These are Final Construction Documents for a stabilization project at Vicksburg National Military Park in Mississippi. The documents detail ground anchor stabilization, slope remediation, and landscape restoration across multiple areas with challenging terrain. The project involves installing multiple rows of ground anchors (6 rows with varying strand configurations), horizontal drains, erosion control measures, and a comprehensive revegetation plan.

The technical specifications include precise geotechnical requirements such as soil nail walls, anchor trench details, drainage systems, and specific planting guidelines. The construction will involve excavation, grading, installing reinforced concrete anchor plates, geotextile fabrics, drainage gravel, and replanting with native vegetation. The project area includes approximately 1,751 square feet of wetland and 6,774 square feet of upland zones, with detailed planting specifications for trees, shrubs, and herbaceous ground cover. The documents provide extensive cross-section diagrams, anchor placement coordinates, and technical details for ensuring slope stability and environmental restoration.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USS CAIRO

MUSEUM

NATIONAL

CEMETERY

BUS

ILLINOIS

CENTRAL

GULF

RAILROAD

FORT

GARROTT

SHIRLEY

HOUSE

OPENWOOD STREET

STREET

MAIN

EAST

CLAY STREET

GROVE STREET

M

IS

S

IO

N

R O

A D

SKY

FARM

AVENUE

JACKSON ROAD

W A

S H

IN

G

TO

N

S

TR

E E

T

D R

IV

E

FO

R

T

HIL

L

M

IS

S

IS

S

IP

P I

LO

U

IS

IA

N A

DOWNTOWN

VICKSBURG

UNION

AVENUE GRANT AVEN UE

U N

IO

N

A V

E N

U E

C O

N

FE

E R

A T

E D

AVENUE

HEBREW

CEMETERY

C H

E R

R Y

S T

R E

E T

BALDWIN FERRY

RO

AD

HQ. & V.C.

MEMORIAL

ARCH

TO MISSISSIPPI

RIVER BRIDGE

TO

JACKSON,

MISSISSIPPI

TO 61

TO

LELAND,

MISSISSIPPI

YAZOO CANAL

(OLD MISSISSIPPI RIVER)

THIS PROJECT

VICKSBURG JACKSON

GREENVILLE

MONROE

HATTIESBURG

NATCHEZ

McCOMB

BROOKHAVEN

CRYSTAL

SPRINGS

YAZOO

CITY

GREENWOOD

WINONA

MONTICELLO

CROSSETT

LAKE

PROVIDENCE

ARKANSAS

LOUISIANA

LELAND

VICKSBURG

NATIONAL

MILITARY

PARK

MISSISSIPPI

LOUISIANA

E

W

MISSISSIPPI

RIVER

ALEXANDRIA

FINAL CONSTRUCTION DOCUMENTS _ VICK 209252

C 6.

D W

G

SCALE OF MILES

20 0 20

MONUMENTS

INFORMATION CENTER

PICNIC AREA

RANGER STATION

PARK HEADQUARTERS

VISITOR CENTER

HQ.

V.C.

STATE LINE

CREEK OR RIVER

PAVED ROAD

PARK BOUNDARY

LEGEND

SCALE OF METERS

SCALE OF FEET

1,000

0 2,000

250 500

1,000

SHEET INDEX

1 COVER SHEET

2 C1 GENERAL NOTES

3 C2 PROJECT LOCATION

4 C3 EXISTING CONDITIONS PLAN

5 C4 CLEARING AND GRADING CONSTRUCTION LIMITS, AND ACCESS

ROAD AND LAYDOWN PLAN

6 C5 HORIZONTAL DRAINS, GRADING AND REMEDIATION PLAN

7 C6 ANCHOR LAYOUT PLAN

8 C7 ANCHOR ROW PROFILES

9 C8 ANCHOR ROW PROFILES

10 C9 ANCHOR ROW PROFILES

12 C10 TYPICAL GROUND ANCHOR STABILIZATION CROSS SECTION

12 C11 TYPICAL GROUND ANCHOR STABILIZATION CROSS SECTION

13 C12 TYPICAL GROUND ANCHOR STABILIZATION CROSS SECTION

14 C13 TYPICAL GROUND ANCHOR STABILIZATION CROSS SECTION

15 C14 GROUND ANCHOR DETAILS

16 C15 GROUND ANCHOR DETAILS

17 C16 DRAINAGE AND SLOPE FACING DETAILS

18 C17 PLANTING PLAN

SHEET

NUMBER

SUBSHEET

NUMBER

SHEET

NAME

PMIS - 209252

AutoCAD SHX Text

AutoCAD SHX Text

COVER SHEET

AutoCAD SHX Text

STABILIZE MINT SPRING BAYOU VICKSBURG NATIONAL MILITARY PARK

AutoCAD SHX Text

SUB SHEET NO

AutoCAD SHX Text

A/E FIRM

AutoCAD SHX Text

PRIME:

AutoCAD SHX Text

SUB:

AutoCAD SHX Text

DRAWING NO.

AutoCAD SHX Text

PMIS/PKG NO.

AutoCAD SHX Text

SHEET

AutoCAD SHX Text

OF

AutoCAD SHX Text

TITLE OF SHEET

AutoCAD SHX Text

DATE:

AutoCAD SHX Text

DESIGNED:

AutoCAD SHX Text

TECH. REVIEW:

AutoCAD SHX Text

JAN 4, 2024

AutoCAD SHX Text 132934

AutoCAD SHX Text

AutoCAD SHX Text 04 JANUARY 2024 AUTOCAD2024 P:\VICK\209252\FINAL CDs\CIVIL\

AutoCAD SHX Text

AutoCAD SHX Text

VHB

AutoCAD SHX Text

WILLIAMSBURG, VA

AutoCAD SHX Text 209252

AutoCAD SHX Text

TERRACON

AutoCAD SHX Text

JACKSON, MS

AutoCAD SHX Text

MWF

AutoCAD SHX Text

TTA

AutoCAD SHX Text

TMK

AutoCAD SHX Text

VICKSBURG NATIONAL

AutoCAD SHX Text

MILITARY PARK

FINAL CONSTRUCTION DOCUMENTS _ VICK 209252

C 1.

D W G

AutoCAD SHX Text

AutoCAD SHX Text C1

AutoCAD SHX Text

GENERAL NOTES

AutoCAD SHX Text

STABILIZE MINT SPRING BAYOU VICKSBURG NATIONAL MILITARY PARK

AutoCAD SHX Text

SUB SHEET NO

AutoCAD SHX Text

A/E FIRM

AutoCAD SHX Text

PRIME:

AutoCAD SHX Text

SUB:

AutoCAD SHX Text

DRAWING NO.

AutoCAD SHX Text

PMIS/PKG NO.

AutoCAD SHX Text

SHEET

AutoCAD SHX Text

OF

AutoCAD SHX Text

TITLE OF SHEET

AutoCAD SHX Text

DATE:

AutoCAD SHX Text

DESIGNED:

AutoCAD SHX Text

TECH. REVIEW:

AutoCAD SHX Text

JAN 4, 2024

AutoCAD SHX Text 132934

AutoCAD SHX Text

AutoCAD SHX Text 04 JANUARY 2024 AUTOCAD2024 P:\VICK\209252\FINAL CDs\CIVIL\

AutoCAD SHX Text

AutoCAD SHX Text

VHB

AutoCAD SHX Text

WILLIAMSBURG, VA

AutoCAD SHX Text 209252

AutoCAD SHX Text

TERRACON

AutoCAD SHX Text

JACKSON, MS

AutoCAD SHX Text

MWF

AutoCAD SHX Text

TTA

AutoCAD SHX Text

TMK

AutoCAD SHX Text GENERAL NOTES AND SOIL DESIGN PARAMETERS A. ALL MATERIALS AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND ALL MATERIALS AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND ALL MATERIALS AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND MATERIALS AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND MATERIALS AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND WORKMANSHIP SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND BE IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND IN ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND ACCORDANCE WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND WITH THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND THE REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND REQUIREMENTS OF THESE PLANS, DETAIL DRAWINGS, AND OF THESE PLANS, DETAIL DRAWINGS, AND OF THESE PLANS, DETAIL DRAWINGS, AND THESE PLANS, DETAIL DRAWINGS, AND THESE PLANS, DETAIL DRAWINGS, AND PLANS, DETAIL DRAWINGS, AND PLANS, DETAIL DRAWINGS, AND DETAIL DRAWINGS, AND DETAIL DRAWINGS, AND DRAWINGS, AND DRAWINGS, AND AND AND CONSTRUCTION SPECIFICATIONS. B. CONSTRUCTION SPECIFICATIONS: CONSTRUCTION SPECIFICATIONS: 1. SECTION 033055 - PRECAST CONCRETE (OFFSITE) SECTION 033055 - PRECAST CONCRETE (OFFSITE) 2. SECTION 310000 - EARTHWORK SECTION 310000 - EARTHWORK 3. SECTION 311000 - SITE CLEARING SECTION 311000 - SITE CLEARING 4. SECTION 312500 - EROSION & SEDIMENTATION CONTROLS SECTION 312500 - EROSION & SEDIMENTATION CONTROLS 5. SECTION 314119 - HORIZONTAL DRAINS AND ANCHOR BENCH DRAINS SECTION 314119 - HORIZONTAL DRAINS AND ANCHOR BENCH DRAINS 6. SECTION 315113 - GROUND ANCHOR SYSTEMS SECTION 315113 - GROUND ANCHOR SYSTEMS 7. SECTION 329220 - SEEDING SECTION 329220 - SEEDING 8. SECTION 329300 - PLANTS SECTION 329300 - PLANTS - PLANTS C. SOIL DESIGN PARAMETERS: SOIL DESIGN PARAMETERS: SOILS: UNIT WEIGHT: COHESION: FRICTION ANGLE: UNIT WEIGHT: COHESION: FRICTION ANGLE: COHESION: FRICTION ANGLE: FRICTION ANGLE: LEAN CLAY LOESS 120 PCF 150 PSF 30 120 PCF 150 PSF 30 150 PSF 30 30°SILT LOESS 120 PCF 25 PSF 33 120 PCF 25 PSF 33 25 PSF 33 33°UPPER SM 120 PCF 0 PSF 34 120 PCF 0 PSF 34 0 PSF 34 34°UPPER CL 120 PCF 50 PSF 29 120 PCF 50 PSF 29 50 PSF 29 29°UPPER CH 125 PCF 100 PSF 25 125 PCF 100 PSF 25 100 PSF 25 25°LOWER CH 130 PCF 200 PSF 26 130 PCF 200 PSF 26 200 PSF 26 26°LOWER CL 120 PCF 150 PSF 31 120 PCF 150 PSF 31 150 PSF 31 31°LOWER SM 130 PCF 25 PSF 38 130 PCF 25 PSF 38 25 PSF 38 38°COLLUVIUM 115 PCF 0 PSF 30 115 PCF 0 PSF 30 0 PSF 30 30°D. CLEARING, CONSTRUCTION LIMITS, AND ACCESS ROAD AND LAYDOWN AREA CLEARING, CONSTRUCTION LIMITS, AND ACCESS ROAD AND LAYDOWN AREA 1. CONTRACTOR SHALL ACQUIRE THE NECESSARY ENTRANCE PERMITS FROM THE CITY/MISSISSIPPI DEPARTMENT OF TRANSPORTATION. CONTRACTOR SHALL ACQUIRE THE NECESSARY ENTRANCE PERMITS FROM THE CITY/MISSISSIPPI DEPARTMENT OF TRANSPORTATION. 2. CONTRACTOR PERSONNEL ACCESS SHALL BE FROM NORTH WASHINGTON STREET. CONTRACTOR PERSONNEL ACCESS SHALL BE FROM NORTH WASHINGTON STREET. 3. STANDARD TRAFFIC DIRECTIONAL (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED STANDARD TRAFFIC DIRECTIONAL (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED TRAFFIC DIRECTIONAL (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED TRAFFIC DIRECTIONAL (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED DIRECTIONAL (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED DIRECTIONAL (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED (GUIDE) SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED SIGNS/CONTROLS SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED SHALL BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED BE REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED REMOVED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED OR NEW SIGNS/CONTROLS SHALL BE FURNISHED NEW SIGNS/CONTROLS SHALL BE FURNISHED NEW SIGNS/CONTROLS SHALL BE FURNISHED SIGNS/CONTROLS SHALL BE FURNISHED SIGNS/CONTROLS SHALL BE FURNISHED SHALL BE FURNISHED SHALL BE FURNISHED BE FURNISHED BE FURNISHED FURNISHED FURNISHED AND INSTALLED AS DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON INSTALLED AS DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON INSTALLED AS DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON INSTALLED AS DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON AS DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON AS DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON DIRECTED BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON BY CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON CONTRACTING OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON OFFICER (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON (CO) FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON FOR SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON SMOOTH RUNNING OF THE TRAFFIC ON NORTH WASHINGTON RUNNING OF THE TRAFFIC ON NORTH WASHINGTON RUNNING OF THE TRAFFIC ON NORTH WASHINGTON OF THE TRAFFIC ON NORTH WASHINGTON OF THE TRAFFIC ON NORTH WASHINGTON THE TRAFFIC ON NORTH WASHINGTON THE TRAFFIC ON NORTH WASHINGTON TRAFFIC ON NORTH WASHINGTON TRAFFIC ON NORTH WASHINGTON ON NORTH WASHINGTON ON NORTH WASHINGTON NORTH WASHINGTON NORTH WASHINGTON WASHINGTON WASHINGTON STREET DURING THE CONSTRUCTION PERIOD. 4. CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING ALL EXISTING UTILITIES AND SURVEY CONTROL. CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING ALL EXISTING UTILITIES AND SURVEY CONTROL. 5. PRIOR TO ANY LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, PRIOR TO ANY LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, TO ANY LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, TO ANY LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, ANY LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, ANY LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, LAND DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, DISTURBING ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, ACTIVITIES, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, THE BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, BOUNDARY OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, OF THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, THE CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, CLEARING LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, LIMITS, STAGING AREA, CONSTRUCTION ACCESS ROAD, STAGING AREA, CONSTRUCTION ACCESS ROAD, STAGING AREA, CONSTRUCTION ACCESS ROAD, AREA, CONSTRUCTION ACCESS ROAD, AREA, CONSTRUCTION ACCESS ROAD, CONSTRUCTION ACCESS ROAD, CONSTRUCTION ACCESS ROAD, ACCESS ROAD, ACCESS ROAD, ROAD, ROAD, CONSTRUCTION LIMITS, AND WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION LIMITS, AND WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION LIMITS, AND WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION AND WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION AND WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION WETLAND SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION SHOWN ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION ON THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION THIS PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION PLAN SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION SHALL BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION BE DELINEATED IN THE FIELD. DURING THE CONSTRUCTION DELINEATED IN THE FIELD. DURING THE CONSTRUCTION DELINEATED IN THE FIELD. DURING THE CONSTRUCTION IN THE FIELD. DURING THE CONSTRUCTION IN THE FIELD. DURING THE CONSTRUCTION THE FIELD. DURING THE CONSTRUCTION THE FIELD. DURING THE CONSTRUCTION FIELD. DURING THE CONSTRUCTION FIELD. DURING THE CONSTRUCTION DURING THE CONSTRUCTION DURING THE CONSTRUCTION DURING THE CONSTRUCTION THE CONSTRUCTION THE CONSTRUCTION CONSTRUCTION CONSTRUCTION PERIOD, NO ACTIVITIES ARE PERMITTED TO OCCUR BEYOND THE CONSTRUCTION LIMITS. 6. CONTRACTOR SHALL IDENTIFY, MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND CONTRACTOR SHALL IDENTIFY, MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND SHALL IDENTIFY, MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND SHALL IDENTIFY, MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND IDENTIFY, MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND IDENTIFY, MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND MARK, AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND CLEAR THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND THOSE TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND TREES WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND WHICH ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND ARE WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND WITHIN THE CONSTRUCTION ACCESS AND CLEARING AND THE CONSTRUCTION ACCESS AND CLEARING AND THE CONSTRUCTION ACCESS AND CLEARING AND CONSTRUCTION ACCESS AND CLEARING AND CONSTRUCTION ACCESS AND CLEARING AND ACCESS AND CLEARING AND ACCESS AND CLEARING AND AND CLEARING AND AND CLEARING AND CLEARING AND CLEARING AND AND AND CONSTRUCTION LIMITS. 7. WETLANDS SHALL BE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE WETLANDS SHALL BE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE SHALL BE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE SHALL BE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE BE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE BE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE CLEARLY MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE MARKED, STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE STAKED AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE AND LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE LIMITS ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE ESTABLISHED AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE AND CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE CLEARLY MARKED IN THE FIELD WITH HIGHLY VISIBLE MARKED IN THE FIELD WITH HIGHLY VISIBLE MARKED IN THE FIELD WITH HIGHLY VISIBLE IN THE FIELD WITH HIGHLY VISIBLE IN THE FIELD WITH HIGHLY VISIBLE THE FIELD WITH HIGHLY VISIBLE THE FIELD WITH HIGHLY VISIBLE FIELD WITH HIGHLY VISIBLE FIELD WITH HIGHLY VISIBLE WITH HIGHLY VISIBLE WITH HIGHLY VISIBLE HIGHLY VISIBLE HIGHLY VISIBLE VISIBLE VISIBLE SIGNS AND FLAGGING. 8. ALL WORK AREA SHALL BE OUTSIDE OF WETLAND BOUNDARIES OR ACCORDING TO THE PLAN. ALL WORK AREA SHALL BE OUTSIDE OF WETLAND BOUNDARIES OR ACCORDING TO THE PLAN. 9. ALL BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND ALL BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND STAGING AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND AREA, GRAVEL CONSTRUCTION ACCESS DRIVE, AND GRAVEL CONSTRUCTION ACCESS DRIVE, AND GRAVEL CONSTRUCTION ACCESS DRIVE, AND CONSTRUCTION ACCESS DRIVE, AND CONSTRUCTION ACCESS DRIVE, AND ACCESS DRIVE, AND ACCESS DRIVE, AND DRIVE, AND DRIVE, AND AND AND ALONG PERIMETER OF THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR PERIMETER OF THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR PERIMETER OF THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR OF THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR OF THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR THE CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR CONSTRUCTION AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR AREA MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR MUST BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR BE IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR IN-PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR AND APPROVED IN AN INITIAL INSPECTION, PRIOR AND APPROVED IN AN INITIAL INSPECTION, PRIOR APPROVED IN AN INITIAL INSPECTION, PRIOR APPROVED IN AN INITIAL INSPECTION, PRIOR IN AN INITIAL INSPECTION, PRIOR IN AN INITIAL INSPECTION, PRIOR AN INITIAL INSPECTION, PRIOR AN INITIAL INSPECTION, PRIOR INITIAL INSPECTION, PRIOR INITIAL INSPECTION, PRIOR INSPECTION, PRIOR INSPECTION, PRIOR PRIOR PRIOR TO COMMENCEMENT OF CONSTRUCTION ACTIVITIES. 10. SEDIMENT BARRIERS APPROVED FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR SEDIMENT BARRIERS APPROVED FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR BARRIERS APPROVED FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR BARRIERS APPROVED FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR APPROVED FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR APPROVED FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR FOR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR USE SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR SHALL INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR INCLUDE TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR TEMPORARY SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR SILT FENCE, TEMPORARY EROSION CHECKS USING HAY OR FENCE, TEMPORARY EROSION CHECKS USING HAY OR FENCE, TEMPORARY EROSION CHECKS USING HAY OR TEMPORARY EROSION CHECKS USING HAY OR TEMPORARY EROSION CHECKS USING HAY OR EROSION CHECKS USING HAY OR EROSION CHECKS USING HAY OR CHECKS USING HAY OR CHECKS USING HAY OR USING HAY OR USING HAY OR HAY OR HAY OR OR OR STRAW BALES OR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR BALES OR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR BALES OR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR OR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR OR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR OTHER APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR APPROVED MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR MATERIALS CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR CONSTRUCTED AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR AS PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR PER THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR THE CONSTRUCTION DRAWINGS OR SPECIFICATION FOR CONSTRUCTION DRAWINGS OR SPECIFICATION FOR CONSTRUCTION DRAWINGS OR SPECIFICATION FOR DRAWINGS OR SPECIFICATION FOR DRAWINGS OR SPECIFICATION FOR OR SPECIFICATION FOR OR SPECIFICATION FOR SPECIFICATION FOR SPECIFICATION FOR FOR FOR EROSION AND SEDIMENTATION CONTROLS. 11. CONSTRUCTION ENTRANCE SHALL BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE CONSTRUCTION ENTRANCE SHALL BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE ENTRANCE SHALL BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE ENTRANCE SHALL BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE SHALL BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE SHALL BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE BE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE INSTALLED AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE AT THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE BEGINNING OF THE CONSTRUCTION AND MAINTAINED DURING THE OF THE CONSTRUCTION AND MAINTAINED DURING THE OF THE CONSTRUCTION AND MAINTAINED DURING THE THE CONSTRUCTION AND MAINTAINED DURING THE THE CONSTRUCTION AND MAINTAINED DURING THE CONSTRUCTION AND MAINTAINED DURING THE CONSTRUCTION AND MAINTAINED DURING THE AND MAINTAINED DURING THE AND MAINTAINED DURING THE MAINTAINED DURING THE MAINTAINED DURING THE DURING THE DURING THE THE THE CONSTRUCTION OF THE PROJECT. 12. CONSTRUCT A 20 FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION CONSTRUCT A 20 FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION A 20 FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION A 20 FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION 20 FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION 20 FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION FOOT WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION WIDE CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION CONSTRUCTION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION ACCESS ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION ROAD AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION AS PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION PER THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION THE CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION CONSTRUCTION DRAWINGS. APPLY SOIL STABILIZATION DRAWINGS. APPLY SOIL STABILIZATION DRAWINGS. APPLY SOIL STABILIZATION APPLY SOIL STABILIZATION APPLY SOIL STABILIZATION APPLY SOIL STABILIZATION SOIL STABILIZATION SOIL STABILIZATION STABILIZATION STABILIZATION MEASURES IMMEDIATELY ON ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE IMMEDIATELY ON ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE IMMEDIATELY ON ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ON ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ON ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ALL DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE DISTURBED AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE AREAS FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE FOR ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ALL CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE CONSTRUCTION ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ACCESS ROAD. CONSTRUCTION OF A CULVERT MAY BE ROAD. CONSTRUCTION OF A CULVERT MAY BE ROAD. CONSTRUCTION OF A CULVERT MAY BE CONSTRUCTION OF A CULVERT MAY BE CONSTRUCTION OF A CULVERT MAY BE CONSTRUCTION OF A CULVERT MAY BE OF A CULVERT MAY BE OF A CULVERT MAY BE A CULVERT MAY BE A CULVERT MAY BE CULVERT MAY BE CULVERT MAY BE MAY BE MAY BE BE BE REQUIRED BENEATH THE ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST BENEATH THE ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST BENEATH THE ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST THE ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST THE ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST ACCESS DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST DRIVE. IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST IF NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST NEEDED IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST IT SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST SHALL BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST BE INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST INSTALLED BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST BY THE CONTRACTOR AT NO ADDITIONAL TIME OR COST THE CONTRACTOR AT NO ADDITIONAL TIME OR COST THE CONTRACTOR AT NO ADDITIONAL TIME OR COST CONTRACTOR AT NO ADDITIONAL TIME OR COST CONTRACTOR AT NO ADDITIONAL TIME OR COST AT NO ADDITIONAL TIME OR COST AT NO ADDITIONAL TIME OR COST NO ADDITIONAL TIME OR COST NO ADDITIONAL TIME OR COST ADDITIONAL TIME OR COST ADDITIONAL TIME OR COST TIME OR COST TIME OR COST OR COST OR COST COST COST TO THE GOVERNMENT. 13. ESTABLISH A LAYDOWN AND STAGING AREA IN A LOCATION SHOWN ON THE PLANS. ESTABLISH A LAYDOWN AND STAGING AREA IN A LOCATION SHOWN ON THE PLANS. 14. RUN-ON AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO RUN-ON AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SHALL BE IN PLACE AND FUNCTIONING PRIOR TO BE IN PLACE AND FUNCTIONING PRIOR TO BE IN PLACE AND FUNCTIONING PRIOR TO IN PLACE AND FUNCTIONING PRIOR TO IN PLACE AND FUNCTIONING PRIOR TO PLACE AND FUNCTIONING PRIOR TO PLACE AND FUNCTIONING PRIOR TO AND FUNCTIONING PRIOR TO AND FUNCTIONING PRIOR TO FUNCTIONING PRIOR TO FUNCTIONING PRIOR TO PRIOR TO PRIOR TO TO TO BEGINNING SUBSTANTIAL CONSTRUCTION ACTIVITIES. 15. PRESERVE EXISTING VEGETATION WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE PRESERVE EXISTING VEGETATION WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE EXISTING VEGETATION WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE EXISTING VEGETATION WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE VEGETATION WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE VEGETATION WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE WHEN PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE PRACTICAL AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE AND RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE RE-VEGETATE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE OPEN AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE AREAS. RE-VEGETATE OPEN AREAS WHEN PRACTICABLE RE-VEGETATE OPEN AREAS WHEN PRACTICABLE RE-VEGETATE OPEN AREAS WHEN PRACTICABLE RE-VEGETATE OPEN AREAS WHEN PRACTICABLE OPEN AREAS WHEN PRACTICABLE OPEN AREAS WHEN PRACTICABLE AREAS WHEN PRACTICABLE AREAS WHEN PRACTICABLE WHEN PRACTICABLE WHEN PRACTICABLE PRACTICABLE PRACTICABLE BEFORE AND AFTER GRADING OR CONSTRUCTION PER SPECIFICATIONS.

E. CONSTRUCTION NOTES CONSTRUCTION NOTES 1. CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING ALL UTILITIES AND SURVEY CONTROL. CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING ALL UTILITIES AND SURVEY CONTROL. 2. ALL BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND ALL BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND BASE EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND EROSION AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND SEDIMENT CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND CONTROL MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND MEASURES ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND ALONG THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND THE STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND STAGING AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND AREA, GRAVEL CONSTRUCTION ACCESS ROAD, AND GRAVEL CONSTRUCTION ACCESS ROAD, AND GRAVEL CONSTRUCTION ACCESS ROAD, AND CONSTRUCTION ACCESS ROAD, AND CONSTRUCTION ACCESS ROAD, AND ACCESS ROAD, AND ACCESS ROAD, AND ROAD, AND ROAD, AND AND AND ALONG PERIMETER OF THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR PERIMETER OF THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR PERIMETER OF THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR OF THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR OF THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR THE CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR CONSTRUCTION AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR AREA MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR MUST BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR BE IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR IN PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR PLACE, FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR FUNCTIONAL, AND APPROVED IN AN INITIAL INSPECTION, PRIOR AND APPROVED IN AN INITIAL INSPECTION, PRIOR AND APPROVED IN AN INITIAL INSPECTION, PRIOR APPROVED IN AN INITIAL INSPECTION, PRIOR APPROVED IN AN INITIAL INSPECTION, PRIOR IN AN INITIAL INSPECTION, PRIOR IN AN INITIAL INSPECTION, PRIOR AN INITIAL INSPECTION, PRIOR AN INITIAL INSPECTION, PRIOR INITIAL INSPECTION, PRIOR INITIAL INSPECTION, PRIOR INSPECTION, PRIOR INSPECTION, PRIOR PRIOR PRIOR TO COMMENCMENT OF CONSTRUCTION ACTIVITIES. 3. RUN-ON AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO RUN-ON AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO RUN-OFF CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO CONTROL SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SUCH AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AS SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SLOPE DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO AND WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO WEEP DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO DRAINS SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SHALL BE IN PLACE AND FUNCTIONING PRIOR TO SHALL BE IN PLACE AND FUNCTIONING PRIOR TO BE IN PLACE AND FUNCTIONING PRIOR TO BE IN PLACE AND FUNCTIONING PRIOR TO IN PLACE AND FUNCTIONING PRIOR TO IN PLACE AND FUNCTIONING PRIOR TO PLACE AND FUNCTIONING PRIOR TO PLACE AND FUNCTIONING PRIOR TO AND FUNCTIONING PRIOR TO AND FUNCTIONING PRIOR TO FUNCTIONING PRIOR TO FUNCTIONING PRIOR TO PRIOR TO PRIOR TO TO TO BEGINNING SUBSTANTIAL CONSTRUCTION ACTIVITIES. 4. ALL ORGANIC MATTER, VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE ALL ORGANIC MATTER, VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE ORGANIC MATTER, VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE ORGANIC MATTER, VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE MATTER, VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE MATTER, VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE VEGETATION, SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE SLIDE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE DEBRIS AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE AND OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE OTHER UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE UNSUITABLE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE MATERIALS SHALL BE STRIPPED OFF AND THE SUBGRADE SHALL BE STRIPPED OFF AND THE SUBGRADE SHALL BE STRIPPED OFF AND THE SUBGRADE BE STRIPPED OFF AND THE SUBGRADE BE STRIPPED OFF AND THE SUBGRADE STRIPPED OFF AND THE SUBGRADE STRIPPED OFF AND THE SUBGRADE OFF AND THE SUBGRADE OFF AND THE SUBGRADE AND THE SUBGRADE AND THE SUBGRADE THE SUBGRADE THE SUBGRADE SUBGRADE SUBGRADE COMPACTED PER THE DRAWINGS OR SPECIFICATIONS FOR EARTHWORK. 5. PERFORATED BURIED HORIZONTAL DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR PERFORATED BURIED HORIZONTAL DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR BURIED HORIZONTAL DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR BURIED HORIZONTAL DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR HORIZONTAL DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR HORIZONTAL DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR DRAINS IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR IN THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR THE NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR NATIVE SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR SOILS SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR SHALL BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR BE INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR INSTALLED AS PER THE DRAWINGS OR SPECIFICATIONS FOR AS PER THE DRAWINGS OR SPECIFICATIONS FOR AS PER THE DRAWINGS OR SPECIFICATIONS FOR PER THE DRAWINGS OR SPECIFICATIONS FOR PER THE DRAWINGS OR SPECIFICATIONS FOR THE DRAWINGS OR SPECIFICATIONS FOR THE DRAWINGS OR SPECIFICATIONS FOR DRAWINGS OR SPECIFICATIONS FOR DRAWINGS OR SPECIFICATIONS FOR OR SPECIFICATIONS FOR OR SPECIFICATIONS FOR SPECIFICATIONS FOR SPECIFICATIONS FOR FOR FOR DRAINAGE SYSTEM. 6.