This document contains the project specifications for the Schoodic Wastewater Replacement project in Acadia National Park, Maine. The work includes demolition of the existing wastewater treatment plant and replacing it with a new subsurface treatment system. The project will be constructed under a single prime contract and will be executed in multiple phases to ensure the existing system remains operational until the new system is fully operational. The contractor will be responsible for obtaining all necessary permits, with coordination required for the overboard discharge system abandonment. Key elements include modifications to the sewer collection system, installation of new holding tanks, a new effluent pump station and force main, and a new disposal field. The contractor must submit a detailed construction schedule, required submittals, and coordinate project management activities using a designated project management software program provided by the National Park Service.

View the file

Other files for this federal contract opportunity

Other files attached to ACAD -REPLACE SCHOODIC WASTEWATER SYSTEM, newest first.
File Type Posted
Sol_140P4324R0019_Amd_0002.pdf PDF
Sol_140P4324R0019_Amd_0001.pdf PDF
B08_Attachment_4_Construction_Contract_Administration.docx DOCX document
B08_Attachment_2_Drawings.pdf PDF
B08_Attachment_3_DOL_Wage_Determination.pdf PDF
Sol_140P4324R0019.pdf PDF
B08_Attachment_5_Limitation_on_Subcontracting_Report.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACADIA NATIONAL PARK

Hancock County, Maine

SCHOODIC WASTEWATER REPLACEMENT

ACAD 187203

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

ACADIA NATIONAL PARK

100% CONSTRUCTION

DOCUMENTS

February 14, 2024

AllisonGreen Placed Image

Typewriter

THIS PAGE LEFT INTENTIONALLY BLANK

ACAD – 187203 TOC-1

REPLACE SCHOODIC WASTEWATER

100% CD SET - SPECIFICATIONS

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

Per Government

DIVISION 01 - GENERAL REQUIREMENTS

011100 Summary of Work

012601 Contract Modification Procedures

012700 Definition of Contract Line Items

013100 Project Management & Coordination

013216 Construction Schedule

013233 Photographic Documentation

013323 Submittal Procedures

013523 Safety Requirements

013525 Explosives

014000 Quality Requirements

014200 Reference Standards

015000 Temporary Facilities and Controls

015526 Traffic Control

015719.11 Indoor Air Quality Management

015719.12 Noise & Acoustics Management

015723 Temporary Storm Water Pollution Prevention

016700 Product Requirements

017329 Cutting and Patching

017340 Execution

017419 Construction Waste Management and Disposal

017419A Appendix A – Project Waste Management Plan Worksheet

017419B Appendix B – Standard Solid Waste Conversions

017700 Closeout Procedures

017823 Operation and Maintenance Data

017900 Demonstration and Training

DIVISION 02 – EXISTING CONDITIONS

02 41 13 Selective Site Demolition

02 41 19 Selective Structure Demolition

ACAD – 187203 TOC-2

DIVISION 03 – CONCRETE

03 30 00 Cast-In-Place Concrete

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 10 00 Rough Carpentry

06 20 13 Exterior Finish Carpentry

DIVISION 09 – FINISHES

09 91 13 Exterior Painting

DIVISION 26 – ELECTRICAL

26 05 00 Electrical General Provisions

26 05 19 Power Conductors and Cables

26 05 26 Grounding and Bonding

26 05 28 Supporting Devices

26 05 29 Hangers & Supports for Electrical System

26 05 33 Raceway & Boxes for Electrical Systems

26 05 41 Underground Electrical Construction

26 05 44 Sleeves & Sleeve Seals for Electrical Raceways and Cabling

26 05 83 Wiring Connections

26 06 20 Electrical Distribution

26 24 16 Panelboards

26 27 26 Wiring Devices

26 27 28 Disconnect Switches

DIVISION 31 – EARTHWORK

31 10 00 Site Clearing

31 20 00 Earth Moving

31 25 00 Temporary Erosion and Sediment Control Plan

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 Hot Mix Asphalt Paving

32 92 00 Meadow Grass

32 94 00 Topsoil

DIVISION 33 – UTILITIES

33 30 00 Sanitary Sewage Utilities & Structures

33 32 00 Wastewater Utility Pumping Stations

33 34 00 Subsurface Sewage Disposal Field

33 46 00 Subdrainage

ACAD – 187203 TOC-3

APPENDICIES

APPENDIX 1 Hazardous Building Materials Inspection Report

APPENDIX 2 HHE-200 and Soil Test Pit Logs

Typewriter

ACAD - 187203 01 11 00 - 1

091015 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Acadia National Park, Schoodic Point, Acadia Dr., Winter Harbor, ME

B. The Work consists of the following:

1. The Work includes demolition of the wastewater treatment plant Schoodic Education and

Research Center to eliminate the overboard discharge system and to replace with a new subsurface treatment system appropriately sized for current and future demands. New subsurface treatment system consists of modifications to the sewer collection system, new holding tanks, new effluent pump station and force main, new disposal fields.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in phases in order to ensure the existing system remains operational until the new system is fully operational. The following are the broad phases of the project, but do not intend to include all steps required to ensure the project is effectively executed. Phases may need to overlap or be concurrent to ensure appropriate timing. Phases will need to take into account any lead times, seasonal or regulatory limitations, or limitations based on contractor/skilled trade availability. Contractor will need to consult with Contracting Officer to ensure phasing meets the needs of the project.

1. Phase 1: Begin construction of subsurface wastewater system.

2. Phase 2: Begin demolition of only the structures required to begin construction of new system (including burning and disposal of reed bed according to MDEP regulations) and

ACAD - 187203 01 11 00 - 2

ensure continuing proper operation of existing wastewater treatment. Perform any additional necessary demolition to begin installation of septic tanks and pump station.

3. Phase 3: Build new portion of collection system without interrupting existing system.

4. Phase 4: Begin installation of septic tanks, pump station, gravity piping and sewer force main. This includes any necessary demolition and/or preparation for abandoning and/or removing piping that will not be part of the new system network.

5. Phase 5: Upon commissioning of new subsurface wastewater system, intercept existing flows and divert to new system, disconnect and decommission old wastewater system. This includes cutting, capping and abandoning or removing obsolete gravity and force main lines.

6. Phase 5: Entirely abandon obsolete wastewater treatment system, including overboard discharge abandonment, burning and disposal of reed bed and any additional demolition that need to be completed.

B. See Section 01 31 00 – Project Management and Coordination for other requirements regarding projects coordination and phasing.

1.4 GOVERNMENT-FURNISHED MATERIALS

A. Government will furnish products indicated.

1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.

3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.

4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.

5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.

7. Contractor shall install and otherwise incorporate Government-furnished items into the

Work.

B. Government-Furnished Products:

1. None.

1.5 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to areas indicated on the construction documents.

2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities

ACAD - 187203 01 11 00 - 3

less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

B. Storage of Materials: Confine storage of materials to areas indicated on the Site Plan.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to

Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.6 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

Road closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum of 8 hours per day. In no case shall access to the SERC Campus be fully blocked to vehicle traffic.

1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings that will be affected construction during the entire contract period. Cooperate with Government during

ACAD - 187203 01 11 00 - 4

construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

1.8 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 24 hours in advance of the work to the

Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.9 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of

7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Weekend work shall not be permitted without written approval from the

Contracting Officer.

2. Early Morning Hours: No restrictions.

3. Hours for Noise Marking Operations: 7:00 a.m. to 5:00 p.m., Monday through Friday

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

ACAD - 187203 01 11 00 - 5

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: Coordinate with Government for timing of any utility shutdown. Utilities shall not be interrupted for more than 4 hours, unless longer durations are approved by the Government.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.10 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management Software: Project management software provided by the Contractor and administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on Project

Management Software.

B. Timing of certain decommissioning activities related to the existing wastewater treatment system, such as burning and disposal of reed beds, and overboard discharge abandonment, must be coordinated with the State.

1.11 HAZARDOUS MATERIALS REPORT

A. Analysis was conducted for hazardous materials in the existing Wastewater Treatment Plan. See

Appendix 1 for further information.

1.12 SOILS INVESTIGATION REPORT

A. Soils test pits and investigation was performed by Atlantic Resources Co, LLC. During the design of the subsurface wastewater system. See the Application for Subsurface Wastewater Disposal in

Appendix 2 for more information.

B. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

DANE FARM ROAD HOUSING 06 17 45 - 8

FRIENDS OF ACADIA WOOD TRUSSES AND JOISTS

ACAD - 187203 01 26 01 - 1

031414 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

ACAD - 187203 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating

General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

ACAD - 187203 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General

Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct

ACAD - 187203 01 26 01 - 4

own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction

Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the

Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

ACAD - 187203 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the

US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10%

Profit…………………...5.6%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

ACAD - 187203 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

ACAD - 187203 01 27 00 - 1

082714 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 00010 Wastewater Treatment Plant Demolition and

Decomissioning, Existing Systems Removal

1. This item consists of decommissioning existing wastewater treatment plant and overboard discharge, abandonment of existing sludge tanks and overflow tanks, overboard discharge piping. It includes demolition and removal of all Wastewater Treatment Plant (WWTP) components detailed on the drawings and described in the specifications. Included in this item is all demolition of existing sewer components (except reed beds) required to accommodate the work. Included in this item is pumping of tanks, transport and legal disposal of effluent, and any sludge or waste materials left in WWTP systems. Abatement of lead paint items is considered incidental to this item.

2. Measurement for payment will be percentage of the work complete including equipment, materials, and labor.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 00020 Selective Site Demolition

1. This item consists of all site demolition, building and building slab demolition, fence removal, dugout removal, excavation, trenching, removals, and temporary storage of materials to be reused. It is intended to cover all items required to accommodate the work regardless if each item is graphically shown or specifically noted on the plans or in the specifications. Included in this item are erosion control items required during site demolition.

2. Measurement for payment will be percentage of the work complete including equipment, materials, and labor.

3. Payment will be made at the contract lump sum price.

ACAD - 187203 01 27 00 - 2

C. Contract Line Item No. 00030 Ledge Excavation

1. This item consists of furnishing all labor, materials and equipment required to remove rock as authorized in the field and described in the specifications for both trench and general rock. This item includes providing all labor, materials and equipment required to remove the rock as authorized. Pre-blast surveys shall be considered incidental to this pay item.

2. Measurement for payment will be the number of cubic yards acceptably excavated, computed by multiplying the authorized trench width times the average depth times the distance along the trench or the authorized excavation width times the average depth times the distance of material requiring removal. The method of measurement for boulders will be as spheres (V (CY) = 0.16R³) where R is the average radius in feet computed on the basis of at least three representative measurements of circumference.

The minimum size of a boulder which will be paid for will be 3 CY. Authorized trench width for utilities shall be 3’. Authorized pay limit for utility structures is the diameter or total width plus 4’.

3. Payment will be made at the contract unit price.

CI. Contract Line Item No. 00040 Gravity Sewer and Effluent Forcemain Installation

1. This item consists of modifications to and extension of the existing sewer collection system. It includes manhole modifications and replacement, new sewer manhole installation, modification to existing sewer main and sewer forcemain, installation of new sewer main and effluent forcemain. Included in this item are all associated erosion controls, excavation, backfill, curb reinstallation, pavement patching, site restoration, sewer bypass pumping, sewer pipe and manhole testing and all work shown or described on the plans and in the specifications.

2. Measurement for payment will be percentage of the work complete including equipment, materials, and labor.

3. Payment will be made at the contract lump sum price.

CII. Contract Line Item No. 00050 Septic Tank and Sewer Pump Station Construction

1. This item consists of installation of new septic holding tanks, new effluent pump station wet well, new effluent pump station. It includes all items related to the holding tanks and pump station including, but not limited to tanks, piping between tanks, outlet filters and internal piping, risers and covers, concrete slab, fence enclosure, electrical service and all items related to the septic tanks and effluent pump station. It includes all excavation, material storage, structural fill, drainage, electrical connections, panels and distribution lines, alarms, and work shown or described on the plans and in the specifications.

2. Measurement for payment will be percentage of the work complete including equipment, materials, and labor.

3. Payment will be made at the contract lump sum price.

CIII. Contract Line Item No. 00060 Septic Disposal Field Construction

1. This item consists of excavation, backfill and installation of new concrete chamber disposal fields. It includes a surge tank, distribution manhole, distribution boxes and piping, loam, seeding, and restoration to a meadow area. All required erosion controls shall be included in this item.

ACAD - 187203 01 27 00 - 3

2. Measurement for payment will be percentage of the work complete including equipment, materials, and labor.

3. Payment will be made at the contract lump sum price.

G. Contract Line Item No. 00070 Reed Bed Disposal

1. This item consists of demolition and legal disposal of reed disposal bed including reed bed burning, sampling and analyzing of sludge, transport and legal disposal of sludge.

This item includes transport and legal disposal of all associated piping and equipment demolished during these activities. All required coordination with State authorities included in this item.

2. Measurement for payment will be percentage of the work complete including equipment, materials, and labor.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

ACAD - 187203 01 27 00 - 4

THIS PAGE INTENTIONALLY LEFT BLANK

ACAD - 187203 01 31 00 - 1

091015 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on

Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. Project Management Software.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

4. Section 01 91 14 “Total Building Commissioning” for coordinating the work with

Owner’s Commissioning Authority.

1.2 DEFINITIONS

A. Agency with Jurisdiction: An Agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.

B. Construction Permits – Contractor Provided: Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service. Examples of typical

Contractor Provided Permits are: National Pollutant Discharge Elimination System (NPDES)

Construction Permit (ground disturbance), dewatering permit, permit for work in a roadway

(with traffic management plan), temporary utility tap permit, etc.

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate http://www.nps.gov/dscw/definitionsdc_a.htm#awj https://www.nps.gov/dscw/definitionsdc_p.htm#permit http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp https://www.nps.gov/dscw/definitionsdc_c.htm#contractor https://www.nps.gov/dscw/definitionsdc_a.htm#awj

ACAD - 187203 01 31 00 - 2

construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings as needed if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base

Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).

3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.

ACAD - 187203 01 31 00 - 3

4. Review: Contracting Officer (CO) will review coordination drawings to confirm that the

Work is being coordinated, but not for the details of the coordination, which are

Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform

Contractor, who shall make changes as directed and resubmit.

5. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."

6. File Preparation Format: Same digital data software program, version, and operating system as original Drawings

7. File Submittal Format: Submit or post coordination drawing files using Portable

Document Format (PDF) file format.

B. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. Indoor Air Quality (IAQ) Management Plan.

12. Contractors Commissioning Plan.

13. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

C. All items listed must be provided to the Contracting Officer before the Pre-Construction

Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to

Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the Project Management Software.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

ACAD - 187203 01 31 00 - 4

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the Project Management Software and submit in a manner consistent with the software that appropriately alerts the Government and/or CO of the

RFI for timely processing.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the

Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT MANAGEMENT SOFTWARE PROGRAM

A. The Contractor shall provide a project management program that has real-time work management features that support Task Management, Team Collaboration and Document

Management. The project management program shall be software stored, managed, and processed on a network of remote servers hosted on the Internet in which software is accessed

ACAD - 187203 01 31 00 - 5

online via subscription. Example programs include but are not limited to: Procore®, Project

Team, Wrike®, etc.

B. At a minimum, program features shall include:

1. Project Document Management:

a. Unlimited Storage;

b. Unlimited Users;

c. Document Tracking – disposition of documents in review, pending actions from users per workflow, revisions, etc.;

d. Document and Folder Permissions granted to administrators who can choose the level of access and permissions for users per each project;

1) Administrators will be Owner/National Park Service (NPS) personnel;

2) Users will include NPS personnel and external NPS personnel;

3) External NPS entities include the Construction Contractor (Contractor), Revegetation Contractor, Contracting Officer Representative (COR), and

Architect-Engineer (AE);

e. Provide access to the program 24 hours per day, 7 days a week, except for maintenance activities. Maintenance activities shall be coordinated to occur outside of normal working hours, with email notification to users at least 48 hours prior to any activities that limit user document access;

f. Ability to reference/link/tag project documents to other project documents to establish a record link; and

g. Allow for the search of names, description, document type, document disposition, and contents of documents within the documents tool.

h. Provide ability for administrators and permissible users to cancel a workflow and/or identify documents as obsolete.

i. Promotes ability to manage documents remotely using mobile devices.

j. Promotes ability to manage documents using email only, without logging into/accessing the system

2. Project Directory/Post-Log-In View/Dashboard:

a. Provide access to multiple projects per each user as defined by administrators;

b. Provide user directory with emails and ability to assign to an organization (i.e.

NPS, Contractor, Revegetation Contractor, COR, or AE);

c. Provide access to Submittals, Requests for Information (RFIs), Schedule, Drawings, Specifications, Meeting Minutes, Daily Reports/Logs, and Photographs;

and

d. Provide a listing or access to a listing or report of and with linkages to submittals, RFIs, tasks, etc. that are pending user action/input including the date the task is due per Submittal or RFI workflows.

3. Submittals:

a. General:

1) Provide ability to upload, download, view, and automatically route

Informational and Action Submittal documents per each workflow;

2) Provide user ability to select submittal disposition type when routing;

3) Provide administrators ability to manage use permissions to modify workflow duration dates and default review periods per each project;

4) Provide administrators ability to manage user permissions to modify email notification settings to include other users per each project;

5) Provide notifications when an item becomes a user’s responsibility including the due date of the item and ability to provide more frequent notifications as selected by administrators;

ACAD - 187203 01 31 00 - 6

6) Provide ability to sort submittals by specification section, information or action submittal, date, or submittal disposition; and

7) Provide ability to track and document workflow processes, user action(s), document sent/received times/dates, document disposition etc.

b. Informational Submittals:

1) The Default Informational Submittal Workflow is as follows:

a) Start workflow – Contractor can create/start, then route to NPS and

COR

b) Option for NPS or COR to assign/route to Contractor, COR, or AE;

c) If routed to Contractor, COR, or AE, they route back to NPS and

COR; and

d) From NPS to Contractor – end workflow.

2) Default Informational Submittal review duration:

a) NPS Information Submittal workflow of ten (10) days.

3) The NPS selects the disposition type during their transmittal to the contractor in the workflow, with disposition types as follow:

a) Accept; or

b) Reject

c. Action Submittals

1) The Default Action Submittal sequential workflow is as follows:

a) Start workflow – Contractor can create/start, then route to NPS and

COR;

b) Option for NPS or COR to assign/route to AE or Disapprove and route to Contractor for their re-submittal;

c) If routed to the AE, the AE routes back to NPS and COR; and

d) NPS selects deposition and routes to Contractor – end workflow.

2) Default Action Submittal review durations:

a) NPS Action Submittal workflow of thirty (30) days;

b) NPS Action Re-Submittal workflow of thirty (30) days; and

c) AE review time for Action Submittal workflow of twelve (12) days.

3) The AE selects disposition types during their transmittal in the workflow and the NPS concurs with the transmittal to the contractor in the workflow, with disposition types as follow:

a) Approved;

b) Approved with Notations;

c) Disapproved – Resubmit;

4. Requests For Information (RFIs)

a. Provide ability to upload, download, view, and automatically route RFI documents per the following default sequential workflow;

1) Start workflow – Contractor, NPS, or COR can create/start, then route to

NPS and COR;

2) Option for NPS or COR to route back to Contractor or AE;

3) If routed to the AE, the AE routes back to NPS and COR; and;

4) From NPS to Contractor – end workflow;

b. Provide administrators ability to modify workflow duration dates per each project;

1) Default NPS review time for RFI workflow is fourteen (14) days;

2) Default AE review time for RFIs is seven (7) days;

c. Provide administrators ability to modify email notification settings to include other users per each project;

ACAD - 187203 01 31 00 - 7

d. Provide notifications when an item becomes a user’s responsibility including the due date of the item and ability to provide more frequent notifications as selected by administrators;

e. Provide ability to track and document workflow processes, user action(s), document sent/received times/dates, etc.; and

f. Provide ability to track and document review comments and responses.

5. Project Schedule:

a. Provide ability to upload baseline schedule and schedule updates from, but not limited to, Primavera P6 and Microsoft Project file formats;

b. Provide ability to view uploaded schedules in Gant or calendar (i.e. user-selectable by year, month, week, and day) formats, including activity starts/ends and milestone dates; and

c. Provide ability for users to view multiple project schedules that they have permissions/access to within a view or report.

6. Drawings:

a. Provide ability to upload, download, and view drawings.

7.…