RFQ P1226Q0014 - BLCA/CURE Mag Chloride Gravel Roads Summary
This is a Statement of Work for a Request for Quote (RFQ) issued by the National Park Service for magnesium chloride dust abatement services on gravel roads at Black Canyon National Park and Curecanti National Recreation Area in Gunnison, Colorado. The work consists of one annual application of magnesium chloride to be applied between April 13, 2026, and May 1, 2026, with an exact date determined by the Park Point of Contact based on road moisture and freezing conditions. The contractor must apply the material using computer calibration at 0.50 gallons per square yard for 9 miles of North Rim Road at Black Canyon (39,000 gallons maximum) and at 0.25 gallons per square yard for 8.7 miles of various roads at Curecanti (22,400 gallons maximum). All roadways are 18 feet wide with government-prepared surfaces, and the application spray pattern must span the entire width in one pass to minimize public road closure time.
The magnesium chloride solution must meet strict chemical and physical specifications, including 30-33 percent magnesium chloride content, specific pH and weight requirements, and maximum allowable levels for various contaminants including heavy metals and ammonia. The period of performance is 14 calendar days after Notice to Proceed. Payment is firm fixed price based on actual supplies and services delivered, with a single payment anticipated upon contract completion. The contractor must submit products, Material Safety Data Sheets, and Insurance Certificate for approval before commencing work and must adhere to all park requirements, regulations, and speed limits. Payment requests must be submitted electronically through the U.S. Department of Treasury's Invoice Processing Platform (IPP), and the contractor is responsible for determining and adhering to all applicable roadway regulations and permits. Contract line items include application of magnesium chloride at Black Canyon (00010), application at Curecanti (00020), and hauling and application of water, estimated at 6,000 gallons, to support Black Canyon operations (00030).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ P1226Q0014 - BLCA/CURE Mag Chloride Gravel Roads
STATEMENT OF WORK
DESCRIPTION OF WORK
The work consists of providing Magnesium Chloride application to gravel roads at Black Canyon National Park, and Curecanti National Recreation Area, in the Gunnison Colorado areas.
SPECIFICATIONS
One (1) application per year of Magnesium Chloride dust abatement to be applied on or about: April 13, 2026 – May 1, 2026. Material must be applied via computer calibration at the rate of 0.25 gallons per square yard along roadway for
8.7 miles at Curecanti (The total allowable amount of gallons is 22,400 for Curecanti) and applied at 0.50 gallons per square yard along roadway for 9 miles of the North Rim of the Black Canyon (The total allowable amount of gallons is 39,000 for Black Canyon).
Roadway surface at Black Canyon is approximately 9 miles long by 18’ wide. Government will prepare road surface.
Roadway surface at Curecanti National Recreation Area is approximately 8.7 miles long by 18’ wide. Government will prepare road surface.
Application spray pattern must span the entire 18’ roadway in one pass, this saves government time and shortens the time of road closures to the public during the season.
Payment will be made based on actual material applied not to exceed award amount.
Magnesium Chloride Solution Specifications:
Chemical Properties Magnesium Chloride 30-33%; Sulfates 0-3.5%, Potassium 0-0.5%; Sodium 0-0.7%
Physical Properties Clear to yellow in color; 10.85-11lbs per gallon; 6-7.5 pH of a 5% solution
Constituents
Total Phosphorous, Barium, or Zinc < 10.00mg/L Molybdenum < 15.00 mg/L Cyanide or Mercury < 0.05 mg/L Arsenic < 3.00 mg/L Copper < 0.10 mg/L Lead < 0.50 mg/L Chromium < 0.10 mg/L Cadmium < 0.15 mg/L Selenium < 0.30 mg/L Ammonia or Nitrogen < 0.00 mg/L
DELIVERY SCHEDULE and CONTRACT PERIOD The awarded vendor will be expected to provide the services requested upon receipt of “notice to proceed” from the contracting officer, or as may be coordinated sooner, or as otherwise arranged. The Contracting Officer and/or the Park POC shall coordinate with the awarded vendor for a date and time to begin the requested services.
PERIOD OF PERFORMANCE
The period of performance is 14 calendar days after Notice to Proceed (NTP).
WORK DATES
Work estimated to take place April 13, 2026 – May 1, 2026. The exact date will be set based on ensuring that freezing conditions do not exist in the roads, yet ensuring there is still enough moisture in the roads and as approved by the Park POC for this requirement.
LOCATION
Black Canyon of the Gunnison National Park, North Rim Road, is located approximately 15 miles southeast of Crawford Colorado. Curecanti National Recreation Area is located approximately 15 miles west of Gunnison Colorado.
PARK REQUIREMENTS
-The contractor shall determine and adhere to roadway use regulations for all roads between the point of origin and the delivery site and be responsible for any applicable permits.
-The contractor shall adhere to all park requirements, rules, regulations and posted speed limits within all park boundaries.
SUBMITTALS
The awarded contractor will be required to provide the following for review and approval prior to commencement of work:
-Submittals for all products, chemicals, etc., expected to be provided in the completion of this contract -Material Safety Data Sheets (MSDS) for all products, chemicals, etc. to be provided in the completion of this contract.
-Insurance Certificate
MEASUREMENT AND PAYMENT
The measurement for payment shall be for the actual supplies & services quoted as a firm fixed price. All work shall be approved and accepted by the Contracting Officer. Payment will be made at the contracted prices. A single payment, upon contract completion, is anticipated for this contract.
Payment requests must be submitted electronically through the U.S. Department of the Treasury's Invoice Processing Platform System (IPP). "Payment request" means any request for contract financing payment or invoice payment by the Contractor. Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Copy of vendor invoice document in PDF format, which shows pricing breakdown for all items being invoiced for and must include the contract number, date(s) of service (if applicable), date of invoice, and the vendor’s standard invoice letterhead.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131. The IPP website address is: https://www.ipp.gov.
WARRANTY
The Contractor shall ensure that the dust suppressant meets the requirements of these specifications and the submittals upon delivery.
CONTACT INFORMATION
For information regarding this solicitation contact: Contracting Officer
CONTRACT LINE ITEMS
Contract line item 00010:
Magnesium Chloride shall be applied to the road surface on the North Rim Road of Black Canyon of the Gunnison National Park. The supplier will spray/apply Magnesium Chloride at the rate of 0.50 gallons per square yard for 9 miles.
The application will cover nine (9) miles of road at a width of eighteen feet (18'). Application spray pattern must span the entire eighteen-foot roadway in one pass. The total allowable amount of gallons is 39,000. This work will be completed one (1) mile at a time, depending on moisture content, water trucks, and equipment. This process may take one to two days for completion.
North Rim Road- 9 miles
Total allowable amount of gallons is 39,000 per year
Contract Line item 00020:
Magnesium Chloride shall be applied to the road surfaces at Curecanti National Recreation Area. The supplier will spray/apply Magnesium Chloride at the rate of 0.25 gallons per square yard to 8.7 miles of road, at a width of eighteen feet (18'). The total allowable amount of gallons is 22,400 per year. Application spray pattern must span the entire eighteen-foot roadway in one pass. This work will consist of the application to multiple short roadways along highway 50 and Ponderosa Campground as follows:
Soap Creek Road - 3 and 1/10 miles (3.1) Ponderosa Campground Road - 2 and 8/10 miles (2.8) Red Creek Road - 4/10 mile (.4) Dry Gulch Road - 6/10 mile (.6) Bay of Chickens - 3/10 mile (.3) East Elk Creek - 1 and 2/10 miles (1.2) North Willow Creek - 3/10 mile (.3)
The total allowable amount of gallons is 22,400 per year
Contract Line Item 00030:
This line item is for the hauling and application of water to the North Rim Road of Black Canyon of the Gunnison National Park. The quoter shall provide a quote price, which should include a total amount for the truck, driver and water. It is estimated that as much as 6,000 gallons of water will be required.
| DESCRIPTION OF WORK The work consists of providing Magnesium Chloride application to gravel roads at Black Canyon National Park, and Curecanti National Recreation Area, in the Gunnison Colorado areas. |
| SPECIFICATIONS |
| LOCATION |
| PARK REQUIREMENTS |
| SUBMITTALS |
| MEASUREMENT AND PAYMENT |
| WARRANTY |
| CONTACT INFORMATION |
File details come from the government source that posted it. Updated .