B08_Attachment_1_HVAC_SOW_Final.docx
DOCX document 802 KB Posted
- Attached to
- REPLACE MAINTENANCE HVAC SYSTEMS
- Solicitation number
- 140P8526Q0057
About this file
This is a Statement of Work (SOW) for HVAC System Replacement and Upgrade at John Muir National Historic Site's maintenance facilities in Martinez, California. The contractor must provide all labor, supervision, materials, equipment, tools, transportation, permits, and disposal necessary to remove and replace existing HVAC systems, including installation of air conditioning in previously unconditioned spaces, and all associated electrical and mechanical modifications, testing, startup, and commissioning.
The scope requires demolition and removal of three existing heating units (Ultra V Advantage furnace in maintenance office, Infra-Rez ceiling-mounted heater in woodworking shop, and X-106 Bryant Plus furnace in maintenance garage) along with associated thermostats, controls, refrigerant, and piping. The contractor must install three new commercial-grade, high-efficiency heating systems and air conditioning systems in the maintenance office and garage areas, perform ductwork modifications, refrigerant piping, condensate drainage, venting, electrical disconnects, and control wiring, and provide programmable thermostats allowing independent temperature control of each conditioned area. All work must comply with current federal and state energy efficiency standards, OSHA requirements, and applicable federal, state, and local codes. The contractor shall obtain all required permits and inspections, coordinate utility shutdowns with the government, perform startup and operational testing, and provide a minimum one-year warranty on workmanship. Completion must occur within sixty (60) calendar days after receipt of Notice to Proceed, with submittals including manufacturer product data, equipment cut sheets, warranty information, operation and maintenance manuals, and as-built drawings if significant layout changes occur. This is a Small Business set-aside procurement with a construction magnitude between $25,000 and $100,000, under NAICS code 238220.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_Attachment_3_140P8526Q0057_Tech_Info_Form.docx | DOCX document | |
| Sol_140P8526Q0057.pdf | ||
| B08_Attachment_2_Wage_Determination_CA20260016.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work HVAC System Replacement and Upgrade – Maintenance Facilities Scope of Work HVAC System Replacement and Upgrade – Maintenance Facilities
1.0 Project Overview
The Contractor shall provide all labor, supervision, materials, equipment, tools, transportation, permits, incidentals, and disposal necessary to remove, replace, and upgrade existing HVAC systems at maintenance facilities located at John Muir National Historic Site.
The work includes replacement of existing heating equipment, installation of air conditioning systems in previously unconditioned spaces, associated electrical and mechanical modifications, testing, startup, and commissioning of all installed systems.
The Contractor shall field verify all existing conditions and dimensions prior to beginning work.
1.1 Place of Performance
The place of performance for this project is:
John Muir National Historic Site Maintenance Building 1415 Franklin Canyon Rd Martinez, CA 94553
All work shall be performed at the Government facilities located within the park boundaries unless otherwise approved by the Contracting Officer.
2.0 Scope of Services
2.1 Existing Conditions
The Contractor shall verify all field conditions, measurements, utility connections, and existing system configurations prior to installation.
Any discrepancies or unforeseen conditions shall be immediately brought to the attention of the Contracting Officer and COR prior to proceeding with affected work.
2.2 Demolition and Removal
The Contractor shall remove and properly dispose of existing HVAC equipment, components, and associated materials, including but not limited to:
• One (1) existing furnace serving the maintenance office area (Ultra V Advantage 93, G1D93AC090D20C-1)
• One (1) ceiling-mounted heating unit serving the woodworking shop (Infra-Rez Heater By Reznor)
• One (1) existing furnace serving the maintenance equipment repair/storage garage (X-106 Bryant Plus 90
• Existing thermostats and controls associated with replaced equipment (Honeywell-T8000C- Maint Office Area, Emerson-1F83C-11PR- Woodworking Shop, Totaline Signature-CPV220-Part Number P374-2200- Maint Garage)
• Associated refrigerant, piping, and obsolete HVAC components as necessary
Please see the below attached pictures of the current system and site for additional information.
The Contractor shall recover and dispose of refrigerants in accordance with EPA requirements and all applicable federal, state, and local regulations.
The Contractor shall protect adjacent finishes, equipment, utilities, and building components during demolition activities.
2.3 HVAC Equipment Installation
The Contractor shall furnish and install new HVAC equipment sized appropriately for the existing facilities and intended operational use.
New equipment shall include:
• One (1) high-efficiency heating system for the maintenance office area
• One (1) replacement heating unit for the woodworking shop
• One (1) high-efficiency heating system for the maintenance equipment repair/storage garage
• Air conditioning systems for the maintenance office area and maintenance equipment repair/storage garage Equipment shall be commercial-grade and suitable for continuous use in office and maintenance/shop environments.
Minimum efficiency requirements shall comply with current applicable federal and state energy efficiency standards.
The Contractor shall provide manufacturer product data and equipment specifications for Government review prior to installation.
2.4 HVAC System Requirements
The Contractor shall ensure all systems are properly installed, balanced, and fully operational.
Work shall include, but not be limited to:
• Ductwork modifications as required
• Refrigerant piping
• Condensate drain piping
• Venting components
• Air distribution components
• Electrical disconnects
• Controls wiring
• Thermostats and programmable controls
• Equipment pads, supports, and mounting hardware as required
Existing ductwork may be reused if determined by the Contractor to be in serviceable condition and compatible with the new equipment.
All electrical work shall comply with applicable codes and shall be coordinated with existing building electrical service.
2.5 Controls
The Contractor shall provide programmable thermostats and associated controls for all new systems.
Controls shall allow independent temperature control of each conditioned area.
3.0 Permits and Inspections
The Contractor shall obtain and pay for all permits, inspections, licenses, and approvals required for performance of the work unless otherwise directed by the Government.
The Contractor shall coordinate all required inspections with the appropriate authorities having jurisdiction.
4.0 Safety Requirements
The Contractor shall comply with all applicable OSHA requirements, federal regulations, state regulations, and local codes.
The Contractor shall maintain a safe worksite and minimize disruption to ongoing facility operations.
The Contractor shall protect Government property and maintain safe pedestrian and vehicle access throughout the project.
5.0 Construction Operations
Normal working hours shall be coordinated with the COR.
Any utility shutdowns or disruptions to occupied areas shall be coordinated in advance with the Government.
The Contractor shall maintain the worksite in a clean and orderly condition on a daily basis and remove all construction debris from Government property.
6.0 Testing and Commissioning
Upon completion of installation, the Contractor shall:
• Perform startup and operational testing of all systems
• Verify proper airflow and temperature control
• Test heating and cooling functions
• Verify thermostat and control operation
• Correct deficiencies identified during testing prior to final acceptance
7.0 Submittals and Deliverables
The Contractor shall provide the following submittals:
• Manufacturer product data and specifications
• Equipment cut sheets
• Warranty information
• Operation and maintenance manuals
• Startup and testing documentation
• As-built drawings if significant layout changes occur
8.0 Warranty
The Contractor shall provide a minimum one-year warranty on workmanship and installation beginning on the date of Government acceptance.
Manufacturer warranties shall be transferred to the Government upon project completion.
9.0 Period of Performance
The Contractor shall complete all work within sixty (60) calendar days after receipt of the Notice to Proceed.
Maintenance Office Area:
Wood Working Shop:
Maintenance Equipment/Storage Garage: