B08-Bid_Sheet_Beale_House_Boiler_Replacement_4_7_26_0001.docx

DOCX document 22 KB Posted

Attached to
Replace Boilers at Beale House located at Adams Na
Solicitation number
140P4326R0026
Issued by

About this file

This is a Bid Sheet for the replacement of boilers at Beale House, located at Adams National Historic Park in Quincy, Massachusetts. The National Park Service, Northeast Region, New England Major Acquisition Buying Office issued a Request for Proposal (RFP) under solicitation number 140P4326R0026 for this project. Contractors are required to provide all labor, qualified supervision, materials, tools, equipment, supplies, and incidentals necessary to replace the existing gas-fired boiler system with new, high-efficiency, code-compliant units. The work must be performed in a manner that protects historic fabric and ensures compatibility with existing mechanical, electrical, and control systems. A mandatory site visit was scheduled for Wednesday, June 24, 2026, at 10:00 a.m. EDT at 181 Adams Street, Quincy, Massachusetts 02169.

The bid sheet document serves as the pricing and submission template for interested contractors responding to this solicitation. Detailed specifications for the boiler replacement work are provided within the solicitation documents. This is a federal contracting opportunity issued by the Department of the Interior National Park Service Northeast Region, with the federal meta opportunity ID 6a288cef47ba62ce2d0cdc92.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Beale House Boiler Replacement Adams National Historical Park – Quincy, MA Prepared By: Kevin W. Kelly, Facility Manager Date: April 7, 2026

1. Project Overview This estimate covers the removal of three existing gas‑fired boilers and the installation of three new high‑efficiency natural‑gas hot‑water boilers, including reconnection of gas, hydronic piping, electrical systems, controls, and commissioning requirements as defined in the project SOW

2. Cost Summary A. Demolition & Removal – $

• Drain, disconnect, and remove existing boilers and obsolete accessories

• Protect historic fabric and dispose of materials in compliance with requirements B. Equipment / Supplies & Materials $

• Three high‑efficiency boilers

• Valves, insulation, bypass piping, supports, condensate pumps, and associated hardware.

C. Installation Labor – $

• Mechanical, electrical, venting, and piping installation

• Work conducted within an occupied historic structure under NPS protocols D. Controls, TAB & Commissioning – $

• Controls integration (existing system or compatible replacements)

• Testing, adjusting, balancing, and final commissioning report.

E. Cleanup & Closeout – $

• Debris removal, broom‑clean condition, documentation delivery.

3. Total Project Cost $

4. Assumptions

• No hazardous materials abatement required

• All work completed within standard NPS work hours (Mon–Fri, 7:00 a.m.–3:00 p.m.)

• Existing utilities are adequate for reconnection

• One‑year warranty on labor and materials required by SOW

File details come from the government source that posted it. Updated .