This document is a comprehensive Statement of Work (SOW) for the repair of the earthen roof at Fort Tompkins, a historic structure within Gateway National Recreation Area's Staten Island Unit. The project involves a phased restoration approach focusing on addressing water infiltration issues in the historic roof structure, with Phase 1 targeting a single bay and including three additional exploratory probe areas. Key work components include archaeological monitoring, hand excavation of earthen fill, masonry structure repair, waterproofing, replacement of roof leaders, backfilling, and replanting the vegetated surface.
The project scope requires specialized historic preservation techniques, with strict archaeological and environmental protection protocols. Contractors must comply with Secretary of the Interior's Standards for Historic Properties, handle potential unexploded ordnance risks, and work within specific environmental and operational constraints. The work will be performed under a single prime contract, with temperature and weather limitations governing construction activities. Anticipated challenges include preserving the historic fabric of the 1850s fortification, managing potential contamination, and implementing a comprehensive waterproofing solution to prevent further structural deterioration caused by increased rainfall events.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GATEWAY NATIONAL RECREATION AREA
STATEN ISLAND UNIT
FORT TOMPKINS EARTHEN ROOF
GATE 308184
PROJECT SPECIFICATIONS
CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE (NPS)
FEBRUARY 29, 2024
GATE 308184 TABLE OF CONTENTS - 1
GATE 308184 Fort Tompkins Earthen Roof
Project Specifications
Table of Contents
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK 5
01 26 01 CONTRACT MODIFICATION PROCEDURES 6
01 27 00 DEFINITION OF CONTRACT LINE ITEMS 2
01 31 00 PROJECT MANAGEMENT AND COORDINATION 8
01 32 16 CONSTRUCTION SCHEDULE 9
01 32 33 PHOTO DOCUMENTATION 2
01 33 23 SUBMITTAL PROCEDURES 8
01 35 13.22 ARCHEOLOGICAL PROTECTION 6
01 35 23 SAFETY REQUIREMENTS 5
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES 7
01 40 00 QUALITY REQUIREMENTS 8
01 42 00 REFERENCE STANDARDS 13
01 50 00 TEMPORARY FACILITIES AND CONTROLS 8
01 57 19.12 NOISE AND ACCOUSTICS MANAGEMENT 3
01 57 23 UNDER-AN-ACRE POLLUTION PREVENTION 7
01 67 00 PRODUCT REQUIREMENTS 8
01 73 29 CUTTING AND PATCHING 3
01 73 40 EXECUTION 4
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 8
01 77 00 CLOSEOUT PROCEDURES 5
DIVISION 02 - EXISTING CONDITIONS
02 42 97 SELECTIVE REMOVALS AND SALVAGING 8
DIVISION 04 - MASONRY
04 03 22 HISTORIC BRICK UNIT MASONRY REPAIR & REPLACEMENT 9
04 03 23 HISTORIC BRICK UNIT MASONRY REPOINTING 8
04 03 42 HISTORIC STONE MASONRY REPAIR 9
04 03 43 HISTORIC STONE MASONRY REPOINTING 8
04 10 00 MORTAR 4
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
073363 VEGETATED ROOF ASSEMBLY: HIGH PERFORMANCE BUILT-UP 15
07 56 00.11 FLUID-APPLIED MEMBRANE ROOFING 12
07 92 00 JOINT SEALANTS 8
GATE 308184 TABLE OF CONTENTS - 2
DIVISION 31 - EARTHWORK
31 10 00 SITE CLEARING 4
31 20 00 EARTH MOVING 9
31 50 00 EXCAVATION SUPPORT AND PROTECTION 4
DIVISION 33 – SITE UTILITIES
33 42 00 STORMWATER CONVEYANCE 7
END OF TABLE OF CONTENTS
GATE 308184 01 11 00 - 1
112723 SUMMARY OF WORK
GATE 308184
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Construction Contractor Use of Site
3. Public Use of Site
4. Occupancy Requirements for Buildings
5. Conduct of Operations
6. Work Restrictions
7. Resource Preservation
B. Project Location: Fort Tompkins, a part of Fort Wadsworth, Gateway NRA Staten Island Unit, Staten
Island, NY.
C. Project Background: Fort Tompkins Quadrangle (1859 – 1876) was individually listed in the
National Register of Historic Places in 1974, and is also identified as a fundamental contributing structure to the proposed Fort Wadsworth National Register Historic District. It is in current use for both park operations and visitor use. Water infiltration through the earthen-filled roof structure of
Fort Tompkins has been an on-going problem for many years. With the increased frequency and intensity of rain events due to climate change, it is critical to begin a comprehensive approach to the waterproofing and repair of the earthen roof structure of Fort Tompkins, to reduce water infiltration and protect the historic resource from further material deterioration or loss of important character-defining features.
D. Be advised, Gateway National Recreation Area (GATE) is home to former active military sites and there could be unexploded ordnance (UXO) contained within the ground and/or waters of the park. If a UXO is discovered, extreme caution is warranted, and it should be treated as a live/active munition until proven otherwise. If a UXO is discovered or suspected, immediately cease operations and notify the GATE Dispatch Center (24/7) by calling 718-354-4700. Advise all personnel to clear the area and do not touch the item(s). Emergency response officials will respond and investigate.
E. The Work consists of:
1. The project is Phase 1 of the earthen roof restoration at Fort Tompkins. Fort Tompkins is a Third Period Fortification dating to the 1850s. Its roof consists of earthen fill over masonry vault structures with a depth of fill ranging from 3’ to 20’. There is an original roof drainage system consisting of a culvert and leader at each valley between the vaults.
The function of this system is highly compromised, as is the overall waterproofing system, allowing significant water infiltration into the structure of the fort. This project will
GATE 308184 01 11 00 - 2
investigate and address one bay at the south range of the fort, and undertake additional probes in other areas of the fort. All work shall be performed in accordance with the Secretary of the Interior's Standard for the Treatment of Historic Properties
2. Work includes:
a. Provide archaeological monitoring and investigation as work progresses.
b. Hand-excavate and remove earthen fill above the masonry structure, with archaeological investigation of the fill.
c. Repair and protect masonry structures uncovered. Dismantle and reconstruct brick chimney.
d. Provide waterproofing system at all exposed masonry surfaces.
e. Jet and TV investigate roof leaders. Replace leader pipes.
f. Backfill with existing soil plus an allowance for imported fill.
g. Provide topsoil and plantings at finished surface.
h. Perform three exploratory probes including removal and replacement of fill where indicated.
i. Test soil in excavation areas for contamination.
F. Project will be constructed under a single prime contract.
1.2 CONSTRUCTION CONTRACTOR USE OF SITE
A. General: Construction Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Do not disturb portions of
Project site beyond areas in which the Work is indicated.
B. Storage of Materials: Confine storage of materials to staging areas shown on plans.
C. Parking: Confine parking to staging areas.
D. Stockpiling: Confine stockpiling to staging areas.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
COR and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
G. Construction Camp: Establishment of a camp within park will not be permitted.
GATE 308184 01 11 00 - 3
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.
1.3 PUBLIC USE OF SITE
A. The Parade and areas of the first tier will be open to the public for supervised tours during construction. Coordinate schedule with COR.
B. Construction Contractor shall conduct his operations to ensure the least inconvenience to public.
Road closures may be permitted, when required, upon specific approval of COR for a maximum of eight hours.
1.4 OCCUPANCY REQUIREMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will occupy premises during entire construction period, with exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from COR.
1.5 CONDUCT OF OPERATIONS
A. Construction Contractor shall conduct operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the
Work Restrictions below or without prior consent from the COR. Submit requests 3 business days in advance of the work to the COR for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the COR.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of
7:00 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated.
1. Off-hour and weekend working times are only allowed with Park specific approval.
Requests for off-hour work will be evaluated on a case-by-case basis.
GATE 308184 01 11 00 - 4
B. Existing Utilities
1. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify COR not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without COR’s written permission.
3. Hours and length of Utility Shutdowns: Obtain Government approval of any shut-downs.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building, on the roof, or within 25 feet of entrances, operable windows, or outdoor air intakes.,
1.7 RESOURCE PRESERVATION
A. Soil:
1. Intact native topsoil from the project area shall be retained whenever feasible. Should additional fill be needed, all fills must be of quality suitable for use in a National Park Unit and meet the New York State Department of Environmental Conservation standards for general fill (6 CRR-NY 360.13). Any fill materials required for the project must be obtained from a park-approved source. Backfill material shall be replaced in the order removed.
2. Imported soils and materials: Such materials are to be clean of contaminants and free of exotic seeds and spores. Written verification of such should be provided to the CO and
COR prior to delivery of material.
B. Soil Erosion: Protect against erosion and topsoil depletion.
C. Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds.
D. Vegetation: Vegetation may not be trimmed, removed, sprayed, or otherwise damaged to accommodate ladders or other equipment to conduct the work around the buildings. If such modification of vegetation is later determined to be necessary, then NPS/Park Resource
Stewardship Division must be contacted through the contracting officer’s representative (COR) to conduct an inspection of the work area prior to initiating the proposed vegetation modification.
The Contractor shall protect tree trunks and root systems of trees in, or adjacent to, work areas.
E. Wildlife: Do not intentionally disturb wildlife nesting, breeding, or other activities. If exterior project work will be implemented during period of March 15 to September 1, Park Natural
Resource Stewardship must be contacted to conduct an inspection of the work area prior to initiating work to determine if there is any nesting activity that could be impacted by the project.
If nest building begins, birds must not be harassed in any manner to deter nesting activity. Park approval is required prior to placement of any structures to deter osprey nesting and any such structure may only be put in place between September 2 and March 14.
GATE 308184 01 11 00 - 5
1. The contractor shall adhere to a seasonal restriction on the use of heavy construction equipment/machinery within 300 meters of any active osprey nest along the project limit of disturbance from April 1 through August 31 of each calendar year.
F. Naturally growing milkweed plants are likely present in areas of dense vegetation and are home to Monarch Butterflies. In the discovery of a habitat (concentration of milkweed plants) mitigation procedures must be undertaken. Notify Park Natural Resource Stewardship.
G. It is the Contractor’s responsibility to check any wildlife habitats within the project site and notify the Contracting Officer in writing. If habitats are found, all work should be suspended in that location and no work should proceed until Park Natural Resource Stewardship approval is obtained.
H. Visitor Experience: Provide the Project Manager with the project schedule as soon as it is known and provide periodic updates of project work. Should closure or rerouting of visitors be necessary, closures would be for the minimal time required to complete the work activity or correct the problem.
I. Air and Water Pollution Control:
1. Minimize tailpipe emissions, do not leave construction equipment idling longer than necessary for safety and mechanical reasons.
2. Minimize construction dust by applying water to problem areas. Limit equipment to fenced project area to minimize soil disturbance and dust generation.
3. Take necessary reasonable measures to reduce air and water pollution with material or equipment used during construction. Keep volatile wastes in covered containers.
4. All machinery containing fuels and oils shall have a spill kit available to immediately use in the event of a spill. In the event of a fuel or oil leak or spill, the work shall cease immediately, spill containment deployed, and Gateway NRA Dispatch (718) 354-4700 shall be called immediately.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
GATE 308184 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
GATE 308184
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
GATE 308184 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
GATE 308184 01 26 01 - 3
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank
GATE 308184 01 26 01 - 4
utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the COR upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book http://www.nps.gov/dscw/publicforms.htm
GATE 308184 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project.
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.E,1 above).
It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
GATE 308184 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
GATE 308184 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
GATE 308184
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 1 Phase 1 Work Area – Single Bay Scope.
1. This item consists of removal of earthen fill, restoration and repointing of below-grade structures, provision of below-grade waterproofing, replacement of earthen fill, and replanting the vegetated surface.
2. Measurement for payment will be per cent complete.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item Number 2 Probe A.
1. This item consists of an exploratory probe at the southwest corner to document conditions.
Waterproofing is included.
2. Measurement for payment will be per cent complete.
3. Payment will be made at the lump sum price.
C. Contract Line Item Number 3 Probe B.
1. This item consists of an exploratory probe at the East Range.
2. Measurement for payment will be per cent complete.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item Number 4 Probe C.
1. This item consists of an exploratory probe at the southeast corner to document conditions.
Waterproofing is included.
2. Measurement for payment will be per cent complete.
GATE 308184 01 27 00 - 2
012721 DEFINITION OF CONTRACT LINE ITEMS
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
GATE 308184 01 31 00 - 1
112723 PROJECT MANAGEMENT AND COORDINATION
GATE 308184
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Construction
Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Make provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm http://www.nps.gov/dscw/definitionsdc_c.htm http://www.nps.gov/dscw/definitionsdc_g.htm
GATE 308184 01 31 00 - 2
3. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
4. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Construction Contractor Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination
Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
b. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
c. Indicate required installation sequences.
2. Refer to individual Sections for Coordination Drawing requirements for Work in those
Sections.
3. Follow NPS Electronic Drawing Standards.
B. Coordination Digital Data Files: Prepare coordination digital data files according to:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
GATE 308184 01 31 00 - 3
2. File Submittal Format: Submit or post coordination drawing files using Portable Document
Format (PDF) file format.
3. Contracting Officer will furnish Construction Contractor one set of digital data files
(AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
C. Division 1 documents:
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Under-an-Acre Pollution Prevention Plan (UPPP)
11. Historic Preservation Treatment Plan (HPTP)
12. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
D. Provide items listed to Contracting Officer at least one week prior to Pre-Construction
Conference, or as directed by Contracting Officer.
1. Failure to submit items may result in:
a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.
b. Work shall not commence until written Notice to Proceed has been issued and
Certificates of Insurance and SF1413 documents are received for Construction
Contractor and all Subcontractors.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Construction Contractor shall prepare and submit an RFI.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Construction Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
GATE 308184 01 31 00 - 4
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Construction Contractor's suggested resolution: If suggested resolution impacts Contract
Time or Contract Sum, Construction Contractor shall state impact in RFI.
8. Construction Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Construction Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or
Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Construction Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
GATE 308184 01 31 00 - 5
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Construction Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Construction Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. Acceptance/rejection of work
17. Progress meetings
18. Submittal procedures
19. Environmental requirements
20. Permit requirements
21. As-constructed drawings/operation and maintenance (O&M) manuals.
22. Saturday, Sunday, holiday and night work.
23. Reference materials
24. Value engineering
25. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Construction
Contractor.
1. Attendees: In addition to Government Representatives, each Construction Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented.
Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
GATE 308184 01 31 00 - 6
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting
Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Construction Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Construction Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
GATE 308184 01 31 00 - 7
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Under-an-Acre Pollution Prevention Plan (UPPP).
d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
e. Training for Construction Contractor personnel in accordance with position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Noise and Acoustics Management
4. Temporary Pollution Prevention Environmental Management
5. Construction Waste Management
C. Construction Contractor’s Environmental Training Program: Construction Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Noise and Acoustics Management
c. Under-an-Acre Pollution Prevention
4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Construction Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan and Under-an-Acre Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Construction Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Construction Contractor shall also be responsible for damages to persons or property that occur as a result of Construction Contractor’s fault or negligence;
GATE 308184 01 31 00 - 8
and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Construction Contractor will not be considered an agent of the Government. Construction Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. None.
C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist
Construction Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Construction Contractors’ responsibility to determine means and methods and obtain required permits. Construction
Contractor shall obtain all permits required to legally conduct work.
1. ARPA (Archaeological Resource Protection Act) Permit.
D. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
E. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS project management and communication software when permits are obtained.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
GATE 308184 01 32 16 - 1
010824 CONSTRUCTION SCHEDULE
GATE 308184
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Construction Contractor. It shall assist the
Construction Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Construction Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
GATE 308184 01 32 16 - 2
1. Float: Not for the exclusive use or benefit of the Government or Construction Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: Schedules and reports submitted shall be posted on the NPS project management and communication software as PDF (portable document format) files. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.
D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit three paper copies of the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
E. Construction Schedule Updates: On or before 7th day preceding progress payment request date, submit estimates of percent…