This document is a Request for Quotation (RFQ) for the demolition and installation of a new automatic dry-type sprinkler system in the maintenance shop building at John Day Fossil Beds National Monument in Kimberly, Oregon.

The solicitation, issued by the Department of the Interior's National Park Service Pacific West Region, requires the contractor to demolish the existing sprinkler system and configure and install a new hydraulically designed NFPA 13 automatic dry-type sprinkler system connected to the potable water system. The project location is a 4,410 square foot non-historic maintenance shop building. The project must be completed within 120 calendar days after receipt of the notice to proceed. Responses are due by the date specified in the solicitation or latest amendment. Award will be made on a firm-fixed price basis to the contractor whose quote provides the best value based on technical capability, relevant experience, past performance, and price reasonableness. The Buy American Act applies to construction materials used in this project.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

(JODA)

SECTION A: Solicitation/contract form (Standard Form 1442) (Pages 1-3)

SECTION B: Supplies or services and price/cost

Fill in pricing using the Price Schedule provided in “Forms to Return with Quote” Word document as part of the “Quote and Business Information” contents described in Section L, below.

52.252-2 FAR Clauses Incorporated By Reference (Feb 1998)

This contract incorporates one or more Federal Acquisition Regulation (FAR) and Department of the Interior Acquisition Regulation (DIAR) clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses: FAR -https://www.acquisition.gov/?q=browsefar

DIAR http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl

Full text versions of all Deviations are found at https://www.acquisition.gov/content/caac-letter

SECTION C: Description/Specifications

Demo the existing sprinkler system then configure and install of a new hydraulically designed NFPA 13 automatic dry type sprinkler system. The system shall be connected to the potable water system in a dedicated sprinkler pipe. This is a 4,410 square foot non historic maintenance shop building with two small offices, two bathrooms, one small kitchen, micro conference room and three garage bays. Demo all existing fire sprinkler components prior to the installation of the new sprinkler system and remove the old components from John Day Fossil Beds National Monument and deliver to the appropriate recycle or disposal facility.

Project Location: 32651 Highway 19, Kimberly Oregon 97848 – (Grant County, Oregon, United States)

See attached statement of work for detailed information.

SECTION D: Packaging and Marking (Intentionally Left Blank) https://www.acquisition.gov/?q=browsefar http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl https://www.acquisition.gov/content/caac-letter

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

SECTION E: Inspection and Acceptance

52.246-12 Inspection of Construction. (AUG 1996)

(a) Definition. “Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not-

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this- section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may-

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of clause)

52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (Aug 1996)

SECTION F: Deliveries or Performance

52.236-15 Schedules for Construction Contracts (APR 1984)

52.242-14 Suspension of Work. (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work, Alternate I. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the entire work within 120 calendar days after issuance of the NTP. The time stated for completion shall include final cleanup of the premises.

F.1 Period of Performance Dates and Seasonal Conditions

Although NPS does not intend to suspend work during contract performance, seasonal weather conditions may restrict the contractor’s construction activities. The Contractor’s construction schedule should take into account historic weather patterns when planning the work sequence. Precipitation, both rain and snow, is heaviest November through January.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

SECTION G: Contract Administration Data

1452.201-70 Authorities and Delegations (SEPT 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award.

The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor.

Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.

The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph

(d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

1452.204-70 Release of Claims—Department of the Interior (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

G.1 Appointment of Contractor Representative / Superintendent

Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer and COR the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.

G.2 Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (Feb 2021)

Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP; https://www.ipp.gov).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov .

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice (upload your business invoice as an attachment to the IPP invoice before you click “submit” in

IPP):

1. Contractor’s standard business invoice,

2. Signed certification required by FAR clause 52.232-5,

3. Schedule of values for work being invoiced, and

4. If submitting a final invoice, also attach a signed copy of the Release of Claims form.

Contractor’s failure to attach the required documentation as specified above will result in the IPP invoice being rejected and cause a delay in payment.

The Contractor must use the IPP website for submitting requests for payment. The Contractor Government Business Point of Contact (as listed SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

G.3 NPS Contact Information

Contracting Officer: Mickey Chisolm (360) 565-3025 Mickey_Chisolm@nps.gov

Contracting Officer’s Representative: Aaron Bougie (541) 987-2333 X:1216 Aaron_Bougie@nps.gov https://www.ipp.gov/ https://www.ipp.gov/ mailto:Mickey_Chisolm@nps.gov mailto:Aaron_Bougie@nps.gov

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

SECTION H: SPECIAL CONTRACT REQUIREMENTS

H.1 Wage Determination

U.S. Department of Labor General Wage Decision no. OR20240093 (Grant County, Oregon, United States), is incorporated into this solicitation/contract, as shown in Section J.

H.2 Progress Meetings

The Contracting Officer will convene periodic meetings described in Attachment 1; the contractor will be required to attend in person or by phone. The Contracting Officer will provide specific details regarding the date, time, and location of the preconstruction conference, any need for attendance by subcontractors, and information regarding the items to be discussed.

H.3 Notice of Required Bonds

The awardee shall furnish a payment bond, using Standard Form 25A, or irrevocable letter of credit, within 10 days after contract award. The penal sum of the payment bond shall be 100% of the contract price.

H.4 Interpretations of Contract: Notice of Ambiguities

This written contract and any and all identified writings or documents incorporated by reference herein or physically attached hereto constitute the parties' complete agreement and no other prior or contemporaneous agreements either written or oral shall be considered to change, modify, or contradict it.

Any ambiguity in the contract will not be strictly construed against the drafter of the contract language but shall be resolved by applying the most reasonable interpretation under the circumstances, giving full consideration to the intentions of the parties at the time of contracting.

The Contractor shall exercise due diligence to discover and to bring to the attention of the Contracting Officer at the earliest possible time any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated. Failure to comply with such obligation may be deemed a waiver and release of any and all claims for extra costs or delay arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.

H.5 Worker’s Compensation Insurance Requirements

The Contractor shall maintain compensation insurance for employees engaged in the work complying with the worker's compensation laws of the State in which the work is to be performed and shall maintain liability insurance protecting the Contractor from claims because of bodily injury (including death) and property damage arising under this Contract.

H.7 Conduct of Operations

At all times the Contractor shall conduct their organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. The park compendium is available at Superintendent's Compendium – John Day Fossil Beds National Monument (U.S. National Park Service) (nps.gov).

In addition, work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with prior approval of the Contracting

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

Officer. Rowdy, disruptive behavior and/or sexual harassment will not be tolerated, and the offending individual(s) will be removed from the site. Amplified playing of music or talk programs is prohibited on site or in buildings.

H.8 KEY PERSONNEL

(a) The Contractor shall assign to this contract the following key personnel:

Site Superintendent

Quality Control Manager

(a) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph

(b) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.

H.9 ARCHEOLOGICAL FINDINGS

Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover, or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery;

notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, s/he will be compensated by an equitable adjustment under the General Provisions of the Contract.

H.10 SITE SPECIFIC SAFETY AND HEALTH PLAN

A site specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site specific plan. The site specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

As work proceeds, the site specific safety and health plan shall be adapted to new situations and new conditions. Changes and modifications to the accepted site specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office.

Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.

Prior to submittal to the COR, the site specific safety and health plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The site specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site specific safety and health plan for review and approval by the safety office.

Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.

(End of Clause)

SECTION I: Federal Acquisition Regulation (FAR) Contract Clauses

52.202-1 Definitions. (JUN 2020) 52.203-6 Restrictions on Subcontractor Sales to the Government. (JUN 2020) 52.203-7 Anti-Kickback Procedures. (JUN 2020) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements (JAN 2017) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUN 2020) 52.204-13 System for Award Management Maintenance. (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV 2021) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records—Negotiation (JUN 2020) 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997) 52.215-19 Notification of Ownership Changes (OCT 1997) 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data— Modifications (NOV 2021)

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns. (OCT 2022) 52.219-28 Post-Award Small Business Program Rerepresentation. (MAR 2023) 52.222-3 Convict Labor. (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAR 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds. (MAY 2014) 52.222-8 Payrolls and Basic Records. (JUL 2021) 52.222-9 Apprentices and Trainees. (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (MAY 2014) 52.222-12 Contract Termination - Debarment. (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (MAY 2014) 52.222-21 Prohibition of Segregated Facilities. (APR 2015) 52.222-26 Equal Opportunity. (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015) 52.222-35 Equal Opportunity for Veterans. (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities. (JUN 2020) 52.222-37 Employment Reports on Veterans. (JUN 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010) 52.222-50 Combating Trafficking in Persons. (NOV 2021) 52.222-54 Employment Eligibility Verification. (MAY 2022) 52.222-55 Minimum Wages Under Executive Order 13658 (JAN 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2022) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (JUN 2020) 52.225-13 Restrictions on Certain Foreign Purchases. (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007) 52.228-2 Additional Bond Security. (OCT 1997) 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) 52.228-11 Individual Surety Pledges of Assets. (FEB 2021) (DEVIATION APR 2020) 52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds - Construction. (JUN 2020) (DEVIATION APR 2020) 52.229-4 Federal, State, and Local Taxes (FEB 2013) 52.229-12 Tax on Certain Foreign Procurements- Notice and Representation (FEB 2021) 52.232-5 Payments under Fixed-Price Construction Contracts. (JUN 2020) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims. (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes, Alt. 1. (MAY 2014, DEC 1991) 52.233-3 Protest after Award. (AUG 1996)

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-2 Differing Site Conditions. (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-5 Material and Workmanship. (APR 1984) 52.236-6 Superintendence by the Contractor. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991) 52.236-8 Other Contracts. (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

(APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984) 52.236-11 Use and Possession Prior to Completion. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-14 Availability and Use of Utility Services. (APR 1984) 52.236-17 Layout of Work. (APR 1984) 52.236-21 Specifications and Drawings for Construction. (FEB 1997) 52.236-26 Preconstruction Conference. (FEB 1995) 52.242-13 Bankruptcy. (JUL 1995) 52.243-4 Changes. (JUN 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services. (MAR 2023) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction. (MAR 1994) - Alternate I (APR 1984) 52.248-3 Value Engineering - Construction. (OCT 2022) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I

(SEP 1996)

52.249-10 Default (Fixed-Price Construction). (APR 1984) 52.252-6 Authorized Deviations in Clauses (NOV 2020) (b) Department of the Interior (48 CFR 14) 52.253-1 Computer Generated Forms. (JAN 1991) 1452.215-70 Examination of Records by the Department of the Interior (APR 1984)

52.225-9 Buy American - Construction Materials. (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products. "Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if– (A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material.

The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that- (i)The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components. (1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Measure Quantity Price (dollars)*

Item1:

Foreign construction material

Domestic construction material

Item2:

Foreign construction material

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

Domestic construction material

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

(End of clause)

52.228-13 Alternative Payment Protections (JULY 2000)

(a) The Contractor shall submit one of the following payment protections: payment bond (on SF25A) or irrevocable letter of credit.

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within 10 days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

52.236-13 Accident Prevention. (NOV 1991) - Alternate I

(a) The Contractor shall provide and maintain work environments and procedures which will -

(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;

(2) Avoid interruptions of Government operations and delays in project completion dates; and

(3) Control costs in the performance of this contract.

(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall -

(1) Provide appropriate safety barricades, signs, and signal lights;

(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and

(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.

(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1- 1, in effect on the date of the solicitation.

(d) Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument contract price or extension of the performance schedule on any stop work order issued under this clause.

(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.

(f) Before commencing the work, the Contractor shall -

(1) Submit a written proposed plan for implementing this clause. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards; and

(2) Meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.

1452.203-70 Restriction on Endorsements—Department of the Interior (JUL 1996)

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

1452.228-70 Liability Insurance - Department of the Interior (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

Employer's liability $100,000 General liability $3,000,000 Construction Per person $500,000 Per occurrence $1,000,000 Property damage $3,000,000 Architect-Engineer Per person $200,000 Per occurrence $500,000 Property damage $ 20,000 Automobile liability Per person $200,000 Per occurrence for bodily injury $500,000 (other than passenger liability) Per occurrence for property damage $20,000

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

1452.236-70 Prohibition Against Use of Lead-based Paint—Department of the Interior

(JUL 1996)

Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.

SECTION J: List of Documents, Exhibits and Other Attachments

Number Attachment Title Number of Pages 1 Project Specifications/Statement of Work (SOW) 13 2 Wage Determination (OR20240093) 6 3 Forms to return with quote 13

- Form 1 – SF 1442 3

- Terms Provisions Clauses 21

Information and requirements stated in Sections A through J and the attachments noted in section J apply to this solicitation and the subsequent contract.

Sections K through M apply to the solicitation only

Solicitation #140P8324Q0057, Maintenance Shop Sprinkler System - John Day Fossil Beds National Monument

SECTION L: Instructions, Conditions, and Notices to Offerors

L.1 FEDERAL ACQUISITION REGULATION PROVISIONS

52.252-1 Solicitation Provisions incorporated by reference (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

FAR - https://www.acquisition.gov/?q=browsefar DIAR http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl

Full text versions of all Deviations are found at https://www.acquisition.gov/content/caac-letter

52.204-7 System for Award Management. (OCT 2018) 52.204-16 Commercial and Government Entity Code Reporting (AUG 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.211-6 Brand Name or Equal (AUG 1999) 52.215-1 Instructions to Offerors—Competitive Acquisition (NOV 2021) 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work.