About this file

This statement of work outlines requirements for the purchase and delivery of road chips for Yellowstone National Park. The National Park Service Intermountain Region seeks to procure 6000 tons of blended and washed chip sealing aggregate to be delivered to the Norris Pit location by July 3rd, 2024. The material must meet specified gradation and composition standards and is subject to government testing. Successful offerors must have an approved weed management plan and pass an annual pit inspection. Delivery vehicles are restricted to dump trucks and trailers under 75 feet, and must be pressure washed and inspected for invasive species at park entrances. The contractor will provide delivery manifests and is responsible for adhering to park traffic regulations and reworking or replacing noncompliant material.

View the file

Other files for this federal contract opportunity

Other files attached to Purchase Road Chips for Yellowstone National Park, newest first.
File Type Posted
B08_Attachment_2_YNP_Gravel_Pit_Inspections_Report_2022-2023.pdf PDF
Sol_140P1424Q0034.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Chip Sealing Chips, Yellowstone National Park FY24

Statement of Work:

Quantity: 6000 tons

Delivery Location: Norris Pit, located 21 miles south of Mammoth Hot Springs WY 82190- and 1-mile East of Norris junction.

Period of Performance: May 20th to July 3rd, 2024

Specifications:

Cover material shall meet the requirements of the following table of gradations. Blended and washed.

Aggregation Gradation Table:

Sieve Size Percent Passing by Weight

3/8” 99% No. 4 15/30% No. 8 0/5% No. 200 0/2%

• The composite aggregate must not have adherent films of clay, vegetable matter, frozen lumps, or other extraneous matter that prevents thorough coating with bituminous material.

Bituminous material must remain adhered to the material upon contact with water. No combination of shale, clay, coal, or soft particles shall exceed 1.5 percent.

• The material shall have a wear not to exceed 30 percent at 500 revolutions.

• A minimum of 70 percent by weight of the coarse aggregate for Grades 1A through 4A must have at least one fractured face. A minimum of 70 percent by weight of the coarse aggregate must have at least one fractured face.

Measurement and Payment:

• The contractor shall furnish weigh tickets from state certified scales for each delivery made.

• Payment will be made on actual quantities received.

Testing:

• The contractor shall have test samples submitted to the Government for suitability evaluation at least two (2) weeks prior to the actual delivery for acceptance of the cover aggregate.

• Government may require additional material testing if specifications are suspect.

• Material must meet the specified gradation at all stages of delivery.

• The awarded contractor will be responsible for reworking or replacing material to meet specifications if it fails testing during the delivery of material.

Vegetation Management:

• The control of noxious weeds shall be achieved through a weed management plan. All parties submitting offers for sand and gravel must have a current weed management plan that has been approved by the local county weed board and Yellowstone National Park (Park).

• All plans require one annual inspection by Park staff during the growing season (June – August) prior to sale of material. Parties submitting offers must provide proof of the most recent weed inspection by Park staff. (Current Pit inspection report from Yellowstone National Park Provided as Attachment 2)

• The weed inspection will designate a pit in one of three rating categories: acceptable, conditionally acceptable, or unacceptable. Sand and gravel from a pit designated as unacceptable can be used if the material is heat treated to 300 degrees Fahrenheit and promptly transported from the quarry to the Park or a pre-approved weed free storage area to prevent possible weed contamination.

Hauling:

• All vehicles and equipment to be used in Yellowstone National Park shall be thoroughly pressure washed prior to arrival.

• Equipment shall be inspected at the appropriate Park entrance station by a designated Park employee and only clean equipment shall be permitted into the Park.

• Particular attention must be shown to the under carriage and any surface where soil containing exotic weed seeds may exist.

• All loaded trucks and trailer shall be covered (tarped) when loaded. These efforts are critical to prevent the introduction and establishment of non-native plant species into the Park.

• Equipment inspection will be scheduled by the maintenance office and take place at the Park entrance stations. Inspection records shall be maintained by the Park Service.

• Equipment found operating in the Park that has not been inspected shall be dead lined and subject to a citation.

Delivery:

• All deliveries will be made with dump trucks, dump trucks with pup trailers, side dump and end dump type trailers only.

• Length of any unit delivering within the Park shall not exceed 75 feet in total length of the unit/units.

• The contractor shall adhere to all roadway use regulations and posted speed limits within the Park.

• The use of engine brakes (either compression or exhaust) in a 3-mile radius of Mammoth is prohibited due to housing area and campground in Mammoth.

• The contractor shall deliver chips to the approximate location noted in the line item above.

• The contractor shall coordinate the exact dates and times of delivery with the NPS in advance.

• The contractor shall insure that the total for all amounts ordered and delivered does not exceed the amount noted in the contract line item.

• Violation may result in vehicles being removed from hauling within the Park.

Submittals: At the time of delivery and with each invoice the contractor shall provide trucking manifests which shall serve as contractor certification as to the number of tons delivered.