B08_Attachment_4_-_PPQ.doc

DOC document 100 KB Posted

Attached to
Bryce Canyon - Steel Roof and Siding Replacement
Solicitation number
140P6224Q0018
Issued by

About this file

This document is a Past Performance Questionnaire (PPQ) that is part of a federal contract opportunity. The Department of Interior National Park Service is considering a company for a project opportunity and is requesting information about the company's past performance.

The PPQ includes instructions for the offeror to complete Section A with project details, and for the project owner/evaluator to complete Section B with ratings and comments on the company's past performance across various criteria such as relationship with the client, quality control, schedule adherence, and customer satisfaction. The PPQ must be returned by the specified deadline to be considered with the complete proposal package. The related federal contract opportunity is for the removal and replacement of the roof, siding, and porch components of a building at Bryce Canyon National Park, with an estimated 3,074 square feet of standing seam metal roof and 2,500 square feet of siding to be replaced.

View the file

Other files

File Type Posted
B08_Attachment_1_-_SOW.pdf PDF
B08_Attachment_3_-_Technical_Questionnaire.docx DOCX document
Sol_140P6224Q0018.pdf PDF
B08_Attachment_5_-_Pricing_Schedule.xlsx XLSX spreadsheet
B08_Attachment_2_-_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Interior

Past Performance Questionnaire (PPQ)

U.S. Department of the Interior, National Park Service is considering the company listed below in Section A for a project opportunity - Your comments would be appreciated regarding this company’s past performance.

Instructions:

1) The offeror is to complete only the information in Section A, then send the entire past performance questionnaire to project owner/evaluator for completion.

2) The project owner/evaluator (or reference) is to complete Section B, then send the entire past performance questionnaire back to the offeror to be provided with their complete proposal package, which will then be reviewed for evaluation.

3) The past performance questionnaire must be received by the contracting point of contact by the date and time specified in the solicitation (or any amendments). Please note that for electronic submissions, offerors should consider and account for potential delays in transmissions between when an electronic submission is submitted and when an electronic submission is received. Late past performance questionnaires will not be accepted.

4) One past performance questionnaire is to be used for each past performance project submitted. The offeror may submit between 3-5 past performance questionnaires for this solicitation. Past performance projects must have been completed within five years of the completion of performance of the evaluated contract or order.

Section A

Project Title:

Location:

Description:

Company Name:
Unique Entity ID/Cage Code:
Owner/Project Manager Name:
Email Address:
Start Date:
Completion Date:
Initial Amount:
Final Amount:

Section B

Evaluator

Evaluator Name:
Company/Agency Name:
Address:
POC Email:

Position Held or Function in Relation to Project:

Ratings Overview

Rating: If the rating is Marginal or Unacceptable, please provide additional information in the appropriate block or in the remarks section of this form.

“O”
Outstanding
Performance greatly exceeded the contract requirements.
“A”
Above Average
Performance exceeded the contract requirements.
“S”
Satisfactory
Performance met the contract requirements.
“M”
Marginal
Performance met the minimum contract requirements but

Some material aspects of the contractor’s performance were less than satisfactory.

“U”
Unacceptable
Performance was poor and/or did not satisfy contract requirements.

Questionnaire

Please select the appropriate rating and provide supporting information for the following questions.

1. The relationship between the company and client’s/customer’s contract team:
O

FORMCHECKBOX

A

FORMCHECKBOX

S

FORMCHECKBOX

M

FORMCHECKBOX

U

FORMCHECKBOX

2. Overall corporate management, integrity, reasonableness, and cooperative conduct:

O

FORMCHECKBOX

A

FORMCHECKBOX

S

FORMCHECKBOX

M

FORMCHECKBOX

U

3. Quality control:

O

FORMCHECKBOX

A

FORMCHECKBOX

S

FORMCHECKBOX

M

FORMCHECKBOX

U

4. Ability to meet the performance schedule:

O

FORMCHECKBOX

A

FORMCHECKBOX

S

FORMCHECKBOX

M

FORMCHECKBOX

U

5. Have any cure notices, show cause letters, letter of reprimand, suspension of payment, or termination been issued? If yes, please explain:

Yes

FORMCHECKBOX

No

6. Would you award another contract to the company being evaluated? If no, please explain:

Yes

No

7. Was the customer satisfied with the final product and services? If no, please explain:
Yes

No

8. Has the firm being evaluated been provided an opportunity to discuss or respond to any negative comments or performance ratings? If so, what were the results?

Yes

FORMCHECKBOX

No

9. Overall Rating

O

A

FORMCHECKBOX

S

FORMCHECKBOX

M

FORMCHECKBOX

U

10. Comments

Evaluator Signature

Name

Date:

File details come from the government source that posted it. Updated .