This document contains an itemized bid schedule for a drainage project at the Tishomingo National Fish Hatchery in Oklahoma. The project involves construction of three water control structures including two box culverts and one additional water control structure.

Structure 1 includes items for earthwork, a 10'x8'x20' concrete box culvert, stop log adaptation and materials, road work and surfacing, guard rails, materials testing, mobilization and demobilization, and design, survey and site visits. Structure 2 involves earthwork, a concrete base, a water control structure, culvert materials including delivery and labor, and the same mobilization, testing, and design items. Structure 3 is for another box culvert and includes similar earthwork, structure, road work, testing, and mobilization items. Bids are solicited with a total price required for all three structures. The related federal contract opportunity is solicitation number 140F0221R0008 from the Department of the Interior Fish and Wildlife Service Region 2 for the drainage and water control project at Tishomingo National Fish Hatchery.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE

TISHOMINGO NFH - DRAINAGE PROJECT BID SCHEDULE
ITEMIZED BID SCHEDULE
ITEM NO.BOX CULVERT WATER CONTROL STRUCTURE 1QUANTITYUNITUNIT PRICEAMOUNT
1Earthwork for Box Culvert & ChannelCY$ - 0
2Concrete Box Culvert 10'x8'x20'LF$ - 0
3Stop Log adaptation of box culvertHrs$ - 0
4Stop Log materialsJob$ - 0
5Road work, excavation & surfacingCY$ - 0
6Guard rails at road crossingLF$ - 0
7Materials TestingDays$ - 0
8Mobilization & DemobilizationJob$ - 0
Subtotal$ - 0
Remote Location$ - 0
OH&P$ - 0
Add Bonds & Insurance$ - 0
Design, survey, design site visits$ - 0
STRUCTURE 1 TOTAL$ - 0
ITEM NO.WATER CONTROL STRUCTURE 2
QUANTITYUNITUNIT PRICEAMOUNT
1Earthwork for WCSCY$ - 0
2Concrete BaseCY$ - 0
3WCSLF$ - 0
4Delivery of WCSJob$ - 0
5CulvertLF$ - 0
6Culvert bandsEa$ - 0
7Culvert deliveryJob$ - 0
8Culvert LaborHrs$ - 0
9Materials TestingDays$ - 0
10Mobilization & DemobilizationJob$ - 0
Subtotal$ - 0
Remote Location$ - 0
OH&P$ - 0
Add Bonds & Insurance$ - 0
Design, survey, design site visits$ - 0
STRUCTURE 2 TOTAL$ - 0

BOX CULVERT AT CREEK STRUCTURE 3

ITEM NO.BOX CULVERT WATER CONTROL STRUCTURE 1QUANTITYUNITUNIT PRICEAMOUNT
1Earthwork for Box CulvertCY$ - 0
2Concrete Box Culvert 10'x8'x20'LF$ - 0
3Road/trail work, excavation & surfacingCY$ - 0
4Materials TestingDays$ - 0
5Mobilization & DemobilizationJob$ - 0
Subtotal$ - 0
Remote Location$ - 0
OH&P$ - 0
Add Bonds & Insurance$ - 0
Design, survey, design site visits$ - 0
STRUCTURE 3 TOTAL$ - 0

TOTAL STRUCTURES 1, 2 & 3 $ - 0