B08_RFQ_Attachment_6_-_Price_Schedule_Breakdown.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- DINO REPLACE SWING ARM GATES
- Solicitation number
- 140P1426Q0113
About this file
This is a Price Schedule Breakdown attachment for a Request for Proposal related to the replacement of swing arm gates at a National Park Service facility under PMIS Project DINO 344849. The document serves as a pricing template for offerors to complete with their proposed costs and is currently blank, showing all line items and totals at $0.
The scope of work encompasses comprehensive gate replacement services including removal of existing gates, posts, footings, signs, and reflectors; installation of new concrete footings for gates and bollards; fabrication of new gate posts (3.5 feet high) and gate leafs (various lengths totaling 400 linear feet); procurement of hardware and related components; painting and installation of new gates in safety yellow; installation of MCTUD signs and reflectors; and associated site services including portable toilets with weekly cleaning service, haul away and dump charges, and hazmat management. The contract also includes a Quality Control and Site Specific Safety Plan, as well as mobilization and demobilization costs covering administration and bonds. Offerors are invited to submit alternate proposals demonstrating cost savings to the Government, with clear justification for the advantages of such alternatives. The document instructs offerors to reference FAR Clause 52.215-1 and DSC-36 Clause provisions for submission requirements and alternate proposal guidelines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised IGE
| CONTRACT PRICE SCHEDULE |
| REQUEST FOR PROPOSAL: N/A |
| PMIS PROJECT: DINO 344849 |
| Replace Gates Parkwide |
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. |
| LINE ITEM NUMBER | DESCRIPTION | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Replace Gates | ||||
| Remove Existing Gates, Posts, Footings, Signs & Reflectors etc | 12 | Lump | $0 | ||
| New Concrete Footings for Gates | 22 | Each | $0 | ||
| Fabricate New Gate Posts (3.5 feet high) | 11 | Each | $0 | ||
| Fabricate New Gate Leafs (various lengths) | 400 | LF | $0 | ||
| Hardware and Related Components | 11 | Lump | $0 | ||
| Paint & Install New Gates (Safety Yellow) | 11 | Lump | $0 | ||
| Install New MCTUD Signs & Reflectors | 11 | Lump | $0 | ||
| New Concrete Footings for Bollards | 72 | Each | $0 | ||
| Install new bollards | 72 | Each | $0 | ||
| Portable Toilets (includes weekly cleaning service) | 4 | Week | $0 | ||
| Haul Away & Dump Charges | 1 | LS | $0 | ||
| HAZMAT, Q/C and Site Specific Safety Plan | 1 | LS | $0 | ||
| Mobilization/ Demobilization (Administration, Bonds, etc.) | 1 | LS | $0 | ||
| Total | $0 | ||||
| Profit Mark Up - enter percentage in column/row E23 | 1 | LS | $0 |
Total CLIN 1 ------------------------------------ $0
| TOTAL OF ALL LINE ITEMS - Total of CLIN 1 | $0 |
| All measurement and payment information is included in the Scope of Work and/or Project Specifications. |
MEVE - 206133
CPS - &P
File details come from the government source that posted it. Updated .