B08_ATTACHMENT_A_SOW.pdf

PDF 6 MB Posted

Attached to
Replace Garage Bay Doors on Auto Shop Building Federal contract opportunity
Solicitation number
140P8125Q0027
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is a Summary of Work (Section 01 11 00) for a federal contract to replace six existing vehicle door systems at the auto shop in Death Valley National Park, California. The primary objectives include removing and disposing of six non-functional overhead garage doors and tracks, and installing new commercial-grade sectional overhead doors with specific performance requirements. The new doors must have a wind rating of at least 95 mph/50 PSF, an R18 insulation value, be white in color, and include automatic openers, sensors, control units, weather seals, and safety devices.

The project specifications mandate that the replacement doors match or exceed the current Thermacore® XA592 Full Vision doors' performance, with improvements to reduce heat transfer. One door (101A) requires a standard pedestrian door. The contractor must ensure all systems comply with OSHA, ANSI/DASMA, NFPA 80/105, and ABA/ADA standards. The work must be completed within 120 days after the notice to proceed, with specific requirements for site setup, safety, demolition, installation, testing, and final inspection. The project emphasizes energy efficiency, safety, and maintaining the facility's operational functionality throughout the renovation process.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Garage Bay Doors on Auto Shop Building, newest first.
File Type Posted
Sol_140P8125Q0027.pdf PDF
B08_ATTACHMENT_D_Construction_Contract_Administration.pdf PDF
B08_ATTACHMENT_B_MAPS.pdf PDF
B08_ATTACHMENT_C_DB_Wage_Rates_Inyo_County_CA_2025.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 11 00 – SUMMARY OF WORK

PART 1 – GENERAL

1.1 SUMMARY

The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, to remove and replace six (6) existing, non-functional vehicle door systems at the auto shop in Death Valley National Park, California.

This work includes:

• Removal and disposal of six (6) existing overhead garage doors and tracks

• Supply, Delivery and Installation of six (6) new sectional overhead garage doors and tracks

New doors and tracks shall be secure, weather-tight and commercial-grade door systems, consistent with industry standards. The current doors are Thermacore® XA592 Full Vision (14’2” W x 14’3” H). The current doors have three rows of windows (approx. 18"x36", 4 across), which allow significant heat transfer.

The building is located at: 579 Cow Creek Service Road, Death Valley California, 92328.

36°30'10.7"N 116°52'05.6"W. See attached Maps to the solicitation.

1.2 OBJECTIVES

The primary objective is to ensure the delivery of fully operational vehicle access door systems that meet all safety, accessibility, and performance criteria. This includes:

• Removing and disposing of the six existing, failed door systems, six (6) overhead doors Thermacore® Sectional Steel Door – 592 with LiftMaster H5011L4L.

• Installing six (6) new doors that have a wind rating of at least 95mph/50PSF and an insulation value of R18, white in color.

• Providing automatic openers/lifts, sensors, control units, weather seals, and safety devices for six doors.

• Ensuring all systems are compliant with OSHA, ANSI/DASMA, NFPA 80/105, and ABA/ADA where applicable.

• Door number 101A listed below must have a standard pedestrian door.

• Replacement doors shall match or exceed the insulation and durability rating, with fewer or reconfigured windows (e.g., one row, smaller panes, or insulated glass), using high-performance glazing (e.g., tinted or low-e) to reduce afternoon heat gain—prioritizing energy efficiency while balancing natural light and exterior aesthetics.

• Replacement doors shall not require structural modification to install. Direct replacement only.

Original installation as-built auto shop door schedule.

DOOR SCHEDULE DOOR FRAME

DOOR NO. Type Size THK MATL FINISH MATL FINISH R.O. AT MASONRY REMARKS

101 – Bay 2 M 14' x 2" x 14' x 1" 2" STL PT STL N/A 14' 0" x 14' 0"

Insulated overhead door with insulated glazing

101A – Bay 3 T 14' x 2" x 14' x 1"

2" STL PT STL N/A 14' 0" x 14' 0"

4' x 8' Man Door installed in insulated overhead door, no overhead tracks, door panel fixed

101B – Bay 4 M 14' x 2" x 14' x 1" 2" STL PT STL N/A 14' 0" x 14' 0"

Insulated overhead door with insulated glazing

101C – Bay 5 M 14' x 2" x 14' x 1" 2" STL PT STL N/A 14' 0" x 14' 0"

Insulated overhead door with insulated glazing

101D – Bay 6 M 14' x 2" x 14' x 1"

2" STL PT STL N/A 14' 0" x 14' 0"

Insulated overhead door with insulated glazing

101E – Bay 7 M 14' x 2" x 14' x 1"

2" STL PT STL N/A 14' 0" x 14' 0"

Insulated overhead door with insulated glazing

1.3 CONTRACTOR REQUIREMENTS

The contractor shall:

• Comply with all laws, regulations, and policies, to include, but not be limited to, the latest applicable versions of applicable federal, state and local codes.

o Licensure: All work shall be performed by workers who hold appropriate licenses in one of the 50 States, the District of Columbia, Puerto Rico, or other US territory. Work may be conducted by unlicensed workers provided the work is overseen by a licensed contractor. The Prime must be a licensed General or appropriate specialty contractor. Submit current license with Quote.

• Comply with ANSI/DASMA 102 for performance standards of sectional garage doors.

• Ensure all electrical connections follow the National Electrical Code (NEC).

• Follow OSHA 29 CFR 1926 for all safety and fall protection during demolition and installation.

• Use UL-listed components where applicable.

• Ensure accessibility and clearance are compliant with ABA/ADA standards.

• Coordinate all utility shutoffs and service connections with park staff with 24-hour notice, minimum.

• Submit shop drawings and product data for Government approval prior to ordering.

• Prime Contractor is responsible for directly superintending the project, onsite, all days in which work is being done.

• Contractor shall provide one-year labor warranty.

• Contractor shall respond to warranty service calls within 3 calendar days.

• All affected areas must be left in a clean and tidy condition. Any damages to Government property will be fixed and repaired at no cost to the Government.

1.4 ASBESTOS AND HAZARDOUS MATERIALS

- A survey of asbestos containing materials (ACM) is not available for this building. There are no known ACM present.

- The Contractor shall conduct all work that impacts asbestos or hazardous materials, including lead-based or lead-containing paint and animal droppings or carcasses according to applicable laws, regulations, and policies, and by adhering to industry best practices.

- Impacts to known asbestos containing material, known hazardous materials, or materials reasonably expected to contain hazardous materials or animal waste shall be conducted at no additional cost to the Government.

- Asbestos or hazardous materials not reasonably expected to be encountered shall be treated as a differing site conditions.

1.5 WORK SEQUENCE

The contractor shall complete the work in the following logical and controlled sequence to ensure safety, operational continuity, and site security. Each phase must be fully completed, inspected, and approved before proceeding to the next. Under no circumstances shall more than one bay be non-operational at a time. Bays shall be treated in numerical order from left to right. Vehicle lifts are located in bays 5 and 6; at least one of these bays must remain operational throughout the project.

Site Setup and Safety Assessment

1.1. Establish construction staging and laydown area with the COR, using clearly defined boundaries to isolate the work zone from public or NPS operational areas.

1.2. Perform pre-work safety hazard assessment in accordance with OSHA 29 CFR 1926 and ANSI/ASSE A10.

1.3. Install temporary dust barriers, signage, and protective plywood panel partitions or modular frame walls to enclose bays not under active work.

1.4. Confirm overhead clearance and equipment maneuverability within work zones.

1.5. Implement overnight security closure using sectional panel inserts or framed plywood systems to ensure facility is fully secured at all times if the doors cannot be replaced same day.

Demolition and Removal of Existing Door Systems (One Bay at a Time)

2.1. Begin with Bay 2, then proceed sequentially through Bay 7.

2.2. Disconnect and isolate all electrical and mechanical systems in accordance with NFPA 70E and IBC 3303.

2.3. Remove and dispose of all existing door assemblies, tracks, motors, sensors, and associated controls per EPA RCRA disposal standards.

2.4. Cap or safely terminate all temporary electrical systems prior to new installation.

2.5 Ensure electrical power is not disrupted in adjacent bays where NPS Personnel may be working. Coordinate with NPS if an electrical power disruption that effects more than one bay is required.

Installation of Sectional Overhead Doors

3.1. Install new sectional doors with commercial-grade galvanized steel panels, weather stripping, heavy-duty torsion spring assemblies, and motorized lift systems rated per ANSI/DASMA 102 standards.

3.2. Ensure alignment, weather-seals, and clearance verification in each bay prior to continuing. Each new bay door shall be fully operational before proceeding to the next bay to work.

3.3. Connect electrical control wiring to existing systems, ensuring compliance with NECA and UL 325 standards for motor-operated doors.

3.4. Provide mechanical fastening of tracks and reinforcements per manufacturer’s specs and ASTM F1578 for sectional door systems.

Testing and Calibration

4.1. Conduct full operational testing for each door’s opening/closing sequence, safety stop, and auto-reverse systems.

4.2. Calibrate lift motors, remote controls, wall buttons, and safety sensors in accordance with UL 325 and NFPA 70.

4.3. Validate emergency manual operation mechanisms. Document results and receive sign off by the COR.

Final Inspection and Commissioning

5.1. Perform final walkthrough with Contracting Officer’s Representative (COR) or Park Representative following completion of each door.

5.2. Ensure all safety decals, instructions, and documentation are in place and in required locations per OSHA .

5.3. Submit manufacturer warranty certificates, calibration logs, and installation checklists to COR at time of final inspection.

5.4. Confirm the integrity and security of the entire facility, ensuring the final configuration maintains operational functionality and site access continuity.

1.6 CONTRACTOR USE OF PREMISES

• Coordinate use of premises with COR.

• Maintain access to adjacent occupied areas and emergency routes.

• Limit work to areas identified in the contract and restrict access to non-construction zones.

• Ensure daily cleanup and material storage meet park safety and environmental standards.

• The Contractor shall be identifiable with uniforms, name tags, marked vehicles, high-visibility vests, hats, or hardhats with company logo, or similar, and maintain a professional decorum and appearance.

• Do not drive vehicles off road or access non-project areas without permission from the COR.

• Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

• Smoking is prohibited inside or outside within 25 feet of any buildings in the park.

This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

• Confine storage of equipment and materials to the staging / lay-down/ storage areas identified by the COR or as established at the preconstruction meeting.

• The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting.

• The Contractor shall keep driveways and entrances serving the premises clear and available to the Government, government employees, tenants, the public, and emergency vehicles always.

• Prevent damage to natural surroundings. Restore damaged areas and replace damaged vegetation and landscape items, at no expense to the Govern

1.7 WORK RESTRICTIONS

• Work hours shall be Monday through Friday, 6:00 AM – 4:30 PM, unless otherwise approved.

• Minimize dust and debris, ensuring no disruption to adjacent operations or facilities.

• Access to bay 5 or bay 6 must always be maintained to facilitate the continuity of GSA repair work. If bay 5 is being worked on bay 6 must be open and if bay 6 is being worked on bay 5 must be accessible by the mechanic.

1.8 ACCESSIBILITY REQUIREMENTS

All installed systems shall comply with the Architectural Barriers Act (ABA) Accessibility Standards, including but not limited to:

• Controls mounted at accessible heights (where applicable)

• Clear space maintained around equipment. Markings are currently painted on the floor.

• Safety sensors installed to prevent door closure on persons or objects

1.9 SAFETY AND ENVIRONMENTAL REQUIREMENTS

The Contractor shall be fully responsible for developing, implementing, and maintaining a comprehensive Site Safety and Health Plan (SSHP) tailored to the environmental hazards and operational risks present at this site. The SSHP must comply with all applicable federal, state, and local regulations, including but not limited to:

OSHA 29 CFR 1926 (Construction Standards)

OSHA 29 CFR 1910 (General Industry Standards)

EPA regulations (40 CFR 112 & 261)

ANSI, CDC, NIOSH, and NFPA guidance

National Park Service (NPS) hazardous materials policy

The SSHP shall include, at minimum, the following required safety program elements:

1. Heat Illness Prevention

Implement a Heat Illness Prevention Program (HIPP) that meets or exceeds OSHA Technical Manual Section III: Chapter 4 and NIOSH guidance.

Train all personnel to recognize symptoms of heat-related illness (e.g., heat exhaustion, heat stroke).

Provide shaded rest areas and air-conditioned cooling stations within a 5-minute walk of work zones.

Ensure access to potable water (minimum 1 quart per worker per hour).

Use a buddy system, enforce scheduled rest breaks, and maintain a written emergency response protocol.

Provide temporary shade or shift schedules to reduce exposure between 11:00 a.m. and 4:00 p.m.

Supply PPE such as brimmed hard hats, UV-rated clothing, and cooling vests.

2. Spill Prevention, Control, and Countermeasure (SPCC)

Handle hazardous materials (fuel, oil, solvents, sewage) per the EPA SPCC Rule (40 CFR

112) and NPS policy.

Provide spill kits proportional to on-site materials, including absorbents, booms, PPE, disposal containers, and neutralizers.

Train all personnel in spill response, containment, and reporting procedures.

Contractor is fully responsible for containment, cleanup, and disposal per 40 CFR 261.

Assign a spill response supervisor for planning and documentation.

3. Wind and Particulate Exposure Control

Conduct wind hazard risk assessments; implement controls when wind speeds exceed 25 mph.

Provide sealed ANSI Z87.1-rated eye protection and NIOSH P100 respirators during high dust/silica events.

Minimize skin exposure with long sleeves, neck coverings, and UV-resistant outerwear.

4. Slips, Trips, and Falls

Evaluate site for trip hazards: uneven terrain, trenches, cords, and loose gravel.

Stabilize and mark walkways with caution tape or signage.

Require ASTM F2413-rated slip-resistant footwear.

Implement fall protection for elevated work per OSHA 1926.501.

5. Concrete and Masonry Cutting Safety

Use wet-cutting methods to suppress silica dust per OSHA 1926.1153.

Dry cutting only permitted with prior COR approval and HEPA dust control systems.

Require use of NIOSH APF 10 respirators, face shields, and hearing protection as determined by a Job Hazard Analysis (JHA).

6. Personal Protective Equipment (PPE) and General Safety

Ensure all personnel wear task-appropriate PPE (e.g., hard hats, hi-vis vests, gloves, safety glasses, and protective boots).

All PPE must comply with ANSI/ISEA, OSHA, or NIOSH standards.

Conduct daily safety briefings and toolbox talks.

Report all safety violations or incidents to the COR immediately, including a root cause analysis within 48 hours.

7. General Environmental and Fire Safety

Follow OSHA regulations at all times.

Dispose of all waste per EPA regulations and site-specific park rules.

Report and manage any hazardous materials (e.g., lead, asbestos) per OSHA/EPA standards.

Implement fire safety measures in accordance with NFPA 1 and NFPA 80.

1.10 PERIOD OF PERFORMANCE SUBMITTALS AND NOTICE TO PROCEED

Project shall be completed, including release of claims and all inspections, 120 days after notice to proceed.

After contract award, Notice to Proceed #1 will be issued for administrative submittals. The contractor will have 7 business days to submit the following. Once all submittals are approved, a preconstruction meeting will be schedule. Please use the supplied CM16 transmittal form to submit:

- Certificate of Liability Insurance and Alternative Payment Protection/Bond

- Quality control plan and safety plan

- SF-1413 Subcontractor Form

- Letter Designating PRIME Superintendent

- Schedule of Values (to match Bid Schedule)

- Product data for door systems and openers

- Shop drawings

- Manufacturer’s cut sheets and warranty documentation

- Installation and operation manuals

- Safety data sheets (SDS) for any materials used

It is expected that immediately following the preconstruction meeting, Notice to Proceed #2 will be issued to mobilize and begin on site work.

1.11 CERTIFIED PAYROLL

Certified payroll (form WH-347) shall be submitted weekly to the Contracting Officer (CO) and Contracting Officer’s Representative (COR). Weeks with no work completed shall state “no work completed”.

1.11 PROJECT CLOSEOUT

• Contractor shall request final inspection with COR. A walkthrough may result in punch list items. Punch list items will be communicated to the contracting officer and emailed to the contractor. Once punch list items are complete and COR accepts:

o Submit warranties and maintenance instructions.

o Conduct training with NPS personnel on operation and maintenance of installed systems.

o Complete final walkthrough with park facilities manager.

PART 2 – PRODUCTS

• Sectional Overhead Doors: Thermacore® 592 or approved equal. R-value ≥ 17.5, polyurethane insulation, wind load-rated, weather seals, and powder-coated finish.

• Openers and Operators: MAXUM JHDC12S4BMC or approved equal, Heavy-duty commercial openers compatible with doors; must include wall-mounted and remote controls, limit switches, and safety stop.

• Sensors: UL 325-compliant photo-eye and reversing sensors.

• Weather Seals: Top, bottom, and jamb seals to ensure weather-tight integrity.

• Mounting and Hardware: Galvanized steel tracks, brackets, and fasteners; rust resistant.

SITE PHOTOS

Bay Numbering

Bay 2 Exterior Door

Bay 2 Interior

Bay 3 Exterior Door

Bay 3 Interior Door

Bay 3 Interior Door Detail

Bay 4 Exterior Door

Bay 4 Interior Door

Bay 5 Exterior Door

Bay 5 Interior Door

Bay 6 Exterior Door

Bay 6 Interior Door

Bay 7 Exterior Door

Bay 7 Interior

CC348 Auto Shop

Door Lift Details