This document is a Statement of Work (SOW) for a federal contract opportunity to provide solid waste disposal services to the National Park Service (NPS) at the Point Reyes National Seashore in Marin County, California.
The SOW outlines the requirement for the contractor to provide landfill services to dispose of an estimated 200 tons of non-hazardous trash annually, with NPS employees delivering the trash up to twice per week during peak season and once per week during off-peak season. The contractor must have a California State Certified landfill site located within 25 miles of the park address. The contract period of performance is from June 17, 2024 to May 31, 2025. Payment will be on a firm-fixed price basis, and the contractor must submit invoices through the U.S. Department of the Treasury's Invoice Processing Platform System. The total estimated value of the requirement is less than $25,000.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Attachment01_QUOTE_SHEET_140P8424Q0048.pdf | ||
| B08_Attachment03_SCA_WD_2015-5725_140P8424Q0048.pdf | ||
| B08_Attachment04_52_212-3_Full_Text_(May_2024)_140P8424Q0048.pdf | ||
| B08_Attachment05_Exp_PP_Form_140P8424Q0048.pdf | ||
| Sol_140P8424Q0048.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solid Waste Disposal-Landfill Fees, Point Reyes National Seashore Page 1 of 3
STATEMENT OF WORK (SOW)
Point Reyes National Seashore
Solid Waste Disposal to Landfill Site
STATEMENT OF WORK
1.0 Overview
2.0 Background
3.0 Scope
4.0 Objectives
5.0 Tasks
6.0 Delivery
7.0 Government-Furnished Property
8.0 Place of Performance
9.0 Period of Performance
10.0 Contract Administration
1.0 Overview
The National Park Service (NPS) , Point Reyes National Seashore (PRNS), located in Marin County, California, has a requirement for solid waste disposal to landfill site services. The solid waste consists of non-hazardous trash collected by the NPS from the Park and transported to the landfill site by the NPS. The estimated base amount is up to 175 tons annually, with an option for up to 25 tons of additional waste disposed.
During the months of April through October, deliveries will occur twice a week or during the months November through March, deliveries will occur once a week. Capable businesses must be able to provide landfill service Monday through Friday from 10:00am to 3:00pm. Landfill must be California State Certified.
2.0 Background
Point Reyes National Seashore collects trash from Park visitors, residents, and employees, and has a requirement for disposing of this trash, estimated to be 200 tons annually, to a California State Certified landfill within 25 miles of the Park address:
1 Bear Valley Road, Point Reyes, CA 94956-9703.
Solid Waste Disposal-Landfill Fees, Point Reyes National Seashore Page 2 of 3
3.0 Scope
PRNS employees will deliver the trash to the landfill site up to twice per week.
Contractor shall provide landfill service Monday through Friday, from 10:00am to 3:00pm.
4.0 Objectives
Landfill site service to dispose of up to 200 tons annually.
Compliance with California state laws.
5.0 Tasks
During peak visitation season, considered to be the months of April through October, trash drop off by NPS will occur twice per week. During non-peak season the trash drop off will occur once per week.
On average, the NPS will bring between 1 to 6 tons of trash for disposal each week.
6.0 Delivery
Contractor's facility within 25 miles of PRNS shall provide landfill site services that can meet stated capacity of 200 tons annually.
Contractor shall provide NPS employees delivery ticket receipts documenting the weight of each delivery.
7.0 Government-Furnished Property
No Government-Furnished Property will be provided to the contractor however, the trash will be delivered to the contractor's facility by NPS employees in a Government owned trash compactor.
8.0 Place of Performance
Performance shall occur at the contractor's landfill site, located within 25 miles of Point Reyes National Seashore, 1 Bear Valley Road, Point Reyes, CA, 94956.
9.0 Period of Performance
June 17, 2024 to May 31, 2025
Solid Waste Disposal-Landfill Fees, Point Reyes National Seashore Page 3 of 3
10.0 Contract Administration
Payment:
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP) at https://www.ipp.gov/. The Contractor shall submit all invoices through www.ipp.gov within 30 days of work completion. Failure of the contractor to upload an attached copy of the invoice and any requested documentation through IPP.gov will result in invoice being rejected.
Key Contacts:
The Contracting Officer’s Representative (COR) for this order will be:
Jesse Macklin, Buildings, Utilities and Grounds Lead or Acting Buildings, Utilities and Grounds Supervisor (TBD) Point Reyes National Seashore 1 Bear Valley Road Point Reyes Station, CA 94956 Office 415-464-5155 jesse_macklin@nps.gov
The Contract Specialist (CS) responsible for administering this order will be:
Loren Thomas, Contract Specialist National Park Service
(415) 464-5233 loren_thomas@nps.gov
The Contracting Officer (CO) with overall responsibility for this order will be:
Elizabeth Chico, Contracting Officer National Park Service
(530) 595-6113 elizabeth_chico@nps.gov