment removed from the contract area during the duration of the contract must be steam cleaned or pressure washed and approved by the contracting officer or his/her representative before it is returned to the contract area.
C. The location of temporary access roads which are necessary for excavation, riprap placement or other work shall be approved in writing by the contracting officer.
All such roads shall be abandoned immediately when the construction of the portion of the project for which they are required is completed. The natural surfaces disturbed by their construction and use shall be restored as nearly as possible to their original condition by the contractor, at his expense, and to the satisfaction of the contracting officer.
D. Contractor shall apply for and acquire all permits required to accomplish the work. The BLM will obtain DSL and COE permits, as needed. Permits shall be issued, by the regulating authority, prior to commencing work.
E. Contractor shall provide a portable toilet. The portable toilet shall be a self-contained unit and shall be maintained and serviced throughout the duration of this project. Any contaminated soil material shall be removed and disposed of in a legal refuge which receives such waste products. All transportation and disposal of waste or contaminated soils shall be done in accordance with federal, state, and local laws. This requirement may be waved at the discretion of the contracting officer.
1.09 SEQUENCING AND SCHEDULING:
Work Schedule: The schedule shall be submitted at the pre-work conference.
When requested, the contractor shall submit an updated schedule within 5 calendar days.
PART 2: PRODUCTS
Spark Arresters: Shall meet the requirements of the State of Oregon’s regulations.
PART 3: EXECUTION
3.01 PROJECT MEETINGS:
A. Pre-Work Conference:
1. A pre-work conference will be held prior to the start of work. The contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the contract.
001009-7
2. The contractor, or contractor’s representative authorized to act on the contractor’s behalf shall be present at the meeting. Subcontractors are encouraged, and welcome to attend the pre-work.
3. The contractor shall be prepared to summarize and explain procedures planned for the project and present the submittals required in the specifications.
B. Progress Meetings:
1. Meetings shall be held at the project site or as determined by the contracting officer.
2. Meetings may be called by either the contracting officer or the contractor.
Request shall state who should attend and include an agenda.
C. Final Inspection:
1. Inspection will be held at the project site.
2. The contractor shall submit a written request for a final inspection a minimum of three working days in advance of the requested inspection date. At the discretion of the contracting officer’s representative, verbal request may be made in lieu of the written request.
3. The contractor shall require the superintendent to be present during this inspection if requested by the contracting officer.
3.02 PREPARATION:
Work Layout: The government has set control points at the work site. Control points are shown on the drawings. Control points disturbed or removed during construction shall be reset by the contractor at the contractor's expense.
Additional survey and staking needed by the contractor to accomplish the contract requirements are the contractor’s responsibility. Control points designated in the drawings shall be maintained by the contractor during construction.
3.03 UTILITIES:
A. Water: No water is available on site.
B. Electrical: No electrical power is available at the site.
001009-8
3.04 DISPOSAL OF DEBRIS:
Requirements: vegetative debris may be disposed of within the project limits where designated by the Contracting officer. Other items or debris not designated as salvage for the Government shall become the property of the contractor. The Contractor shall be responsible for disposal of materials in a legal manner and for payment of any fees required. Sale of material onsite is not allowed unless authorized in writing by the Contracting Officer.
3.05 HAZARDOUS MATERIAL CONTAINMENT/CLEANUP
A. During contractor operations on lands managed by the BLM, in event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, the Contractor shall immediately implement the modified SPCC plan as referenced herein and notify the on-site Government Contract Representative (COR or PI). The Government Representative will initiate the District’s Hazardous Materials Contingency Plan and/or Spill Containment Plan reporting requirements. The Government Representative will remain on scene until relieved by the District Hazardous Materials Management Coordinator (HMMC) or his/her representative.
B. Spill Prevention, Control, and Countermeasure Plan (SPCC): The Contractor shall develop a modified SPCC Plan as defined under 40 CFR Part 112. The SPCC Plan will be reviewed and accepted by the Contracting Officer prior to initiating project work. The SPCC Plan shall, as a minimum, contain the following information:
1. Response Priorities
2. Contractor Representative in Charge
3. Duties of Contractor Personnel
4. Contractor Emergency Response Procedures
5. Contents of Spill Containment Kit (SCK)
6. Spill Response Diagram
C. Spill Containment Kit (SCK): The Contractor shall have a SCK, as described in the modified SPCC, on-site during any operation and provide training to employees on how components of the SCK are used. The SCK must be designed for use with petroleum products, and must contain, as a minimum, the following items:
001009-9
1. Two Bales (4 Booms/Bale, of 8" dia. X 10’ length Oil-only Absorbent
Booms)
2. Two Bales (100 Pads/Bale, of Oil-only Absorbent Pads, minimum of 17"x19"x1/4")
3. One Oil-only Absorbent Sweep (minimum of 18" dia. X 100' length)
4. One Floating On-Water Containment Boom (minimum 18” width x 100’ length) (only required for in-stream or riparian work within 50 feet or less of a waterway.)
5. Gloves (PVC and Latex), Goggles, and Garbage Bags sufficient to contain soiled absorbents.
D. The Contractor shall implement the Emergency Response Actions described in the modified SPCC plan. Those actions include, but are not limited to, immediate action to protect employee health and safety, immediate action to stop the flow of product from the equipment, removal of equipment from the waterway if required and/or possible, deployment of the absorbent booms and pads downstream from the equipment, and any other immediate action as specified by Federal and/or State On-Scene Coordinators or his/her representative. The Contractor shall be responsible for cleanup/removal and proper disposal of contaminated materials from the site.
E. If the HMMC determines that additional resources are needed, the HMMC will implement the District’s Hazardous Materials Contingency Plan and the District Spill Containment Plan. The Contractor may be responsible for any or all costs associated with this level of effort. The amount of actual damage will be deducted by the Government from the amount due the Contractor prior to final payment.
PART 4: PAYMENT
4.01 BASIS OF PAYMENT:
No direct payment for the work described under this section will be made. The contractor shall include consideration for this item in the bid price for other items of the contract.
END OF SECTION
DIVISION 1 SECTION 001410
GENERAL REQUIREMENTS TESTING LABORATORY SERVICES
001410-1
1.01 SUMMARY
Section Includes: Requirements for the contractor to provide a certified independent testing laboratory to conduct specific tests for all contractor required testing.
1.02 SUBMITTALS:
Test Reports: The contractor shall provide one (1) copy of test results to the contracting officer within three (3) days of receiving the reports.
1.03 QUALITY ASSURANCE:
A. Approval of Laboratory: The qualified, independent testing laboratory, which will be conducting the specific tests required in this contract, must have authority or be licensed to operate in the State in which the project is located. The testing laboratory shall be approved by the Contracting Officer prior to the Contractor beginning work.
B. Responsibilities of Laboratory:
1. Test samples of mixes submitted by the Contractor.
2. Provide qualified personnel at project site. Cooperate with the Contracting
Officer and Contractor in performance of services.
3. Perform specified sampling and testing of products and materials in accordance with specified standards.
4. Ascertain compliance of materials and mixes with requirements of specifications.
5. Promptly notify the Contracting Officer and Contractor of observed irregularities or non-conformance of work, products, or materials.
6. Perform additional tests required by the Contracting Officer.
7. Attend preconstruction meetings and progress meetings.
C. Limitations on Laboratory:
1. Laboratory may not release, revoke, alter, or enlarge on requirements of specifications.
2. Laboratory may not approve or accept partial portions of the work.
3. Laboratory may not assume duties of the Contractor unless approved in writing by the Contracting Officer.
DIVISION 1 SECTION 001410
GENERAL REQUIREMENTS TESTING LABORATORY SERVICES
001410-2
1.04 SEQUENCING AND SCHEDULING:
A. Establishing Testing Schedule:
1. In advance of the required testing, the contractor shall arrange for the laboratory to perform the testing and to issue its findings.
2. The contractor shall coordinate the laboratory test frequency and timing with the contracting officer.
B. Revising Testing Schedule: If the initial construction schedule changes, the contractor shall re-schedule testing with the testing laboratory.
There are no applicable requirements.
3.01 QUALITY CONTROL:
Requirements: See "Quality Control" paragraph for specific testing requirements in specific sections. When applicable the contractor shall:
1. Ensure that samples are taken by qualified testing personnel.
2. Properly identify sample material and sources.
3. Ensure that tests are completed according to the testing schedule.
PART 4: MEASUREMENT AND PAYMENT
4.01 BASIS OF PAYMENT:
Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item Pay Unit
001410(01) Testing Laboratory Services Lump Sum
END SECTION
DIVISION 1 SECTION 001505
GENERAL REQUIREMENTS MOBILIZATION
001505 – 1
Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site.
Also includes other work and operations which must be performed and/or costs incurred prior to beginning work on the components listed in the schedule of items.
4.01 METHOD OF MEASUREMENT:
Progress payments will be made as follows:
A. When 5% of the original contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original contract amount, whichever is the lesser will be paid.
B. When 10% of the original contract amount is earned from other bid items, 100% of the bid for mobilization or 10% of the original contract amount, whichever is the lesser will be paid.
C. Upon completion of the work for the project, payment of the amount bid for mobilization in excess of 10% of the original contract amount will be paid.
D. The total sum of all payments shall not exceed the original contract mobilization amount bid for mobilization regardless of the fact that the Contractor may have shut down the work on the project or moved equipment away from the project and then back again.
DIVISION 1 SECTION 001505
GENERAL REQUIREMENTS MOBILIZATION
001505 – 2
4.02 BASIS OF PAYMENT:
Payment will be full compensation for the work described in this section. Payment will be made under:
001505(01) Mobilization Lump Sum
DIVISION 2 SECTION 002213
SITEWORK SITE GRADING
002213-1
1.01 SUMMARY: Grade parking lot and site road following existing slope of surface.
A. Section Includes: Filling, grading, and other related work to prepare the road prism to the dimensions shown on the drawings, and the grading and compaction of the road surfaces prior to placing aggregate surfacing and asphalt.
B. Related Sections:
General Information and Requirements Section 001009 Aggregate Surfacing Section 002233 Asphalt Concrete Paving Section 002551
1.02 DEFINITIONS:
A. Fill Material: Shall be mineral soil free from peat, frozen material, brush, trees, roots over 2 inches in diameter and rocks over 6 inches in greatest dimension obtained from site during excavation.
B. Muck Excavation: Shall consist of the removal and disposal of deposits of saturated or unsaturated mixtures of soils and organic matter not suitable for foundation material regardless of moisture content.
C. Road Prism: The portion of the road within the limits of construction, usually from the toe of fill slope to a point where the cut slope intersects the natural ground line.
D. Unclassified Excavation: Shall consist of the material excavation and placement regardless of its nature.
E. Optimum Moisture Content: Shall be determined by hand clump test i.e., where soil sample forms a firm ball by hand that does not crumble, or free moisture is not visible on the surface and material does not squeeze between fingers.
1.03 QUALITY ASSURANCE:
Rejection Criteria: Not limited to the following:
1. Formation of pools of moisture on any road subgrade due to uneven or inadequate grade.
2. Inadequate road subgrade (including curve widening and turnouts) and/or ditch line and catch basin width.
3. Settlement of fill.
4. Failure to compact subgrade prior to surfacing.
DIVISION 2 SECTION 002213
SITEWORK SITE GRADING
002213-2
1.04 PROJECT/SITE CONDITIONS:
Environmental Conditions: Do not attempt to grade frozen or saturated material.
Apply water to dry material to prevent dust and provide adequate compaction.
2.01 MATERIALS:
General: See definitions.
3.01 PREPARATION:
Clearing: No clearing will be necessary.
Traffic Control: Entrance may be blocked off from visitors entering the site throughout construction.
3.02 INSTALLATION:
A. Grading:
1. Road Surfaces: Subgrade roughness shall not vary more that 1 inch from a 10 foot straight line stretched parallel to, or at 90 degrees to the subgrade centerline.
B. Compaction:
1. Filled areas: Adjust the moisture content of the material to optimum moisture content to form maximum compaction and filled areas of the subgrade by rolling with the described vibratory roller, or other equipment which will produce equivalent results as determined by the Contracting Officer. Compaction shall consist of a minimum of 3 passes or until visual deformation ceases per 6 inch lift of material.
2. Subgrade: Material shall be at the optimum moisture content suitable for attaining the required compaction. The full width of the road surface shall be compacted a minimum of 3 passes or until visual deformation ceases prior to placement of aggregate surfacing.
3. Compaction Equipment: Shall be a vibratory roller with a drum diameter not less than
48 inches, drum width not less than 58 inches, and have a turning radius of 15 feet or less. Vibration frequency shall be regulated in steps to 1400, 1500, and 1600 vibrations per minute (VPM), corresponding to engine speeds of 1575, 1690, and 1800 RPM. The centrifugal force developed shall be 7 tons at 1600 RPM. It shall be activated by power unit of not less than 25 horsepower. The vibratory roller shall be
DIVISION 2 SECTION 002213
SITEWORK SITE GRADING
002213-3 self-propelled or drawn by a vehicle of sufficient horsepower to enable the unit to travel through a loose layer of material at a speed ranging from 0.09 to 1.8 miles per hour. Mechanical hand compacting equipment which has been approved by the Contracting Officer may also be in tight areas where a vibratory will not fit.
3.03 FIELD QUALITY CONTROL:
A. Construction Tolerances: Maximum allowable deviation from dimensions shown on the drawings shall be as follows:
Roadbed width (feet) + 0.5
B. Compaction: The Government will check grade and surface compaction by visual inspection.
The work described in this section will be measured and paid for on a lump sum basis.
Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
002213(01) Site Grading Lump Sum
DIVISION 2 SECTION 002233
SITE WORK AGGREGATE SURFACING
002233-1
A. Description of Work: Furnishing, placing, grading, and compacting one (1) lift of crushed 1 ½” minus aggregate on the existing Site Road and Upper Parking Lot subgrade; including on the widened corners to establish a wider road subbase. Refer to drawings for dimensions.
Furnishing, placing, grading, and compacting 4” of crushed 1 ½” minus aggregate on the Lower Parking Lot graded subbase, after the upper parking lot and site road have been asphalted. Slope aggregate away from proposed asphalt of Site Road.
General Information & Requirements Section 001009 Site Grading Section 002213
1.02 REFERENCES:
American Association of State Highway and Transportation Officials
AASHTO T11 Amount of Material Finer than No. 200 Sieve in Mineral Aggregates by Washing
AASHTO T27 Sieve Analysis of Course and Fine Aggregates
AASHTO T96 Resistance to Abrasion of Small Size Coarse Aggregate by Use of the Los Angeles Machine
AASHTO T89 Determining the Liquid Limit of Soils
AASHTO T90 Determining the Plastic Limit and Plasticity Index of Soils
AASHTO M147 Materials for Aggregate and Soil Aggregate Subbase, Base and
Surface Courses
AASHTO T210 Production of Plastic Fines in Aggregates
1.03 SUBMITTALS:
The Contractor shall submit a Certificate of Conformance as required in Section 001009 to the Contracting Officer prior to placing of aggregate.
002233-2
1.04 PROJECT/SITE CONDITIONS:
Crushed aggregate shall be supplied by the Contractor from a Contracting Officer approved commercial source at the Contractor’s expense. Crushed aggregate shall not be quarried from Bureau of Land Management (BLM) property.
PART 2: PRODUCTS:
A. Crushed aggregate shall meet AASHTO M147 and conform to the following:
1. Crushed rock material retained on the No. 4 sieve shall have a percentage of loss of not more than 35 at 500 revolutions, as determined by AASHTO T96.
2. Crushed rock material shall show a durability value of not less than 35 as determined by
AASHTO T210.
3. That portion of crushed rock material passing the No. 40 sieve, including blending filler, shall not have a liquid limit value that is more than 35, nor a plasticity index value that is less than 4 nor more than 12 as determined by AASHTO T89 and AASHTO T90.
4. When crushed rock material is produced from gravel, not less than 75%, by weight, of particles retained on the No. 4 sieve shall have 3 manufactured faces. If necessary to meet this requirement or to eliminate an excess of filler, the gravel shall be screened before crushing.
Crushed river rock is not acceptable.
B. Gradation: Crushed aggregate shall meet the following gradation:
Gradation A:
Percent by weight passing square Sieve Designation mesh sieves AASHTO T 11 and T 27
1 inch 100 3/4 inch 97-100 No. 4 41-71 No. 40 12-28 No. 200 5-16
Gradation B:
1½ inch 100
002233-3
¾ inch 50 - 90 No. 4 25 - 50 No. 40 5 - 25 No. 200 2 - 15
Gradation C:
3 inch 100 2 inch 65 - 95 ¾ inch 28 - 70 No. 4 10 - 35 No. 200 0 - 10
PART 3: EXECUTION:
3.01 CONSTRUCTION REQUIREMENTS:
A. Preparation:
1. The Contractor shall prepare the subgrade by grading and compacting the subgrade.
2. Subgrade shall be approved at least 1 day prior to placing crushed rock material.
3. Subgrade approval remains effective so long as the condition of the subgrade remains unchanged.
B. Aggregate Placement:
1. Place and shape the crushed aggregate surfacing on the prepared subgrade between the stations shown on the drawings or specifications. The final dimensions are the compacted widths, depths, and slopes as shown on the drawings.
2. When hauling is done over previously placed material, the hauling equipment shall be routed uniformly over the width of the material.
C. Processing:
Crushed aggregate surfacing shall be watered, graded, windrowed and spread in a uniform layer, with no segregation of size, and to a loose depth that shall produce the required thickness when compacted.
002233-4
D. Grading:
The aggregate shall be graded uniformly over the surface in layers. Compacted layers shall not exceed 6 inches. When more than 1 layer is required, each shall be shaped, processed and compacted before the succeeding layer is placed.
E. Compaction:
Compaction equipment shall meet the following requirements:
Compaction equipment shall be capable of exerting a force of not less than 250 pounds per inch of roller drum width, or vibratory steel-wheel rollers shall be a minimum weight of 6 tons. Aggregate shall be compacted by equipment operated over the full width of each layer until visual displacement ceases, but not fewer than six complete passes.
F. Watering:
The Contractor shall provide water and watering equipment to control dust and obtain required compaction. This work shall be done at no additional cost to the Government.
PART 4: PAYMENT:
Units:
The work described in this section will be measured and paid for as shown. The cubic yard volume will be measured in the hauling vehicle using three dimensional measurements at the point of delivery. Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purposes if the conversion factors are mutually agreed to in writing.
4.02 METHOD OF PAYMENT:
Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under
002233(01) Aggregate Surfacing, Grading B Cubic Yards
END SECTION
DIVISION 2 SECTION 002551
SITE WORK ASPHALT CONCRETE PAVING
002551-1
A. Section Includes: Furnishing and placement of Asphalt Concrete (AC) surface course on a prepared base in the depths, amounts, and locations as shown in the drawings.
General Information and Requirements Section 001009 Testing Laboratory Services Section 001410 Aggregate Surfacing Section 002233
1.02 SUBMITTALS
A. The Contractor shall submit a certificate of conformance that the AC meets the requirements of ODOT Class C, Hot Mix Asphalt Concrete (HMAC) Level 3, ½” dense mix within the last 12 months.
A. AC Surface Course: ODOT Class C, HMAC, ½” dense, Level 3.
B. Bituminous Material: Asphalt cement shall meet the requirement of ODOT publication “Standard Specifications for Asphalt Materials”.
C. Aggregate for AC Surface Course: Shall be crushed stone, or gravel meeting the quality requirements below:
AASHTO
Description Test Method Requirement
Abrasion T 96 40 max.
Durability Index, Coarse and Fine T 210 35 min.
Sand Equivalent (Alternate Method) T 176 45 min.
Number 2
D. Additives for AC Surface Course: Additives, such as filler, hydrated lime, anti-strip agents may be used as necessary to meet specifications. Reclaimed Asphalt
002551-2
Pavement (RAP) Material – Using processed, reclaimed AC pavement (RAP) material in the production of new AC pavement is optional. No more than 30% RAP material will be allowed in the new pavement.
3.01 DELIVERY AND PLACEMENT:
A. Transportation of AC Mixtures: Trucks used for hauling AC mixtures shall have tight, clean, smooth metal beds that have been thinly coated with a material to prevent the mixture from adhering to the beds. Truck beds shall be drained prior to loading. Each truck shall have a cover to protect the mixture from weather.
When necessary to ensure that the AC mixture will be delivered at the specified temperature, truck beds shall be insulated, and covers shall be securely fastened.
B. AC pavers shall have an adjustable vibrating screed or strike-off assembly, heated, if necessary, an auger ahead of the screed to distribute the mixture, and shall be capable of spreading and finishing a course of AC mix material in lane widths and thicknesses shown on the drawings. Unless otherwise shown on the drawings, towed type pavers, or Layton type pavers may be used to place and spread the AC mix material.
C. Three to five ton rollers maybe used where it is impractical to operate larger rollers.
D. The AC mixture shall not be placed when weather conditions prevent proper handling or finishing. Such conditions include but are not limited to the following: when the base course has pools of water, is frozen, or when the average temperature (over the last 24 hours) of the underlying surface upon which the AC mixture is to be placed is less than 45 degrees F.
E. Immediately before placing the AC mixture, the existing contact surface shall be cleaned of loose or deleterious materials.
F. The edge of existing asphalt which is directly adjacent to new paving shall be saw cut to form a straight, smooth, vertical line. All contacted surfaces of saw cuts, curbing, manhole, and other structures will be cleaned of loose material and coated with a thin, uniform layer of asphalt tackifier prior to placing AC.
G. The COR may reject any batch, load, or section of roadway that appears defective in gradation, asphalt cement content or moisture content. Material rejected before placement shall not be incorporated into the pavement. Any rejected section of roadway shall be removed. No payment will be made for the rejected materials or the removal of the materials.
002551-3
H. The AC mixture shall be spread and struck off to the grade and elevation established. Maximum compacted lift thickness shall be four (4) inches unless otherwise shown on the drawings.
I. The longitudinal joint in one layer shall offset that in the layer immediately below by approximately six inches. The joint in the top layer shall be at the centerline of two-lane traveled way. Traverse joints in seceding layers and in adjacent lanes shall be offset at least ten feet.
J. On areas where irregularities or unavoidable obstacles make the use of mechanical spreading and finishing equipment impracticable, the AC mixture may be placed and finished by hand tools.
K. Initial breakdown rolling shall be accomplished while the AC mix temperature exceeds 250°F. Rolling shall be completed while AC mix temperature exceeds 175°F.
3.02 COMPACTING:
A. Compaction equipment shall be capable of obtaining compaction requirements without detrimentally affecting the compacted material. The compacting units may be of any type, provided they are capable of compacting each lift of material as specified and requirements for rollers are as follows:
1. In areas too small for the roller, a vibrating plate compactor shall be used.
2. Steel-wheeled rollers, other than vibratory, shall be capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.
3. Vibratory steel-wheeled rollers shall have a minimum weight of 6 tons. The compactor shall be equipped with amplitude and frequency controls and specifically designed to compact material on which it is used.
4. Pneumatic-type rollers shall have smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.
3.03 TESTING
A. Requirements: Nuclear Density Gauge (NDG) testing shall be performed to determine that ideal compaction is in range between 92% to 98%, in accordance with ASTM D2950.
002551-4
3.04 CLEANING:
A. Requirements: The contractor shall be responsible for cleanup of all waste, spilled, and excess material as a result of this work.
3.05 PROTECTION:
A. Requirements: The Contractor shall provide for controls to prevent unauthorized traffic in or on work areas until those areas are suitably prepared for traffic.
3.06 SHOULDER BACKFILL:
A. Backfill against asphalt surfaces as shown on the drawings.
A. Units: The work described in this section will be measured and paid for on a lump sum basis.
A. Payment: Prices and payment will be full compensation for work described in this section. Payment will be made under:
002510(01) Asphalt Concrete Paving Tons
DIVISION 2 SECTION 002765
SITEWORK PAVEMENT MARKINGS
002765-1
PART 1 - GENERAL
1.1 SUMMARY:
A. Section includes painted markings applied to asphalt. The painted markings for the West Entrance Parking Lot include approximately 420 LF of 4” striping, four
(4) directional arrows, and two (2) handicap accessible symbols, as locations are indicated on the plans. Paint color to be used for striping and arrows is white.
Paint colors to be used for the accessibility symbols are blue and white.
Directional arrow locations to be decided by COR. Parking stall markings shall be staked out by COR after paving is completed.
Furnish, place and secure rubber parking stop curb and hardware for each parking spot. Eight (8) existing rubber parking stop curbs on site will be reused, but all hardware is to be replaced with ½” rebar spikes. One new rubber parking stop curb is to be purchased. Secure rubber parking stops in four places with rebar.
Refer to drawings.
Note: Quantities provided are approximate and are provided for biddability purposes only, the Contractor is solely responsible to verify by field measurement the size and location of all features.
B. Related Sections:
General Information and Requirements Section 001009 Mobilization Section 001505
1.2 SUBMITTALS
A. Product Data: Submit copies for each type of product used.
1.3 PROJECT/SITE CONDITIONS
A. Environmental Requirements: Apply marking paint in dry weather conditions when pavement and atmosphere temperatures are 50oF or above and are anticipated to remain above 50oF for at least 4 hours after completing application.
Also make sure that ground conditions must be dry before applying the marking paint.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
1. AkzoNobel.
DIVISION 2 SECTION 002765
SITEWORK PAVEMENT MARKINGS
002765-2
2. Columbia Paint & Coatings.
3. Coronado Paint; Division of INSL-X Products Corporation.
4. Diamond Vogel Paints.
5. General Paint.
6. Ennis-Flint Traffic Paint.
7. Kwal Paint.
8. M.A.B. Paints.
9. Mobile Paint.
10. Parker Paint Mfg. Co. Inc.
11. PPG Industries.
12. Pratt & Lambert.
13. Rodda Paint Co.
14. Sherwin-Williams Company (The).
15. TriCom Coatings, Inc.
2.2 PAVEMENT MARKING PAINT
A. Pavement Marking Paint: MPI #32, AASHTO M 248, Type H alkyd contractor grade traffic marking paint.
1. Color: White.
2. Color: Blue.
3. Color: Yellow.
4. Color: Red.
B. Glass Beads: AASHTO M 247, Type 1 made of 100 percent recycled glass.
PART 3 - EXECUTION
3.1 PAVEMENT MARKING
A. Do not apply pavement-marking paint until layout, colors, and placement have been verified with the COR. COR shall stake out parking stalls after paving is completed.
B. Ensure pavement surface preparation meets manufacture’s recommendations before starting pavement marking operations.
C. Sweep and clean surface to eliminate loose material and dust.
D. Apply paint with mechanical equipment to produce pavement markings, of dimensions indicated, with uniform, straight edges. Apply at manufacturer's recommended rates to provide a minimum wet film thickness of 15 mils.
1. Apply graphic symbols and lettering with paint-resistant, die-cut stencils.
Apply paint so that it cannot run beneath the stencil.
2. Broadcast glass beads uniformly into wet markings at a rate of 6 lb/gal.
DIVISION 2 SECTION 002765
SITEWORK PAVEMENT MARKINGS
002765-3
4.1 METHOD OF MEASUREMENT
A. Units: Payment will be made following satisfactory completion of the work described in this section and at the contract price as indicated in the Bid Schedule.
4.2 BASIS OF PAYMENT
A. Payment: Payment will be made at the Contract price, as indicated in the Bid Schedule, and will include full compensation for the work described in the Contract. Payment will be made under:
Pay Item Pay Item
002765(01) Pavement Markings Linear Feet 002765(02) Parking Curb Stops and Hardware Lump Sum
PART VII – PLANS/ DRAWINGS
DRAWINGS ATTACHED UNDER SEPARATE COVER
Sheet Title Drawing Number
1 Title Sheet OR-25-West Entrance #1
2 Vicinity Map OR-25-West Entrance #2
3 Proposed Plan View OR-25-West Entrance #3
4 Existing Site Pictures OR-25-West Entrance #4
| PART II Schedule of Items |
| PART VI Specifications |
| 001009 General Requirements |
| 001410 Testing Laboratory Services |
| Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under: |
| 001505 Mobilization |
| 002213 Site Grading |
| PART 1: GENERAL |
| PART 2: PRODUCTS |
| PART 3: EXECUTION |
| PART 4: PAYMENT |
| 002233 Aggregate Surfacing (compaction test) |
| PART 1: GENERAL |
| 002551 Asphalt Concrete Paving |
| 002765 Pavement Markings |
| A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: |
| 1. AkzoNobel. |
| 2. Columbia Paint & Coatings. |
| 3. Coronado Paint; Division of INSL-X Products Corporation. |
| 4. Diamond Vogel Paints. |
| 5. General Paint. |
| 6. Ennis-Flint Traffic Paint. |
| 7. Kwal Paint. |
| 8. M.A.B. Paints. |
| 9. Mobile Paint. |
| 10. Parker Paint Mfg. Co. Inc. |
| 11. PPG Industries. |
| 12. Pratt & Lambert. |
| 13. Rodda Paint Co. |
| 14. Sherwin-Williams Company (The). |
| 15. TriCom Coatings, Inc. |
| 1. Color: White. |
| 2. Color: Blue. |
| 3. Color: Yellow. |
| 4. Color: Red. |
| B. Glass Beads: AASHTO M 247, Type 1 made of 100 percent recycled glass. |
| A. Do not apply pavement-marking paint until layout, colors, and placement have been verified with the COR. COR shall stake out parking stalls after paving is completed. |
| B. Ensure pavement surface preparation meets manufacture’s recommendations before starting pavement marking operations. |
| C. Sweep and clean surface to eliminate loose material and dust. |
| D. Apply paint with mechanical equipment to produce pavement markings, of dimensions indicated, with uniform, straight edges. Apply at manufacturer's recommended rates to provide a minimum wet film thickness of 15 mils. |
PART VII Plans Drawings