This document is a Price Schedule for the DEWA Replace Bushkill Firehouse Roof project. It provides a detailed breakdown of the labor, material, and other direct costs associated with this federal contract opportunity.
The Price Schedule includes line items for labor categories, materials such as shingles, wood trim, and gutters, as well as a 20-yard dumpster. It also includes sections for travel costs, equipment purchases, and other direct costs. The total price for this project is provided as the "FY TOTAL SUBTOTAL" at the bottom of the document.
The related federal contract opportunity is for the DEWA Replace Bushkill Firehouse Roof, solicitation number 140P4524R0026, issued by the Department of the Interior National Park Service Northeast Region. This is a civilian agency contract opportunity.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4524R0026_Amd_0002.pdf | ||
| Sol_140P4524R0026_Amd_0001.pdf | ||
| B08_Solicitation_Bushkill_Firehouse_Roof_DEWA.pdf | ||
| Sol_140P4524R0026.pdf | ||
| B08_Attachment_2_WD_PA20240103_Bushkill_Firehouse_Roof_DEWA.pdf | ||
| B08_Attachment_1_SOW_Bushkill_Firehouse_Roof_DEWA.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Labor Category Hours Rate Amount 1 Prime/Sub
Item Description Quantity Unit Price Total 1 0 $0.00 $0.00 2 0 $0.00 $0.00 3 0 $0.00 $0.00
$0.00
Item Description Quantity Unit Price Total 1 0 $0.00 $0.00 2 0 $0.00 $0.00 3 0 $0.00 $0.00
$0.00
Travel (To/From) No. of Trips Price Per Trip Total 1 0 $0.00 $0.00 2 0 $0.00 $0.00 3 0 $0.00 $0.00
$0.00
Item Description Quantity Unit Price Total 1 shingles 2 wood Trim 3 Gutters, 4 20 YD Dumpster
Item Description Quantity Unit Price Total 1 0 $0.00 $0.00 2 0 $0.00 $0.00 3 0 $0.00 $0.00
$0.00
FY TOTAL
SUBTOTAL
SOFTWARE PURCHASES
SUBTOTAL
OTHER DIRECT COST
REQUIRED TRAVEL: (Not-to-Exceed Amount; Worse Case)
SUBTOTAL
MATERIAL/SUPPLIES: (List Below)
SUBTOTAL
OTHER: (Anything not covered above)
SUBTOTAL
DIRECT LABOR (BURDENED RATES)
SUBTOTAL
EQUIPMENT PURCHASES
Price Schedule
DEWA Replace Bushkill Firehouse Roof
Total
Option Year 1
File details come from the government source that posted it. Updated .