This document provides construction specifications for remodeling public restrooms at the Kelso Depot in Mojave National Preserve. The project involves interior renovation of existing men's, women's, and all-gender restrooms as well as electrical and janitor closets. Exterior work includes replacing light fixtures, installing wall-mounted drinking fountains, and a new water shut-off valve. Specifications cover demolition, new finishes, plumbing fixtures, lighting, signage, and other aspects of the restroom remodel. Electrical, mechanical, and accessibility requirements are also included. The National Park Service Pacific West Region is the contracting agency for this project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOJAVE NATIONAL PRESERVE
KELSO DEPOT COMFORT STATION
REHABILITATION
PMIS NO. 309905, 328288
100% CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE
APRIL 2023
MOJA – 309905, 328288 TABLE OF CONTENTS - 1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 33 23 Submittal Procedures
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 50 00 Temporary Facilities and Controls
01 73 29 Cutting and Patching
01 73 40 Execution
01 77 00 Closeout Procedures
DIVISION 02 - EXISTING CONDITIONS
02 41 19 Selective Demolition
DIVISIONS 03 - 05
Not used
DIVISION 06 - WOOD, PLASTIC AND COMPOSITES
06 20 00 Finish Carpentry
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
08 31 13 Access Doors and Panels
08 71 00 Door Hardware
08 74 13 Low Energy Door Operators
DIVISION 09 - FINISHES
09 22 16 Non-Structural Metal Framing
09 29 00 Gypsum Board
09 65 10 Resilient Base
09 77 30 Fiberglass Wall Panels
09 91 00 Painting
MOJA – 309905, 328288 TABLE OF CONTENTS - 2
DIVISION 10 - SPECIALTIES
10 14 00 Signage
10 21 13 Toilet Compartments
10 28 13 Toilet Accessories
DIVISIONS 11 - 21
DIVISION 22 - PLUMBING
22 00 00 Plumbing Basic Requirements
22 05 19 Plumbing Devices
22 05 23 Valves
22 05 53 Identification for Plumbing Piping and Equipment
22 05 93 Tests and Balancing
22 10 00 Plumbing Piping
22 40 00 Plumbing Fixtures
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
DIVISION 26 - ELECTRICAL
26 00 00 Electrical Basic Requirements
26 05 00 Common Work Results for Electrical
26 51 00 Lighting
APPENDIX
Site Location Map
Kelso Depot Rehabilitation Selected As-Built Drawings dated May 2004
END OF TABLE OF CONTENTS
MOJA – 309905, 328288 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Kelso, CA is located within Mojave National Preserve in San Bernadino
County. Maps and park information may be viewed at www.nps.gov/moja
B. The Work consists of: Interior renovation of the existing men’s restroom, women’s restroom, all gender restroom, janitor closet, and electrical closet inside the existing comfort station next to
Kelso Depot. The project includes new finishes, light fixtures, plumbing fixtures, and painting.
Exterior work includes light fixture replacement, installation of new wall-mounted drinking fountains, and new water shut-off valve.
C. Project will be constructed under a single prime contract.
1.2 REFERENCE DOCUMENTS AND REPORTS
A. General: The following reference documents and reports are attached or available upon request to supplement the information in the specifications:
1. NPS Forms (RFI, CM-16, and QC Daily Report)
2. Site Location Map with Project Area Limits, Preferred Access, Approved Staging and
Storage Area, and Sensitive Avoidance Areas
1.3 CODES, STANDARDS, & REGULATIONS
A. General: The Contractor shall complete all work in accordance with the latest versions of applicable codes, standards, and regulations.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to the project area limits as indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Storage of Materials: Storage of construction materials is allowed on-site, at a location designated by the Contracting Officer’s Representative. Storage of hazardous materials must meet all federal, state, and local guidelines and regulations. On-site storage of the Contractor’s materials does not imply acceptance or protection of materials by the Government.
C. Parking: Confine parking to designated areas as established at the preconstruction meeting.
MOJA – 309905, 328288 01 11 00 - 2
D. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Construction Camp: Establishment of a camp within park will not be permitted.
G. Hauling Restrictions: Comply with legal load restrictions in hauling of materials.
H. Other Contracts, Work, and Events: During the contract performance period, there may be other contracts, work, or events occurring in the park or within the project area limits that may affect the Contractor’s operations. The Contractor shall conduct his operations in consideration of these other activities. If the other activities are affecting the critical path of the construction schedule, the Contractor shall document the issue in the daily reports and report the issue to the Contracting
Officer. The following contracts, work, or events are known to be occurring during the contract performance period:
1. Kelso Depot HVAC and Water Heating System Replacement
I. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
1.5 PUBLIC USE OF SITE
A. The building will be closed to the public during construction.
B. Contractor shall conduct his operations to ensure the least inconvenience to public.
1.6 CONDUCT OF OPERATIONS
A. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
MOJA – 309905, 328288 01 11 00 - 3
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during daylight hours from 7 a.m. to 4 p.m., Monday through Sunday, excluding government holidays. Work outside regular hours requires advance approval from the Contracting Officer.
B. Existing Utilities: Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within
25 feet of any buildings in the park, including existing buildings and buildings under construction or renovation.
1.8 ADDITIONAL DOCUMENTATION
A. Kelso Depot Rehabilitation As-Built Drawings dated May 2004 are included as an appendix with this package.
END OF SECTION 01 11 00
MOJA – 309905, 328288 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 31 00 Project Management and Coordination, for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
MOJA – 309905, 328288 01 26 01 - 2
CONTRACT MODIFICATION PROCEDURES
C. Materials:
1. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment" in proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
END OF SECTION 012601
MOJA – 309905, 328288 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 0001:
1. This item consists of:
a. Replacement of existing interior gypsum board on walls and ceilings.
b. Replacement of existing metal wall and ceiling framing only as needed. (Existing framing to remain in place if in reusable condition.)
c. New interior finishes including FRP panels and rubber base
d. Replacement of existing wall access panels
e. Replacement of existing interior plumbing fixtures including water closets, urinals, flush valves, lavatories, faucets, and associated carriers and piping as required
f. Replacement of existing toilet partitions and urinal screens
g. Replacement of existing toilet accessories including grab bars, soap dispensers, mirrors, seat cover dispensers, sanitary napkin disposals, coat hooks on toilet partitions
h. Demolition associated with above items
2. Measurement for payment will be percent complete.
3. Payment will be made at the contract lump sum price.
MOJA – 309905, 328288 01 27 00 - 2
DEFINITION OF CONTRACT LINE ITEMS
B. Contract Line Item Number 0002:
1. This item consists of:
a. New actuators at exterior doors and associated electrical work
b. Replacement of all door hardware
c. Repainting existing doors (interior and exterior), door frames (interior and exterior), exposed wood trusses (interior), and exposed underside of roof sheathing (interior)
d. Painting interior CMU walls
e. Replacement of existing janitor mop sink and mop sink faucet
f. Replacement of exterior drinking fountains and filters
g. New building exterior shut-off valve and valve box
h. Replacement of existing electric hand dryers
i. Replacement of existing interior and exterior building lighting, lighting controls, and sensors
j. Replacement of existing toilet accessories including toilet paper dispensers, paper towel/trash receptacle, and baby changing stations
k. Replacement of accessibility signage
l. Demolition associated with above items
2. Measurement for payment will be percent complete.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
MOJA – 309905, 328288 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
1.2 SUBMITTALS
A. Division 1 documents: The following items shall be submitted a minimum of one week prior to
Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre-
Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule:
a. The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the
Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments.
b. Submit a baseline schedule with start date, end date, submission dates, major work activities and durations, estimated pre-final (substantially complete) and final
MOJA – 309905, 328288 01 31 00 - 2
(entirely complete) inspection dates, and other major milestones. Provide updates to baseline schedule as needed or as requested (when there is a change to the critical path).
c. Show sequence and interdependence of activities required for completion of work.
Ensure work sequences are logical and Construction Schedule shows a coordinated plan of the work. Identify critical path activities.
d. Consider seasonal weather conditions in planning and scheduling work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of work within contract time.
3. Schedule of Values: Submit a schedule of values with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan: Submit a construction waste management plan that addresses storage, handling, and disposal of all trash, recyclables, non-hazardous construction waste, and hazardous waste generated from the execution of the work.
9. Quality Control Plan
10. Under-An-Acre Pollution Prevention Plan (UPPP): For projects with ground disturbance estimated to be less than 1-acre, complete and submit an UPPP to the NPS with best management practices (BMP’s) to prevent the discharges of pollutants. BMP’s shall be checked daily and after storm events to ensure they are performing as intended.
11. Indoor Air Quality (IAQ) Management Plan: Complete and submit an indoor air quality management plan that addresses control of dust and airborne particulates, emissions from motorized equipment, fumes or vapors from products, moisture and humidity, and ventilation.
B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.3 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit an RFI utilizing NPS form.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
MOJA – 309905, 328288 01 31 00 - 3
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1.4 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Project information
a. Jobsite Safety
b. Park access and vehicle reporting
c. Jobsite access and parking
d. Staging, storage, and laydown area(s)
e. Temporary facilities and controls
f. Jobsite restrictions
g. Resource protection
h. Weather, climate, environmental conditions
i. Reference documents
j. Other contracts or ongoing work
4. Submittals
a. Status of Division 01 submittals
b. Status of Divisions 02-49 submittals
5. Key contractor personnel
6. Coordination of Subcontractors
7. Labor standards provisions
8. Labor interviews
9. Change orders or modifications
10. Payments to Contractor
11. Payroll reports
12. Contract period of performance
13. Liquidated damages
14. QC daily reports
15. Notice to proceed
16. Correspondence procedures
17. Acceptance/rejection of work
18. Progress meetings
19. Submittal procedures
MOJA – 309905, 328288 01 31 00 - 4
20. Inspections
21. Closeout procedures and submittals
22. Permit requirements
23. Operation and maintenance (O&M) manuals.
24. Work hours and weekend, holiday and night work.
25. Schedule of Values
B. Progress Meetings: The Contracting Officer may schedule periodic meetings to discuss the progress of the work with the Contractor, Subcontractor(s), and key NPS staff. The need for and frequency of these meetings with be discussed at the preconstruction meeting. Progress meetings will likely be held via teleconference and last no more than 30 minutes. The Contractor shall take meeting minutes and distribute to the attendees within a day of the call.
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting
Officer of scheduled meeting dates.
2. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.5 PERMITS
A. General: The Contractor shall obtain all applicable permits associated with the work and comply with all permit conditions furnished by the NPS. A general building permit is not required for work on NPS land; however, the Contractor must still comply with state and local building code provisions. The following permits must be obtained by the Contractor prior to the commencement of work to include: None anticipated at the outset of the contract.
END OF SECTION 01 31 00
MOJA – 309905, 328288 01 33 23 - 1
SUBMITTAL PROCEDURE
SECTION 01 33 23 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 DEFINITIONS
A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
1.2 GENERAL SUBMITTAL PROCEDURES
A. General: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual specific sections.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review for legibility, accuracy, completeness, and compliance with
Contract Documents.
A. Processing Time: Allow time for submittal review, including time for re-submittals, as follows.
When Contracting Officer has completed review, e-mail notification will be sent to Contractor indicating submittal has been processed. No extension of Contract Time will be authorized because of failure to transmit submittals in a timely manner.
1. Action Submittals
a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
b. Re-submittal Review: Allow 14 days for review of each re-submittal.
2. Informational submittals
a. Review: Allow 14 days for review of each submittal.
B. Approved Equals:
1. For each item proposed as an "approved equal," submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the salient characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature
f. Compliance with the Buy American Act
2. A request for approval constitutes a representation that Contractor:
MOJA – 309905, 328288 01 33 23 - 2
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate installation of an approved item and make changes required in other elements of the work because of the substitution.
e. Waives claims for additional expenses that may be incurred as a result of the substitution.
C. Electronic Submittals: Identify and incorporate information in each electronic submittal as follows:
1. Transmittal Form (CM-16): All submittals shall be transmitted using National Park
Service Transmittal Form (CM-16) in PDF format sent via email or approved File
Transfer Protocol (FTP) site. The form can be downloaded from the DSC Workflows website's Submittal Review page. No action will be taken on a submittal item unless accompanied by this Transmittal Form. Complete all applicable fields, sign the form, and attach all supporting documentation.
2. Physical samples: Complete Transmittal Form (CM-16). Deliver physical sample to the
Contracting Officer (or designee) on site for processing. All comments and actions will be documented on the Transmittal Form (CM-16).
D. Identification: Submittal number or other unique identifier, including revision identifier.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Mark each submittal to show which products and options are applicable.
2. As applicable, include:
a. Manufacturer’s product specifications.
b. Manufacturer’s installation instructions.
c. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.
B. Shop Drawings: A shop drawing is a drawing or set of drawings produced by the contractor, supplier, manufacturer, subcontractor, or fabricator. Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Drawings shall be developed in AutoCAD or similar drafting software and submitted as
PDF electronic file.
2. Drawings shall include details, dimensions (including field verified dimensions where required), notational information and other data to ensure the contractor has a complete
MOJA – 309905, 328288 01 33 23 - 3
understanding of the work. Relationship to adjoining construction shall be clearly indicated.
3. Drawings (DRAFT) shall be submitted to the Contracting Officer for review. The
Contractor shall incorporate review comments into the shop drawings and resubmit for final approval.
4. Update shop drawings during and after installation and submit in the O&M Manual.
C. Samples: When requested, submit a physical sample of a product or an array of color choices for approval, if applicable.
1. Identification: Attach label on unexposed side of Samples that includes:
a. Generic description of Sample
b. Product name and name of manufacturer
c. Sample source
d. Submittal Number and title of appropriate Specification Section
END OF SECTION 01 33 23
MOJA – 309905, 328288 01 35 23 - 1
SAFETY REQUIREMENTS
SECTION 01 35 23 - SAFETY REQUIREMENTS
PART 1 - GENERAL
1.1 SUBMITTALS
A. Accident Prevention Plan (APP): Submit APP after contract award and before Pre-Construction conference. Contracting Officer (CO) will review proposed APP. If APP requires any revisions or corrections, Contractor shall resubmit Plan within 10 days. No progress payments will be made until the APP is accepted.
PART 2 - PRODUCTS
2.1 ACCIDENT PREVENTION PLAN (APP)
A. Submit a “site specific” accident prevention plan with the following information (at a minimum):
1. Name and qualifications of supervisor responsible to carry out program.
2. Emergency contact phone numbers
3. Map of local area emergency medical facilities relative to the jobsite.
4. First aid and rescue procedures.
5. Company safety plan or protocol
6. Job Hazard Analysis (JHA) for each major work activity. List of hazards associated and methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees.
PART 3 - EXECUTION
3.1 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at work site.
3.2 HAZARDOUS MATERIALS: Hazardous materials are explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
Store hazardous materials in accordance with manufacturer’s and OSHA Subpart D requirements.
Maintain Safety Data Sheets (SDS) for each chemical readily available on site.
3.3 PERSONAL PROTECTIVE EQUIPMENT (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees
MOJA – 309905, 328288 01 35 23 - 2
SAFETY REQUIREMENTS
3.4 FIRE PREVENTION AND PROTECTION:
A. Hazard Control: The contractor must take all necessary precautions to prevent fire during construction. The Contractor must not store flammable or combustible liquids in non-approved containers. Provide adequate ventilation during use of volatile or noxious substances.
B. The Contractor must provide all equipment and procedures for fire protection on site. The Contractor must assign a capable and qualified person on site in charge of fire protection at all times. The responsibilities include locating and maintaining fire protective equipment and establishing and maintaining safe working procedures.
3.5 SAFETY MEETINGS: At a minimum, conduct weekly 15-minute "toolbox" safety meeting conducted by a foreman or supervisor and attended by construction personnel at worksite. Topics shall coincide with work scheduled for the week.
3.6 FIRST AID EQUIPMENT: Provide adequate first aid equipment for number of employees and appropriate to construction hazards at the site.
3.7 FIRST AID TRAINING: Provide training to personnel to ensure prompt and efficient first aid.
3.8 ACCIDENT REPORTING
A. In the event of an emergency / medical incident, the Contractor shall go to nearby Kelso Depot Visitor Center where NPS staff will contact emergency services through dispatch. There is no cell phone service at job site location.
B. Reportable Accidents: Defined as: death, occupational disease, and/or traumatic injury to employees or the public; fires; and/or property damage by accident in excess of $100.
1. Notify Contracting Officer immediately in the event of a reportable accident.
2. Fill out and forward an Accident/Property Damage Report Form (CM-22) to Contracting
Officer within 7 days of a reportable accident. Obtain form from Contracting Officer.
END OF SECTION 01 35 23
MOJA – 309905, 328288 01 40 00 - 1
QUALITY REQUIREMENTS
SECTION 01 40 00 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 GENERAL
A. The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance comply with applicable specifications, drawings, codes and standards, and the QC Plan.
1.2 SUBMITTALS
A. Quality Control Plan:
1. After contract award and before Pre-Construction conference, submit a “site specific” Contractor Quality Control (CQC) plan with the following information at a minimum:
i. Name of the supervisor responsible for executing the plan.
ii. Organizational flow chart showing key staff and subcontractors.
iii. Qualifications of key staff and subcontractors with applicable licenses and certificates.
iv. Communications and reporting plan, procedures, forms (include NPS daily report form, RFI form, and CM-16 form along with Contractor forms).
v. Testing and inspection procedures at all phases of the project (i.e. preparatory, initial, follow-up) to ensure quality, with steps for correction of work and re-work.
2. If plan requires revisions or corrections, Contractor shall resubmit plan within 10 days.
3. Government reserves the right to require changes in plan during contract period as necessary to obtain the quality specified.
4. No change in the approved plan may be made without written concurrence by Contracting
Officer.
B. Contractor Quality Control (CQC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. Quality Control Supervisor shall utilize DSC Forms. The report shall be typed, legible, and complete and include representative photos. The report shall be submitted on a daily basis no later than the day after the work.
END OF SECTION 01 40 00
http://www.nps.gov/dscw/publicforms.htm http://www.nps.gov/dscw/publicforms.htm
MOJA – 309905, 328288 01 50 00 - 1
TEMPORARY FACILITIES AND CONTROLS
SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 General: The contractor will be allowed to set up temporary facilities and controls as outlined.
All temporary facilities and controls shall be removed from the site before final acceptance of the work.
1.2 TEMPORARY UTILITIES
A. Water Service: Potable water from existing water system is available at or near the project site for use on the contract without charge. Provide all connections and extensions of services with proper backflow prevention devices in compliance with AWWA standards and local regulations.
B. Electric Power Service: Electric power from existing system is available for use at or near the project site for use on the contract without charge. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations.
C. Sanitary Facilities: Restrooms are not available at the site. The contractor shall supply properly ventilated, weather-proof, lockable, portable toilets. Contractor shall locate portable toilets in an area acceptable to the Contracting Officer’s Representative. The contractor shall properly pump and empty these toilets on a regular basis, and keep toilets clean so as not to attract insects and animals.
D. Telephone Cellular Service: The project site does not have cellular service.
1.3 TEMPORARY FACILITIES
A. Temporary Office: The construction of temporary office buildings or installation of trailers will not be allowed in the park. If the contractor requires office space, the park will attempt to accommodate the contractor with an existing space for administrative work.
1.4 TEMPORARY STORAGE
A. Temporary Storage: The Contractor is responsible for ensuring all materials are new and undamaged from weather, age, or neglect. All temporary storage sheds or containers shall be weather tight to prevent damage to materials. If materials appear to be used, damaged, aged, or neglected, the Contracting Officer may request the items be replaced with new at no additional cost to the government.
MOJA – 309905, 328288 01 50 00 - 2
TEMPORARY FACILITIES AND CONTROLS
PART 2 - PRODUCTS (not used)
PART 3 - EXECUTION
3.1 SUPPORT FACILITIES INSTALLATION
A. Temporary Traffic Controls: The contractor shall erect and maintain barricades, danger signals, and warning signs in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), latest edition. The contractor shall provide adequate traffic control, including flaggers on either side of any work performed in the road. Any workers on or near the road must wear highly visible, bright clothing
3.2 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
B. Temporary Enclosures: For uncontrolled sites, the contractor shall construct an enclosure fence, barrier, or partition to prevent people (and animals) from entering the project site except by gates or doors. Enclosures shall be checked daily to ensure they are performing as intended.
END OF SECTION 01 50 00
MOJA – 309905, 328288 01 73 29 - 1
CUTTING AND PATCHING
SECTION 01 73 29 - CUTTING AND PATCHING
PART 1 - GENERAL
1.1 QUALITY ASSURANCE
A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.
PART 2 - PRODUCTS
2.1 MATERIALS
A. In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.
1. If identical materials are unavailable or cannot be used, use materials that will match the visual and functional performance of in-place materials when installed.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.
B. Existing Utility Services and Mechanical/Electrical Systems: Where existing services/systems are required to be removed, relocated, or abandoned, bypass such services/systems before cutting.
3.2 PERFORMANCE
A. Examination: Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed. Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.
B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
MOJA – 309905, 328288 01 73 29 - 2
CUTTING AND PATCHING
2. Finished Surfaces: Cut or drill from exposed or finished side into concealed surfaces.
3. Concrete & Masonry: Cut using an abrasive saw or a diamond-core drill.
4. Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.
5. Proceed with patching after construction operations cutting are complete.
C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams as invisible as possible. Provide materials and comply with installation requirements specified in other Sections.
1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.
2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
3. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weather tight condition.
D. Cleaning: Clean areas and spaces where cutting and patching are performed. Remove paint, mortar, oils, putty, and similar materials.
END OF SECTION 01 73 29
MOJA – 309905, 328288 01 73 40 - 1
EXECUTION
SECTION 01 73 40 - EXECUTION
PART 1 - GENERAL (Not Used)
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.
B. Existing Conditions: Existence and location of underground and other utilities and construction indicated as existing are not guaranteed.
1. Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.
2. Before construction, verify the location and points of connection of utility services.
3. Before beginning sitework, investigate and verify existence and location of underground utilities and other construction affecting Work
3.2 PREPARATION
A. Field Measurements: Take field measurements or conduct surveys to verify quantities and dimensions before procurement and fabrication or installation.
B. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.
C. Digging: Exercise caution when digging with heavy equipment. Tone and mark for utilities in advance of digging. If a buried utility or feature is discovered, exercise extreme caution or hand dig to prevent damage to the utility or feature. If the utility or feature is damaged, repair at no additional cost to the government.
D. Review of Contract Documents and Field Conditions: Immediately on discovery of need for clarification of the Contract Documents caused by differing field conditions outside control of Contractor, submit request for information to Contracting Officer in accordance with Section 01 31 00 Project Management and Coordination.
MOJA – 309905, 328288 01 73 40 - 2
EXECUTION
3.3 INSTALLATION
A. Install all systems or components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations. All systems or components shall be complete and operable.
B. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of Work. Where mounting heights are not indicated, mount components at heights directed by Contracting Officer.
3.4 PROGRESS CLEANING
A. General: Clean Project site, work areas, and common areas daily. Keep site free of waste and debris in proper containment. Properly dispose of all waste and debris offsite.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to level of cleanliness necessary for proper execution of Work.
D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials not hazardous to health or property and will not damage exposed surfaces.
E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.
F. Clean and protect construction in progress and adjoining materials already in place during handling and installation. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
G. Final Cleaning: At completion of Work, remove remaining waste materials, rubbish, tools, equipment, machinery and surplus materials. Clean exposed surfaces and leave Project clean and ready for occupancy. Legally dispose of all waste items.
3.5 CORRECTION OF THE WORK
A. Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
B. Remove and replace damaged surfaces exposed to view if surfaces cannot be repaired without visible evidence of repair.
C. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.
END OF SECTION 01 73 40
MOJA – 309905, 328288 01 70 00 - 1
CLOSEOUT PROCEDURES
SECTION 01 77 00 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 PROJECT RECORD DRAWINGS
A. Maintain one complete full-size set of contract drawings and one full-size set of vendor-supplied drawings. Clearly mark changes, deletions, and additions to show actual construction conditions.
B. Keep record drawings current. Make record drawings available to Contracting Officer (CO) for inspection at the time of monthly progress payment requests.
C. Submit complete record drawings on completion of total project. Include shop drawings, sketches, and additional drawings to be included in final set.
1.2 CLOSEOUT SUBMITTALS
A. Submit the following before requesting final inspection:
1. Specific warranties, guarantees, workmanship bonds, final certifications, and similar documents.
2. Project Record Documents
3. Operation and maintenance (O&M) manuals.
a. Submit two (2) hard copies (in D-ring binders) to the onsite Point of Contact (POC) and one (1) electronic copy (PDF) to the Contracting Officer with all applicable operation and maintenance information including but not limited to:
1) Preventative maintenance schedule for all major components.
2) Operating instructions, if applicable. Furnish operating instructions attached to or posted adjacent to equipment. Include wiring diagrams, control diagrams, control sequence, start up, adjustment, operation, lubrication, shut down, safety precautions, procedures in the event of equipment failure, and other items of instruction recommended by manufacturer.
3) Product / material cut sheets (all approved products used on the project).
4) Updated system diagrams or shop drawings, as applicable.
5) Progress photos showing all phases of the work numbered sequentially.
6) Product warranties for individual products and systems.
7) A one (1) year Contractor-issued warranty on all workmanship starting from the date of final acceptance.
1.3 DEMONSTRATION & TRAINING
1. Provide onsite demonstration and training to NPS personnel on operation, adjustment, and maintenance of products, equipment, and systems.
MOJA – 309905, 328288 01 70 00 - 2
CLOSEOUT PROCEDURES
1.4 FINAL INSPECTION, SUBSTANTIAL COMPLETION AND ACCEPTANCE
PROCEDURES
A. Request pre-final inspection in writing when project or designated portion of project is substantially complete. Contracting Officer will proceed with pre-final inspection within 14 days of receipt of written request or will advise Contractor of items that prevent project from being substantially complete.
B. If work is determined substantially complete following pre-final inspection, Contracting Officer will issue a Letter of Substantial Completion and prepare Punch List of deficiencies to be corrected before final inspection and acceptance.
C. If work is not determined substantially complete following pre-final inspection, Contracting Officer will notify Contractor in writing. Contractor shall request new pre-final inspection after completing work. Re-inspection costs may be charged against Contractor in accordance with Inspection of Construction contract clause.
D. Contractor shall complete the work described in the Punch List within 30 calendar days, weather permitting. Once all Punch List work is complete, the Contractor shall request a final inspection in writing to arrange for the confirmation of Punch List completion.
E. If Contractor completes items of work on Punch List and contractually required items, Contracting Officer will issue Letter of final acceptance of work.