B08_Attach_4-Price_Schedule_BFMC(FY21).xlsx
XLSX spreadsheet 47 KB Posted
- Attached to
- KA KFALLS PAVEMENT REHAB AND MAINTENANCE
- Solicitation number
- 140L0621R0039
About this file
This document contains a price schedule for a federal contract solicitation to rehabilitate and maintain pavement on several roads in Klamath Falls, Oregon. The solicitation was issued by the Bureau of Land Management and includes a base requirement and three bid options. The base requirement involves full depth reclamation, fog sealing, double chip sealing, and pavement patching on Burton Flat and Miners Creek Roads. Bid Option 1 consists of road reconditioning, slurry sealing, and pavement patching on Spencer Creek Road. Bid Option 2 is for removing a cattle guard on Burton Flat Road. Bid Option 3 involves installing an 18-inch culvert on Miners Creek Road. Pricing is to be provided using unit prices for individual work items. The total bid price should incorporate the base requirement and selected bid options. The response deadline is not specified in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Bid BFMC
1040L0621R0039 BID SCHEDULE
| Description of Work | Scheduled | Federal Specifications for Highway Construction, FP-14 | ||
| Bid Item No. | Base Bid: Burton Flat and Miners Creek Road Paving Rehabilitation FY21 | Value | Specification References in the Solicitation | |
| Division 150 | Project Requirements | % | $ - |
| 15101 | Mobilization | Lump sum | 1.00 | $ - | Sections FP-151 |
| 15201 | Construction Survey and Staking | Lump sum | 1.00 | $ - | Sections FP-152 |
| 15401 | Contractor Sampling and Testing | Lump sum | 1.00 | $ - | Sections FP-154 |
| 15501 | Schedules for Construction Contracts | Lump sum | 1.00 | $ - | Sections FP-155 |
Division 300 Aggregate and Base Courses Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
| 30301 | Road Reconditioning (Brushing) | Miles | 6.52 | $ - | Sections FP-304 |
| 30302 | Road Reconditioning (Ditch Cleaning) | Miles | 6.52 | $ - | Sections FP-304 |
| 30401 | Full Depth Reclamation, 2-4 inch | Square Yard | 29,650 | $ - | Sections FP-304 |
Division 400 Asphalt Pavements and Surface Treatments Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
| 40601 | Fog Seal | Square Yard | 54,801 | $ - | Sections FP-406 |
| 40701 | Double Chip Seal | Square Yard | 54,801 | $ - | Sections FP-407 |
| 41801 | Pavement Patching | Square Yard | 10 | $ - | Sections FP-407 |
Division 600 Incidental Construction Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
| 60201 | Culvert Replacement 24" | Each | 2.00 | $ - | Sections FP-602 |
| 60202 | Culvert Replacement 18" | Each | 1.00 | $ - | Sections FP-602 |
| 61901 | Gate Installation | Each | 2.00 | $ - | Sections FP-619 |
| 63501 | Temporary Traffic Control | Lump sum | 1.00 | $ - | Sections FP-635 |
BASE REQUIREMENT TOTAL $ -
| BID OPTION 1 | $ - |
| BID OPTION 2 | $ - |
| BID OPTION 3 | $ - |
TOTAL BID PRICE: $ -
&"-,Bold"&K000000 LADMAK4M0000
Bid Option 1
BID SCHEDULE
| Description of Work | Scheduled | Federal Specifications for Highway Construction, FP-14 | ||
| Bid Item No. | Bid Option 1: Spencer Creek Pavement Maintenance FY21 | Value | Specification References in the Solicitation | |
| Division 150 | Project Requirements | % | $ - |
| 15101 | Mobilization | Lump sum | 1.00 | $ - | Sections FP-151 |
| 15401 | Contractor Sampling and Testing | Lump sum | 1.00 | $ - | Sections FP-154 |
| 15501 | Schedules for Construction Contracts | Lump sum | 1.00 | $ - | Sections FP-155 |
Division 300 Aggregate and Base Courses Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
| 30301 | Road Reconditioning (Brushing) | Miles | 4.10 | $ - | Sections FP-304 |
| 30302 | Road Reconditioning (Ditch Cleaning) | Miles | 4.10 | $ - | Sections FP-304 |
Division 400 Asphalt Pavements and Surface Treatments Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
| 41401 | Crack Sealing and Filling | Lineal Foot | 250 | $ - | Sections FP-401 |
| 41001 | Slurry Seal | Square Yard | 34,264 | $ - | Sections FP-406 |
| 41801 | Pavement Patching | Square Yard | 60 | $ - | Sections FP-407 |
Division 600 Incidental Construction Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
63501 Temporary Traffic Control Lump sum 1.00 $ - Sections FP-635
| SUBTOTAL | $ - | Subtotal Sections 150-600 | |
| BID OPTION 1 TOTAL: | $ - |
&"-,Bold"&K000000 LADMAK4M0000
Bid Option 2
BID SCHEDULE
| Description of Work | Scheduled | Federal Specifications for Highway Construction, FP-14 | |
| Bid Item No. | Bid Option 2: Remove Cattle Guard Burton Flat Road | Value | Specification References in the Solicitation |
Division 600 Incidental Construction Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
61902 Remove Cattle Guard Lump sum 1.00 $ - Sections FP-635
| SUBTOTAL | $ - | Subtotal Sections 150-600 | ||||
| Miscellaneous | Unit of Measure | Unit Price | Contract Quantity | DIV TOTAL | $ - |
| Overhead | Lump sum | 1.00 | $ - 0 | Contract Terms and Conditions |
| Profit | Lump sum | 1.00 | $0.00 | Contract Terms and Conditions |
| Bonds & Insurance | Lump sum | 1.00 | $ - 0 | Contract Terms and Conditions |
BID OPTION 2 TOTAL: $ -
&"-,Bold"&K000000 LADMAK4M0000
Bid Option 3
BID SCHEDULE
| Description of Work | Scheduled | Federal Specifications for Highway Construction, FP-14 | |
| Bid Item No. | Bid Option 3: 18" Cross Drain Culvert Miners Creek Road | Value | Specification References in the Solicitation |
Division 600 Incidental Construction Unit of Measure Unit Price Contract Quantity DIV TOTAL $ -
| 60203 | Install 18" CMP (40 Ft long) | Lump sum | 1.00 | $ - | Sections FP-635 |
| BID OPTION 3 TOTAL: | $ - |
&"-,Bold"&K000000 LADMAK4M0000 image1.jpeg
File details come from the government source that posted it. Updated .