This document is a Performance Work Statement (PWS) for a Request for Proposals (RFP) to provide maintenance and site improvements at three abandoned mine land (AML) sites in southwest Colorado - the Anaconda Mine, GNOME Mine, and Polar Star Complex. The work includes soil sampling and analysis, lime amendment to raise soil pH and allow revegetation, erosion control measures, and drainage improvements. The period of performance is 660 days from notice to proceed. The contract will be awarded by September 30, 2024. All work must be performed on BLM-managed property. The contractor must develop a work plan, sampling plan, health and safety plan, and quality assurance plan for BLM's review and approval prior to field activities. The contractor must possess the required expertise, knowledge, equipment, and tools to meet the government's objectives in accordance with industry standards. There is no incumbent contractor identified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1724R0008.pdf | ||
| B08_ATTACHMENT_2-_WAGE_RATES_2015-5435.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 July 9, 2024
Request for Proposals – Task Order under an Existing IDIQ 140L0620D0008 North Wind Construction 140L0620D0009 Applied Intellect Joint Venture
Project Title: Anaconda Mine, GNOME Mine and Polar Star Complex AML Sites O&M
Gunnison, Hinsdale and San Juan Counties, Colorado
Period of Performance: 660 days from NTP
Additional information:
Please submit total cost and separate costs for each separate Abandoned Mine Land Site.
Virtual or on site Pre-Bid offered based on availability of bidders and snowpack conditions.
Award by September 30, 2024-
This contract is for maintenance work at three different project areas located on BLM administered lands in the Gunnison Field Office area in southwest Colorado. The Anaconda Mine, Gnome, and Polar Star AML sites.
Site Backgrounds
Anaconda Mine:
The historic Anaconda Mine Site includes a backfilled shaft that is beginning to subside and an acidic waste rock pad and collar around the old shaft. The mine is in a massive sulfide deposit located within the Gunnison Gold Belt. The acidic runoff from the waste rock is causing a dead zone to migrate down slope to a drainage. The objective is to amend the soil with lime (pulverized and crushed) to raise the pH of the soil to allow for revegetation of the site. The site is located at latitude 38.341857°, longitude -107.101527°. The site can also be described as located in Township 47 North, Range 2 West, section 9, SE1/4SW1/4NE1/4, NMPM.
The site has been determined to be not eligible for listing on the National Register of Historic Places (NRHP). No cultural resource monitoring of the site is required.
The site is located approximately 450 feet from CO Highway 149. Materials and equipment can easily access the project area. The area of the Site is approximately 1.5 acres. Staging of materials and equipment can be set up at the edge of the Site.
Scope of work:
The work will consist of, but is not necessarily limited to, providing all labor, materials, equipment, earthwork, and incidentals necessary to complete the following maintenance and site improvements:
Activities to be completed include:
• Sample soil to determine concentrations of heavy metals and other contaminants (minimum 20 samples TAL metals) utilizing appropriate field sampling parameters.
2 July 9, 2024
• On-site analysis of soil with an XRF unit in a grid pattern to identify hot spots in the waste rock.
• Determine depth of waste rock and contaminated soil to be used for determining volume of lime needed.
• Determine pH of the soil and calculate amount of lime amendment needed to raise the pH to a suitable level to support vegetative growth.
• Describe equipment needed to amend the waste rock and soil, regrade and recontour the site. Describe measures and materials that will be used to for erosion control.
Please provide a technical proposal outlining all means and methods (which may include sketches, preliminary drawings, etc.) for the above activities.
BLM will review and approve all submittals before any mobilization for construction or construction work begins. The contractor should submit drafts of all submittals to the project COR for comments. All comments should be addressed before construction work begins.
Site Map/Photos:
Location of Anaconda Mine Site.
3 July 9, 2024
GNOME Mine- Background:
The historic GNOME Mine Site includes a backfilled shaft a draining adit and a waste rock pile.
The Site had reclamation work done in 2018, consisting of channeling the drainage away from the waste rock pile to avoid infiltration and development of acid mine drainage (AMD). The waste rock was then treated with an experimental biologic agent to reduce sulfur and other contaminants in the waste rock. The Site now needs maintenance to prevent the water from infiltrating the waste rock dump and the addition of a lime amendment to raise the pH of the waste rock dump. The draining adit connects with the Lake Fork of the Gunnison River a short distance downstream. The objective is to amend the soil with lime (pulverized and crushed) to raise the pH of the soil to allow for revegetation of the site and redirect the mine drainage. The site is located at latitude 37.920681°, longitude -107.516869°. The site can also be described as located in Township 42 North, Range 6 West, section 3, SE1/4SW1/4SW1/4, NMPM.
The site has been determined to be not eligible for listing on the National Register of Historic Places (NRHP). No cultural resource monitoring of the site is required.
The site is located in American Basin on the Alpine Loop Scenic Byway. The site is located approximately 150 feet from Hinsdale County Road 12 (CR 12), which connects with Hinsdale CR30. A small trailer may be able to move materials and smaller equipment 4.5 miles from Burrows Park/Silver Creek to the site. Larger sized equipment cannot be moved by a long trailer or semi; larger equipment will have to be walked in approximately 8.5 miles from the junction of Hinsdale CR 30 and CR35 (the road will not accommodate long trailered vehicles). Due to the limited access to the site, equipment and materials will be brought into the site from the staging area; sling drop of materials may be another option.
Scope of work:
The work will consist of, but is not necessarily limited to, providing all labor, materials, equipment, earthwork, and incidentals necessary to complete the following maintenance and site improvements:
Activities to be completed include:
• Sample water from adit discharge and adjacent stream to the east and below the holding pond and soils from the toe of the repository to determine contaminants and concentrations (minimum 20 samples TAL metals).
• Sample soil to determine concentrations of heavy metals and other contaminants (minimum 20 samples TAL metals) utilizing appropriate field sampling parameters.
• On-site analysis of soil with an XRF unit in a grid pattern to identify hot spots in the waste rock.
• Determine depth of waste rock and contaminated soil to be used for determining volume of lime needed for treatment.
• Determine pH of the soil and calculate amount of lime amendment needed to raise the pH to a suitable level to support vegetative growth.
4 July 9, 2024
• Describe equipment needed to amend the waste rock and soil, regrade and recontour the site. Describe measures and materials that will be used to for erosion control.
• Drainage ditch improvement to redirect the flow away from the waste rock dump back to the settling pond.
• Plan for mob/demob of materials and equipment to the site.
Please provide a technical proposal outlining all means and methods (which may include sketches, preliminary drawings, etc.) for the above activities.
BLM will review and approve all submittals before any mobilization for construction or construction work begins. The contractor should submit drafts of all submittals to the project COR for comments. All comments should be addressed before construction work begins.
Site Map/Photos:
Route to GNOME Mine from junction CR 30 and CR 15.
5 July 9, 2024
Route to GNOME Mine from Burrows Park/Silver Creek along CR 30.
6 July 9, 2024
Polar Star Complex:
The historic Polar Star Mine Complex AML Site includes waste rock dumps that are contributing to the degradation of water quality in Palmetto Gulch. The site area is on top of Engineer Pass, straddling both Hinsdale and Ouray Counties. Mine waste from waste rock dumps and adjacent mines are contaminating soil and stream water quality in Upper Palmetto Gulch. The objective of the work is to establish and map high levels of contamination and determine the quantities of materials of materials needed to neutralize or immobilize the contaminant sources to prevent further contamination. The site is located at latitude 37.971141°, longitude -107.577520°. The site can also be described as located in Township 43 North, Range 7 West, section 24, NE1/4SE1/4NE1/4, and Township 43 North, Range 6 West, section 19, NW1/4NW1/4SW1/4
NMPM.
The site has been determined to be not eligible for listing on the National Register of Historic Places (NRHP). No cultural resource monitoring of the site is required.
The site is located approximately 1000 feet from Hinsdale CR 20 near Engineer Pass along the Alpine Loop Scenic Byway. CO Highway 149. Materials and equipment can easily access the project area. The site is accessible by existing roads over Engineer Pass which is a 4-wheel drive road that is heavily travelled by recreational UTVs during the summer months.
Scope of work:
The work will consist of, but is not necessarily limited to, providing all labor, materials, equipment, earthwork, and incidentals necessary to complete the following maintenance and site improvements:
Activities to be completed include:
• Sample water from adit discharge and adjacent stream to the east and below the holding pond and soils from the toe of the repository to determine contaminants and concentrations (minimum 20 samples TAL metals).
• Sample soil to determine concentrations of heavy metals and other contaminants (minimum 20 samples TAL metals) utilizing appropriate field sampling parameters.
• On-site analysis of soil with an XRF unit in a grid pattern to identify hot spots in the waste rock.
• Determine depth of waste rock and contaminated soil to be used for determining volume of lime needed for treatment.
• Determine pH of the soil and calculate amount of lime amendment needed to raise the pH to a suitable level to support vegetative growth.
• Determine sources of offsite contamination affecting the site and water.
Please provide a technical proposal outlining all means and methods (which may include sketches, preliminary drawings, etc.) for the above activities.
7 July 9, 2024
Site Maps/Photos:
Map of Polar Star Complex AML sites.
8 July 9, 2024
Overview of claim areas, view facing WSW.
9 July 9, 2024
Overview of claim areas from Hough Mine (across valley). View facing SSE.
Contracting information that is common to all sites:
BLM will review and approve all submittals before any mobilization for construction or construction work begins. The contractor should submit drafts of all submittals to the project COR for comments. All comments should be addressed before construction work begins.
All personnel working at the identified sites shall have current OSHA certifications for working at hazardous waste sites, including but not limited to the 40 hour Hazardous Waste Operations and Emergency Response (HAZWOPER) training and current 8-hour HAZWOPER refresher. At a minimum, two field personnel shall be certified in first aid and CPR. The Contractor shall provide all support activities necessary to ensure the safe and effective accomplishment of all work. For all work performed under this contract, the Contractor shall also develop and implement a workplan with health and safety and quality control measures consistent with all applicable federal and state regulatory requirements and standards.
It is the Contractor's responsibility to comply with all applicable federal, state and local laws and regulations and to fulfill the performance objectives of this PWS in a manner that is consistent with any local, state and Federal guidance, policies and regulations, for the duration of the contract.
The Contractor shall provide all personnel, supervision, and other items and non-personal services necessary to perform the work as defined. The Government shall not exercise any supervision or control over any subcontractors performing the work herein. Such subcontractors shall be accountable solely to the prime Contractor who, 10 July 9, 2024 in turn is responsible to the Government. The Contractor must possess all the required expertise, knowledge, equipment and tools required to meet or exceed the government’s objectives in accordance with established industry standards. When possible, BLM will assist the Contractor in obtaining pertinent sampling data, documentary materials, historical information, surveys, maps, photographs, as-builts, site plans, forms, and other material as available. All documentary materials provided to the Contractor or generated by the Contractor over the course of the investigations will remain or become property of the U.S. Government and must be returned to the BLM before final payment.
The Contractor shall identify applicable federal, state and local laws and regulations;
applicable Site-specific orders, agreements, or rules; and perform its work in accordance with said applicable requirements. The Contractor shall ensure that all activities performed by its personnel, subcontractors and suppliers are executed in accordance with said authorities. Any incident of noncompliance noted by the Contractor shall immediately be brought to the attention of the COR telephonically and then by written notice. Nothing in this contract shall relieve the Contractor of its responsibility to comply with applicable laws and regulations. The Contractor shall obtain all permits, licenses, approvals, and/or certificates required or necessary to accomplish the work. When the work to be performed requires facility clearances, such as digging or drilling permits, the Contractor shall obtain such clearances and/or permits, with the assistance of the COR, prior to any drilling or excavating operations.
The Contractor shall coordinate all such work with the COR prior to performing work.
Contractors on environmental sites are required to perform their own utility checks based on Installation-supplied utility maps. The Contractor shall comply with all site-specific time and procedural requirements (federal, state, and local) described in the permits they obtain.
Any service or submittal performed that does not meet contract requirements shall be corrected or re-performed by the Contractor and at no additional cost to the Government.
Task 1 Work Plan and Submittals including Schedule, SAP, HASP, QAPP
Schedule The contractor must provide a written schedule in electronic format before work begins. The schedule will be updated as needed.
Sampling Plan
11 July 9, 2024
A BLM approved field sampling plan will be required prior to any sample collection. If any XRF sampling is required, A minimum of 10% of all XRF samples collected must be sent to a certified laboratory for confirmation analysis.
Health and Safety Plan (HASP) The Contractor is required by regulation to develop and maintain a written safety and health program in compliance with the requirements of Occupational Safety and Health Administration (OSHA) standard 29 Code of Federal Regulations (CFR) 1910.120(b)/29 CFR 1926.65(b). The Contractor shall prepare the HASP in accordance with the requirements of EM 385-1-1 and 29 CFR 1910.120(b)/ 29 CFR 1926.65(b) and other applicable federal, state, and local safety and health requirements. All COVID-19 state, and county protocols must be followed at all times. The HASP shall be developed, approved, and implemented by a qualified Safety and Health Professional appointed by the contractor. The Contractor shall integrate all subcontractor work activities into the HASP, make the HASP available to all contractor and subcontractor employees, and ensure that all subcontractors integrate provisions of the HASP in their work activities.
The draft HASP shall be submitted electronically to the BLM COR and Project Inspector as draft for review. BLM will review the HASP and provide comments to the Contractor. The Contractor shall address all comments and revise the HASP and submit this revision to the BLM COR and PI as a final. The level of detail of the plan should be commensurate with the expected variety and severity of hazards to be encountered. The final HASP shall incorporate or otherwise address all reviewer comments.
Task 2: Field Effort Field work shall be accomplished only on BLM-managed property. No work shall take place off BLM-managed land unless contamination appears to be migrating onto BLM property or off of BLM property.
The smallest, most efficient equipment shall be used to perform the work, as heavy OHV traffic and fragile alpine tundra may be present. The contractor shall stay on existing roads and trails whenever possible. All work locations shall be recorded using a hand-held GPS instrument.
Daily morning safety briefings must be held to ensure all crew members understand the limitations of working in a high alpine environment and driving on steep, narrow single-track roads.
Deliverables
If not otherwise stated in the task order, the following requirements generally apply to all deliverables submitted:
All deliverables shall be submitted electronically, unless otherwise noted, to the following address:
msmeins@blm.gov and dlazorch@blm.gov for distribution via email and/or a SharePoint site.
mailto:msmeins@blm.gov mailto:dlazorch@blm.gov
12 July 9, 2024
Any hard copy deliverables or other necessary correspondence shall be addressed as follows:
Melissa Smeins BLM – Royal Gorge Field Office 3028 East Main Street Canon City, CO 81212
And
Dave Lazorchak BLM-Gunnison Field Office 2500 E New York Ave Gunnison, CO 81230
All draft documents will normally be reviewed within 30 days of receipt unless otherwise specified. Generally, one review will be sufficient. However, based upon the amount or complexity of comments, the Government shall have the option of reviewing drafts until they are satisfactorily revised. The contractor, upon receipt of revision or comments, will generally have 15 days to respond (unless otherwise specified) with the necessary written revisions.
| BLM will review and approve all submittals before any mobilization for construction or construction work begins. The contractor should submit drafts of all submittals to the project COR for comments. All comments should be addressed before construct... |
| Task 1 Work Plan and Submittals including Schedule, SAP, HASP, QAPP |
| Schedule |
| Health and Safety Plan (HASP) |
| Task 2: Field Effort |
| Field work shall be accomplished only on BLM-managed property. No work shall take place off BLM-managed land unless contamination appears to be migrating onto BLM property or off of BLM property. |
| The smallest, most efficient equipment shall be used to perform the work, as heavy OHV traffic and fragile alpine tundra may be present. The contractor shall stay on existing roads and trails whenever possible. All work locations shall be recorded u... |