B08_Copy_of_Combined_Synopsis_Solicitation.pdf
PDF 249 KB Posted
- Attached to
- James A Garfield NHS - Water Service Line Repair
- Solicitation number
- 140P6226Q0008
About this file
This is a Request for Quote (RFQ) issued by the National Park Service Contracting Operations Central for repair of a water service line at James A. Garfield National Historic Site in Mentor, Ohio. The solicitation number is 140P6226Q0008, with a closing response date of September 8, 2026 at 18:00 EDT. This is a Total Small Business Set-Aside under NAICS code 238220 (Plumbing Contractors) with a size standard of $19 million. The Government will award a firm, fixed-price contract to the responsible offeror whose quote is most advantageous considering price and technical factors. The contract contains a single line item (CLIN 0010) for water service line repair based on specifications provided in the attached Statement of Work.
Offerors must submit quotes via email to matthew_frank@ios.doi.gov on company letterhead with a detailed breakdown of estimated labor and materials. All interested parties must be registered and active in the System for Award Management (SAM) and provide their SAM Unique Entity Identifier (UEI) with their quote. A mandatory site visit is scheduled for September 3, 2026 at 13:00 EDT at 8095 Mentor Avenue, Mentor, Ohio 44060, with offerors required to notify the contracting officer of their intent to attend. Performance must begin within ten days of issuance of the notice to proceed. There is no bonding requirement. Quotes are valid for 60 days. The contract incorporates numerous FAR clauses applicable to commercial construction services, including Buy American requirements for construction materials, construction wage rate requirements, and various labor standards and compliance provisions. Payment requests must be submitted electronically through the Department of the Treasury's Invoice Processing Platform (IPP) system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B03_Wage_Determination.pdf | ||
| A04_SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
CONTRACTING OPERATIONS - CENTRAL
1849 C Street NW Washington, DC 20240
(1) Not Applicable
(2) 28 August
(3) 2026
(4) Contracting Office Zip: 63123
(5) Product Service Code: Z2NZ – Repair of Other Utilities
(6) National Park Service Contracting Operations Central, Missouri Major Acquisition Buying Office
(7) Request for Quotes for Repair of Water Service Line
(8) 140P6226Q0008
(9) Closing Response Date: 8 September 2026
(10) Contracting Officer: matthew_frank@ios.doi.gov
(11-15) Not Applicable
(16) Description:
(i) This is a combined synopsis/solicitation for a commercial item / commercial construction services being procured in accordance with the format in Subpart 12.6, as supplemented with additional information as included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. All clauses may be viewed in the entirety at www.acquisition.gov. A copy of this combined synopsis solicitation is included as a PDF attachment to this posting for your convenience.
(ii) The solicitation number 140P6226Q0008 and is issued as a Request for Quote (RFQ).
(iii) The solicitation incorporates provisions and clauses in effect through the current Federal Acquisition Circular: 2026-01
(iv) Total Small Business Set-Aside, 238220 - Plumbing Contractors Size Standard: $19M
(v) Line Items:
CLIN 0010 – Repair of water service line.
(vi) The National Park Service (NPS) is seeking quotes for repair of a water service line for James A. Garfield NHS in Mentor, OH. The quote shall be a single line item for the repair based upon the information provided in the attached statement of work.
Key dates:
Site visit: 3 September at 13:00 EDT (see below for more information)
Quotes due by 8 September 2026 at 18:00 EDT
(vii) Begin performance within ten (10) days of issuance of notice to proceed.
(viii) FAR provision 52.212-1 Instructions to Offerors - Commercial Products and Services applies to this acquisition.
All interested parties shall be registered and active in the System for Award Management or SAM at time an offer or quotation is submitted. SAM UEI to be provided with quote.
The offerors shall submit a quote to the contracting officer by email to:
matthew_frank@ios.doi.gov
Quote shall be provided on company letterhead including a breakout of estimated labor and materials.
There is no bonding requirement for this action.
(ix) The Government will award a firm, fixed price contract resulting from this solicitation to the responsible offeror or offerors whose quote(s) conforming to the solicitation will be most advantageous to the Government, price and technical factors considered.
(x) Offers shall include a completed copy of paragraph (b) from within FAR provision 52.212-3 - Offer Representations and Certifications - Commercial Products and Services with its offer.
(xi) FAR clause 52.212-4, Contract Terms and Conditions - Commercial Products and Commercial Services (Nov 2023) (DEVIATION Mar 2026), applies to this acquisition. No addenda are attached.
(xii) The following clauses are applicable to the contract resulting from this Request for Quote:
52.252-2 Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es):
www.acquisition.gov
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-13 System for Award Management Maintenance (Oct 2018) (DEVIATION Mar 2026) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025) (DEVIATION May 2026) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) (DEVIATION May 2026) 52.219-6 Notice of Total Small Business Set-Aside (Mar 2020) (DEVIATION Jan 2026) 52.219-28 Post-Award Small Business Program Representation (Jan 2025) (DEVIATION Jan 2026) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) (DEVIATION May 2026) 52.222-3 Convict Labor (Jun 2003) (DEVIATION May 2026) 52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) (DEVIATION May 2026 52.222-6 Construction Wage Rate Requirements (Aug 2018) (DEVIATION May 2026) 52.222-7 Withholding of Funds (May 2014) (DEVIATION May 2026) 52.222-8 Payrolls and Basic Records (Jul 2021) (DEVIATION May 2026) 52.222-9 Apprentices and Trainees (Jul 2005) (DEVIATION May 2026) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) (DEVIATION May 2026) 52.222-11 Subcontracts (Labor Standards) (May 2014) (DEVIATION May 2026) 52.222-12 Contract Termination-Debarment (May 2014) (DEVIATION May 2026) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) (DEVIATION May 2026) 52.222-15 Certification of Eligibility (May 2014) 52.222-19 Child Labor-Cooperation with Authorities and Remedies (Mar 2026) (DEVIATION May 2026) 52.222-50 Combating Trafficking in Persons (Oct 2025) (DEVIATION May 2026) 52.222-55 Minimum Wages Under Executive Order 14026 (Jan 2022) (DEVIATION May 2026) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) (DEVIATION May 2026) 52.222-90 Addressing DEI Discrimination by Federal Contractors (Mar 2026) (DEVIATION May 2026) 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021) (DEVIATION May 2026) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.232-90 Fast Payment Procedure (Dec 2025) DEVIATION DATE 52.233-1 Disputes (May 2014) DEVIATION DATE 52.233-3 Protest after Award (Aug 1996) DEVIATION DATE
52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) DEVIATION DATE 52.236-2 Differing Site Conditions (Apr 1984) (DEVIATION Jan 2026) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) (DEVIATION Jan 2026) 52.236-5 Material and Workmanship (Apr 1984) (DEVIATION Jan 2026) 52.236-6 Superintendence by the Contractor (Apr 1984) (DEVIATION Jan 2026) 52.236-7 Permits and Responsibilities (Nov 1991) (DEVIATION Jan 2026) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) (DEVIATION Jan 2026) 52.236-10 Operations and Storage Areas (Apr 1984) (DEVIATION Jan 2026) 52.236-11 Use and Possession Prior to Completion (Apr 1984) (DEVIATION Jan 2026) 52.236-12 Cleaning Up (Apr 1984) (DEVIATION Jan 2026) 52.236-13 Accident Prevention (Nov 1991) (DEVIATION Jan 2026) 52.236-14 Availability and Use of Utility Services (Apr 1984) (DEVIATION Jan 2026) 52.236-21 Specifications and Drawings for Construction (Feb 1997) (DEVIATION Jan 2026) 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (Apr 1984) 52.240-91 Security Prohibitions and Exclusions (Dec 2025) (DEVIATION Mar 2026) 52.240-93 Basic Safeguarding of Covered Contractor Information Systems (Dec 2025) (DEVIATION Mar 2026) 52.246-21 Warranty of Construction (Mar 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 52.249-4 Termination for Convenience of the Government (Services) (Short Form) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)
52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
www.acquisition.gov
(End of provision)
52.252-5 Authorized Deviations in Provisions (Nov 2020)
As prescribed in 52.107(e), insert the following provision in solicitations that include any FAR or supplemental provision with an authorized deviation. Whenever any FAR or supplemental provision is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the provision when it is used without deviation, include regulation name for any supplemental provision, except that the contracting officer shall insert "(DEVIATION)" after the date of the provision.
Authorized Deviations in Provisions (Nov 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any ______________ [insert regulation name](48 CFR Chapter______) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
The following provisions are included by reference:
52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.204-7 System for Award Management - Registration (Nov 2024) (DEVIATION Mar 2026) 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations – Representation (Nov 2015) (DEVIATION May 2026) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan-Certification (Aug 2009) DEVIATION DATE 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications (Jun 2020) DEVIATION DATE 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Dec 2025) (DEVIATION Mar 2026)
(xiii) The following provisions and clauses are included in full text as prescribed:
52.204-26 Covered Telecommunications Equipment or Services - Representation (Oct 2020)
(a) Definitions. As used in this provision, "covered telecommunications equipment or services" and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services".
(c) Representations. (1) The Offeror represents that it [ ] does, [ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ] does, [ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (Feb 2016) (DEVIATION May 2026)
(a) As required by sections 744 and 745 of Division E of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L 113-235), and similar provisions, if contained in subsequent appropriations acts, the Government will not enter into a contract with any corporation that--
(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless an agency has considered suspension or debarment of the corporation and made a determination that suspension or debarment is not necessary to protect the interests of the Government; or
(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless an agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.
(b) The Offeror represents that—
(1) It is [ ] is not [ ] a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability; and
(2) It is [ ] is not [ ] a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.
(End of provision)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)
(a)
(1) In accordance with 31 U.S.C. 3903 and 10 U.S.C. 3801, within 15 days after receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract, to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, after receipt of a proper invoice and all other required documentation from the small business subcontractor.
(2) The Contractor agrees to make such payments to its small business subcontractors without any further consideration from or fees charged to the subcontractor.
(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.
(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial products or commercial services.
(End of clause)
52.225-10 -- Notice of Buy American Requirement--Construction Materials (May 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American--Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.225-9 -- Buy American–Construction Materials (Oct 2022) DEVIATION DATE
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
NONE
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.
However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
(End of clause)
52.216-1 – Type of Contract (Apr 1984) DEVIATION DATE
The Government contemplates award of a Firm Fixed Price Contract resulting from this solicitation.
52.222-5 -- Construction Wage Rate Requirements—Secondary Site of the Work (May 2014) (DEVIATION May 2026)
(a)
(1) The offeror must notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222- 6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror must request a determination from the Contracting Officer.
(b)
(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror must request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
52.233-2 Service of Protest Department of the Interior (Sep 2006) (DEVIATION) (Jul 1996)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Katherine Bernard – katherine_bernard@ios.doi.gov or at the address in Block 8 of Form 1442.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(c) A copy of the protest served on the Contracting Officer shall be simultaneously furnished by the protester to the Department of the Interior Assistant Solicitor, Acquisitions and Intellectual Property, 1849 C Street, NW., Room 6511, Washington, DC 20240.
52.242-14 -- Suspension of Work (Apr 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not --
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.
The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may --
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction.
However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
Invoicing Processing Platform (IPP) - Treasury Electronic Invoicing System (May 2016)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Products and Commercial Services included in commercial item contracts. The IPP website address is:
https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Copy of vendor invoice document in PDF format, which shows pricing breakdown for all items being invoiced for and must include the contract number, date(s) of service (if applicable), date of invoice, and the vendor's standard invoice letterhead.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 - 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
1452.201-70 AUTHORITIES AND DELEGATIONS (Sep 2011) (REMOVE IF NOT
APPLICABLE)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment. The COR for this contract will be:
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.
(End of Clause)
1452.203-70 -- Restrictions on Endorsements (Jul 1996)
Restriction on Endorsements—Department of the Interior
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
1452.204-70 -- Release of Claims – Department of Interior (Jul 1996)
Release of Claims—Department of the Interior
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
1452.236-71 – Additive or Deductive Items – Department of the Interior (Jul 1996)
So that the Government may obtain the most desirable features of work within the limit of its funds available at time of bid evaluation, award may be made to the bidder having the lowest total of the base bid and a combination of additive and deductive items. All bids shall be evaluated on the basis of the same additive and deductive bid items using the order of priority of the items listed in the schedule.
52.237-1 Site Visit (Apr 1984)
Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Site visit location:
James A Garfield NHS 8095 Mentor Avenue, Mentor Ohio 44060
Time:
13:00 EDT 3 September 2026
Please inform the contracting officer of your intent to attend the site visit at matthew_frank@ios.doi.gov. Please note that site visit time is subject to change. Any changes to the site visit will be published via amendment to this request for quote.
(End of Provision)
(xiv) N/A
(xv) All quotes shall be received, via email to matthew_frank@ios.doi.gov, no later than 18:00 EDT, on 8 September 2026. Quotes shall be valid for 60 days. Include the solicitation number, 140P6226Q0008, in the email subject line.
(xvi) All communication regarding this solicitation, including questions, requests for additional information, documentation, etc., shall be emailed to matthew_frank@ios.doi.gov. Questions will NOT be answered via phone or text message.
List of Attachments
1. Specifications – SOW
2. Wage Determination
3. PDF Copy of Combined Synopsis Solicitation
File details come from the government source that posted it. Updated .