This document is a Statement of Work (SOW) for the removal of wallpaper and painting of walls in the A3 hallway space at the Columbia Environmental Research Center (CERC) facility in Columbia, Missouri. The contractor will be required to remove approximately 1,520 square feet of wallpaper, prepare the walls, and paint them with a minimum of one coat of primer and two coats of finish paint. The work must be completed within 90 calendar days of the notice to proceed and is subject to inspection and approval by the USGS Technical Liaison. The related federal contract opportunity is a Request for Quote (RFQ) solicitation number 140G0124Q0123, which will be issued on 3/28/2024 with written quotes due on 4/8/2024. This is a 100% Total Small Business set-aside with a NAICS code of 238320 and a size standard of $19 million. The magnitude of construction is less than $25,000.

View the file

Other files for this federal contract opportunity

Other files attached to CERC A3 Wallpaper Removal & Paint, newest first.
File Type Posted
Sol_140G0124Q0123_Amd_0001.pdf PDF
B09_Attachment_5_Q_A_Amendment_001_0001.docx DOCX document
Sol_140G0124Q0123.pdf PDF
B08_Attachment_2_Approximate_Measurements.pptx PPTX presentation
B08_Attachment_4__WD_MO20240084_1_5_2024.pdf PDF
B08_Attachment_3_Pictures.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

U. S. GEOLOGICAL SURVEY

Columbia Environmental Research Center (CERC) 4200 New Haven Road Columbia, Missouri 65201

STATEMENT OF WORK

CERC WALLPAPER REMOVAL & PAINT

I. GENERAL INFORMATION

a. INTRODUCTION. The Department of the Interior (DOI), U.S. Geological Survey (USGS), Columbia Environmental Research Center (CERC) 4200 New Haven Road, Columbia, MO 65202 has a requirement to remove wallpaper and prepare and paint walls in the A3 hallway space building.

b. BACKGROUND. The Columbia Environmental Research Center (CERC) conducts research needed to address national and international environmental contaminant issues and effects of habitat alterations on aquatic and terrestrial ecosystems. The A3 Main Building at the CERC is a 34,019 square foot research laboratory building that houses several research laboratories, office space, and a 6,000 square foot research wet laboratory. This project will only affect the hall on the north side of the building.

c. DEFINITION/APPLICABLE DOCUMENTS.

i. Attachment 1 Pictures

ii. Attachment 2 Approximate Measurements

d. SCOPE. The contractor shall provide all materials, labor, equipment, travel and supervision necessary to remove wallpaper and prepare and paint walls in the A3 hallway space building.

II. WORK REQUIREMENTS

a. TECHNICAL REQUIREMENTS

i. Remove approximately 1,520 square feet of wall wallpaper.

ii. Remove any items attached to the walls.

iii. Prepare cinderblocks/wallboard to assure that it is properly cleaned and prepped for greatest adherence of drywall mudding.

iv. Assure all holes are filled with recommended and government approved filler to achieve a flat and clean final product.

v. Assure level 5 finish on cinderblock with mud compound.

vi. Prime and Paint walls with commercial grade paint. Color is to be determined. Minimum of 1 coat of primer and 2 coats of finish paint over entire surface.

vii. Replace all items previously hanging from the walls in exact location that they were located pre removal.

viii. Cleanup any remaining products from the job site nightly. Contractor can use government furnished dumpster for any disposal of items.

ix. No debris/dust left over night on job site.

x. Contractor shall stage work into 3 distinct areas to allow access to the majority of the facility during the period of performance. The staged areas shall be agreed upon by government representative.

xi. Site visit during solicitation phase is strongly encouraged. Contractor is responsible for visiting the worksite to verify measurements and to ascertain the nature and location of the work to be performed and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve the contractor of his responsibility for estimating properly the difficulty or cost of successfully performing the work.

b. GENERAL REQUIREMENTS

i. Schedule. Within five (5) calendar days after the notice to proceed is issued, the Contractor shall submit in writing to the USGS Technical Liaison a schedule of construction for the project. The schedule shall indicate the dates of the periods of time that the Contractor intends to be on site. The schedule shall indicate the dates that major components of the work will be accomplished. When preparing the schedule, the Contractor shall consider lead times for utility outages, permit requirements and material/ equipment procurement, and shall consider the permitted hours of work indicated in Time of Work Performance clause. The Contractor shall notify the USGS Technical Liaison immediately if any anticipated on-site date is expected to change from the original schedule. The Contractor shall be responsible for determining the labor staffing levels needed to complete the project by the established delivery date.

c. WARRANTY. The Contractor shall warranty all workmanship to meet the specifications set forth in this Statement of Work. Additionally, the Contractor shall warranty all Contractor workmanship for a (minimum) period of 12 months from the date of Government acceptance.

III. SUPPORTING INFORMATION.

a. GOVERNMENT FURNISHED PROPERTY (GFP): None.

b. SECURITY. Building access shall be coordinated with the Facility Manager or USGS Technical Liaison. *Provided upon award*

c. PLACE OF PERFORMANCE. USGS, Columbia Environmental Research Center (CERC), 4200 New Haven Road, Columbia, MO 65201

d. PERIOD OF PERFORMANCE. 90 calendar days ARO

e. SPECIAL CONSIDERATIONS

i. The CERC normal facility business hours are 7:00 AM to 4:30 PM, Monday thru Friday.

ii. Utility/Service Interruptions: The Facility Manager and USGS Technical Liaison shall be notified not less than 3 calendar days in advance of any interruptions of building utility/services. The contractor shall describe in writing the work to be done and the time and duration of the interruption. No work shall be done until approval is received from the USGS Technical Liaison.

iii. The contractor shall be responsible for complying with all National, Federal, State and local laws, codes and regulations in connection with the execution of the contract.

iv. Contractor is responsible for visiting the worksite to verify measurements and to ascertain the nature and location of the work to be performed and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve the contractor of his responsibility for estimating properly the difficulty or cost of successfully performing the work.

v. Occupancy: During construction the Government will occupy the existing facility. The contractor shall not restrict nearby pedestrian or vehicular traffic to this facility and shall coordinate construction with the Contracting Officer to minimize conflicts and to facilitate usage. The contractor shall perform the work so as not to interfere with ongoing operations.

vi. Any changes affecting the scope of work shall be originated from and approved by the Contracting Officer.

vii. All materials and workmanship shall be subject to the inspection and approval of the USGS Technical Liaison. All work unsatisfactorily performed shall be promptly corrected and made acceptable to the Government at no additional Cost.

viii. Final inspection and acceptance shall be performed with the contractor, on site by the USGS Technical Liaison upon completion of job performance.

ix. MATERIALS. The contractor shall furnish all supplies, materials, and equipment necessary for performance of the work included in this contract unless otherwise specified. Materials and supplies to be used shall be commercially available products of reputable manufacturers or suppliers and shall be of a quality to conform to applicable Federal Specifications.

x. SPECIFICATIONS. In any case of discrepancy in the specifications, the matter shall be immediately submitted to the Contracting Officer, without whose decision said discrepancy shall not be adjusted by the Contractor, save only at his own risk and expense. Any changes affecting the scope of the work shall originate from and be approved by the Contracting Officer.

xi. SCHEDULING CONTRACT WORK. The contractor shall make necessary arrangement with the Facility Manager and USGS Technical Liaison to perform the work and shall arrange and schedule his work so that the minimum amount of interference with government activities will result.

xii. USE OF BUILDING FACILITIES. The contractor may use utility services and toilet facilities of the building subject to approval of the Facility Manager.

xiii. CONDITIONS AFFECTING THE WORK. It will be the responsibility of the contractor to inspect the site, determine quality of work involved. Compare the specifications with the work to be done, and inform themselves as to all conditions, including other work, if any, being performed. Failure to do so will in no way relieve the successful contractor from the necessity of furnishing any materials or performing any work that may be required to carry out the contract in accordance with the true intent and meaning of the specifications without additional cost to the Government.

xiv. EMPLOYEES. The contractor shall be responsible at all times for the supervision and control of the employees that may be assigned to render services under the contract. Fully qualified work personnel shall be available for work on the date this purchase order begins and shall be maintained throughout the period of performance.

xv. LICENSES-PERMITS. The contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses or permits, and for complying with any Federal, State, and Municipal laws, codes and regulations in connection with the execution of the work.

xvi. ACCIDENT PREVENTION AND FIRE HAZARDS. The contractor shall take all necessary precautions to prevent fires or injury to the public, building occupant(s), or damage to property of others during the performance of this contract. For the purpose of this contract, the public or building occupant shall include all persons not employed by the contractor or a subcontractor working under his/her direction. If welding is required, permission shall be obtained from the COTR.

xvii. INDEMNITY. The contractor shall confine all work on Government premises to areas authorized or approved by the Contracting Officer or COTR. The contractor shall save and keep harmless and indemnify the Government against any and all liability claims, and costs of whatsoever kind and nature of injury to or death of any person or persons and for loss or damage to any property (Government or otherwise) occurring in connection with or in any way incident to or arising out of the occupancy, use, service, operations, or performance of work in connection with this contract, resulting in whole or part from the negligent acts or omissions of the contractor.

xviii. GREEN ACQUISITIONS. The USGS is committed to promoting the natural environment and protecting the health and well-being of people. In the performance of work under this contract, the Contractor shall exert its best efforts to provide services in a manner that will promote the natural environment and protect health and well-being. Green purchasing or environmentally preferable contracting includes the initiatives described below:

1. Alternative Fuels and Vehicles are described at http://www.afdc.energy.gov/afdc/

2. Biobased Products are described at http://www.biopreferred.gov/

3. Energy efficient products are described at http://energystar.gov/products for Energy Star products and at http://www.eere.energy.gov/femp/procurement for FEMP designated products

4. Environmentally Preferable Computers are described at http://www.epeat.net

5. Significant New Alternatives Program (SNAP) are described at http://www.epa.gov/snap/overview-snap

6. The Comprehensive Procurement Guidelines promote the use of recovered and recycled products at http://www3.epa.gov/epawaste/conserve/tools/cpg/index.htm

7. Water efficient products and services are described at http://www3.epa.gov/watersense/about_us/what_is_ws.htm

f. Construction Contract Administration

i. Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract image1.png