This performance work statement outlines maintenance, inspection, testing, and minor repair requirements for 242 fire suppression systems across 50 buildings at Tobyhanna Army Depot. Key responsibilities for the contractor include annual and biennial inspections and testing of wet pipe, dry pipe, deluge, and pre-action sprinkler systems as well as fire pumps, according to NFPA 25 and UFC 3-601-02 standards. The contractor must also perform preventative maintenance, address any issues identified, and report inspection results on a monthly basis. The initial period of performance is 12 months with two optional one-year extensions. The solicitation was issued by the Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS) Sprinkler Systems Annual Inspection, Testing, Maintenance/Minor Repairs (ITM) (Annual Inspection/Testing Only) 2022-2025
1.0 Introduction
| 1.1 Background |
| 1.2 Place of Performance |
| 1.3 Period of Performance |
1.4 Type of Contract
2.0 Performance Requirements
| 2.1 General |
| 2.2 Inspection, Testing, and Minor Repair/Maintenance |
| 2.2.1 Inspection and Testing |
| 2.2.2 Minor Repairs/Maintenance |
| 2.2.2.1 Identification |
2.2.2.1.2 Notification
2.2.2.2 Approval Process
2.2.3 Invoicing
| 2.2.2.4 Sprinkler Systems Requiring Minor Repair / Maintenance |
| 2.3 Five Alarm Panels |
| 2.4 Stationary Fire Pumps |
| 2.5 Reporting |
| 2.6 TYAD Water Based Fire Protection Systems |
| 2.6.1 Risers |
| 2.6.2 Fire Pumps |
| 2.6.3 Sprinkler System |
| 2.7 Quality Assurance. |
| 2.7.1 Performance Requirements Summary/Quality Assurance |
| 2.7.2 Methods of Surveillance |
| 2.7.3 Ratings |
| 2.7.4 Documenting Performance |
| 2.7.4.1 Acceptable Performance |
| 2.7.4.2 Unacceptable Performance |
| 2.7.4.3 Corrective Action |
3.0 Contractor Responsibilities and Qualifications
| 3.1 Management |
| 3.2 Schedule |
| 3.3 Contractor Qualifications |
| 3.4 Personnel |
| 3.4.1 General |
| 3.4.2 Qualifications |
| 3.4.3 Labor Standards |
| 3.4.4 In-Processing |
3.4.4.1 Roster
3.4.4.2 Non Resident/Non Immigrant Personnel
| 3.4.4.3 ELTY 648-C Processing |
| 3.4.4.4 Planning |
| 3.4.4.5 Accessibility Issues |
| 3.4.4.6 Secure Areas |
| 3.4.4.7 Hours of Operation |
4.0 Security Requirements
1.0 Introduction.
1.1 Background. The Tobyhanna Army Depot (TYAD) is a recognized leader in providing World-Class Logistics Support for Command, Control, Communications, Computers, Intelligence, Surveillance, and Reconnaissance (C4ISR) Systems across the Department of Defense. Located in Northeast Pennsylvania, TYAD is an installation comprised of a complex assortment of buildings and structures. Water based fire protection systems in place provide protection to two hundred thirty four (242) zones across over fifty (50) buildings and structures. A system consists of a riser with a main and branch lines to an area being served, including any and all sprinkler heads, control valves, test connections, etc.
1.2 Place of Performance. All of the systems within the scope of work are located on the Tobyhanna Army Depot (TYAD), located in the Pocono Northeast region of Pennsylvania.
1.3 Period of Performance. The period of performance for this award is twelve (12) months. The Government reserves the right to exercise Option Year One and Option Year Two, (FAR 52.217-9; Option to Extend Services). The Government retains the discretion and right to unilaterally exercise the options contained in this contract.
1.4 Type of Contract. This contract will be a Firm-Fixed Price (FFP) Contract Line Item Number (CLIN) for the inspection, testing, preventative maintenance and remedial repairs.
2.0 Performance Requirements.
2.1 General. The contractor shall inspect, test, and perform minor repairs to the water based fire protection systems in accordance with the latest version Unified Facilities Criteria (UFC) 3-601-02: Inspection, Testing & Maintenance of Water Based Fire Protection Systems. The contractor shall perform the Annual, Two (2) and Five (5) year inspection, testing and maintenance (including minor repairs) on all items listed in UFC 3-601-02. Technical guidance is contained in National Fire Protection Association (NFPA) 25. A complete listing of the 242 systems by building may be referenced in “Solicitation Attachment - Systems by Building.
2.2 Inspection, Testing, and Minor Repair/Maintenance. UFC 3-601-02 provides requirements for inspection, test, and maintenance of fire protection features in Department of Defense (DoD) facilities. The latest UFC 3-601-02, “Operations and Maintenance: Inspection, Testing, and Maintenance of Fire Protection Systems” may be obtained at http://www.wbdg.org/FFC/dod/unified-facilities-criteria-ufc .
2.2.1 Inspection and Testing. “Annual” Inspections will be required in the Base Year and Option Year Two of the contract. An Annual, Two (2) Year and Five (5) Year Inspection will be required in Option Year One of the contract to all applicable systems.
2.2.2 Minor Repair/Maintenance. Based on historical data the price of materials/hours to be used is estimated at $40,000.00, on average annually, and include repairing or replacing automatic heads, tamper switches, water flow switches, pressure switches drain valves, check valves, alarm lines, drain lines, main drains and repacking of control valves, as well as any additional work identified during inspection/testing (as approved by the COR).
All minor repairs shall be performed In Accordance With (IAW) standard industry practices, equipment manufacturer’s recommendations, and applicable standards (National Fire Protection Association, National Electric Code, Standard Plumbing Code, etc.) It is noted that minor repairs shall include both services that require labor only and services that require both labor and parts. Any repairs must be approved by the COR before the commencement of any work.
2.2.2.1. Identification. Upon identifying a need for a repair, the contractor shall notify the COR of the repair requirement.
2.2.2.1.1. Notification. The contractor shall notify the Point of Contact (POC) via email, phone or text by 7:00AM EST, anytime the contractor will not be on-site by 7:30 AM EST so that all appropriate government personnel may be notified, In the of the unavailability of the contractor’s normally designated on-site personnel, the contractor shall be responsible for providing substitute personnel who are of the same training and qualifications; and are familiar with the performance of the contract requirements so that no disruption to government services are evident.
2.2.2.2. Approval Process. The COR will review the requirement and determine if the repair constitutes a minor repair/maintenance within the scope of this effort. Upon determining that a requirement is within scope, the COR will direct the contractor to submit a quote for the repair. Following the approval from the COR, the contractor shall proceed with the work to be completed. Upon completion, the COR will verify that the repair/maintenance has been completed as agreed upon and approved.
2.2.2.3. Invoicing. Upon completion of the minor repair/maintenance, the contractor shall submit an invoice through Wide Area Workflow (WAWF). The COR, upon determining that the effort has been satisfactorily been complete, will accept the invoice in WAWF, which will authorize payment.
2.2.2.4 Sprinkler Systems Requiring Minor Repair / Maintenance.
2.2.2.4.1 Sprinkler systems shall be installed per UFC 3-600-01 Fire Protection Engineering for Facilities. New sprinkler valve housings and support piping shall be a Viking system (by Viking Corporation) or approved equivalent. Water piping other than Schedule 40 must be approved by the Engineering Branch, Directorate of Installation Services, Tobyhanna Army Depot, for a certain application.
2.2.2.4.2 Any system that is to be dropped from the main system shall have low point drains.
2.2.2.4.3 Installed or renovated sprinkler piping shall be painted red.
2.2.2.4.4 All devices shall be labeled with their respective device address or circuit number on the exterior of each device for fire department identification.
2.2.2.4.5 Maintain fire and/or smoke ratings of all separations (i.e. fire-rated walls, partitions, shafts, and floors). Any penetrations must be fire stopped by an approved or listed method in accordance with ASTM E814 or UL 1479.
2.3 Fire Alarm Panels. Disabling and the restoration of fire alarm control panels shall be the responsibility of the contractor prior to the inspection of each system(s). The contractor shall notify the communications center before disabling and after restoring alarm control panels. The panel must be clear showing no trouble supervisory or alarm conditions upon completion of the test and/or work.
If an issue with the panel(s) should arise the contractor may notify the communication center and Contracting Officer Representative (COR) for assistance.
2.4 Stationary Fire Pumps. Stationary Fire Pumps shall be included in the inspections and shall be exercised weekly during the period of performance.
2.5 Reporting. Reports shall be submitted for the inspections/testing performed in the previous month. These reports shall be submitted in the approved format to the COR no later than the fifth workday of the next month.
2.6 TYAD Water Based Fire Protection Systems.
2.6.1 Risers. Each system is supplied by one riser.
2.6.2 Fire Pumps. Stationary fire pumps shall be included in the inspections. Reference “Attachment – Systems by Building” for a listing of the systems by building and type (Dry/Wet).
2.6.3 Sprinkler System. NFPA 25 - 3.6.4: A system that consists of an integrated network of piping designed in accordance with fire protection engineering standards that includes a water supply source, a water control valve, a water flow alarm and a drain. The portion of the sprinkler system above ground is a network of specifically sized or hydraulically designed piping installed in a building, structure, or area, generally overhead and to which sprinklers are attached in a systematic pattern. The system is commonly activated by heat from a fire and discharges water over the fire area.
2.7 Quality Assurance.
2.7.1 Performance Requirements Summary/Quality Assurance Surveillance Plan (QASP):
2.7.2 Methods of Surveillance. Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP.
2.7.2.1 100% inspection. This includes reviewing inspection reports and on-site visits.
2.7.2.2 Customer feedback.
2.7.3 Ratings. Metrics and methods are designed to determine if performance exceeds, meets, or does not meet a given standard and acceptable quality level. A rating scale shall be used to determine a positive, neutral, or negative outcome. The following ratings shall be used: Acceptable / Unacceptable
2.7.4 Documenting Performance. The following are the documented ratings that will be used to ensure contract compliance:
2.7.4.1 Acceptable Performance. The Government shall document positive performance. Any report may become a part of the supporting documentation for any contractual action.
2.7.4.2 Unacceptable Performance. When unacceptable performance occurs, the COR shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the COR shall document the discussion and place it in the COR file.
2.7.4.3 Corrective action. When the COR determines formal written communication is required, the COR shall prepare a Contract Discrepancy Report (CDR), and present it to the contractor's program manager. The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will also state how long after receipt the contractor has to present this corrective action plan to the COR. The Government shall review the contractor's corrective action plan to determine acceptability. Any CDRs may become a part of the supporting documentation for any contractual action deemed necessary by the Contracting Officer.
3.0 Contractor Responsibilities and Qualifications.
3.1 Management. The personnel rendering the services are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees (Reference FAR 37.101). The contractor shall provide all management, quality control, labor, supervision, parts, materials, tools, equipment, supplies, transportation and other services necessary for the inspection, testing, maintenance and minor repairs on the water based fire protection systems at TYAD. The contractor shall, without additional expense to the government, be responsible for obtaining any and all necessary licenses and permits and shall comply with any applicable safety and health requirements by Federal, State and Local laws, codes or ordinances in connection with performance of this contract.
3.2 Schedule. The schedule as agreed upon in the contractor’s proposal shall serve as the standard for completing the effort outlined in this PWS.
3.3 Contractor Qualifications. The contractor shall demonstrate that they have the experience and expertise to perform the required tasks as outlined and implied in this PWS.
3.4 Personnel. The contractor’s technicians shall be trained and experienced with the (NFPA), Unified Facilities Codes (UFC) standards and American Society of Safety Engineers (ASSE) certified regarding, inspection, testing and maintenance of water based fire protection systems. Contractors must acknowledge on company letterhead that the personnel assigned to this effort have been trained and are experienced. Where appropriate, employees must possess and provide the appropriate National Institute for Certification in Engineering Technology (NICET). Comment by Boylan, Michael J CIV (US): Training Requirements
3.4.1. General. ITM tasks shall be performed by crafts-persons trained or qualified in the maintenance and repair of the specific fire protection system or subsystem.
3.4.2. Qualifications. “Trained or qualified” personnel shall perform ITM and repair tasks only on the systems for which these personnel have been specifically qualified. Trained or qualified personnel may supervise other less qualified personnel in the execution of the tasks covered in this UFC. At no time shall apprentice-level crafts-persons be allowed to execute the ITM tasks in this UFC without a qualified supervisor on site. Trained or qualified personnel shall perform ITM and repair tasks only within the scope of their specific qualification. Generally accepted qualifications include:
3.4.2.1. Crafts-persons with other recognized journeyman or craftsman-level qualifications for fire protection systems, such as National Institute for Certification in Engineering Technologies (NICET) (Level III certification in Fire Alarm Systems, Inspection and Testing of Water-Based Systems, or Special Hazard Suppression Systems), or formalized labor organization-based journeyman training, or similar programs. Comment by Boylan, Michael J CIV (US): Training requirements
3.4.2.2 Crafts-persons holding a valid, current qualification or license from any state (or local jurisdiction if delegated authority by the state). Local jurisdictions and other organizations may require varying levels of continuing education to maintain recognized journeyman or craftsman-level qualifications.
3.4.2.3. Installation or base operating support (BOS) contractor personnel must meet the state (in which the installation is located) (or local, if delegated authority by the state) qualification and licensing requirements. Where some form of licensing, certification, or approval is required, it shall be current in accordance with the state or local requirements, as applicable. All ITM and repair tasks will be accomplished under the supervision of a licensed craftsperson.
3.4.2.4. Other contractors performing ITM and repair tasks must meet the state (in which the installation is located, or local, if delegated authority by the state) qualification and licensing requirements. Where some form of licensing, certification, or approval is required, it shall be current in accordance with the state or local requirements, as applicable. The contractor must have at least one licensed supervisory employee present on the installation when contractor personnel are executing ITM and repair tasks.
3.4.2.5. General or equipment-specific qualification/endorsement provided by an equipment manufacturer for the manufacturer’s equipment.
3.4.3. Labor Standards. FAR 37.107 and 41 USC Chapter 67, Service Contract Labor Standards, provides for minimum wages and fringe benefits as well as other conditions of work under certain types of service contracts. Service Contract Labor Standards are applicable to this acquisition. Prevailing wage rates may be referenced at the following link: https://wdol.gov , Wage Determination 15-5797 (dated 01/16/2018) or the latest version, whichever is most recent.
3.4.4. In processing. Prior to the commencement of performance under the contract and within seven (7) workdays of contract award, the Contractor shall submit through the COR to the Chief, Security Division, TYAD, a roster of all Contractor personnel, inclusive of on-site supervisory or managerial personnel and sub-contractor personnel, that the Contractor anticipates will be performing work on-site.
3.4.4.1. Roster. The roster shall indicate which individuals are U.S. citizens and which are resident aliens (immigrants). Due to limited availability of Government personnel, Contractors shall not be permitted to employ non-resident/non-immigrant aliens as part of the Contractor’s on-site workforce. The COR will forward an ELTY Form 648-C, “Request for Access to Tobyhanna Army Depot”, to be completed by each contractor employee seeking to gain access. Upon completing the forms, the contractor shall return them to the COR for processing and obtaining access to TYAD.
3.4.4.2 Non Resident/Non Immigrant Personnel. All non-resident/non-immigrant aliens must have approval prior to being permitted access to TYAD. Such approval must be obtained by requesting access through the following: apply at the alien-resident’s embassy; proceed to the U.S. Embassy; proceed to the Department of the Army; proceed to Army Materiel Command; proceed to U.S. Communications-Electronics Command (CECOM); proceed to TYAD. All non-resident/non-immigrant aliens granted access to TYAD or assigned duty location are required to be escorted by Government personnel. One Government escort can accommodate a maximum of two non-resident/non-immigrant aliens. Due to limited availability of Government personnel, visitors requiring escort may not be permitted access, or access may be limited to a certain time and duration. The following documentation shall accompany the roster for each individual named on the roster as a resident alien (immigrant): a) a copy of a verifiable form of identification, such as a driver’s license or a passport; and b) a copy of a valid Department of Justice Immigration and Naturalization Service Form I-551, Alien Registration Receipt Card (“Green Card”). Contractors who fail to identify any and all resident aliens (immigrants) who will be used for onsite performance and who will seek access to TYAD or assigned duty location as a worker for or through the Contractor, inclusive of managerial and subcontractor personnel, may be subject to civil and criminal penalties and sanctions as well as contract remedies.
3.4.4.3. ELTY 648-C Processing. After the ELTY Form 648-C and required documentation have been processed (usually five days), the Government will notify the contractor of the personnel permitted to work on-site. However, actual access to TYAD will remain contingent upon being cleared. Resident alien (immigrant) individuals must present two (2) forms of identification in order to process into the Depot through the Security building: a valid Form I-551, Alien Registration Receipt Card (“Green Card”) in addition to at least one other verifiable form of identification.
3.4.4.4. Planning. It is understood that there is a strong likelihood that personnel changes may be necessitated. As a result, it is recommended that the contractor include access requests for those who may require access as a contingency or “backup” in order to avoid a processing delay and negative impact performance. Security screening shall be completed on all contractor and all subcontractor personnel requesting access TYAD. No contractor personnel will be granted access to the worksite until security screening is completed and access approved. Personnel who the fail the screening will not be permitted further access to TYAD. Badges will not be issued to personnel unless they have been adequately vetted through the security screening process.
3.4.4.5. Accessibility Issues. Contractors whose personnel are denied entry to TYAD or assigned duty location due to the security requirements are not relieved of their obligation to provide the required contract performance and must do so at no additional cost to the Government. Any Contractor failing to perform or that fails to perform in a timely manner under such circumstances may be terminated for default or be subject to other contractual remedies as appropriate.
3.4.4.6 Secure Areas. If work requirements dictate that contractor personnel require access to secured locations/buildings, it is the responsibility of the contractor to coordinate with the POC to obtain the escort(s) required and any associated elevated security clearances.
3.4.4.7. Hours of Operation. All contractor services shall be performed between the hours of 7:00 AM and 4:30 PM Monday through Friday, excluding federal holidays and hard closures. The Tobyhanna Army Depot operates on both an alternate and regular work schedule. Reference “Attachment 2 – TYAD Operating Schedule” for a TYAD Calendar identifying the days of operation and hard closures. Questions concerning depot access and
UFC 3-601-02
2-2.8 Fire Pumps.
Technical guidance on these tasks is contained in NFPA 20, Standard for the Installation of Stationary Pumps for Fire Protection, and NFPA 25. When generators are installed specifically to meet fire protection requirements, or generators are used to provide standby power for fire pumps, conduct all the requirements related to the engine drives on the generator engines. These requirements must not supersede requirements for generators serving demands other than fire protection. Generators serving both fire protection and other demands must conform to the most stringent guidance.
WARNING
Fire pump systems with redundant pumps must have all pumps and pump drivers in-service to meet redundancy requirements. Redundant pumps are not spare or stand-by pumps. Redundant pumps ensure the minimum number pumps will start if any minimum required pump fails to start. A redundant pump out-of-service means the pumping capacity is degraded- /impaired and any supported fire protection features downstream are also degraded/impaired. Two or more pumps out-of-service where redundancy means the pumping system is out-of-service as is all the supported fire protection features downstream. (Table 2-7, Tasks - Monthly 6.1)
7 October 2021
Fire pump stations without redundant pumps must have all pumps and pump drivers in-service. A pump or pump driver out-of-service means the pumping capacity is out-of-service and any supported fire protection features downstream is out-of-service. (Table 2-7, Tasks - Monthly 6.1)
Table 2-7 Fire Pumps ITM Tasks Comment by Boylan, Michael J CIV (US): I believe all the different systems ITM tasks are numbered correctly.
| Frequency |
| Component |
| Tasks |
| Monthly |
| 1. Pump House |
| 1. Inspect for proper condition, ventilation, and heating. |
2. Check packing leakage for proper water lubrication.
3. Verify proper drainage.
| 2. Control Valves and Isolation Valves (without seals, locks, or electric supervision) |
| 1. Verify proper valve position. |
| 3. Pressure Gauges |
| 1. Check reading and verify gauge operability. |
| 4. Controllers |
| 1. Verify that automatic controllers are in the automatic (AUTO) setting. |
2. Inspect electric connections.
3. Operate manual and automatic starting methods.
4. Resolve all trouble indications.
| 5. Batteries |
| 1. Verify proper charge. (Replace batteries in accordance with the driver manufacturer’s recommendations or when the full recharged battery voltage or current falls below either the driver or battery’s manufacturer’s recommendations.) |
| 6. Pumps |
| 1. Start and churn to verify operability. (Where equipment permits, allow water to flow back to the source.) [Operate electric pumps for 10 minutes and operate engine- driven pumps for 30 minutes.] |
2. Verify operation of relief valves.
3. Verify fuel level (for engine-driven pumps).
4. Inspect exhaust system for leaks (for engine-driven pumps).
5. For engine driven pumps, start again using second battery set and churn to verify operability. (Where equipment permits, allow water to flow back to the source.)
FC 3-601-02
| Frequency |
| Component |
| Tasks |
| Annually |
| 1. Control Valves (sealed, locked, and electrically supervised) |
| 1. Verify proper valve position. |
| Semi-Annually |
| 1. Fuel (engine-driven pumps) |
| 1. Sample fuel to verify quality. |
| 2 Years |
| 1. Control Valves |
| 1. Operate valve through entire travel to verify function. |
2. Lubricate valves to ensure operability.
3. Verify that valve supervisory switches detect a change in valve position.
| 2. Controllers |
| 1. Calibrate pressure switches. |
2. Exercise circuit breakers and switches to verify operability.
3. Inspect fuses.
| 3. Pumps |
| 1. Check coupling alignment to ensure that the shaft is aligned. |
2. Check pump shaft end play.
3. Lubricate bearings.
4. Lubricate couplings.
5. Lubricate right-angle drives.
| 4. Relief Valves |
| 1. Calibrate valves. |
| 5. Emergency Power Supply |
| 1. Test to verify availability and capacity for pump motor. |
| 5 Years |
| 1. Pump |
| 1. Conduct flow test to verify pump output. Test may be through a flow meter returning the water to a storage reservoir or through the test header. Recirculation of water to the suction piping is not permitted. In a multi-pump installation, each pump may be tested separately at not less than 100 percent design capacity for 30 minutes. |
2. Verify that the results are within acceptable limits or identify corrective measures.
| 2. Gauges and Flow Meters |
| 1. Calibrate or replace flow meter prior to fire pump flow test. |
2-2.11 Wet Pipe Automatic Sprinkler Systems
Technical guidance on the tasks is contained in NFPA 25. Residential sprinkler systems are addressed in Chapter 3.
UFC 3-601-02
7 October 2021
Main drain static or residual test pressures that have decreased more than 20 percent from the original acceptance readings or the previous test readings indicate a potential emergency situation. In this case, immediate distribution system flow testing is indicated. Immediately conduct main drain tests on all adjacent sprinkler systems to determine the extent to which the sprinkler systems are compromised. (Table 2-10, Task - Annual 4.3)
CAUTION
Main drain static or residual test pressures that have decreased more than 10 percent from the previous test readings require immediate evaluation to determine the cause. (Table 2-10, Task - Annual 4.3)
Table 2-10 Wet Pipe Sprinkler Systems ITM Tasks
| Frequency |
| Component |
| Tasks |
| Monthly |
| 1. Control Valves (without seal, lock, or electric supervision) |
| 1. Verify proper valve position. |
| Annually |
| 1. Control Valves (sealed, locked, or electrically supervised) |
| 1. Verify proper valve position. |
| 2. Water Flow Alarm Devices |
| 1. Verify initiation and receipt of alarm (alternate use of alarm test line and inspectors test connection annually). |
2. Verify operation of exterior water flow alarm (if present).
3. Verify alarm test valve alignment and tamper switch (if sealed or electrically supervised).
| 3. Alarm Valve and Trim |
| 1. Visually check the exterior of valves, gauges, trim alignment. |
2. Verify valve pressure and legibility of the hydraulic nameplate.
| Frequency |
| Component |
| Tasks |
| 4. Main Drain |
| 1. Conduct a main drain test to verify supply (valve position). |
2. Document static and residual pressure readings on a 3-inch by 5-inch tag and secure it to the system pressure gauge.
3. Compare results with results from previous main drain tests and original acceptance test.
4. Verify that the results are within acceptable limits or identify corrective measures.
| 5. Fire Department Connection |
| 1. Verify accessibility and condition. |
2. If caps are removed or missing, check for obstructions.
3. Verify system check valve is not leaking.
4. Verify Gaskets are present.
5. Lubricate if swivels do not rotate smoothly.
6. Verify proper operation of ball drip drain prior to the cold season.
| 2 Years |
| 1. Control Valves |
| 1. Operate valve through entire travel to verify function. |
2. Lubricate valves and stems to ensure operability.
3. Verify that valve supervisory switches detect a change in valve position.
| 5 Years |
| 1. Alarm Valve |
| 1. Clean and inspect internally to verify condition. |
| 2. Anti-freeze Loops |
| 1. Determine solution type. If solution type is no longer permitted or cannot be positively identified, drain system completely and replace with an acceptable solution. |
2. Confirm correct solution mixture.
| 3. Strainers |
| 1. Inspect internally and clean to good condition. |
| 4. Automatic Air Release Valve |
| 1. Confirm proper operation. |
| 10 Years |
| 1. Gauges |
| 1. Calibrate or replace gauges. |
| 2. Dry Barrel Sprinklers |
| 1. Replace all sprinklers.1 |
| 20 Years |
| 1. Fast Response Sprinklers and Extra High Temperature Sprinklers |
| 1. Replace all.1 |
| Frequency |
| Component |
| Tasks |
50 Years, and Every 20 Years Thereafter
| 1. Standard Sprinklers |
| 1. Replace all sprinklers or test a sample of sprinklers to verify response characteristics.1 |
| Following System Modification or Repair |
| 1. Main Drain (following maintenance or repair action requiring the water supply to be shut off) |
| 1. Conduct main drain test to verify supply (valve position). |
2. Compare results with results from previous main drain tests and original acceptance test.
3. Verify that the results are within acceptable limits or identify corrective measures.
4. Document static and residual pressure readings on a 3-inch by 5-inch tag and secure it to the system pressure gauge.
| As Part of Other Building Inspection (not part of the ITM requirements) |
| 1. Entire System |
| 1. Visually check: |
a. Pipe hangers and seismic bracing.
b. Sprinklers for obstruction.
c. Piping for leaks.
d. Riser condition.
e. Verify sprinkler spares.
Note: A representative sample of sprinklers for testing must consist of one (1) percent of the sprinklers installed of the same type, with a minimum of four (4) sprinklers sampled. Submit sprinklers to a recognized testing laboratory (NRTL) for these tests.
2-2.12 Dry Pipe Automatic Sprinkler Systems.
Technical guidance for these tasks is contained in NFPA 25.
Main drain static or residual test pressures that have decreased more than 20 percent from the original acceptance readings or the previous test readings indicate a potential emergency situation. In this case, immediate distribution system flow testing is indicated. Immediately conduct main drain tests on all adjacent sprinkler systems to determine the extent to which the sprinkler systems are compromised. (Table 2-11, Task - Annual 4.3)
Main drain static or residual test pressures that have decreased more than 10 percent from the previous test readings require immediate evaluation to determine the cause. (Table 2-11, Task - Annual 4.3)
Table 2-11 Dry Pipe Automatic Sprinkler Systems ITM Tasks
| Frequency |
| Component |
| Tasks |
| Monthly |
| 1. Control Valves (without seal, lock, or electric supervision) |
| 1. Verify proper valve position. |
| Before the Onset of Freezing Weather |
| 1. Low Point Drains |
| 1. Drain all low points to remove condensation prior to the cold season. |
| 2. Dry Pipe Alarm Valve Enclosure Heating |
| 1. Verify operability at the beginning of the heating season (annually for constant cold areas). |
| 3. Low Temperature Alarm |
| 1. Verify initiation and receipt of alarm at the beginning of the heating season. |
| Annually |
| 1. Control Valves (sealed, locked, or electrically supervised) |
| 1. Verify proper valve position. |
| 2. Water Flow Alarm Devices |
| 1. Operate alarm test valve to verify initiation and receipt of alarm. |
2. Verify alarm test valve alignment and tamper switch (if sealed or electrically supervised).
| 3. Dry Pipe Alarm Valve and Trim |
| 1. Visually inspect the exterior of valves, gauges, trim alignment. |
3. Verify valve position of provided quick opening devices are in the normal position.
| 4. Main Drain |
| 1. Conduct main drain test to verify supply (valve position). |
2. Document static and residual pressure readings on a 3-inch by 5- inch tag and secure it to the system pressure gauge.
| Frequency |
| Component |
| Tasks |
| 5. Fire Department Connection |
| 1. Verify accessibility and condition. |
2. If caps are removed or missing, check for obstructions.
3. Verify system check valve is not leaking.
4. Verify gaskets are present.
5. Lubricate if swivels do not rotate smoothly.
6. Verify proper operation of ball drip drain prior to the cold season.
| 6. Low Point Drains |
| 1. Drain all low points to remove condensation prior to the cold season. |
| 2 Years |
| 1. Control Valves |
| 1. Operate valve through entire travel to verify function. |
2. Lubricate valves and stems to ensure operability.
| 2. Dry Pipe Alarm Valves |
| 1. Trip valve to verify operability. |
2. Inspect internal condition before resetting, and clean valve seat.
3. Check priming water level (before and after trip test).
| 3. Quick-Opening Devices |
| 1. Test to verify operability. |
| 4. Low/High Air Pressure Alarms |
| 1. Test to verify initiation and receipt of supervisory alarms. |
| 5. Automatic Air Pressure Maintenance Devices |
| 1. Inspect to verify proper operation. |
| 5 Years |
| 1. Strainers |
| 1. Inspect internally and clean to verify condition. |
| 10 Years |
| 1. Gauges |
| 1. Calibrate or replace gauges. |
| 10 Years |
| 1. Dry Barrel Sprinklers |
| 1. Replace all.1 |
| 20 Years |
| 1. Fast Response Sprinklers and Extra High Temperature Sprinklers |
| 1. Replace all sprinklers.1 |
50 Years, and Every 20 Years Thereafter
| 1. Standard Sprinkler |
| 1. Replace all sprinklers or test a sample of sprinklers to verify response characteristics.1 |
| Following System Modification or Repair |
| 1. Main Drain (following maintenance or repair action requiring the water supply to be shut off) |
| 1. Conduct main drain test to verify supply (valve position). |
| Frequency |
| Component |
| Tasks |
3. Compare results with results from previous main drain tests and original acceptance test.
5. Document static and residual pressure readings on a 3-inch x 5- inch tag and secure it to the system pressure gauge.
| As Part of Other Building Inspection (not part of the ITM requirements) |
| 1. Entire System |
| 1. Visually check: |
a. Pipe hangers and seismic bracing.
b. Sprinklers for obstruction.
c. Piping for leaks.
d. Riser condition.
e. Sprinkler spares.
Note: A representative sample of sprinklers for testing must consist of one (1) percent of the sprinklers installed of the same type, with a minimum of four (4) sprinklers sampled. The sprinklers must be submitted to a recognized testing laboratory (NRTL) for these tests.
2-2.13 Deluge Sprinkler Systems.
Detection devices for actuation are addressed in Section 2-2.2, “Fire Detection and Alarm Systems.” Technical guidance on these tasks is contained in NFPA 25 and NFPA 15, Standard for Water Spray Fixed Systems for Fire Protection.
WARNING
Main drain static or residual test pressures that have decreased more than 20 percent from the original acceptance readings or the previous test readings indicate a potential emergency situation. In this case, immediate distribution system flow testing is indicated. Immediately conduct main drain tests on all adjacent sprinkler systems to determine the extent to which the sprinkler systems are compromised. (Table 2-12, Task - Annual 4.3)
Main drain static or residual test pressures that have decreased more than 10 percent from the previous test readings require immediate evaluation to determine the cause. (Table 2-12, Task - Annual 4.3)
Table 2-12 Deluge Sprinkler Systems ITM Tasks
| Frequency |
| Component |
| Tasks |
| Monthly |
| 1. Control Valves (without seal, lock, or electric supervision) |
| 1. Verify proper valve position. |
| Before the Onset of Freezing Weather |
| 1. Valve and Riser Heated Enclosure (if provided) |
| 1. Verify operability at the beginning of the heating season. |
| 2. Low Temperature Alarm |
| 1. Verify initiation and receipt of alarm at the beginning of the heating season. |
| 3. Low Point Drains |
| 1. Drain all low points after deluge valve test and before cold weather. |
| Annually |
| 1. Control Valves (sealed, locked, or electrically supervised) |
| 1. Verify proper valve position. |
| 2. Water Flow Alarm Devices |
| 2. Operate alarm test valve to verify initiation and receipt of alarm. |
3. Verify alarm test valve alignment and tamper switch (if sealed or electrically supervised).
| 3. Deluge Alarm Valve and Trim |
| 1. Inspect the exterior of valves, gauges, trim alignment. |
| 4. Main Drain |
| 1. Conduct a main drain test to verify supply (valve position). |
2. Document static and residual pressure readings on a 3-inch by 5-inch tag and secure it to the system pressure gauge.
| 5. Fire Department Connection |
| 1. Verify accessibility and condition. |
2. If caps are removed or missing, check for obstructions.
3. Verify system check valve is not leaking.
4. Verify Gaskets are present.
5. Lubricate if swivels do not rotate smoothly.
6. Verify proper operation of ball drip drain prior to the cold season.
| Frequency |
| Component |
| Tasks |
| 2 Years |
| 1. Control Valves |
| 1. Operate valve through entire travel to verify function. |
| 2. Deluge Valve |
| 1. Trip to verify operability. |
2. Verify that manual actuators are operable.
3. Inspect the internal condition and clean valve seat before resetting.
| 3. Low Point Drains |
| 1. Drain all low points after each valve trip. |
| 5 Years |
| 1. Strainers |
| 1. Inspect internally and clean to verify condition. |
| 10 Years |
| 1. Gauges |
| 1. Calibrate or replace. |
| 2. Deluge Valve |
| 1. Conduct full flow test. |
| 1. Distribution System |
| 1. Verify nozzle (sprinkler) coverage during flow test. |
2. Inspect piping and nozzles for condition and location.
| Following System Modification or Repair |
| 1. Main Drain (following maintenance or repair action requiring the water supply to be shut off) |
| 1. Conduct main drain test to verify supply (valve position). |
2. Compare results with results from previous main drain tests and original acceptance test.
3. Verify that the results are within acceptable limits or identify corrective measures.
4. Document static and residual pressure readings on a 3-inch by 5-inch tag and secure it to the system pressure gauge.
| As Part of Other Building Inspection (not part of the ITM requirements) |
| 1. Entire System |
| 1. Visually check: |
a. Pipe hangers and seismic bracing.
b. Sprinklers/nozzles for obstruction.
c. Piping for leaks.
d. Riser condition.
e. Sprinkler spares.
2. Ensure:
a. Manual stations in place and unobstructed.
b. Detectors unblocked/uncovered.
c. Panels secured and indicator lamps functional.
d. Notification appliances in place.
2-2.14 Pre-Action Automatic Sprinkler Systems.
Detection devices for actuation are addressed in Section 2-2.2, “Fire Detection and Alarm Systems.” Technical guidance on these tasks is contained in NFPA 25.
WARNING
Main drain static or residual test pressures that have decreased more than 20 percent from the original acceptance readings or the previous test readings indicate a potential emergency situation. In this case, immediate distribution system flow testing is indicated. Immediately conduct main drain tests on all adjacent sprinkler systems to determine the extent to which the sprinkler systems are compromised. (Table 2-13, Task - Annual 4.3)
Main drain static or residual test pressures that have decreased more than 10 percent from the previous test readings require immediate evaluation to determine the cause. (Table 2-13, Task - Annual 4.3)
Table 2-13 Pre-Action Automatic Sprinkler Systems ITM Tasks
| Frequency |
| Component |
| Tasks |
| Monthly |
| 1. Control Valves (without seal, lock, or electric supervision) |
| 1. Verify proper valve position. |
| Before the Onset of Freezing Weather |
| 1. Valve and Riser Heated Enclosure (if provided) |
| 1. Verify operability at beginning of heating season. |
| 2. Low Temperature Alarm |
| 1. Verify initiation and receipt of alarm at the beginning of the heating season. |
| 3. Low Point Drains |
| 1. Drain all low points before cold weather (if unheated area). |
| Annually |
| 1. Control Valves (sealed, locked, or electrically supervised) |
| 1. Verify proper valve position. |
| 2. Water Flow Alarm Devices |
| 1. Operate alarm test valve to verify initiation and receipt of alarm. |
2. Verify alarm test valve alignment and tamper switch (if sealed or electrically supervised).
| 3. Pre-Action Valve and Trim |
| 1. Inspect the exterior of valves, gauges, trim alignment. |
| Frequency |
| Component |
| Tasks |
| 4. Main Drain |
| 1. Conduct a main drain test to verify supply (valve position). |
2. Document static and residual pressure readings on a 3-inch by 5- inch tag and secure it to the system pressure gauge.
| 5. Fire Department Connection |
| 1. Verify accessibility and condition. |
2. If caps are removed or missing, check for obstructions.
3. Verify system check valve is not leaking.
4. Verify gaskets are present.
5. Lubricate if swivels do not rotate smoothly.
6. Verify proper operation of ball drip drain prior to the cold season.
| 2 Years |
| 1. Control Valves |
| 1. Operate valve through entire travel to verify function. |
| 2. Pre-Action Valve |
| 1. Trip to verify proper operation. |
2. Verify function of manual actuators (if provided).
3. Inspect internal condition and clean valve seat before resetting.
| 3. Low Point Drains |
| 1. Drain all low points after pre-action valve trip test. |
| 4. Air Supply (if present) |
| 1. Test the automatic air pressure maintenance device. |
2. Test the low/high air supply alarms.
| 5 Years |
| 1. Strainers |
| 1. Clean and inspect the interior to verify condition. |
| 10 Years |
| 1. Gauges |
| 1. Calibrate or replace gauges. |
| Frequency |
| Component |
| Tasks |
10 Years, and Every 10 Years Thereafter
| 1. Dry Sprinklers |
| 1. Replace all sprinklers or test a sample of sprinklers to verify response characteristics.1 |
20 Years, and Every 10 Years Thereafter
| 1. Fast-Response Sprinklers and Extra High Temperature Sprinklers |
| 1. Replace all sprinklers or test a sample of sprinklers to verify response characteristics.1 |
50 Years, and Every 10 Years Thereafter
| 1. Standard Sprinklers |
| 1. Replace all sprinklers or test sample closed-head sprinklers to verify response characteristics.1 |
| Following System Modification or Repair |
| 1. Main Drain (following maintenance or repair action requiring the water supply to be shut off) |
| 1. Conduct main drain test to verify supply (valve position). |
2. Compare results with results from previous main drain tests and original acceptance test.
3. Verify that the results are within acceptable limits or identify corrective measures.
4. Document static and residual pressure readings on a 3-inch by 5- inch tag and secure it to the system pressure gauge.
| As Part of Other Building Inspection (not part of the ITM requirements) |
| 1. Entire System |
| 1. Visually check: |
a. Pipe hangers and seismic bracing.
b. Sprinklers for obstruction.
c. Piping for leaks.
d. Riser condition.
e. Sprinkler spares.
2. Ensure:
a. Manual stations in place and unobstructed.
b. Detectors unblocked/uncovered.
c. Panels secured and indicator lamps functional.
d. Notification appliances in place.
Note: A representative sample of sprinklers for testing must consist of one (1) percent of the sprinklers installed of the same type, with a minimum of four (4) sprinklers sampled. The sprinklers must be submitted to a recognized testing laboratory (NRTL) for these tests.
4.0 TYAD SECURITY REQUIREMENTS Comment by Boylan, Michael J CIV (US): ATOPSEC Security Requirements, actually in the pre-requirements portion of the PCF files. Along with the additional specs needed for this contract including safety and security.
All TYAD contracts and other acquisition-related documents must ensure privacy and security controls follow the information, and that contractors and service providers protect Privacy Act information in the same way the organization adhering to the Federal Acquisition Regulations (FAR) Privacy Act provisions (Subparts 24.1 and 24.2) and include the specified contract clauses (Parts 52.224-1 and 52.224-2), as appropriate, to ensure that personal information is protected as mandated.
In addition to the changes authorized by the clause of this contract; should Force Protection Condition (FPCON) at the installation change, the Government may require changes in contractor security matters and/or processes.
FPCON impact on work levels. (Please annotate with an X which may apply):
_X____ During FPCONs Charlie and Delta, [XXX] services are discontinued. [XXX] services will resume when the FPCON level is reduced to level Bravo or lower.
_____This contract and its employees are considered mission essential. Therefore, all contractor employees are required to report for duty and remain on duty during declared emergencies and/or elevated FPCON levels unless otherwise directed by the contacting officer via the appropriate COR.
(If Required) The contractor shall provide support during contingencies, exercises, heightened operations, and adverse weather or security closures in the accomplishment of performance requirements. From time to time, the Base Commander may decide to close all or part of a base in response to an unforeseen emergency or similar occurrence. Such emergencies include adverse weather such as snow, or ice, "an act of God such as tornado or earthquake, or a base disaster such as a gas leak or fire.
Base closure announcements will normally be disseminated by local television and radio station.
Contingency Operations Plan The Contractor shall prepare and submit a Contingency Operations Plan to the Government. The Contingency Operations Plan shall document Contractor plans and procedures to maintain support during an emergency. The Contingency Operations Plan shall include the following:
· A description of the Contractor’s emergency management procedures and policy
· A description of how the Contractor will account for their employees during an emergency
· Planned temporary work locations or alternate facilities
· How the Contractor will communicate with Government during emergencies
· A list of primary and alternate Contractor POCs, each with primary and alternate telephone numbers
· Procedures for protecting Government Furnished Equipment (GFE)/Government furnished property (if any)
· Procedures for safeguarding sensitive and/or classified Government information (if applicable) Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.
Antiterrorism (AT) Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training prior to contract report date. This training is required for any additional or new contractor employees, who start after that period. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR/POC within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html for their training. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record, or contractor equivalent. As applicable, contractor employees must complete annual AT awareness training as it pertains the length of the contract.
iWATCH Army Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH Army Program. This will consist of utilizing the tools and media products on the informational iWATCH Army website to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR/POC. The iWATCH training is available at the following website: https://myarmyonesource.com select Family Programs and Services, in the drop down boxes select: Go To, iWATCH Army –“See Something, Say Something”. The contractor shall notify the COR/POC within 10 calendar days of review of the information on the website for any new employees or subcontractor personnel to assure the ELTY form 583 or contractor equivalent is properly documented. Completion of contractor employee training will be documented on ELTY form 583, TYAD On-Post Training Record or contractor equivalent.
Access and General Protection/Security Policy and Procedures. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by TYAD Law Enforcement. Contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by the government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
A background check and approval from Tobyhanna Army Depot (TYAD) Law Enforcement is required for all contractor and subcontractor personnel prior to on-site access at TYAD.