This Performance Work Statement (PWS) details the Bureau of Land Management's (BLM) requirement for outfitting a 2025 Chevrolet Silverado 1500 (VIN: 3GCUKAED7SG203530) as a law enforcement vehicle for the California region. The comprehensive outfitting includes installing emergency equipment such as LED light bars, sirens, communication systems, surveillance equipment, storage solutions, safety gear, vehicle graphics, and specialized law enforcement components. Specific installation tasks include exterior vinyl decals, emergency lighting systems (front and rear), radio antennas, interior console modifications, weapon locks, prisoner transport cage options, and electrical system upgrades.

The contract (Solicitation Number: 140L1225Q0041) requires the contractor to perform complete vehicle builds, potentially reuse existing parts, and provide decommissioning services for old law enforcement vehicles. The period of performance is expected to be completed by September 1st, 2025, with work conducted during regular business hours (7:00am to 4:00pm, Monday through Friday). The primary objective is to equip the BLM with a fully functional law enforcement vehicle meeting California emergency vehicle standards, with the contractor responsible for professional installation, equipment functionality, and adherence to specified technical requirements.

View the file

Other files

File Type Posted
Sol_140L1225Q0041.pdf PDF
B08_Attachment_2_Wage_Det_2015-5627.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT TITLE: Law Enforcement Vehicle Outfitting

Contents

PWS 1.0 Background on the Government’s Requirement2
PWS 2.0 General Scope of Work2
PWS 3.0 Overall Objective(s)2
PWS 4.0 Specific Tasks2
PWS 5.0 Delivery / Performance Schedule7
PWS 6.0 Government-Furnished Property, Materials, Services7
PWS 7.0 Security and Administrative Matters7
PWS 8.0 Technical Exhibits and Definitions8
PERFORMANCE SUMMARY REQUIREMENTS (PRS)9

PWS 1.0 Background on the Government’s Requirement

The Bureau of Land Management (BLM) has a need for law enforcement vehicle outfitting. A stock vehicle as received does not contain any components necessary to conduct regular Law Enforcement duties, nor does it contain upgrades to meet Law Enforcement police standards of operation. Proper and professional installation of integrated equipment is necessary for the safe and legal use of the patrol vehicle by federal law enforcement officers. The work shall meet California state specifications for the vehicle to qualify as an emergency vehicle. In addition, this will cover the decommissioning of old law enforcement vehicle and the removal of law enforcement equipment prior to disposal.

PWS 2.0 General Scope of Work

The contractor shall provide complete outfitting services for law enforcement vehicles, which includes:

Complete Builds:

The contractor will perform complete builds of law enforcement vehicles, involving the installation of all necessary components for a fully outfitted vehicle. This includes, but is not limited to:

Emergency lighting systems (e.g., light bars, interior lights) Sirens and speaker systems Communication equipment (e.g., radios, mobile data terminals) Surveillance systems (e.g., dash cameras, body cameras) Storage solutions (e.g., equipment racks, gun racks) Safety equipment (e.g., first aid kits, fire extinguishers) Vehicle graphics and decals Other specialized equipment as required by the agency

Reusing Parts:

The contractor will also conduct builds that involve the reuse of existing parts and components. This includes:

Assessment and evaluation of existing parts and components for reuse in the outfitting process.

Proper installation and integration of reused components with new systems to ensure functionality and safety.

Documentation of all reused parts, including their condition, compatibility, and any modifications made during installation.

Decommissioning Vehicles:

The contractor will provide decommissioning services for existing law enforcement vehicles, which includes:

Safe removal of law enforcement equipment and components from decommissioned vehicles.

Thorough testing of removed parts for viability and functionality, with the intent to reuse them in new builds or other applications.

Documentation of the condition and testing results of all removed parts, ensuring transparency and traceability for future use.

Place of Performance:

Repairs and Service of Equipment added to the vehicle must be done at the Contractor’s place of business.

The Government will transport the Vehicle and Government Furnished Equipment (GFE) to the Contractor’s place a business.

Period of Performance:

The period of performance is expected to be completed by September 1st, 2025 PWS 3.0 Overall Objective(s)

The objective of this work is to provide the Bureau of Land Management a vehicle that will enable them to perform their duties in a safe and reliable vehicle meeting agency requirements and applicable laws governing emergency vehicles for the state of California.

PWS 4.0 Specific Tasks

Vehicle will be: 2025 Chevrolet Silverado 1500 VIN: 3GCUKAED7SG203530

Task 1: Installation of indicted parts. Items to be provided by Vendor will be Brand Name or Equal. Vendor will consult with customer on placement of all center console items. Electrical components and equipment will be housed underneath rear passenger seat inside of vendor provided locking storage box. Photos added as reference.

VEHICLE EXTERIOR

1. Install vinyl decals and brown stripe on exterior of vehicle. Provided

2. Install- low profile Off-road bumper (preferred with cut outs for off-road light bar/IR light) Not Provided

FRONT GRILL/ FRONT QUARTER PANELS

1. Install –Two forward facing LED light heads with mounts behind grill and program to meet California vehicle code standard- Solid Red (LED Red/Blue 3 light module) Provided

2. Install - Two side facing LED light heads, surface mount / low profile lights on left and right, front quarter panel/fender. (LED Red/Blue 3 light module) Not Provided

3. Install- Rigid, Feniex or equivalent AI LED Flood /Driving Light Bar LED on bumper Provided

4. Install – 2 100 Siren speakers behind grill or bumper Provided

5. Install- Two Hide a Way LED inserts in headlight housing (LED Red/Blue) Not Provided

TAILGATE/REAR QUARTER PANEL/Bumper

1. Install -Two Hide a Way LED Inserts in taillights (LED Red/Blue) Not Provided

2. Install - Two red/blue LED lights License plate mount mounted to rear tailgate. (LED Red/Blue 3 light module) Not Provided

3. Install - Two LED lights surface mount / low profile mounted to rear side quarter panels. (LED Red/Blue 3 light module) Not Provided

4. Install – 6-8 LED Light stick inside rear facing glass of truck. (Amber/Red/Blue) Not Provided

5. Install- Two white LED Rigid or equivalent brand lights with on/off switch not tied into reverse lights- flush mounted to rear bumper Provided

ROOF

1. Install – LED programable light bar 54” Whelen preferred. (White- Takedowns, Scene lighting, and Alley, Red/Blue front and rear) Provided

2. Install - Radio antennas

a. Motorola Radio Antenna Provided

b. Cellular Booster Antenna Provided

3. Install - “Sat-Rad”/GPS Radio system antenna (dome/disc) Provided

INSIDE WINDSHIELD / DASH/CELING

1. Install – Cellular 4G/5G Booster. Provided

2. Install –Ignition override / “Secure Idle” switch with button installed at front top of center console or on dash. Not Provided

CENTER CONSOLE- consult with customer on specific placement

1. Install - Floor plate between seats for mounting console. Not Provided

2. Install – Center Console Havis 12.5” wide Flat 30” vehicle specific console or Troy Products 20″ WIDE-BODY CONSOLE WITH OPEN STORAGE Not Provided

3. Install – Motorola dash mount mobile radio Provided

4. Install – Leave Additional Space/plates for additional radio(s), if applicable

5. Install- 3 Magnetic Radio Mic clips for handheld microphones. Not Provided

6. Install– Satellite Radio /Mic (Mic mounted on console) Provided

7. Install – Siren/PA control box with PA mic. Provided

8. Install – Emergency light control module. Provided

9. Install OBD II emergency lighting interface. Not Provided

10. Program Control Switches – (Whelen is preferred for continuity of fleet)

a. Front off-road driving lights

b. Rear bumper light on/off

c. Rear Prisoner Light

d. Gun Locks

e. Alley Lights

f. Scene Lights

g. Directional Bar (Light Bar)

h. Dim light bar setting.

i. Take Down

j. Wail

k. Air horn

l. Manual Siren selection

m. Yelp

n. Radio

o. Hands Free

p. Black out to turn off lights from accessories.

q. Code 1, 2, 3 response toggle.

11. Install - 12 volt, 3 plug auxiliary power ports x3 Not Provided

12. Install – Flush mount 2 port USB charge socket x2. Not Provided

13. Install – Stream light, Surefire or equivalent Flashlight and Charger x2 Provided

14. Install – Hidden directed powered gun lock switch. Not Provided

15. Install- COMPUTER docking station post (Port replication/Power supply) Not Provided

16. Install color coded wiring loom with schematic (Provide BLM schematic). Loom should be well dressed and fastened. Not Provided

ENGINE COMPARTMENT or VEHICLE INTERIOR The preferred product to accomplish the following is manufactured by 911circuits. (http://www.911circuits.com/ch15-1)

1. Install - Charge guard system to prevent battery drain when minimum voltage is reached (minimum voltage has ability to start truck) Not Provided

2. Install - Circuit breaker, with ability to disconnect emergency equipment from OEM electrical system Not Provided

3. Provide Master auxiliary power/fuse block or box for all aftermarket electronics to access fuses (all fuses labeled) that is easily accessible. (can be mounted in vehicle interior if necessary) Not Provided

BEHIND CONSOLE

1. Install – Rifle custom mount and 1 locks with a 10 second timer. Rifle mount will be vertical overhead (Shotgun lock and Rifle lock to disable the action. Rifle lock must accommodate optics (ACOG/Aim point red dot) mounted on the top rail of the rifle) vendor will consult with customer on gun lock locations prior to installation. Provided

2. Install – double gunlock switch that control gunlocks, one switch on top of console (should be part of emergency control module) and one switch hidden (Discuss location with BLM). Additionally, hidden switch for gunlocks should be disabled without ignition power. Not Provided

PRISONER TRANSPORT CAGE

1. Install- Dual Prisoner transport cage. Not Provided

2. Install- Steel window barrier on both passenger windows. Not Provided

3. Remove and replace- Factory inner door skins with metal door skins. Not Provided

4. Deactivate- Both passenger rear door lock and window controls but leave operable from driver door controls. Not Provided

5. Install- 2 Rear downward facing white/red LED flush / low profile mounted into prisoner cage. Not Provided

6. Install lockable under-seat storage box under rear seat. Havis Lockable Under-Seat Storage Box. Provided

PWS 5.0 Delivery / Performance Schedule

What: A vehicle that is equipped with all the indicated parts to be a fully functional law enforcement vehicle.

When: Must be operational when vehicle is fully outfitted.

PWS 6.0 Government-Furnished Property, Materials, Services

General:

The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Performance Work Statement, except for those items specified as government furnished.

Materials:

The Government shall furnish materials to assist the Contractor in meeting the requirement of this contract, as listed above as BLM provided.

Services: The Government will provide a customer point of contact at the time of award to discuss the installation location of key items in the vehicle PWS 7.0 Security and Administrative Matters

Regular Work Hours:

The performance period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 4:00pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made for access to the work site.

Communications:

“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.

Federal Holidays:

The following Federal Legal Holidays are observed:

New Year’s DayMartin Luther King, Jr. Day
President’s DayMemorial Day
Independence DayLabor Day
Columbus DayVeterans Day
Thanksgiving DayChristmas Day

Fire Danger Season:

If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

PWS 8.0 Technical Exhibits and Definitions

Standard Definitions:

Physical Condition The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.

Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

Quality Assurance (QA) Surveillance of Contractor performance to determine performance requirements are met.

Performance Requirements Summary (PRS) (see Technical Exhibit below) The PRS identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.

Quality Control Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.

Performance Work Statement (PWS)

PWS Page 5

PERFORMANCE REQUIREMENTS SUMMARY (PRS)

Work Tasks to be Performed
Acceptable Quality Level
Method of Surveillance
Consequences, Remedies, and/or Deduction(s)

Task 1: Installation of indicated items including lights, radio, equipment, etc.

Electrical equipment will be installed in a safe and neat manner free of tangles and bundling up.

The customer will inspect random installation sites to see that wiring was done in a safe manner
Vendor will be responsible for redoing the installation till the wires are done in a safe and neat manner.
Vendor will communicate the customer POC for the installation of previously indicated parts
Vendor will communicate with the customer prior to installation of the indicated parts.
Customer should receive a phone call or an email indicating desire to set meeting to a meeting to discuss the work
If three instances of non-communication prior to installation maybe result in a 10% deduction of contract price.
Parts will last as indicated under manufacturer warranty
Parts added to the vehicle will last for the estimated service life as listed under manufacturer warranty
Equipment will remain functional.
If the equipment does not remain functional the vendor will replace the parts that were not provided by BLM.