33-670 Fire Alarm System Upgrade

GENERAL STATEMENT OF WORK

(SOW)

July 22, 2021

Upgrade fire alarm system at building 33-670 located on Pine Bluff Arsenal to full comply with the most recent NFPA (National Fire Protection Agency) and UFC (Unified Facilities Criteria) guidance.

Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform the work as defined in this SOW. Contractor is responsible for purchasing all of the equipment and ancillary supplies necessary for work completion.

All materials to be installed shall be new, free of defect and in compliance with the specifications and drawings within this solicitation and resulting contract. All materials and workmanship shall be subject to the approval of the Contracting Officer or the Contracting Officer’s Representative.

The Contractor shall not begin performing physical work on PBA prior to the issuance of the formal Notice to Proceed from the Contracting Officer. Upon submission of the submittals listed above, the Contracting Officer will review each submittal to ensure each conforms to the solicitation and resultant contract. Only upon Contracting Officer approval will the Notice to Proceed be issued. It is the intent of the Government to issue the Notice to Proceed within 15 days of contract award. However, that timeline is contingent upon successful and timely submission of the Submittals as listed in this SOW. Work shall be completed within 60 calendar days of NTP issuance.

All electrical and electronic equipment (in hazard area) shall be dust tight, per NFPA 70, 500.7 (C).

Upgrades shall conform with UFC and NFPA, and include the following:

1. Demolition and dispose of existing fire alarm system including conduit, wires, UV detectors, etc.

2. Install and test new addressable fire alarm control panel (FACP).

3. Install new smoke detector above the FACP.

4. Install new rigid conduit raceway, color coded and painted, per Army Corps of Engineer specifications.

5. Install new wire for all circuits and devices, color coded and painted, per Army Corps of Engineer specifications.

6. Install and test new rate of rise heat detectors.

7. Install and test duct smoke detectors.

8. Install and test new manual pull stations.

a. One at the exit of the FACP room, one at the east door, and one at the west door.

9. Install and test new UV/IR detectors, set to activate by UV or IR.

10. Install and test new horn and strobe notification appliances.

a. At least 88 decibels for industrial occupancy, per NFPA.

11. Install new Monaco BT-X Transceiver to communicate to the PBA fire department.

a. Monaco system is a D21.

12. Drawings and fire alarm matrix shall be stamped by a qualified fire protection engineer prior to installation.

SUBMITTALS

The Contractor shall submit the following submittals within 10 calendar days of contract award:

S1. Proof of Insurance & Bonds. Proof of insurance and bonds shall be submitted to the Contracting Officer to the amounts specified in the solicitation.

S2. Comprehensive List of Materials.

S3. Listing of all contractor employees and subcontractors requiring access to PBA throughout the duration of the project.

S4. Final Project Schedule. This final project schedule shall be submitted in the form of a GANTT chart or similar. The Contractor will be responsible for adhering to this schedule to the exclusion of events beyond the control of the contractor.

S5. As-Built drawings “G”. Design shall be submitted digitally in AutoCAD within 10 days after contract award.

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following will be submitted in accordance with SECTION 01

33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

As-Built Drawings ‘’G’’

The Contractor will submit one digital design prior to installation and as-built drawings in AutoCAD, to the Contracting Officer’s Representative within 15 days of work completion for inspection by the COR. . The COR’s approval and receipt of printed as-built drawings and digital drawing files fulfill the contractor's obligation for furnishing design and as-built drawings under this contract. The drawings in AutoCAD format will be made using the current release/version of the software or the release/version one previous to the current release of the software at the award of this contract.

When final revisions have been completed, the cover sheet drawing will show the wording "RECORD DRAWING AS-BUILT" followed by the name of the contractor in letters at least 3/16 inch high. All other contract drawings will be marked either "As-Built" drawing denoting no revisions on the sheet or "Revised As-Built" denoting one or more revisions. Original contract drawings will be dated in the revision block.

Within 10 days after government approval of all of the working as-built drawings, the contractor will prepare the final CADD as-built drawings for government review and approval. The government will promptly return one set of prints annotated with any necessary corrections.

Within 7 days the contractor will revise the CADD files accordingly at no additional cost and submit one set of final prints for the completed work to the government. Within 10 days the contractor will submit the final as-built drawing package for the entire project. The Government reserves the right to reject any drawing files it deems incompatible with the customer's CADD system. Paper prints, drawing files and storage media submitted will become the property of the government upon final approval.

OPERATION AND MAINTENANCE MANUALS

Submit one digital copy of the Operation and Maintenance Manuals. Operation and Maintenance (O&M) manuals must be consistent with the manufacturer's standard brochures, schematics, printed instructions, general operating procedures, and safety precautions.

WARRANTY

All fire alarm equipment installed under this contract shall have a guaranteed warranty for a period of one year after close-out. If the fire alarm system fails during the one-year period, service personnel shall be on site to repair system within 24 hours from time of notification during PBA normal working hours.

Environmental Requirements:

1. Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement.

Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR).

2. Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide (https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for-Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials; recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.

3. Compliance with License and Certification Requirements: Contractor shall obtain all license and certification required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.

4. Notification of Federal and State Regulators: Contractor shall immediately notify the COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.

5. Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation.

Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.

6. Reporting Noncompliance: Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR.

7. Verification of National Environmental Policy Act Documents: Contractor shall obtain from the COR, a copy of AMC's National Environmental Policy Act Policy and 32 CFR 651 which addresses http://www.epa.gov/cpg) actions to be taken by contractor. These documents include but is not limited to the analysis- associated decision document of an Environmental Impact Statement and Record of Decision; Environmental Assessment and Finding of No Significant Impact or Notice to Proceed; or Record of Environmental Consideration on the proposed contract actions prior to commencement of such actions.

8. Conformance with Environmental Management System: Contractor shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of contamination, or can negatively impact the natural and/or human environment.

9. Assignment of Environmental Compliance Designee (ECD): Contractor shall appoint an ECD for all contract work periods exceeding 180 consecutive days. Contractor shall appoint a primary and alternate ECD for each production, shop or work area that uses and/or stores hazardous materials and/or generates hazardous wastes. Contractor ECDs shall monitor implementation of all environmental regulatory requirements, report all environmental noncompliance to the work site supervisor, correct all environmental noncompliance, and verify implementation of directed actions to correct identified environmental noncompliance. Contractor shall have at least one ECD on duty at all times at each shop or work area.

Contractor shall require all personnel designated as ECDs to complete the initial ECD training through the installation or Major Subordinate Command (MSC) environmental compliance point of contact within 15 days of the start of contract performance. Contractor personnel appointed as ECDs may perform other duties provided they do not prevent the performance of ECD duties. Contractors may request a waiver of this requirement through the COR, if using and/or storing very small quantities of hazardous materials.

10. Competency Training for Contractor Personnel: Contractor shall not allow personnel to perform any activities and/or tasks on AMC installations without proper and adequate qualifications or job competency training. In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.

11. Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste generated, which cannot be recycled to an approved and permitted off-post disposal facility.

11.1 Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.

11.2 Prior to removing any waste from the installation for disposal, the Contractor shall coordinate with the installation Qualified Recycling Program (QRP) Manager, and COR to arrange for recyclable materials to be removed and diverted from the waste stream.

11.1 Submit in writing the quantities of waste removed and recycled to the COR on a monthly basis.

The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled and the quantities of materials disposed/recycled by weight.

11.4 The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.

11.5 The Contractor shall make maximum effort to reduce and prevent waste.

12. Generation of Hazardous Waste: Contractor shall assign all hazardous waste management responsibilities to the appointed ECD. Contractor shall contact the COR to obtain technical assistance from the Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous waste storage and disposal requirements. Contractor shall properly profile all waste generated as part of this contract to determine if any waste is hazardous waste as defined by 40 CFR. Contractor shall accumulate hazardous waste prior to disposal shipment in a satellite accumulation point at or near the point of generation or in a less-than-90-day site, in accordance with Federal, State, Army, and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement or Status-of-Forces

Agreement. The Contractor shall properly package the hazardous waste and complete the hazardous waste manifest, then take the manifest to COR for approval and signature prior to removing any hazardous waste from the installation. Contractor shall contact COR to obtain the installation’s hazardous waste EPA ID number for the hazardous waste manifest. The Contractor shall notify the COR 24 hours prior to removing any hazardous waste from the installation. The contractor shall remove and dispose of manifested hazardous waste generated by contract activities from the installation, to an approved off-post permitted hazardous waste disposal facility. The COR shall assist contractors with profiling their waste upon request.

13. Use of Hazardous Materials: Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the COR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from COR.

14. Prevention of Storm Water Pollution: The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimum control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as applicable to the Pollutant Discharge Elimination System general permit requirements. Applicable permits include:

1. The installation’s Small Municipal Separate Storm Sewer System (MS4) Permit;

2. The Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activities (MSGP); and,

3. All Construction Activity Storm Water permits minimum control measures include, but not limited to:

• Public Education and Outreach on Storm Water Impacts

• Public Involvement and Participation

• Illicit Discharge Detection and Elimination

• Construction Site Storm Water Run-off Control

• Post Construction Storm Water Management in New Development and Redevelopment

• Pollution Prevention/Good Housekeeping for Municipal Operations Contractors will comply with the MSGP permit when the activity is identified as a permitted industrial activity. BMPs include, but are not limited to:

• Practicing spill prevention and good housekeeping.

• Installing and managing erosion and sediment control.

• Meeting the requirements of the MS4 permit.

• Contractors will obtain permit coverage for construction activities disturbing over one acre of land (total acreage is cumulative across all portions of the project). BMPs include, but are not limited to:

• Preparing and implementing a site-specific Storm Water Pollution Prevention Plan (SWPPP) as outlined in the permit and prior to any soil disturbance.

• Installing and managing erosion and sediment control.

• Make available, upon request, permit associated documentation.

• Practicing spill prevention and good housekeeping.

• Meeting the requirements of the MS4 permit.

• Schedule inspections and provide corrective actions for noted deficiencies.

15. Storm Water Management Low Impact Design/Development (LID): The Contractor shall perform, track, participate, implement, and comply with Section 438 of the Energy Independence and Security Act;

Executive Order 13514; and the DOA memorandum (2010) for full implementation of low impact design/development (LID) techniques to restore predevelopment hydrology to the maximum extent technically feasible for both new and renovation construction projects regardless of size. In support of LID, Contractors will adhere to installation landscape codes and the guidance found in the Installation Design Guide concerning Low Impact Design/Development for storm water management. The following LID practices include, but are not limited to:

• Restoring predevelopment hydrology to the maximum extent technically feasible

• Promoting natural removal of pollutants such as nutrients, oil and grease, and sediments from storm water

• Managing rainfall at the point where it falls

• Meeting the requirements of the MS4 permit

• Important Note: Utilization of permanent retention/detention ponds is prohibited without authorization from the Installation Planning Division.

16. Use of Pesticides: Contractor shall submit the type and quantity of regulated pesticides to be applied, the application purpose, and location to the COR for approval 10 working days prior to the initial application. The Contractor shall submit the actual quantities applied (DD1532 or equivalent) to the COR within 2 working days (48 hours) after each approved application. The Contractor shall utilize Integrated Pest Management (IPM) technology and procedures in strict compliance with all applicable Federal, State, Army, and installation regulations, to include the installation's integrated pest management plan. Pesticide applicators shall be certified and licensed in accordance with the State where work is being performed and/or Department of Defense regulations. The Contractor shall provide evidence of personnel licenses and certifications to the Contracting Officer and the COR prior to the initial application of pesticides. Only those pesticides registered with the US Environmental Protection Agency (EPA) and approved by Army Materiel Command Pest Management Consultant shall be utilized and then only in strict accordance with product labeling. The installation reserves the right to prohibit and limit the amount and type of pesticides used.

17. Protection of Work Site Resources: Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, the Contractor shall coordinate harvesting of saleable timber with the COR. Contractor shall notify the COR if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless permission has been granted in writing by the COR.

18. Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).

19. Protection of Sensitive Areas: Contractor shall comply with all installation designated sensitive and/or off-limit area restrictions. Sensitive areas are generally demarked indicating what activities (e.g., driving, digging, foot traffic) are prohibited. The Contractor shall also adhere to the following installation sensitive areas requirements:

19.1. Cultural Resources Sites: Do not excavate, remove, damage, or otherwise deface any archeological resource located on public lands.

19.2 Endangered Species Habitats: Do not initiate any action that may disturb, endanger, or damage to any degree the habitat of a threaten and endangered species.

19.3 Wetlands: Do not excavate or take any action that could fill or damage any wetland unless working under a project specific Corps of Engineers 404 permit. Wetlands include streams, riparian areas, bogs, marshes, and swamps.

20. Corrective Action for Noncompliance: Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the COR, take immediate corrective action. Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.

21. Noise: Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times. Pile-driving operations shall be coordinated through the COR.

22. Mercury: Mercury is prohibited, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited. Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed. Immediately report to the COR instances of breakage or mercury spillage. Clean mercury spill area to the satisfaction of the Contracting Officer. Cleanup of a mercury spill shall not be recycled and shall be managed as a hazardous waste for disposal.

23. Universal Waste / e-Waste Management: Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.

24. Pollution Prevention / Hazardous Waste Minimization: Minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for supporting waste minimization goals.

CONDITIONS:

a. The contractor shall provide all materials, equipment, tools and labor for the execution of this contract.

Contractor shall be responsible for loading and unloading of equipment, to include forklift or other equipment, operator and labor.

b. Changes or deviations will be submitted in writing to the contracting officer for approval or rejection.

c. Any alteration to the building or any other equipment in the building shall be approved by the Contracting Officer prior to execution and at the expense of the contractor.

d. Design engineering drawings, software and any other documents including editable copy in original file format developed and submitted to the government as part of this contract become the property of the U.S. Government. The government will have the right to reproduce and subsequently edit any of these documents and will reserve the right to procure parts, components or the entire system from any source capable of producing it.

LOCATION OF WORK: The local work covered by this specification is to be performed at Pine Bluff Arsenal. Postal address is Pine Bluff, Arkansas 71602-9500. The Arsenal is located off Highway 65, Exit 32, about 12 miles northwest of Pine Bluff and 35 miles southeast of Little Rock. The job site is Area 8, Section 1, Buildings 81-100, 81-200, 81-300, and 81-400.

ORDER AND SCHEDULING OF WORK: When performing work on Pine Bluff Arsenal the

Contractor shall adhere to the normal duty hours of the Arsenal which are 6:30 AM to 4:00 P.M., Monday thru Thursday and 6:30 AM to 3:00 PM every other Friday. However, contractor shall coordinate Friday work with the Contracting Officer or the COR, to ensure which Friday is the workday. No work will be permitted on Government holidays, days that are observed in lieu of Government holidays and days that are declared non-work days by the Commanding Officer of Pine Bluff Arsenal or officials of higher headquarters. Deviations from the above must be approved in writing by the Contracting Officer at least two working days prior to the proposed deviation.

DISPOSAL OF EXCESS REMOVED MATERIALS: All salvaged rubble, material, and equipment will remain the property of the Government.

a. Uncontaminated rubble, materials, and equipment, will be delivered to an erosion control area as directed by the Contracting Officer. Materials and equipment will be placed in "like material" stacks when delivered to the Property Disposal Yard.

b. Contaminated rubble, materials, and equipment will be placed in containers and delivered to a materials holding area as directed by the Contracting Officer.

SAFETY REQUIREMENTS:

a. General: Limited emergency first aid, to prevent loss of life or limb, is available for contractor personnel at the U.S. Army Health Clinic for injuries sustained in the performance of their duties. This service is normally available from 7:30 A.M. to 4:00 P.M., Monday through Friday. For life threatening emergencies after duty hours, contractor personnel will notify the Medical Officer of the day. For any other injury, contractor personnel should go to Jefferson Regional Medical Center or see their private physician. Use of this Health Clinic constitutes compliance with the First Aid Requirements of the Corps of Engineers Manual EM 385-1 as referenced in, FAR 52.236-13 "Accident Prevention". The requirements of Department of Labor, Occupational Safety and Health Administration (OSHA) Standard 29 CFR 1910 or EM 385-1, General Safety Requirements, whichever is the most stringent, will be followed

b. The regulations and supplements listed below will be adhered to by all contractor and sub-contractor personnel.

PBAR 1-3 Visitors W/change 1 PBAR 190-4 Traffic Code PBAR 210-12 Authorized/Unauthorized Removal of Government Property W/changes 1 & 2 PBAR 385-4 Carrying, Safeguarding or Use of Firearms and Dangerous Weapons PBAR 385-7 Smoking and the Use of Matches and Lighters PBAR 385-2 Occupational Safety and Health Program W/changes 1, 2 & 3 PBAR-14 Post Fire Regulation W/change 1 PBAR-31 Hazardous Work Permit

c. No fire or flame producing device will be used on the Arsenal without prior approval of the Contracting Officer. The Contractor shall also be required to obtain a burn permit from the Fire Department. This includes all forms of welding.

d. Smoking will not be permitted in the production area, except in designated areas.

e. Equipment will be maintained in a safe operating condition and a fire safe condition at all times. It shall be stored in a designated area, approved by the Contracting Officer.

f. Hoists, cranes, derricks, or similar equipment shall not be operated where it is possible to bring any part of the machine, suspended load, or lines closer than ten feet to power lines unless the lines have been de-energized and grounded.

g. Work will be performed in a manner which will allow the passage of traffic, especially emergency vehicles, at all times. Where only one lane is open to traffic, adequate warning signs and flagmen will be used.

h. All personnel working at Pine Bluff Arsenal must have a safety briefing given by Safety personnel prior to beginning work.

i. Contractor shall provide the names and personnel data on all employees scheduled for this contract work at PBA, to the Contracting Officer at least one week prior to actual work. This is necessary for proper identification and issue of security pass to each employee for access to PBA job site.

j. In Accordance with DA PAM 384-64 and DESR 6055.09. Contractor/subcontractor personnel will be entering an explosion hazard area. Hazards may include: danger of death, serious injury and risk of loss, or damage to equipment. Do not stay longer than necessary.

OPSEC REQUIREMENTS:

1. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 10 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.

2. Contractor and all associated sub‐contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

3. Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (TSDB) (Army Directive 2014‐05/AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

4. The contractor and all associated sub‐contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 10 calendar days of contract award and within 20 calendar days of new employees commencing performance with the results reported to the COR NLT 20 calendar days after contract award.

5. Per AR 530‐1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

- End SOW -http://jko.jten.mil/

33-670 Fire Alarm System Upgrade
GENERAL STATEMENT OF WORK (SOW)
CONDITIONS:
SAFETY REQUIREMENTS: