B08_-_Attachment_1_-_PK-2023-BDWK-Specs_Final_6-19-2023.pdf
PDF 5 MB Posted
- Attached to
- PMIS 324723 Replace Perdido Key Discovery Trail Bo Federal contract opportunity
- Solicitation number
- 140P2024R0033
About this file
This document provides specifications for replacing a boardwalk on the Perdido Key Discovery Trail at Gulf Islands National Seashore. The project involves removing the existing timber boardwalk and constructing a new one to the same footprint. Key details include:
-
The work consists of demolishing the existing boardwalk and replacing it with a new timber boardwalk in the same location. Relevant specifications are provided for demolition, concrete, metals, wood, earthwork, and helical foundation piles.
-
The contractor is responsible for obtaining necessary permits and complying with all applicable regulations. Government-furnished permits include an exemption from the Northwest Florida Water Management District, a no-permit-required letter from Escambia County, and a no-permit-required letter from the Army Corps of Engineers.
-
The contractor must follow safety, quality control, and environmental requirements outlined in the specifications. This includes developing a waste management plan and stormwater pollution prevention plan.
-
The project will be conducted under a single prime contract awarded by the National Park Service for the Department of the Interior.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P2024R0033_Amd_0007.pdf | ||
| Sol_140P2024R0033_Amd_0006.pdf | ||
| B08_Solit_PSP_Vol_II_Solit_Attach_07_GenRefs_doc_0006.pdf | ||
| Sol_140P2024R0033_Amd_0005.pdf | ||
| Sol_140P2024R0033_Amd_0004.pdf | ||
| Sol_140P2024R0033_Amd_0003.pdf | ||
| Perdido_Sign-in_Sheet_0003.pdf | ||
| Sol_140P2024R0033_Amd_0002.pdf | ||
| Sol_140P2024R0033_Amd_0001.pdf | ||
| B08_-_Attachment_3_-_Wage_Determination_-_FL20240203.pdf | ||
| Sol_140P2024R0033.pdf | ||
| B08_-_Attachment_6_-_L-4C_Solit_PSP_Vol_I_Exp.docx | DOCX document | |
| B08_-_Attachment_4_-_Subcontracting_Percentage_Worksheet.xlsx | XLSX spreadsheet | |
| B08_-_Attachment_5_-_L-4D_Solit_PSP_Vol_I_PastPerf.docx | DOCX document | |
| B08_-_Attachment_2_-_Pk-2023-BDWK-Drawings_Final.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GULF ISLANDS NATIONAL SEASHORE
GULF BREEZE, FLORIDA
PERDIDO KEY DISCOVERY NATURE TRAIL
AT JOHNSON BEACH
PARK: GUIS
PMIS NO. 304892B
PROJECT SPECIFICATIONS
100% CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
JUNE 19, 2023
GUIS – 304892B TOC-1
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 32 16 Construction Schedule
01 32 33 Photo Documentation
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements (Includes Statement of Structural Tests and Inspections)
01 42 00 Reference Standards
01 50 00 Temporary Facilities and Controls
01 57 19.12 Noise and Acoustics Management
01 57 23 Under-an-Acre Pollution Prevention (UPP)
01 67 00 Product Requirements
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance (O&M) Data
01 79 00 Demonstration & Training
01 81 13 Sustainable Design Requirements-LEED™ (Leadership in Energy & Environmental Design)
Non-LEED Projects
Supporting Documents
Submittal List (01 33 23)
Closeout and Operation & Maintenance (O&M) Requirements (01 77 00, 01 78 23, 01 79 00)
Project Waste Management Plan Worksheet Sample (01 74 19)
Report of Subsurface Exploration and Geotechnical Engineered Evaluation, (01 11 00)
DIVISION 2: EXISTING CONDITIONS
02 40 00 Demolition
DIVISION 3: CONCRETE
03 20 00 Concrete Reinforcement
03 30 00 Cast in Place Concrete
DIVISION 5: METALS
05 73 00 Ornamental Railings
DIVISION 6: WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry
GUIS – 304892B TOC-2
DIVISION 31: EARTHWORK
31 10 00 Site Clearing
31 23 17 Excavating And Backfilling For Structures
31 66 15 Helical Foundation Piles
GUIS 304892B 01 11 00 - 1
061923 SUMMARY OF WORK
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21
GULF ISLANDS NATIONAL SEASHORE, GUIS, PMIS 304892B
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Contractor Use of Site
3. Public Use of Site
4. Conduct of Operations
5. Work Restrictions
6. Special Construction Requirements
7. Soils Investigation Report
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Gulf Islands National Seashore, Perdido Key Area, Johnson Beach Road, off of
Perdido Key Drive, off of Hwy 292, Pensacola, Florida, 32507, 850-9034-2600. The project is the Perdido Key Nature Trail off of Johnson Beach Road.
B. The Work consists of:
1. Demolition and removal of the existing timber boardwalk and replacement with a new timber boardwalk.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the construction limits indicated on drawings. Do not disturb portions of
Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the Limits of Disturbance shown on the plans.
B. Storage of Materials: Confine storage of materials to staging and storage areas shown on the plans.
C. Parking: Confine parking to areas shown on the plans.
GUIS 304892B 01 11 00 - 2
D. Stockpiling: Confine stockpiling to areas shown on the plans.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
1.4 PUBLIC USE OF SITE
A. The buildings, roads, and park areas will not be closed to the public during construction.
B. Contractor shall conduct his operations to ensure the least inconvenience to public. Building or road closures may be permitted, when required, upon specific approval of Contracting Officer for a maximum of one day.
1.5 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
GUIS 304892B 01 11 00 - 3
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests two (2) business days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 7:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: 7:00 a.m. to 7:00 p.m.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours and length of Utility Shutdowns: As determined by Contracting Officer.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within
25 feet of entrances, operable windows, or outdoor air intakes, or boardwalk. Cigarette butts and other smoking and tobacco related paraphernalia must be properly disposed of and removed from the site.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using
Project Website.
GUIS 304892B 01 11 00 - 4
1.8 SOILS INVESTIGATION REPORT
A. The Report of Subsurface Exploration and Geotechnical Engineering Evaluation, Discovery Trail
Boardwalk Replacement – Perdido Key, June 6, 2022, prepared by GeoHydro Engineers is available as an Appendix.
B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
GUIS 304892B 01 26 01 - 1
061923 CONTRACT MODIFICATION PROCEDURES
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
GULF ISLANDS NATIONAL SEASHORE, GUIS, PMIS 304892B
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating
General Conditions:
1. Project Manager (PM), Assistant Project Manager
GUIS 304892B 01 26 01 - 2
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General
Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
GUIS 304892B 01 26 01 - 3
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General
Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank
GUIS 304892B 01 26 01 - 4
by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of
Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a
Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|
GUIS 304892B 01 26 01 - 5
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense
Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army
Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10%
Profit………………10.0%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
GUIS 304892B 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
GUIS 304892B 01 27 00 - 1
061923 DEFINITION OF CONTRACT LINE ITEMS
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
GULF ISLANDS NATIONAL SEASHORE, GUIS, PMIS 304892B
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 0001, Removal, Disposal, and Replacement of Boardwalk at Perdido
Key Discovery Nature Trail at Johnson Beach.
1. This item consists of removal and disposal of the existing boardwalk and construction of a replacement boardwalk.
2. Measurement for payment will be based on a percentage of work completed.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
GUIS 304892B 01 31 00 - 1
061923 PROJECT MANAGEMENT AND COORDINATION
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
GULF ISLANDS NATIONAL SEASHORE, GUIS, PMIS 304892B
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
GUIS 304892B 01 31 00 - 2
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination
Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
GUIS 304892B 01 31 00 - 3
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 millimeters) but no larger than 30 by
40 inches (750 by 1000 millimeters).
3. Number of Copies: Submit two (2) opaque copies of each submittal. Contracting Officer will return one (1) copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Division 1 documents: The following items shall be submitted a minimum of one week prior to
Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre-
Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)
11. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
C. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on
NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
GUIS 304892B 01 31 00 - 4
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or
Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT WEB SITE
A. Use NPS/DSC management software website for communication throughout contract period on:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
GUIS 304892B 01 31 00 - 5
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
B. Some documents are not suitable to be shared using the NPS/DSC management software website.
Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using NPS/DSC management software website and shall be coordinated with Project team as appropriate.
C. Submit to Contracting Officer a list of employees who will need access to the website. Users will receive an invitation to register from Department of Interior (DOI). Once registered on DOI website, user will be given access to NPS/DSC management software website.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later.
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. NPS/DSC Project website
17. Acceptance/rejection of work
GUIS 304892B 01 31 00 - 6
18. Progress meetings
19. Submittal procedures
20. NPS Final Accessibility Inspection
21. Environmental requirements
22. Permit requirements
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials
26. Value engineering
27. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the
Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting
Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
GUIS 304892B 01 31 00 - 7
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.8 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing
Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Indoor Air Quality (IAQ) Management Plan.
d. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
f. Training for Contractor personnel in accordance with position requirements.
g. Monitoring and documentation of environmental procedures.
GUIS 304892B 01 31 00 - 8
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Noise and Acoustics Management
4. Temporary Storm Water Pollution Prevention Environmental Management
5. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Temporary Storm Water Pollution Prevention
4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Planand Storm Water Pollution Prevention Plan.
1.9 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the
Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the
Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. A Permit Exemption was acquired for the boardwalk removal and construction with identification number PDEX-033-310229-1. The Agency(ies) with Jurisdiction for this permit is the Northwest Florida Water Management District and the permit exemption is for an Environmental Resource Permit (ERP).
GUIS 304892B 01 31 00 - 9
2. A No Permit Required letter was acquired for the boardwalk removal and construction with identification number 0287729-003-NPR/17, Escambia County. The Agency(ies) with
Jurisdiction for this permit is the Florida Department of Environmental Protection, Northwest District.
3. A No Permit Required letter was acquired for the boardwalk removal and construction with identification number SAJ-2021-03698(NPR-EPS). The Agency(ies) with Jurisdiction for this permit is the Department of the Army Corps of Engineers, Jacksonville District, Regulatory Division, North Permits Branch, Pensacola Permits Section.
C. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
D. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS/DSC management software website when permits are obtained.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
February 20, 2023
R. W. Jenkins Gulf Islands National Seashore 1801 Gulf Breeze Parkway Gulf Breeze, FL 32563
Re: Replacement of Boardwalks, Perdido Key Discovery Nature Trail at Johnson Beach Application # PDEX-033-310229-1 (Please reference the above number on all correspondence)
Dear R. W. Jenkins:
The Northwest Florida Water Management District (District) received your application on February 14, 2023 requesting an exemption verification for the referenced project.
Based on the information provided, the District has determined that the project is eligible for an exemption under 62-330.051(2). Therefore, the project will not need a District permit pursuant to rule reference.
This exemption verification only applies to the requirements of the District and does not relieve you of meeting the permit requirements of other agencies. Please contact Megan Byers if you have any questions.
Sincerely, Terry Wells Division of Regulatory Services; ERP Bureau Chief
Replacement of Boardwalks, Perdido Key Discovery Nature Trail at Johnson Beach PDEX-033-310229-1
CERTIFICATE OF SERVICE
I hereby certify that on the below date, a true and correct copy of the foregoing document and all attachments were sent to the applicant and/or their representative(s), and any party having made a written request for notice of agency action, and that section 120.60(3), Florida Statutes has been satisfied.
February 20, 2023 Regulatory Support Specialist I Date
FLORIDA DEPARTMENT OF
Environmental Protection
Northwest District
160 W. Government Street, Suite 308 Pensacola, Florida 32502-5740
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
May 4, 2023
R. W. Jenkins Gulf Islands National Seashore 1801 Gulf Breeze Parkway Gulf Breeze, FL 32563 r_w_jenkins@nps.gov
File No.: 0287729-003-NPR/17, Escambia County File Name: Perdido Key Boardwalk Replacement
Dear R. W. Jenkins , On March 27, 2023, we received your request for verification that a State 404 Program permit will not be required for the activity described below.
The proposed activity is to replace 0.276 acres/12,601 square feet of pile supported boardwalks in the same footprint located at parcel #363S321000000000 in Pensacola, Florida, 32507, Section 36, Township 3 South, Range 32 West, Escambia County.
Based on a review of the information submitted and site inspection conducted by staff, the Department has verified that the activity, as proposed does not involve discharge of dredged or fill material into the waters of the United States and therefore, does not require a permit or other form of authorization under the State 404 Program, as described in Chapter 62-331, Florida Administrative Code (F.A.C.).
This verification reflects current regulations and is only valid for a period of no longer than five years from the date of this letter unless new information warrants a revision of this verification before the expiration date.
Please retain this letter. The activities described above may be inspected by authorized state personnel in the future to ensure compliance with appropriate statutes and administrative codes.
If the activities are not in compliance, you may be subject to enforcement action and possible penalties.
This letter does not relieve you from the responsibility of obtaining other federal, state (including ERP), or local authorizations that maybe required for this activity.
File Name: Perdido Key Boardwalk Replacement FDEP File No.: 0287729-003-NPR/17
If you have any questions regarding this letter or permitting requirements, please contact James Hynes by telephone at 850-595-0582 or by e-mail at James.Hynes@FloridaDEP.gov.
Russell Sullivan Environmental Manager
RS;jh
Enclosures:
Project Drawings, 29 Pages WOTUS Form, 5 Pages cc:
James Hynes, FDEP, James.Hynes@FloridaDEP.gov Russell Sullivan, FDEP, Russell.Sullivan@FloridaDEP.gov Blake Chapman, FDEP, Blake.A.Chapman@FloridaDEP.gov R.W. Jenkins, Applicant, r_w_jenkins@nps.gov David Freedman, Consultant, davidf@freedmanengineering.com
Regulatory Division North Permits Branch Pensacola Permits Section
SAJ-2021-03698 (NPR-EPS)
R.W. Jenkins Gulf Islands National Seashore National Park Service 1801 Gulf Breeze Parkway Gulf Breeze, FL 32563
Dear Sir or Madam:
Reference is made to the application received on February 24, 2023, for a Department of the Army permit to replace an existing boardwalk. The proposed project site is located at the Perdido Key Discovery Trail at Johnson Beach, Gulf Islands National Seashore, at 13300 Johnson Beach Road, Pensacola, Escambia County, Florida. The application has been assigned the file number SAJ-2021-03698(NPR-EPS).
Section 10 of the Rivers and Harbors Act of 1899
The project as proposed will not require a Department of the Army permit in accordance with Section 10 of the Rivers and Harbors Act of 1899 as it is not located within a navigable water of the United States.
Section 404 of the Clean Water Act
The U.S. Army Corps of Engineers (Corps) has determined that the proposed project will not require a Department of the Army permit in accordance with Section 404 of the Clean Water Act. The proposed work may occur in waters of the United States that were retained under Corps regulatory authority in accordance with the Memorandum of Agreement Between the Florida Department of Environmental Protection and the Department of the Army dated August 5, 2020. However, the Corps determined that the proposed work does not involve the discharge of dredged or fill material. Provided the work is done in accordance with the enclosed drawings, Department of the Army authorization will not be required.
This determination of “No Permit Required” does not address nor include any consideration for geographic jurisdiction and shall not be interpreted as such.
DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS, JACKSONVILLE DISTRICT
41 N. JEFFERSON STREET, SUITE 301
PENSACOLA, FLORIDA 32502
May 18, 2023
REPLY TO
ATTENTION OF
-2-
Additionally, your project site may contain species protected by the Endangered Species Act (ESA) of 1972, as amended. You should contact your local U.S. Fish and Wildlife Service (FWS) office to determine if federally listed species or their habitat are present on your project site. If it is determined that federally listed species may be affected by the proposed project, authorization for "incidental take" may be required. FWS offices can be contacted by the following telephone numbers: Jacksonville at 904-232-2580; Panama City at 850-769-0552; St.
Petersburg at 727-570-5398; or Vero Beach at 772-562-3909.
This letter does not obviate the requirement to obtain any other Federal, State, or local permits that may be necessary for your project. Should you have any questions, please contact Ed Sarfert at the letterhead address, by email at edward.p.sarfert@usace.army.mil, or by telephone at 850-439-9533.
Thank you for your cooperation with our permit program. The Corps Jacksonville District Regulatory Division is committed to improving service to our customers. We strive to perform our duty in a friendly and timely manner while working to preserve our environment. We invite you to take a few minutes to visit http://per2.nwp.usace.army.mil/survey.html and complete our automated Customer Service Survey. Your input is appreciated – favorable or otherwise.
Please be aware this web address is case sensitive and should be entered as it appears above.
Ed Sarfert Senior Project Manager
Cc: Jolene Williams, NPS Bruce Leutscher, NPS Ashley Warren, NPS David Freedman, PE, Freedman Engineering Group
Enclosures http://per2.nwp.usace.army.mil/survey.html
GUIS 304892B 01 32 18 - 1
061923 CONSTRUCTION SCHEDULE
NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 5-11-21
GULF ISLANDS NATIONAL SEASHORE, GUIS, PMIS 304892B
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and
Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and…
This is the start of the file's text. The full file is on GovTribe.