B08_Attachment_3_Drawings_Annex_Roof_FIIS.pdf

PDF 10 MB Posted

Attached to
FIIS REHABILITATE LH ANNEX ROOF
Solicitation number
140P4524R0017
Issued by

About this file

This document appears to be Attachment 3 - Drawings for the FIIS REHABILITATE LH ANNEX ROOF solicitation. The solicitation is for the rehabilitation of the annex roof at Fort Independence Island State Park, issued by the Department of the Interior National Park Service Northeast Region.

The attachment includes detailed engineering drawings and specifications for the roof rehabilitation project, such as roof plans, elevations, details, and material requirements. This information would be used by offerors to develop their technical and pricing proposals in response to the overall solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHEET

DRAWING NO.

PKG. NO.

UNITED STATES

DEPARTMENT OF THE INTERIOR

NATIONAL PARK SERVICE

HACE OF

NAME OF PARK

LOCATION WITHIN PARK

REGION COUNTY STATE

TITLE OF DRAWINGREVISIONMARK SHEET DATE INITA/E FIRM

FIRE ISLAND NATIONAL SEASHORE

FIRE ISLAND LIGHT STATION ANNEX

CONSTRUCTION DOCUMENTS REPLACE CRITICAL EXTERIOR BUILDING SYSTEMS AT WEST WING

ONE SUFFOLK NEW YORK

192771

FIIS

210056

FIRE ISLAND NATIONAL SEASHORE

FIIS 210056

-- COVER SHEET

A-01 ANNEX ROOF PLAN; BIRD'S-EYE & PHOTO VIEWS

A-02 ELEVATIONS & PHOTO DETAILS -- WEST WING

A-03 ENLARGED ROOF PLAN; COPING TILES

A-04 ROOFING, STUCCO CLADDING & ROOF DRAINAGE DETAILS

LIST OF DRAWINGS

NATIONAL PARK SERVICE, HACE/PFCA

INTERIOR REGION 1,

NORTH ATLANTIC - APPALACHIAN

FIRE ISLAND LIGHT STATION ANNEX:

REPLACE CRITICAL EXTERIOR BUILDING SYSTEMS at WEST WING

THIS PROJECT

LIGHT STATION ANNEX, FROM SOUTH

WEST WING OF ANNEX, FROM NORTHWEST

JG

JG A-01

ANNEX ROOF PLAN;

BIRD'S-EYE & PHOTO VIEWS

x

FIIS

210056 2

03/11/24

REPLACE CRITICAL EXTERIOR BUILDING SYSTEMS

AT LIGHT STATION ANNEX BUILDING WEST WING

FIRE ISLAND NATIONAL SEASHORE

192771

EXISTING COPING, NORTHEAST CORNER

NOT TO SCALE

A-01

EXISTING CONDITIONS, LOOKING SOUTH

NOT TO SCALE

A-01

EXISTING PLUMBING VENT

NOT TO SCALE

A-01

EXISTING CONDITIONS -- BUR ROOFING, FLASHING, ETC.

NOT TO SCALE

A-01

EXISTING CONDITIONS -- COPING / CORNER

NOT TO SCALE

A-01

DRAWING NO.

PKG

NO. SHEET

OF ____

SUB SHEET NO.DESIGNED:

CADD

DESIGNED:

TECH. REVIEW:

DATE:

TITLE OF SHEET

GENERAL NOTES:

1. POTENTIAL ASBESTOS HAZARD: ASSUME THAT EXISTING TAR &

GRAVEL BUILT-UP ROOF (BUR) CONTAINS ASBESTOS. PROVIDE

CONTAINMENT, ABATEMENT AND DISPOSAL PROTOCOLS IN

ACCORDANCE WITH ALL APPLICABLE ENVIRONMENTAL LAWS

AND REGULATIONS.

2. ASSUME PARTIAL REPAIR AND/OR IN-KIND REPLACEMENT

OF DAMAGED ROOF SHEATHING; ALLOW 40 SQ. FT.

SCALE OF FEET

8 4 0 8 16

SCALE A

ROOF PLAN1

A-01 SCALE A

BIRD'S-EYE VIEW FROM SOUTHEAST, ILLUSTRATING EXISTING SINGLE-SLOPE ROOF CONFIGURATION2

A-01 NO SCALE

A-02

BIRD'S-EYE VIEW FROM WEST -- PROPOSED NEW ROOFING SYSTEM & VITRIFIED CLAY TILE COPING3

A-01 NO SCALE

REMOVE EXISTING TAR &

GRAVEL BUR ROOFING,

FLASHING & COPING TILES,

COMPLETE, DOWN TO

EXISTING ROOF DECK.

NOTE: TELECOMUNICATIONS

EQUIPMENT AND ASSOCIATED

DUNNAGE & ACCESSORIES WILL BE

REMOVED BY OTHERS..

REPLACE

EXISTING "ROLL-

DOWN" LEAD

VENT FLASHING

WITH SOLDERED

COPPER SLEEVE.

NOTE EXISTING HIGH POINT

NOTE EXISTING LOW SIDE

(WEST)

A-01 4 A-01

A-01

A-01

A-01

MAIN BLOCK ROOF

(N.I.C)

NEW DOUBLE-SLOPE SBS

MODIFIED-BITUMEN ROOF

SYSTEM AT WEST WING,

COMPLETE.

THIS PROJECT

NEW ROOF DRAIN ASSEMBLY AT NW

CORNER, TO MATCH RECONSTRUCTED

ASSEMBLY AT SW CORNER, COMPLETE.

RE-CLAD EXISTING PLUMBING VENT

STACK IN CONJUNCTION WITH NEW

INTEGRATED SBS ROOFING AND

FLASHING. REFER TO DETAIL 7/A-04.

LINK

(N.I.C)

MAIN BLOCK ROOF

(N.I.C)

REPAIR, PATCH &

REFINISH (100%)

STUCCO CLADDING

OF WEST WING,

COMPLETE.

EXISTING WINDOWS

N.I.C.

ABATE, STRIP & REMOVE ALL

EXISTING TAR & GRAVEL BUR

ROOFING, UNDERLAYMENT,

MASTICS AND ASSOCIATED

FLASHING.

JG A-02

ELEVATIONS & PHOTO

DETAILS -- WEST WING

x

FIIS

210056 3

03/11/24

REPLACE CRITICAL EXTERIOR BUILDING SYSTEMS

AT LIGHT STATION ANNEX BUILDING WEST WING

FIRE ISLAND NATIONAL SEASHORE

192771

EXISTING CONDITIONS -- SOUTHEAST CORNER

NOT TO SCALE

A-02

EXISTING CONDITIONS -- WEST FACE

NOT TO SCALE

A-02

EXISTING CONDITIONS -- NORTHEAST CORNER

NOT TO SCALE

A-02

TYPICAL CONDITION AT STUCCO / COPING JUNCTION

NOT TO SCALE

A-02

PKG

NO. SHEET

OF ____

SUB SHEET NO.DESIGNED:

CADD

DESIGNED:

TECH. REVIEW:

DATE:

TITLE OF SHEET

SCALE OF FEET

2 1 0 2 4

SCALE C

SCALE OF FEET

4 2 0 4 8

SCALE B

DRAWING NO.

GENERAL STUCCO REPAIR/REFINISHING NOTES:

1. STUCCO CRACKS ILLUSTRATED ABOVE IN RED REPRESENT

TYPICAL DEFICIENCIES ONLY AND SHOULD NOT BE USED

FOR DETAILED QUANTITY TAKEOFFS.

2. OFFSET CRACKS: RESET OFFSET CLADDING SEGMENTS IF

POSSIBLE. IF UNDERLYING CLAY BLOCKS ARE OFFSET BUT

STRUCTURALLY SOUND, PATCH AND REFINISH STUCCO AT

AND AROUND IRREGULARITIES TO REMAIN.

NORTH ELEVATION3

A-02 SCALE B

WEST ELEVATION2

A-02 SCALE B

SOUTH ELEVATION1

A-02 SCALE B

EAST ELEVATION OF WEST WING4

A-02 SCALE B

REPAIR, PATCH & REFINISH ALL

STUCCO CLADDING AT WEST

WING, INCLUDING WALLS AND

PILASTERS, COMPLETE.

MAIN BLOCK

(N.I.C)

LINK

(N.I.C)

REPAIR, PATCH & REFINISH ALL

STUCCO CLADDING AT WEST

WING, INCLUDING WALLS AND

PILASTERS, COMPLETE.MAIN BLOCK

(N.I.C)

MAIN BLOCK

(N.I.C)

LINK

(N.I.C)

TIMBER BRIDGE

(N.I.C)

MAIN BLOCK ROOF

(N.I.C)MAIN BLOCK ROOF

(N.I.C)

MAIN BLOCK ROOF

(N.I.C)

REPAIR, PATCH &

REFINISH ALL STUCCO

CLADDING AT WEST

WING, INCL. WALLS AND

PILASTERS, COMPLETE.

METERS

(N.I.C)

EXISTING WINDOW

SASH, FRAMES &

TRIM N.I.C.

REPAIR, PATCH & REFINISH

ALL STUCCO CLADDING AT

WEST WING, INCLUDING

WALLS AND PILASTERS,

COMPLETE.

RETAIN & PROTECT EXISTING

WALL FLASHING, TERMINATION

BARS, ETC. AT LINK.

A-02

A02

A-02

RAKE OUT ALL LOOSE & FRIABLE STUCCO AND

MISC. DEBRIS AT MAJOR CRACKS. PREPARE

SUBSTRATES. PATCH HOLES & CRACKS VIA

INJECTION AND/OR HAND-TOOLING, TYPICAL

AT ALL WEST-WING ELEVATIONS.

EXISTING WINDOWS N.I.C.

SCRAPE OFF ALL LOOSE AND/OR PEELING PAINT;

'FEATHER' EDGES OF SOUND, WELL-ADHERED PAINT TO

REMAIN. PREP, PRIME AND PAINT ALL ELEVATIONS, 100%.

RAKE OUT ALL LOOSE & FRIABLE STUCCO AND

MISC. DEBRIS AT MAJOR CRACKS. PREPARE

SUBSTRATES. PATCH HOLES & CRACKS VIA

INJECTION AND/OR HAND-TOOLING, TYPICAL

AT ALL WEST-WING ELEVATIONS.

RESET OFFSET SOFFITS

IF POSSIBLE, TYPICAL.

REMOVE EXISTING CLAY WALL TILE

COPING & ASSOCIATED MORTAR,

COMPLETE. PREP SUBSTRATE FOR

NEW FLASHING & COPING ASSEMBLY.

A-02

A-02

PROVIDE RECONSTRCTED

DRAINAGE ASSEMBLY AT

SOUTHWEST CORNER, TO MATCH

EXISTING ASSEMBLY, COMPLETE.

TREAT EXISTING STUCCO TO

REMAIN WITH BIOCIDE, IN

CONJUNCTION WITH OTHER

SURFACE PREPARATION WORK.

TREAT EXISTING

STUCCO TO REMAIN

WITH BIOCIDE, IN

CONJUNCTION WITH

OTHER SURFACE

PREPARATION WORK,

ALL SIDES.

PREP AND PAINT METAL DOOR

AND FRAME.

JG A-03

ENLARGED ROOF PLAN;

COPING TILES

x

FIIS

210056 4REPLACE CRITICAL EXTERIOR BUILDING SYSTEMS

AT LIGHT STATION ANNEX BUILDING WEST WING

FIRE ISLAND NATIONAL SEASHORE02/20/24

192771

EXISTING "DOUBLE-SLANT" CLAY COPING TILES

NOT TO SCALE

A-03

PKG

NO. SHEET

OF ____

SUB SHEET NO.DESIGNED:

CADD

DESIGNED:

TECH. REVIEW:

DATE:

TITLE OF SHEET

SCALE OF FEET

2 1 0 2 4

SCALE C

SCALE OF FEET

4 2 0 4 8

SCALE B

THREE WALL COPING TILE "CONDITIONS": FULL-SIZE; FIELD-CUT; CORNER UNITS

EST. 6 EA.; V.I.F. 2 LH+2 RH

DRAWING NO.

ENLARGED ROOF PLAN1

A-03 SCALE C

COLOR-CODED WALL COPING TILE CONFIGURATION2

A-03 NO SCALE

KEY: COLOR-CODED WALL COPING TILES3

A-03 NO SCALE

A-04

SLOPE

S

LO

PE

SLOPE

S

LO

PE

RECONSTRUCTED ROOF

DRAINAGE SCUPPER

ASSEMBLY, CONDUCTOR,

LEADER AND ELBOW.

NEW ROOF DRAINAGE

SCUPPER ASSEMBLY,

CONDUCTOR, LEADER AND

ELBOW.

NEW VITRIFIED CLAY WALL

COPING TILE ASSEMBLY,

INCLUDING FULL-,

CORNER- AND FIELD-CUT

INTERLOCKING TILES,

PROPERLY SET IN

MORTAR BED.

RIDGE

TIMBER BRIDGE

(N.I.C)

ROOF BELOW

(N.I.C)

ROOF BELOW

(N.I.C)

A-03

NEW DOUBLE-SLOPE SBS

MODIFIED-BITUMEN ROOF

SYSTEM AT WEST WING,

COMPLETE.

FULLY-FLASHED RIGID CANT

STRIPS, TYPICAL ALL SIDES.

TERMINATE AT TWO

SCUPPERS AS INDICATED;

REFER TO DETAIL 6/A-04.

VA

LL

EY

VALLEY

JG A-04

ROOFING, STUCCO CLADDING &

ROOF DRAINAGE DETAILS

x

192771

FIIS

210056 5

03/11/24

REPLACE CRITICAL EXTERIOR BUILDING SYSTEMS

AT LIGHT STATION ANNEX BUILDING WEST WING

FIRE ISLAND NATIONAL SEASHORE

SBS ROOFING SYSTEM -- CUTAWAY VIEW

NOT TO SCALE

A-04

SCUPPER & CONDUCTOR BOX

NOT TO SCALE

A-04

VIEW OF NEW & RECONSTRUCTED ROOF DRAINAGE ASSEMBLIES

NOT TO SCALE

A-04

TERMINATION BAR WITH COVER & SEALANT BEAD

NOT TO SCALE

A-04

EXISTING SCUPPER & CONDUCTOR BOX; V.I.F.

NOT TO SCALE

A-04

SCUPPER DETAIL

NOT TO SCALE

A-04

FLASHING AT EXISTING PLUMBING VENT

NOT TO SCALE

A-04

DRAWING NO.

PKG

NO. SHEET

OF ____

SUB SHEET NO.DESIGNED:

CADD

DESIGNED:

TECH. REVIEW:

DATE:

TITLE OF SHEETSUB SHEET NO.DESIGNED:DESIGNED:

REPAIR EXISTING 3/4"

PLYWD. DECK AS REQ'D.

SUPPLY & INSTALL EXTRUDED, STAINLESS

STEEL OR ALUMINUM TERMINATION BAR WITH

COVER AND ACCOMMODATION FOR

CONTINUOUS SEALANT BEAD, ALL ROOF-SIDE

FACES OF PARAPET.

CONTINUOUS FILLET-TYPE FLEXIBLE SEALANT

BEAD.

PROVIDE SELF-ADHERED EPDM MEMBRANE FOR

USE AS FLASHING, AS INDICATED.

MORTAR SETTING BED FOR VITRIFIED CLAY

WALL COPING TILES.

PROVIDE NEW DRAINAGE

ASSEMBLY AT NW CORNER,

TO MATCH RECONSTRUCTED

ASSEMBLY AT SW CORNER,

COMPLETE.

PROVIDE CONTINUOUS

SEALANT AT SCUPPER

PENETRATION PERIMETER.

FABRICATE TWO (2)

REPLICAS OF SCUPPER,

CONDUCTOR BOX &

RAIN LEADER.

PROVIDE NEW DRAINAGE ASSEMBLY AT

NORTHWEST CORNER, TO MATCH

RECONSTRUCTED ASSEMBLY AT

SOUTHWEST CORNER, COMPLETE.

PROVIDE RECONSTRCTED

DRAINAGE ASSEMBLY AT

SOUTHWEST CORNER, TO

MATCH EXISTING ASSEMBLY,

COMPLETE.

TREAT BIOLOGICAL STAINS WITH

BIOCIDE. REPAIR, PATCH & REFINISH

(100%) STUCCO CLADDING OF WEST

WING, COMPLETE.

PROVIDE SELF-ADHERED

BASE FLASHING MEMBRANE

& LIQUID-APPLIED SEALANT

AT SCUPPER PENETRATION

PERIMETER.

PROVIDE WALL

PENETRATION, FLASHING

& SCUPPER ASSEMBLY AT

NW CORNER TO MATCH

SW-CORNER ASSEMBLY.

TAPER CANT ASSEMBLY FOR

PROPER RAINWATER DRAINAGE

TO AND THROUGH SCUPPER,

TYPICAL FOR 2.

NEW VITRIFIED CLAY TILE COPING ASSEMBLY

EXISTING STUCCO-CLAD

HOLLOW CLAY TILE WALL

& PILASTER ASSEMBLY

ELASTOMERIC ADHESIVE

2-1/2" THICK RIGID

POLYISOCYANURATE (CLOSED

CELL) BOARD INSULATION

RIGID COVER BOARD

TYPICAL CANT STRIP

SBS INTERPLY

SBS BASE FLASHING

SBS CAP PLY WITH

GRANULAR SURFACE

SBS CAP FLASHING

SBS BASE PLY

ADHESIVE BLEED, IN ACCORDANCE WITH SBS

SYSTEM MANUFACTURER'S INSTALLATION

INSTRUCTIONS

EXIST'G. ROOF

FRAMING (VIF)

PREP PIPE STACK EXPOSED

SURFACE AND INSTALL

LIQUID-APPLIED FLASHING,

COMPATIBLE WITH SBS

MEMBRANE SYSTEM,

COMPLETE, INCLUDING

PRIMER, REINFORCED-

FABRIC BASE PLIES.

PROVIDE NEW ROLL-DOWN

SOLDERED COPPER SLEEVE

AT EXISTING VENT PIPE

STACK TO REMAIN.

SBS BASE PLY AND

INTERPLY MEMBRANES

SBS CAP PLY WITH

GRANULAR SURFACE

A-04

1" M

IN

File details come from the government source that posted it. Updated .