A04_SOW.pdf

PDF 2 MB Posted

Attached to
James A Garfield NHS - Water Service Line Repair
Solicitation number
140P6226Q0008
Issued by

About this file

This document is a Project Specifications package for Emergency Water Service Repairs at James A. Garfield National Historic Site in Mentor, Ohio, issued by the National Park Service with an effective date of August 10, 2026.

The project addresses a water leak resulting in losses of approximately 1,200 gallons per week. Work includes field verification of existing conditions with utility location; development and submission of an investigation plan detailing investigation extent, methods, and protective measures for nearby active utilities including gas and electric lines; on-site investigation to confirm damage and leak location; replacement of up to 50 linear feet of ¾-inch copper water service pipe from the meter toward the Garfield Home with flared connection fittings; replacement of one gate valve; installation of a second gate valve for the water service line to the Garfield Home; completion of all water service repairs using NSF-approved materials; water line disinfection and testing per specifications and Public Health standards; and pavement and landscape rehabilitation. All work must be completed within 10 calendar days of the Notice to Proceed, inclusive of three weather days. Materials and chemicals must be approved for drinking water systems, and all materials require Contracting Officer and Contracting Officer's Representative approval prior to installation. Water lines must be tested and disinfected in compliance with AWWA Standards and Ohio requirements. The contractor is responsible for coordinating utility shutoffs with local utility providers and may not exceed 2–3 hour shutdown windows. Preconstruction submittals include liability insurance, workman's compensation, bonds, project superintendent designation, construction schedule, schedule of values, accident prevention plan, subcontractor list, labor compliance certifications, and quality control plan.

View the file

Other files

File Type Posted
B08_Copy_of_Combined_Synopsis_Solicitation.pdf PDF
B03_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Div. 1 V. 2021-10-18 Page | 1

James A. Garfield National Historic Site

EMERGENCY WATER SERVICE REPAIRS

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

08/10/2026

Page | 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 - Division 01 Short Form General Requirements

DIVISION 02 – EXISTING CONDITIONS

Section 02 31 00 – Site Excavation and Grading Section 02 32 00 – Utility Trenching, Backfill, Boring and Trenching Section 02 50 10 – Testing of Water Mains Section 02 51 10 – Water Service Lines Section 02 51 20 – Gate Valve with Service Box Section 02 51 90 – Disinfection of Water Lines

APPENDICES

Appendix A – Site Plans Appendix B – Leak Detection Report

Page | 3

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: June 1, 2026, the James A. Garfield National Historic Site was alerted to a high-water usage bill by our business associate. The bill indicated a spike in domestic water usage which prompted us to start an investigation of our facilities. Currently, we are experiencing a water leak loss upwards of 1,200 gallons a week. After ruling out obvious causes of potential leaks, we switched our attention to the grounds. After numerous attempts by Park personnel, both by James A Garfield and Cuyahoga Valley National Park Staff, a leak detection company was hired to locate the leak on August 4, 2026. The approximate, general leak area has been located, and all damage and deficiencies will need to be confirmed and repaired. It is estimated that a portion of the water service lateral and valve near the water meter will need to be replaced.

Additionally, a new gate valve shall be installed at the water lateral for the Garfield Home. Water lines are to be disinfected and tested as specified herein and in accordance with National Park

Service Public Health requirements.

High attention to existing utilities and the historical context of the property is required and of utmost importance for this project.

1.2 Work Covered by the Contract Documents:

A. Project Location: James A Garfield National Historic Site, 8095 Mentor Avenue, Mentor Ohio

44060. Project location is on the site grounds in the southeast corner of the property where the utilities enter from Mentor Avenue. The approximate area is notated on the attached site plan.

B. Work consists of:

1. Field verify existing conditions and obtain a utility locate.

2. Due to the historic significance of the property and concentrated presence of utilities in the area, including gas and electric, develop and submit an investigation plan for

Contracting Officer (CO), Contracting Officer’s Representative (COR), and compliance approval. The plan should clearly outline the extent of investigation, methods to be used, and protective measures to be taken for the active nearby utilities. The Contractor is responsible for coordinating utility shutoffs with the local utility companies to ensure worker, NPS staff, and public safety.

3. Complete the on-site investigation, confirm damage and location of leak, and assess project needs for the extent of repairs and water service replacement including but not limited to:

i. Replacement of up to 50-LF of ¾” copper water service pipe from the meter towards the Garfield Home, terminating at the entrance road and including flared connection fittings.

Page | 4

ii. Replacement of one gate valve

iii. Provide a second gate valve for the water service line for the Garfield Home.

Verify location with the CO/COR prior to installation.

4. Complete all water service repairs. All materials and chemicals to be used must be approved for drinking water systems (NSF approved). Submit all materials to the CO and COR prior to installation.

5. Complete water line disinfection and testing per the specifications and Public Health standards herein. Provide testing reports to the CO and COR.

6. Conduct pavement and landscape rehabilitation.

C. All work will be performed under a single contract.

D. Period of performance: Work shall be completed within 10 calendar days of the start date provided on the Notice to Proceed. The period of performance is inclusive of 3 weather days.

ITEM 2 - EXISTING UTILITIES

2.1 Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative (COR) and utility companies to coordinate proposed locations, times for excavation and request location services prior to any digging operation including investigative potholing or hydrovac. Contractor shall be responsible for coordinating all necessary utility shutoffs with utility providers and the

CO/COR.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

2.3.1 Notify CO and COR not less than two business days in advance of proposed utility interruptions.

2.3.2 Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park

Service, and applicable park rules and regulations prescribed by the Park Superintendent.

Page | 5

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting

Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding

Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal

Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown in Appendix A – Site Plan. Do not disturb portions of

Project site beyond areas in which the Work is indicated.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

Page | 6

C. Utilities

1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

2. Water Service: Water from existing water system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.

3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

4. Toilets: Contractor provided for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.

D. Security and Protection facilities:

1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.

Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR.

a. Restore damaged areas to original condition, repairing or replacing damaged trees and plants, at no additional expense to the Government.

b. Provide temporary barriers to protect existing trees and plants and root zones.

c. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.

d. Do not fasten ropes, cables, or guys to trees.

e. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

Page | 7

5. Temporary Enclosures: Provide temporary enclosures as required for protection of construction in progress and completed, from exposure, foul weather, other construction operations, and similar activities.

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. No cost specific storage and staging area’s may be discussed at the preconstruction briefing.

3.5 Preservation of Natural Features: N/A

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Occupancy Requirements for Buildings:

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings that will be adjacent to construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the

CO or COR.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations.

Protect building and its occupants during construction period.

3.9 Photo Documentation: Contractor must provide existing condition, progress and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email or via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

Page | 8

A. Existing Condition Images: Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

B. Construction Progress Images:

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

C. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety: As a minimum, conduct one weekly 15 minute "toolbox" safety meetings.

These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week.

Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

B. Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics – N/A

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

Page | 9

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items viewable during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS

Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National

Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample

JHA template may be provided upon request.

5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies.

7. Recognition that work will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute

"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

Page | 10

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

ITEM 8 - PRECONSTRUCTION CONFERENCE: If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The

Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

9.1 General Submittal Procedures:

Page | 11

A. General: Prepare and submit submittals required by individual Technical Specification

Sections. Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR

B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to

Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the

Pre-Construction Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Quality Control Plan.

9.2 Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file

(.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this section to include one digital file

(.PDF or .TIF) to COR.

C. Samples: Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

Page | 12

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the

Contractor. If submittals are not approved, Contracting Officer will return all copies to

Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient

2. characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance,

6. including schematics for electrical and hydraulic systems, lubrication requirements,

7. and parts lists. Describe availability of maintenance service, and state source of

8. replacement materials.

B. A request for approval constitutes a representation that Contractor:

1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

2. Will provide the same warranties for the proposed item as for the item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

9.4 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.

Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in

Page | 13 a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of

Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this

Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting

Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

B. If the work is not determined to be complete following the final inspection, the Contracting

Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 2 calendar days, or a time directed by the

CO.

Page | 14

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of

Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

11.5 Warranties

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

JAGA Emergency Water Service Repairs 023100-Page 1 of 2

SITE EXCAVATION AND GRADING

SECTION 02 31 00

PART 1 GENERAL

1 .1 DESCRIPTION

A. The work of this section consists of site excavation and grading.

1 .2 RELATED WORK

A. NOT USED.

1 .3 CLASSIFICATION

A. Rock excavation consists of material that cannot be excavated without blasting or using rippers, including boulders having a volume of 2 cubic yards or more.

B. All other excavation under this section will be considered unclassified regardless of the nature of material encountered.

1 .4 PROJECT CONDITIONS

A. Maintain fills, slopes, and ditches within the limits of the new construction until final acceptance. Repair damaged areas at no additional expense to the Government.

PART 2 PRODUCTS

2 .1 EXISTING EMBANKMENT MATERIAL

A. Material for embankment construction shall be free from frozen material, debris, muck, detrimental quantities of organic materials, and other unsuitable materials.

PART 3 EXECUTION

3 .1 STRIPPING AND STOCKPILING TOPSOIL

A. Strip topsoil within the construction limits to a depth of 2-6 inches. The Contracting Officer will designate locations for stockpiles. The maximum haul distance, pick-up point to stockpile, will not exceed 150 feet. Place an approved barrier below each topsoil stockpile.

Barrier may be 6 mil plastic or tarp in good condition.

3 .2 FIELD QUALITY CONTROL

A. Testing required to determine compliance for the work of this section will be the responsibility of the Contractor, at no additional expense to the Government.

B. ASTM D698-91 shall be used to determine maximum density and ASTM D1556-90 or a standard nuclear method shall be used to determine in-place density.

3 .3 EXCAVATION

JAGA Emergency Water Service Repairs 023100-Page 2 of 2

A. Excavate to lines and grades shown. Keep excavation free from water during construction.

As directed, stockpile excavated material to be used in embankment construction. Excavate rock to a minimum depth of 6 inches and a maximum depth of 12 inches below subgrade.

3 .4 EMBANKMENT CONSTRUCTION

A. Before placing embankment, scarify ground surface to provide ample bond between old and new material. Place embankment material in layers not exceeding 8 inches loose measurement. Compact each layer before placing the next layer. As the compaction of each layer progresses, continually level and manipulate to ensure uniform moisture and density.

Add water to obtain optimum moisture content.

3 .5 COMPACTION

A. Compact the top 2.5 feet of embankments supporting walks and other structures to 95 percent of the maximum density as determined by ASTM D698-91, at plus or minus 2 percent of the optimum moisture content.

B. Compact embankments below the top 2.5 feet and embankments not supporting walks or other structures to 90 percent of maximum density as determined by ASTM D698-91, at plus or minus 2 percent of the optimum moisture content.

3 .6 SUBGRADE TOLERANCE

A. The finish subgrade elevation shall not vary above or below the theoretical grade more than

0.1 foot.

3 .7 PLACING TOPSOIL

A. Section 02911.

3 .8 DISPOSAL

A. Dispose of all surplus and unsuitable material as specified in Section 01570.

PART 4 MEASUREMENT AND PAYMENT

4 .1 SITE EXCAVATION AND GRADING

A. Payment will be included in the contract lump-sum price to which this work relates.

JAGA Emergency Water Service Repairs 023200-Page 1 of 9

UTILITY TRENCHING AND BACKFILLING

SECTION 02 32 00

UTILITY TRENCHING, BACKFILLING, BORING AND SURFACING

A. The work of this section consists of trenching and backfilling for the construction and installation of pipelines, conduits, and cables. All trenching will be open cut.

1 .2 SUBMITTALS

A. Written procedure for trench dewatering and disposal of fluidized materials removed.

B. Written description of barricading, shoring, cribbing, bracing, and sloping precautions.

C. Written procedure for boring and jacking, directional boring, casing pipe and bracing under roadways/driveways/parking lots.

D. Written procedure for roadway and parking lot restoration including asphalt mix, concrete mix/reinforcement, gravel and gravel base.

1 .3 PROJECT CONDITIONS

A. Obtain all required permits and licenses before installing utilities under existing roads, other than Park Service roads, and follow the rules and requirements of the authority having jurisdiction.

B. Arrange construction sequences to provide the shortest practical time that the trenches will be open to avoid hazard to the public, and to minimize the possibility of trench collapse.

1 .4 EXCAVATION CLASSIFICATION

A. Regardless of the nature of material excavated, all excavation will be considered unclassified.

2 .1 GENERAL

A. All backfill material shall be approved before use and be free of cinders, ashes, ice, frozen soil, large hard clods, organic debris, or other deleterious items. Trench excavation materials may be used as approved.

2 .2 BACKFILL MATERIAL

A. Materials used in backfill, are defined as follows:

1. Bedding (BD): When rock, unstable material, or wet trench is encountered at the excavated grade for utility installation, bedding is required. Materials shall be predominantly sand and gravel, having a plasticity index less than 6. Bedding may be omitted if, in the opinion of the Contracting Officer, the excavated trench bottom will adequately support and not damage the utility line.

JAGA Emergency Water Service Repairs 023200-Page 2 of 9

a. BD-1: Gradation as follows:

Sieve Size

Percent Passing

No. 4 100

No. 8 55- 85

No. 40 15- 30

b. BD-2: Gradation as follows:

Sieve Size Percent Passing

1/2-inch 100

No. 4 50- 80

No. 40 10- 25

c. BD-3: Gradation as follows:

1-1/2-inch 100

1/2-inch 45- 75

2. Select Backfill (SB): Materials shall be predominantly sand and gravel, having a plasticity index less than 6.

a. SB-1: Gradation as follows:

Sieve Size Percent Passing

No. 4 100

No. 8 55- 85

No. 40 15- 30

b. SB-2: Gradation as follows:

1/2-inch 100

No. 4 50- 80

JAGA Emergency Water Service Repairs 023200-Page 3 of 9

c. SB-3: Gradation as follows:

Sieve Size Percent Passing

3/4-inch 100

3/8-inch 55- 85

d. SB-4: Gradation as follows:

1-1/2-inch 100

3. Backfill (BF):

a. BF-1: Materials shall be predominantly sand and gravel, having a plasticity index less than 6, and graded as follows:

Sieve Size Percent Passing

1-1/2-inch 100

b. BF-2: Soils that contain no rock larger than 6 inches at greatest dimension. If expansive clays are present, such content shall not exceed one-third of the material by volume, and shall be well mixed with noncohesive soils.

B. ASTM D422-63 shall be used for gradation analysis. ASTM D4318-95 shall be used for determination of plasticity index.

C. Furnish required bedding, select backfill, and backfill materials listed under the appropriate types of utility line in the sections to which this work relates.

1. Water mains and service lines: Use BD-1 bedding material if required and SB-1 select backfill within 6-inches of the pipe if the existing backfill material is unsuitable, and BF-2 backfill.

2. Paved areas: Use BD-2, SB-2 and BF-1

2 .3 UTILITY LINE MARKING

A. All utilities shall be marked for location and identified by marking tapes and tracing wire. The tracing wire will be a 12 gauge solid copper tracing wire buried 24-inches below ground service above the top of the buried pipe. Have the ends of the tracing wire come to the surface at locations approved by the Contracting Officer. Use marking tape labeled with the type of utility being marked.

JAGA Emergency Water Service Repairs 023200-Page 4 of 9

PART 3 EXECUTION

3 .1 TRENCH EXCAVATION

A. Trenching, General: Excavate the trench to the approximate level of the top of the utility line to be installed, using adequate trench width and side slopes to safely accommodate worker access. Continue excavating for the utility line, to a width not greater than is shown on the appropriate trench detail.

1. Rocky Trench Bottom: Where ledge rock, hard pan, boulders, or sharp-edged materials are encountered, over-excavate a minimum depth of 6 inches below the bottom of the utility exterior wall to permit adequate bedding preparation. The installed utility shall have at least 6 inches of clearance from any rock protrusion.

2. Unstable Trench Bottom: Secure approval of depth of over-excavation and stabilization method.

For wet trench construction, use approved method of dewatering through diversion, damming and pumping, well points, or underdrain systems. Dispose of removed fluidized materials as approved.

Use BD-3 material to build a suitable foundation to within 6 inches of finished utility grade, prior to bedding with the specified material. Compact layers to 95 percent of maximum density in not greater than 6-inch layers. Do not proceed with utility installation until wet trench and unstable conditions are under control.

3. NOT USED.

B. NOT USED.

C. Reseed disturbed lawn and pipeline areas with PERI “Park Approved” seed mix. Cover the reseeded area with Curlex or approved equal. Cover must be approved prior to seeding.

3 .2 SHORING AND SHEETING

A. Construct and maintain all shoring, sheeting, and slope lay-back necessary to protect the excavation, as needed for the safety of the employees and as required by applicable State and Federal laws.

B. For trenches over 5 feet deep, provide suitable barricades for worker protection. When work area is left open and unattended by Contractor, provide suitable barricades for public safety, regardless of trench depth.

C. For trenches over 4 feet deep, provide suitable exit means in accordance with applicable provisions of

OSHA.

D. Do not remove timber or sheeting if it is in a compacted zone. Instead, trim it off at a safe level above that zone.

E. As directed, remove all other sheeting and shoring when safe to do so.

3 .3 INSULATION - Not Used.

3 .4 BACKFILLING

A. Compaction:

1. Use vibratory compactors for sand and gravel (noncohesive soils).

2. Use mechanical tampers for sand and gravel containing a significant portion of fine-grained material, such as silt and clay (cohesive soils).

3. Hand tamp around pipe or cable to protect the lines until adequate cushion is attained.

JAGA Emergency Water Service Repairs 023200-Page 5 of 9

4. Puddling or water flooding for consolidation of backfill or compaction by wheel rolling with construction equipment will not be permitted.

B. Bedding: Compact the specified material to 95 percent of maximum density, at a moisture content determined to be suitable for such density. Compaction shall be to the finished utility grade.

C. Utility Installation: Shape the trench bottom to ensure uniform contact with the full length of the installed line and remove any sharp-edged materials that might damage the line. Compaction shall be maintained beneath the line.

D. Select Backfill: Fill by hand placement around the utility to just over half depth, and compact in a manner to ensure against lateral or vertical displacement. Place select backfill to 12 inches above the utility line by hand placement in not more than 6-inch layers. Compact each layer to 95 percent of maximum density, at a moisture content determined to be suitable for such density.

E. Backfill: Place and compact the specified material as follows:

1. NOT USED.

2. Pedestrian and Lawn Areas: Fill and compact in 8-inch maximum layers to 90 percent of maximum density, at moisture content determined to be suitable for such density.

3. Non traffic Areas: Fill and compact in 8-inch maximum layers to 90 percent of maximum density, at moisture content determined to be suitable for such density.

F. Boring and Jacking: Crossing of paved and graveled roadways may be completed by means of a road bore and installation of polyvinyl chloride (PVC), yelomine, high density polyethylene (HDPE), or steel pipe casing under the roadway as shown on the plans.

G. Polyvinyl Chloride (PVC) Casing: PVC casing pipe shall be manufactured from compounds conforming to requirements of ASTM D 1785. All PVC casing pipe shall have a minimum wall thickness of Schedule 80 PVC pipe. All joints on the casing pipe shall be solvent weld connections.

H. Yelomine Casing: Yelomine casing pipe shall be manufactured from compounds conforming to requirements of ASTM D 2241. All yelomine casing pipe shall have a minimum wall thickness of SDR-21 pipe. All connections shall be made by utilizing precision machined grooves on the pipe, and a restraint joint coupling which, when aligned, allow a spline to be inserted, locking the pipe and the coupling together.

I. High Density Polyethylene (HDPE) Casing: HDPE casing pipe shall be the size as indicated on the plans, manufactured from high density, very high molecular weight (VHMW) pipe resin designated by PPI as PE3408. Casing pipe shall have a minimum pressure rating of 100 psi and a SDR of 17. Lengths shall be joined by heat fusion in accordance with manufacturer’s recommendations. Manufacturer’s recommended maximum allowable bending radius for the casing pipe shall be provided by the Contractor in the submittal information.

J. Steel Pipe Casing: Steel casing pipe 8 inches and larger shall be Grade A steel pipe of the diameter shown on the plans with a minimum wall thickness of

K. 0.25 inches and shall meet ASTM Specifications A 53. Casing pipe 2 inches through 6 inches I.D. shall be standard weight galvanized steel pipe conforming to ASTM Specification A 120. The welding of sections of steel casing pipe shall be done with full depth and circumference welds to produce a watertight joint of strength equal to the casing.

L. The casing pipe shall be installed by boring where indicated on the drawings or at a location designated by the Contracting officer/Project Engineer and shall be kept on line and grade by suitable guide rails in the approach pit. The deviation from line and grade of the carrier pipe as established by the Contracting Officer/Project Engineer in the field shall not exceed 1.0 foot per 100 feet of water main and water service

JAGA Emergency Water Service Repairs 023200-Page 6 of 9 line. The Contractor shall be responsible for complying with the local governing authority for the circular annulus size allowed for the size casing installed.

M. The casing pipe for all crossings shall be installed in a manner that will allow for the installation of the carrier pipe in a straight line without contacting the walls of the casing.

N. Casings for water mains and water service lines shall be installed prior to the installation of pipe within 100 feet of the crossing for the main or service line under construction. Crossings for water service lines and water mains shall be a minimum of 5 feet below the surface of the roadway.

O. When crossing roadways, driveways, or other areas requiring the installation of casing pipe by boring, the minimum depth of cover over the top of the casing shall be that shown on the drawings.

P. Casing spacers (skids) shall be used to install the PVC carrier pipe inside the encasement pipe, providing support around the periphery of the pipe should the pipe twist as it is pushed through the casing. The spacers shall be of a projection type that has a minimum of four projections around the circumference.

The total number of projections will vary with the diameter of the pipe and shall be in accordance with industry standards.

Q. Casing spacers shall use double backed tape, provided with the spacers, to fasten tightly onto the carrier pipe so that the spacers do not move during installation. Installation instructions shall be provided with each shipment. Casing spacers shall have a span of 6½ feet to 10 feet dependent on the total load anticipated with the carrier pipe full of liquid. The skid length of the spacers shall be of such length so that the carrier pipe bell does not come in contact with the carrier casing.

R. Casing spacers shall be projection type totally non-metallic spacers constructed of preformed sections of high density polyethylene. Spacers shall be ISO 9002 certified for strength and quality. Projection type spacers shall be RACI type spacers, or approved equal, along with wrap around end seals made of 1/8-inch thick rubber with stainless steel clamps.

S. Directional Drilling: Crossing of paved and graveled roadways, wetlands and streams where specially noted, may be completed by means of directional drilling and installation of High Density Polyethylene (HDPE) carrier and casing pipe.

T. HDPE carrier pipe shall be the (IPS) size as indicated on the plans, with a minimum pressure rating of 200 psi, a SDR of 9 and a cell classification of 355434C or 345434C by ASTM D 3350. Pipe shall be provided in the manufacturer’s standard lengths. Lengths shall be joined by heat fusion in accordance with manufacturer’s recommendations. Manufacturers recommended maximum allowable bending radius for the carrier pipe shall be provided by the Contractor in the submittal information.

U. Fittings for connecting to polyethylene pipe 1½ inches and 2 inches in size shall be red brass insert or pack joint compression type fittings as recommended by the manufacturers. Fittings for connecting to polyethylene pipe 3 inches to 12 inches in size shall be standard commercial products manufactured through injection molding or extrusion and machining. The fittings shall be manufactured from the same resin type, grade, and cell classification as the pipe itself, and shall be rated to the same working pressure of the pipe.

V. HDPE casing pipe shall be the size as indicated on the plans, manufactured from high density, very high molecular weight (VHMW) pipe resin designated by PPI as PE3408. Casing pipe shall have a minimum pressure rating of 100 psi and a SDR of 17. Lengths shall be joined by heat fusion in accordance with manufacturer’s recommendations. Manufacturer’s recommended maximum allowable bending radius for the casing pipe shall be provided by the Contractor in the submittal information.

W. End seals, (1/8-inch synthetic rubber, Pipeline Seal and Insulator, or equal), shall be provided on the casing pipe to prevent entrance of backfill material.

X. The Contractor shall utilize a walkover system or a wire line steering tool and record the readings a minimum of every 25 feet while drilling to ensure that the Contractor keeps a grade alignment within ½-foot of the designed grade shown on the plans. The location of the exit point of the drill bit shall be

JAGA Emergency Water Service Repairs 023200-Page 7 of 9 accurate within 2 percent of the length of the drill hole. It is the intent of the grade shown on the plan profile, that there be no high points allowed in the line, within the area that is to be directional drilled. If a portion of the bore is out of the given tolerance, the drill string shall be pulled back, and that segment of the hole shall be re-drilled.

Y. Upon completion of the pilot hole, the Contractor shall ream the hole to the smaller of either 4 inches larger than the outside diameter of the HDPE casing pipe being installed or approximately 1 ½ times the outside diameter of the HDPE casing pipe to be installed. Drill mud shall be left in the hole to fill all voids around the pipe. The pipe pullback operation shall be carried out as soon as possible following the reaming.