B08_Attach_1_Construction_Specifications_v2.pdf

PDF 959 KB Posted

Attached to
"EO14398" HALE REPLACE ROOFS ON HOUSING FACILITIES Federal contract opportunity
Solicitation number
140P8226B0007
Issued by
Department of the Interior National Park Service

About this file

Construction Specifications Summary

This document is a Construction Specifications package for roof replacement at Haleakalā National Park on Maui, Hawaii (PMIS 340781A), dated March 13, 2026. The project involves replacing roofing systems on five buildings: three duplexes (HQ-34, HQ-35, HQ-36), one common laundry building (HQ-37), and one historic single-family residence (HQ-10). The work encompasses demolition and removal of existing roofing materials, furnishing and installation of complete new roofing systems totaling 10,888 square feet, and replacement of approximately 10% of damaged plywood decking per unit. For the four non-historic buildings (7,546 SF total), color-coated PVDF corrugated metal panels with synthetic underlayment, ice/water shield, and metal ridge caps are specified, with a manufacturer's 40-year panel finish warranty and 20-year watertightness warranty plus 2-year contractor workmanship warranty. For the historic structure HQ-10 (3,342 SF), ASTM D7158 Class G architectural asphalt shingles meeting 120 MPH wind resistance standards with 6-nail fastening patterns are required, with final color approval by Cultural Resource specialists. All work must comply with NPS standards, the Hawaii State Building Code, and the International Building Code 2024.

The specifications contain extensive administrative and operational requirements across 16 division sections covering project management, work restrictions, contract line items, safety, quality control, submittal procedures, construction scheduling, and closeout procedures. Key requirements include pre-construction meetings, weekly progress meetings, quality control daily reports with photos, adherence to NPS resource protection protocols (invasive species prevention, threatened and endangered species protections, archaeological resource management), stormwater pollution prevention compliance, proper waste management and recycling, contractor qualifications including licensed roofing supervision and manufacturer certification, work hours of 7:30 a.m. to 4:00 p.m. Monday through Friday, and coordination with park operations while residents occupy the housing units during construction. The contractor must manage vehicles and equipment according to strict park protocols, including pre-inspection for invasive species and restrictions on equipment from the Big Island. All submittals must use the NPS CM-16 transmittal form, and project completion requires punchlist resolution within 30 days of substantial completion, final inspection acceptance, and delivery of two printed project closeout binders containing record drawings, warranties, operation and maintenance manuals, and project photographs.

View the file

Other files for this federal contract opportunity

Other files attached to "EO14398" HALE REPLACE ROOFS ON HOUSING FACILITIES, newest first.
File Type Posted
Sol_140P8226B0007_Amd_0003.pdf PDF
Sol_140P8226B0007_Amd_0002.pdf PDF
Sol_140P8226B0007_Amd_0001.pdf PDF
B08_Attach_6_WD_27_May_2026.pdf PDF
B08_Attach_4_Payment_Bond_SF25A-23a_Exp_2027.pdf PDF
B08_Attach_7_Contract_Bid_Schedule.docx DOCX document
B08_Attach_5_Performance_Bond_SF25-23a_Exp_2027.pdf PDF
B08_Attach_3_GFD___2_-_Project_Site_Orientation_v2.docx DOCX document
B08_Attach_2_GFD___1_-_Photos_of_Housing_Units.docx DOCX document
Sol_140P8226B0007.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Specifications

Haleakalā National Park

Replace Roofs of Multiple Park Residences

PMIS 340781A

March 13, 2026

Prepared by: James T. Bouknight, Facility Manager

THIS PAGE INTENTIONALLY LEFT BLANK

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION NO. TITLE Total Pages

01 11 00 Summary of Work 14

Hot Work Permit Form HW-1 2

01 11 40 Work Restrictions Resource Protection 10

Commercial Pre-Inspection Checklist 2

01 27 00 Definition of Contract Line Items CLINs 2

01 31 00 Project Management Coordination 2

Request for Information RFI Form 2

01 32 16 Construction Schedule 2

01 33 23 Submittal Procedures 3

CM-16 Transmittal Form 2

01 35 23 Safety Requirements 2

01 40 00 Quality Requirements 2

Quality Control QC Daily Report Form 2

01 57 23 Temporary Stormwater Pollution Prevention 5

01 67 00 Product Requirements 3

01 73 40 Execution 4

01 74 19 Construction Waste Management 2

01 77 00 Closeout Procedures 3

DIVISION 01

GENERAL REQUIREMENTS

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 – GENERAL

1.1 SUMMARY

A. Section Includes:

• Project description and location.

• Scope of work and contract line items (CLINs).

• Work phasing and sequencing.

• Contractor use of the site.

• Government-furnished items, documents, and services.

1.2 Work Covered by Contract Documents

A. Project Location and Conditions:

Haleakalā National Park is located on the island of Maui, Hawaiʻi. The summit district of the park is located 28 miles southeast of Kahului, off of State Highway

378, an extension of State Highway 377 in Maui County. Weather can be unpredictable, including strong winds, fog, rain, and seasonal snow/ice. Narrow access roads, visitor traffic, and steep grades affect logistics, material transport, and work sequencing. Target buildings are in two general locations:

• At mile marker 10: three duplexes (HQ-34, HQ-35, HQ-36) and a common laundry building (HQ-37). Approximately 7,000 feet elevation.

• At mile marker 11: one single-family residence (HQ-10). Approximately 7,500 feet elevation.

• Refer to GFD # 1 and GFD # 2

B. Project Background:

Housing units in the park's maintenance housing area and one single-family residence near the Visitor Center require roof replacement to maintain condition and extend service life. Units include three duplexes, a common laundry building, and one historic single-family residence.

C. Project Scope of Work:

The Work consists of the following: The Contractor shall furnish all labor, supervision, materials, tools, equipment, transportation, installation, testing, inspection, disposal, and incidentals necessary to provide complete roof replacement systems at the buildings listed below.

1. Demolition and Removal: Remove and legally dispose of the following at each building:

• Existing roofing materials (corrugated metal panels or asphalt shingles, as applicable).

• Existing underlayment and ice/water shield.

• Deteriorated drip edge flashing.

• All associated fasteners, closures, sealants, and flashings no longer required.

• Damaged plywood decking identified during inspection (10% allowance per unit.)

Note: All removed materials shall be transported off-site to an approved disposal or recycling facility. No burning of materials is permitted on NPS lands.

2. New Roofing Systems:

A. For Residences HQ-34 A/B, HQ-35 A/B, HQ-36 A/B, and HQ-37.

Total Square Feet = 7546 (Color-Coated Corrugated Metal Roofing):

Furnish and install a complete corrugated metal roofing system including:

• Synthetic underlayment over full roof deck.

• Self-adhering rubberized asphalt (ice/water shield) at eaves and valleys.

• Drip edge flashing at all roof perimeters.

• Color-coated PVDF (Polyvinylidene Fluoride)-coated corrugated metal panels, minimum 24-gauge steel.

• Color samples to be reviewed and approved by COR prior to installation.

• Metal ridge caps, closure strips, and gasketed fasteners per manufacturer high-wind requirements.

• Flashing at all penetrations, rakes, and valleys sealed with butyl tape or approved urethane sealant.

• Complete site cleanup.

Technical Performance Requirements (HQ-34, HQ-35, HQ-36, HQ-37):

• Manufacturer's system warranty: minimum 40 years on panel finish; 20 years on watertightness.

• Contractor workmanship warranty: minimum 2 years.

B. For Residence HQ-10

Total Square Feet = 3342 (Architectural Asphalt Shingle Roofing – Historic

Structure):

Furnish and install a complete architectural asphalt shingle roofing system including:

• Synthetic underlayment over full roof deck.

• Self-adhering rubberized asphalt (ice/water shield) at eaves and valleys.

• Drip edge flashing at all roof perimeters.

• Starter strip shingles per manufacturer requirements.

• Ridge cap shingles; flashing at all penetrations and step/valley conditions.

• Attic ventilation upgrades as required.

• Complete site cleanup.

• Final shingle color to be approved by Cultural Resource (CR) specialists prior to ordering (see Section 1.2.F).

Technical performance requirements (HQ-10)

• Architectural asphalt shingles meeting ASTM D7158 Class G wind resistance to 120 MPH.

• 6-nail high-wind fastening pattern per manufacturer.

All work shall comply with NPS standards, manufacturer instructions, the

Hawaii State Building Code, and the International Building Code (IBC) 2024.

Project will be constructed under a single prime contract. Refer also to

Section 01 27 00 – Definition of Contract Line Items.

E. Allowances:

• Roof Decking Replacement: Base bid includes replacement of 10% of plywood sheathing per unit.

F. HQ-10 Historic Treatment Requirements:

HQ-10 is a historic structure. All treatments shall comply with:

• Secretary's Standards for the Treatment of Historic Properties.

• Relevant NPS Preservation Briefs.

Requirements:

• Use gentle cleaning methods (≤500 psi pressure washing if washing is required).

• Contain debris using skirting or mesh barriers to protect the historic structure.

• Repair rather than replace where feasible; use materials compatible with the historic fabric. This requirement applies to structural and decorative elements of the building, understanding that the asphalt shingles will be fully replaced.

• Final shingle color requires review and approval by Cultural Resource (CR) specialists before ordering.

• Contractor must submit multiple physical color samples via NPS Form CM-16 for CR review and approval.

D. Project Mitigations:

The Contractor shall comply with Section 01 11 40 – Work Restrictions &

Resource Protection, including all invasive species prevention, threatened and endangered species protections, cultural resource and archaeology protocols, and historic structure treatment requirements.

1.3 WORK PHASES / SEQUENCE

A. Work Phases:

The Work will be completed in one (1) single work phase. The Contractor shall sequence work to minimize disruption to park residents and operations, accounting for logistics at elevation, daily weather variability, and narrow access roads. The construction schedule shall include phasing at the CLIN level and be submitted per Section 01 32 16.

1.4 WORK UNDER OTHER CONTRACTS

A. General:

Cooperate with other contractors onsite so that all contracts may be carried out smoothly without interfering with or delaying work under this or other contracts. If another contract is awarded that may have an impact on this contract, the

Contractor will be notified. Coordinate with park staff and other contractors to avoid interference with occupied housing and park operations.

1.5 GOVERNMENT-FURNISHED ITEMS

The Government may furnish items such as materials, equipment, facilities, services, utilities, or housing for Contractor use on this contract. The Government may furnish these items to lower overall project costs, make use of existing items, or out of necessity at a remote location. Items offered below are at no additional cost to the Contractor.

B. Government-Furnished Materials: NONE IDENTIFIED AT THE OUTSET OF

THE CONTRACT.

In the event government-furnished materials are offered (at the outset or furnished later):

• The Government will arrange and pay for delivery of government-furnished materials to the project site or agreed-upon location based on the

Contractor's approved construction schedule.

• The Government will inspect delivered items for damage after delivery. The

Contractor shall be present for, and assist in, the Government's inspection.

• The Government will arrange for replacement of materials if the government-furnished materials are damaged, defective, or missing.

• The Contractor shall protect government-furnished materials from damage during storage and handling, including exposure to the elements.

• The Contractor shall install or incorporate government-furnished materials into the Work as outlined in the contract documents.

C. Government-Furnished Equipment / Transportation: NONE IDENTIFIED AT

THE OUTSET OF THE CONTRACT.

D. Government-Furnished Facilities:

• Restroom: Restrooms available at baseyard or public visitor center.

• Field Office: NOT AVAILABLE.

• Storage Space: Maintenance baseyard and areas immediately adjacent to buildings targeted for roof replacement will be allowed as temporary storage space. At no time whatsoever shall storage of project materials must not impact park employee use of the maintenance baseyard.

E. Government-Furnished Services: NONE IDENTIFIED AT THE OUTSET OF

THE CONTRACT.

F. Government-Furnished Utilities:

• Potable Water: Available from hose bibs in the existing water system at or near the housing area.

• Non-Potable Water: NOT AVAILABLE.

• Electrical Power: NOT AVAILABLE. Contractor shall provide generators for all project power needs.

G. Government-Furnished Housing:

• NOT AVAILABLE.

1.6 GOVERNMENT-FURNISHED DOCUMENTS (GFD)

The Government may furnish reports or other documents for informational purposes to supplement the contract documents (labeled as GFD). In cases of conflict between a GFD and the drawings and specifications, the drawings and specifications will govern.

• GFD #1: Photos of Housing Units

• GFD #2: Project Site Location Overview

1.7 CONDUCT OF OPERATIONS

A. Park Regulations:

The Contractor shall conduct operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park

Service (NPS), and applicable park rules and regulations prescribed by the Park

Superintendent. Law enforcement rangers will intervene if unsafe or unlawful activity is perceived.

B. Work Hours:

Regular work hours shall be 7:30 a.m. to 4:00 p.m., Monday through Friday, unless otherwise approved by the Contracting Officer. No work shall be performed on weekends, or state or federal holidays. Modified work hours require advance written approval from the Contracting Officer.

C. Weather / Climate:

The summit district of Haleakalā National Park experiences extreme and rapidly changing weather, including high winds, heavy rain, and fog. No work will be performed on days the park must close due to weather or climate. Document days "not worked" in the Quality Control Daily Report. Ensure sufficient float is built into the construction schedule to account for weather events.

D. Advertisement:

No signs or advertisements shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.8 CONTRACTOR USE OF THE SITE

A. Park Entry:

Vehicles associated with the contract shall be waived the entrance fee upon entering in marked company vehicles, or by providing full names, vehicle types, and license plate numbers of all employees entering in personal vehicles.

B. Site Access:

The Contractor shall access sites via State Highway 378. Access roads are narrow with steep grades. Heavy equipment and material deliveries must be coordinated with the park Point of Contact (POC) to avoid conflicts with visitor traffic and residents. Oversized vehicles require advance notification per Section

1.15.

C. Project Area Limits:

Limit construction operations to within the project area limits as outlined in the contract documents. Do not disturb areas outside of the project area limits, which may contain sensitive natural, cultural, or archaeological resources.

D. Storage of Materials:

Confine storage of materials to the area(s) outlined in the contract documents. If no specific site is shown, assume staging of materials and equipment is allowed within the project area limits and arrange for staging of materials and equipment with the park facility manager so as not to disrupt normal operations. The

Contractor may install portable storage containers if damaged surfaces are restored to pre-construction conditions. The Contractor is responsible for the security and protection of all materials at the jobsite.

E. Staging of Materials and Equipment:

Confine staging of materials and equipment to the areas as outlined in the drawings or attached map. If no specific site is shown, assume staging of materials and equipment is allowed within the project area limits and arrange for staging of materials and equipment with the park facility manager so as not to disrupt normal operations.

F. No Smoking Policy:

Smoking is prohibited inside or outside within 25 feet of any buildings in the park.

Discarding tobacco products anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

1.9 PUBLIC USE OF THE SITE

Cooperate with NPS and partner staff so that the Work may be carried out smoothly without interfering with or delaying the Work under this or other contracts.

B. Park Visitation:

Individual building work areas will be restricted to the public during construction.

The Contractor shall conduct operations to minimize inconvenience to park residents and visitors. Maintain access to all occupied residences at all times unless written approval is obtained from the Contracting Officer.

C. Park Events:

NONE SCHEDULED at time of contract award.

1.10 GOVERNMENT USE OF THE SITE

Cooperate with NPS and partner staff so that the Work may be carried out smoothly without interfering with or delaying the Work under this or other contracts.

B. Government Occupancy:

The Government will OCCUPY the housing units and housing area during construction. Cooperate with the Government during construction activities to minimize conflicts. Perform Work so as not to interfere with residents' day-to-day operations. Maintain existing building ingress, egress, access walkways, and access roads unless written permission is obtained from the Contracting Officer to close specific areas.

C. Government Occupancy of Completed Areas:

The Government reserves the right to occupy completed buildings or areas. The

Contracting Officer will prepare a Letter of Beneficial Use/Occupancy for each building upon completion. Upon Government occupancy, the Government will assume responsibility for maintenance and custodial services for occupied buildings.

1.11 CODES

The Contractor shall complete all Work in accordance with the latest versions of applicable federal, state, and local codes, standards, and regulations. Per NPS

Policy Memorandum 23-01 (effective January 1, 2024), the NPS has adopted the

International Code Council (ICC) suite of codes and standards. All work shall comply with the ICC suite of codes and the Hawaii State Building Code, where applicable.

Applicable codes and standards include (but are not limited to):

• International Building Code (IBC), latest adopted edition.

• International Residential Code (IRC), latest adopted edition.

• Hawaii State Building Code.

• Wind loads and roof uplift design shall comply with ASCE/SEI 7-22 and the applicable IBC edition, including determination of exposure category per

ASCE 7 based on actual site conditions.

• ASTM E1592: Standard Test Method for Structural Performance of Sheet

Metal Roof and Siding Systems.

• ASTM E1646: Standard Test Method for Water Penetration of Exterior Metal

Roof Panel Systems.

• ASTM D7158: Standard Test Method for Wind Resistance of Asphalt

Shingles (Class G).

• FM 4474: Standard for Evaluating the Simulated Wind Uplift Resistance of

Roof Assemblies.

• UL 580: Tests for Uplift Resistance of Roof Assemblies (Class 90 minimum).

• Secretary's Standards for the Treatment of Historic Properties (applicable to

HQ-10).

In the event of a conflict between codes, standards, and the contract documents, submit an RFI with code references to the Contracting Officer for a determination.

1.12 PERMITS

The Contractor shall comply with all permit conditions. A general building permit is not required for work on NPS land; however, the Contractor must comply with all state and local building code provisions.

B. Hot Work Permit:

Hot work is defined as work activities (such as welding, cutting, blazing, and related work) that can be a source of ignition when flammable materials are present. All hot work operations shall be conducted in accordance with the procedures contained in RM-58, NPS policy on Hot Work Permits (see Appendix

35.8), and 29 CFR 1910.252(a). If the project requires any activities considered

“hot work,” submit a NPS Hot Work Permit (Form HW-1) application to the

Contracting Officer at least 48 hours prior to the scheduled hot work. The NPS will then review and complete Form HW-1 and return a copy to the Contractor with the required conditions or precautions. No hot work shall occur without a completed and signed Form HW-1 and all the required precautions in place. See attached Form HW-1.

C. Government-Furnished Permits: NONE.

D. Other Required Permits: NONE identified at contract outset. Contractor shall verify with Maui County and State of Hawaii prior to commencement.

1.13 PROFESSIONAL SERVICES

E. Contractor Qualifications:

The Contractor shall be a properly licensed roofing contractor authorized to perform work in the State of Hawaii and Maui County. A qualified roofing superintendent shall be physically present on site at all times during roofing operations. Any manufacturer-required installation certification for specified roofing systems shall be provided by the Contractor as part of the contract. Proof of manufacturer installer certification shall be submitted prior to commencing roofing work.

1.14 UTILITY INTERRUPTIONS

Notify the Contracting Officer of any work affecting existing utilities prior to commencing. Do not interrupt utility service to occupied Government housing units unless required by the contract documents. If utility interruptions are necessary, provide a minimum seven (7) calendar day advance notice to the

Contracting Officer. Maintain temporary utility services during interruptions exceeding four (4) hours. Do not proceed with any utility interruption without written permission from the Contracting Officer and the local utility service provider (where applicable.)

1.15 VEHICLES AND HEAVY EQUIPMENT

A. General:

The Contractor shall comply with all park vehicle and heavy equipment restrictions. Access roads to the housing areas at mile markers 11.5 and 12.5 are narrow with steep grades. All vehicle movements shall be coordinated with the park POC to minimize conflicts with park visitors and residents.

B. Rules of the Road:

Vehicles and heavy equipment shall comply with all posted traffic regulations, including speed limits. Vehicles operating on park roads shall take every safe opportunity to use paved pullouts to allow faster-moving traffic to pass.

C. Vehicle Parking:

Confine parking to the areas outlined in the contract documents or as arranged with the park POC. Vehicles are not permitted to park along park roads, in overlooks, or in pullouts. Vehicles are not permitted to park overnight in the park.

D. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to Government employees, vendor deliveries, and emergency vehicles at all times.

E. Vehicle Exhaust: Vehicles shall be properly maintained to ensure the exhaust produced is within legal limits. The effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

F. Spills: The Contractor shall be responsible for prevention of spills and/or cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immediately notify a Law Enforcement

Ranger or NPS Dispatch of any spills at: (808) 985-6170.

G. DOT Compliance: Vehicles and heavy equipment shall be compliant with all

DOT requirements including but not limited to drivers with appropriate license class, possessing a medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, carrying a mounted fire extinguisher, and possessing a valid DOT safety sticker, as applicable.

H. Hauling & Load Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the park road (36 CFR §

4.11). No loads heavier than the current load rating for park roads and bridges will be permitted. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park

Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent.

I. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the park road corridor. Oversized vehicles will require an escort, and drivers must avoid driving on the shoulder of the road. Contractor shall notify the Contracting Officer of oversized vehicles, scheduled arrival dates & times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.).

Vehicles that are oversized are requested to enter the park AFTER 2:00 p.m. and exit the park BEFORE sunset.

J. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the park AFTER 2:00 p.m. and exit the park

BEFORE sunset.

K. Tracked Equipment: Heavy equipment with rubber tires is preferred on paved surfaces in park units. Heavy equipment with metal tracks will not be allowed on paved asphalt surfaces, concrete surfaces, or ceremonial lawn areas without adequate protection to prevent permanent track marks, spalls, cracks, ruts, and other damage. The means and methods of protection (such as secured plywood or metal plates) shall also not damage the surfaces. The following exceptions apply:

1. Tracked equipment will be allowed on paved asphalt surfaces in lieu of surface protection if the Contractor repairs or replaces the affected surfaces to pre-construction condition.

2. Tracked equipment will be allowed on older paved asphalt surfaces if the asphalt surface is scheduled for pavement preservation (by others) within 1 year of contract completion.

3. Tracked equipment will be allowed on un-paved roads if the tracked equipment stays on the road and does not create ruts, damage, or impacts the surface water flow.

4. Tracked equipment will be allowed on grass surfaces within the project area limits if the terrain is re-graded to preconstruction topography / condition prior to the pre-final inspection. Reseeding of re-graded areas with native grass will not be required.

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION 01 11 00

Hot Work Permit (Form HW-1)

Hot Work Permitting Hot work shall only be performed in designated or permit-required areas. Before hot work operations begin in a non-designated location, a signed Hot Work Permit, issued by the Permit Authorizing Individual or his/her designee, shall be issued.

Designated Area A designated area shall be a specific area designed for, or approved by the Permit Authorizing Individual or his/her designee for, such work. A designated area can be a maintenance shop or a detached outside location that is of noncombustible or fire-resistive construction, essentially free of combustible and flammable contents, and suitably segregated from adjacent areas. All designated areas shall have been inspected and approved by the Permit Authorizing Individual or his/her designee.

Permit-Required Area A permit-required area shall be an area that is made fire safe and authorized by the issuance of a signed NPS Hot Work Permit. The Hot Work Permit shall be signed by Permit Authorizing Individual or his/her designee.

Non-permissible Areas Hot work shall not be allowed in the following areas:

(a) In areas not authorized by the Permit Authorizing Individual or his/her designee

(b) In sprinklered buildings while such protection is impaired

(c) In the presence of explosive atmospheres (that is, where mixtures of flammable gases, vapors, liquids, or dusts with air exist)

(d) In explosive atmospheres that can develop inside unclean or improperly prepared drums, tanks, or other containers and equipment that have previously contained such materials

(e) In explosive atmospheres that can develop in areas with an accumulation of combustible dusts

GENERAL

Park: District: Building: Floor:

Work to be done:

Special precautions:

PERSON PERFORMING WORK

Contractor Business Name:

Contractor Representative:

Contractor Contact Number:

NPS Employee’s Name:

NPS Office:

NPS Employee’s Contact Number:

CHECK

Work area and all adjacent areas to which sparks and heat might have spread (including floors above and below and on opposite side of wall(s) were inspected every 20 minutes for 1 hour after the work was completed and were found fire safe.

ATTENTION

Before approving any hot work permit, the Permit Authorizing Individual or his/her designee shall inspect the work area and confirm that the proper precautions have been taken to prevent fire, in accordance with the NPS Hot Work Permit Form (Form HW-1) and the NPS Hot Work Policy.

PRECAUTIONS

Sprinklers in service Hot work equipment in good repair

WITHIN 35 FEET OF HOT WORK AREA

Floors swept, clean of combustibles Combustible floors wetted down, covered w/ damp sand or other shields in place All wall and floor openings covered

WORK ON WALLS OR CEILINGS

Combustibles moved away from opposite side of wall

WORK ON ENCLOSED EQUIPMENT (tanks, containers, ducts, dust collectors etc.)

Equipment cleaned of all combustibles Containers purged of all flammable vapors

FIRE WATCH

To be provided during and 60 minutes after operation Supplied with a fully charged and operable fire extinguisher Trained in use of equipment and activating fire alarm system

FINAL CHECK

To be made every 20 minutes for 60 minutes after completion of any operation unless fire watch is provided

Is a fire watch required? Yes No

The location where the work is to be done has been examined, necessary precautions taken, and permission is granted for this work.

Permit Issue Date: Permit Expires:

Permit Authorizing Individual or Designee:

Signature: Date:

SECTION 01 11 40 – WORK RESTRICTIONS / RESOURCE

PROTECTION

1.1 SUMMARY

A. General: The NPS is the steward of unique resources found within the national parks. The NPS is committed to protecting natural, cultural, historical, archaeological, and other resources found within the parks and the adjacent lands.

B. Section includes work restrictions for protecting resources in the national parks including, but not limited to the following:

1. Preservation of Natural Features

2. Invasive Species Prevention

3. Threatened & Endangered Species (T&E Species)

4. Archaeological Resources

5. Soundscape / Noise

6. Air Quality (Indoor & Outdoor)

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION

3.1 PRESERVATION OF NATURAL FEATURES (applicable to ALL Pacific Island parks)

A. General: The Contractor shall comply with the following work restrictions:

1. Prevent damage to natural surroundings.

2. Provide temporary barriers to protect existing trees, tree roots, plants, grass areas and lawns that are directly impacted by construction operations.

3. Do not fasten ropes, cables, or guys to existing trees, rock outcrops, or other natural features.

4. Do not remove, injure, or destroy existing trees, tree roots, or plants without approval by the Contracting Officer or unless it’s explicitly required in the contract documents.

5. If a tree, tree branch, root, or mass of vegetation is preventing the Contractor from completing the work, notify the Contracting Officer immediately for a determination. Trees may need to be surveyed by park staff for bird nests prior to removal, and tree removal / trimming may be subject to additional restrictions if project is in Hawaiian hoary bat habitat.

6. Carefully supervise the excavation, grading, filling, equipment movement, and other construction operations near trees and tree branches to prevent damage.

3.2 INVASIVE SPECIES PREVENTION (applicable to ALL Hawaii parks)

A. General: The introduction of non-native species including invasive weeds and plants; invasive pests such coqui frogs and frog eggs, little fire ants (LFA), and insects including termites; other vertebrae species such as rats, mice, and reptiles; and diseases such as Rapid ‛Ōhi‛a Death (ROD) spread through contaminated soil can threaten the park’s rare and endangered plants and animals or can create new populations of non-native species not traditionally found in the park. Ensure all vehicles, equipment, machinery, cutting tools, base yards, staging areas, materials, material packaging, material deliveries, material storage, and personal protective equipment (PPE) are clean and free of invasive weeds and plants, invasive pests, and ROD spread through soil.

B. Vehicles, Equipment, & Machinery: In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Vehicles, equipment, and machinery must be thoroughly pressure washed and visibly free of dirt, mud, plant debris, and invasive pests.

Areas of particular concern include bumpers, grills, hood compartments, under the battery, wheel wells, undercarriage, cabs and truck beds.

2. The interior and exterior of vehicles, equipment and machinery must be free of rubbish. The interiors of vehicles and the cabs of machinery must be vacuumed clean. Floor mats must be sanitized with a solution of >70% isopropyl alcohol.

3. All vehicles, equipment, and machinery shall park on pavement and not under trees (where possible).

4. All vehicles, equipment, and machinery will be subject to inspection by NPS personnel.

5. All vehicles, equipment, and machinery that do not pass inspection will be turned away. The vehicle will not be allowed into the park for at least 48 hours.

6. All vehicles, equipment, and machinery leaving the park for any reason must be cleaned prior to re-entry into the park and will require re-inspection.

7. All vehicles, equipment, or machinery being stored at a private residence are to be kept in a pest free area, preferably in a garage, on pavement, and not under trees. Such vehicles, equipment, or machinery will be subject to additional inspection.

C. Cutting Tools: In order to prevent the spread of invasive species (most notably, the spread of Rapid ‛Ōhi‛a Death) the Contractor shall comply with the following:

1. Cutting tools including handsaws, machetes, chainsaws, and loppers must be sanitized to remove visible dirt, contaminants, and potential pathogens prior to entry into the park and when moving to a new project area. Tools must be sanitized using a solution of >70% isopropyl alcohol. One minute after sanitizing, you may apply an oil-based lubricant to chainsaw chains or other metallic parts to prevent corrosion. This applies to all cutting tools for all types of trees (including coconut trees).

2. All cutting tools will be subject to inspection by NPS personnel.

3. Cutting tools that do not pass inspection shall not be used until they pass inspection.

D. Contractor Base Yards and Staging Areas: In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Contractor base yards and staging areas, both inside and outside the park, shall be kept clean and free of invasive pests.

2. Base yards and staging areas may be inspected by NPS personnel for invasive pests.

3. Any invasive pests found at base yards or staging areas shall be removed immediately.

E. Materials, Packaging, Deliveries, and Storage: In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Materials, packaging, deliveries, and storage containers shall be kept clean and free of invasive pests. This includes soil, aggregate, and rock material from quarries or the source location, as well as temporary facilities and best management practice (BMP) items employed to manage surface water drainage and erosion.

2. Materials, packaging, deliveries, and storage containers will be inspected by NPS personnel for invasive pests. This includes soil, aggregate, and rock material from quarries or the source location, as well as temporary facilities and best management practice (BMP) items employed to manage surface water drainage and erosion.

3. Any item that does not pass inspection will be turned away and not allowed into the park.

4. The pest control records from quarries, source locations, or Contractor base yards may be requested.

5. Fresh crushed aggregate is preferred (if readily available) over aggregate that has been stockpiled at a quarry for a lengthy period.

F. Personal Protective Equipment (PPE): In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Before going into the field or the jobsite, visually inspect and clean all personal protective equipment (PPE) to include boots, clothes, hard hats, harnesses, belts, and equipment for dirt, mud, seeds, plant debris, and insects. Soles of shoes must be regularly sanitized using a solution of >70% isopropyl alcohol.

G. Inspections for Invasive Species: In order to prevent the spread of invasive species within the park and adjacent lands, NPS personnel from the park may perform inspections of vehicles, equipment, machinery, cutting tools, base yards, staging areas, materials, material packaging, material deliveries, material storage, and personal protective equipment (PPE). Please permit safe unfettered access to inspection sites or items being inspected for the NPS inspectors. Inspections for invasive species may include the following:

1. NPS inspectors will perform visual inspections for signs of invasive weeds and plants; invasive pests such coqui frogs and frog eggs, little fire ants (LFA), and insects including termites; other vertebrae species such as rats, mice, and reptiles; and mud and dirt that may carry Rapid ‛Ōhi‛a Death (ROD).

2. NPS inspectors will test vehicles, equipment, and machinery for little fire ants (LFA) by placing chopsticks baited with a dab of peanut butter for 30 minutes to 1 hour. About six (6) chopsticks (baits) will be used to test personal vehicles and trucks. Larger vehicles, equipment, and machinery may require up to 10-20 baits. Baits will be placed in the shade, inside the cab, engine compartment, and truck bed if applicable. Please note that baits are only good for detection and do not control ants. Baits will not be left in the vehicle for more than 1 hour as this may attract ants from beyond the area of concern.

3. NPS inspectors may employ the same method of testing (as outlined above in G.2) on materials, material packaging, material deliveries, and material storage to include soil, aggregate, and rock material from quarries or source locations, temporary facilities and BMP items employed to manage surface water drainage and erosion.

4. Any LFA found will be collected, bagged, and labeled for identifications by NPS inspectors (or NPS partners) and the vehicle will not be allowed to enter the park until it is cleaned, sanitized, and re-tested following a minimum 48-hour resting period.

5. Infested vehicles will be sanitized following recommendations by the Hawaii Ant Lab (http://www.littlefireants.com) or other ant control expert and in accordance with all State and Federal laws and baited with a granular or liquid insecticide bait prior to re-entry to the park.

Control records will be required to confirm treatment. Treatment is the responsibility of the Contractor.

6. The park reserves the right to conduct additional test for little fire ants (LFA) at any time during the project or require deployment of preventative granular or liquid insecticide baits.

7. Note that vehicles, equipment, machinery, and cutting tools previously used on the Big Island of Hawai’i will not be approved for entry at Haleakala National Park on Maui, and vice versa (items used on Maui will not be permitted in parks on the Big Island).

H. Invasive Species Disposal / Removal Recommendations: For current disposal / removal recommendations, refer to the following website links:

1. Little Fire Ants: http://www.littlefireants.com

2. Coqui Frogs: http://www.biisc.org

3. Rapid ōhi‛a death (ROD): https://cms.ctahr.hawaii.edu/rod

4. All taxa: http://www.biisc.org

I. Inspection Scheduling / Protocol: If inspections for invasive species are required, the Contractor shall adhere to the following protocol:

1. The Contractor’s construction schedule shall identify the date of project mobilization as well as the preferred date(s) for invasive species inspections in advance of mobilization.

2. The name and contact information for the NPS primary and backup inspectors will be identified at the time of the preconstruction meeting and documented in the meeting notes.

3. Formal requests for inspections shall be made by the Contractor directly to the NPS inspector(s) via the inspector’s contact information.

4. Requests for the initial inspection(s) prior to mobilization shall be made at least three (3) days in advance of the inspection date.

5. Once the project is underway, inspections will be performed daily as needed (typically early morning) at the park’s preferred inspection site for the duration of the contract.

6. Inspection requests outside the pre-established days and times will be performed at the discretion and availability of the inspectors.

7. Inspections shall occur at the park’s preferred inspection sites identified below:

a. At Hawaii Volcanoes National Park – At the gravel pull-out area along Highway 11 across from the Old Volcano Road or other location as determined by inspector.

http://www.littlefireants.com/ http://www.littlefireants.com/ http://www.biisc.org/ https://cms.ctahr.hawaii.edu/rod http://www.biisc.org/

b. At Haleakala National Park – Usually the port of origin or loading (depends on the location of the work). The inspector will go over the park’s Inspection Checklist with the Contractor. The Contractor must present a copy of the Inspection Checklist at the entrance station (signed by the inspector) to enter the park. See checklist.

c. At Kalaupapa National Historical Park – At the Kalaupapa pier after barge delivery of items. If invasive species are found, they may be quarantined until such time that they can be treated by the Contractor per Section 01 11 40, PART 3.2.H, or, sent back to Oahu on the barge at the Contractor’s expense.

d. At Kaloko-Honokohau National Historical Park – At the gravel pull-out area along Queen Kaahumanu Highway directly across from the entrance to the park visitor center (subject to change as this area may be further developed by the County).

e. At Pu’uhonua o Honaunau National Historical Park – At the paved scenic pull-out along Highway mauka of the park entrance.

f. At Pu’ukohola Heiau National Historic Site – Outside the park, TBD by inspector.

g. For all other Pacific Island parks, inspections are not required but the Contractor must still employ invasive species prevention measures.

8. Inspections of soil, aggregate, or rock materials may occur at the quarry or source location at the park’s discretion.

9. If a re-inspection is required, the Contractor shall clean and sanitize the item thoroughly. A re-inspection for a rejected item cannot be scheduled for at least 48 hours.

3.3 THREATENED & ENDANGERED SPECIES (T&E SPECIES)

A. General: Threatened & Endangered Plant and Animal Species are protected by Federal law. Workers must obey all park regulations and drivers must obey all traffic laws and watch for animals on or alongside roads or within the project area. Contact NPS Dispatch at: (808) 985- 6170 immediately if an animal is hit or injured or will not move off the road.

B. General Mitigations: Within the project area, the following mitigation measures are required to minimize disturbance to T&E species:

1. The project area shall be cleaned-up at the end of each work shift so that tools, materials, debris, and trash are not left out in a manner that could be a hazard to T&E species.

2. Noise and vibrations from tools and equipment shall be kept to a minimum when working in the vicinity of a listed T&E species.

3. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.

4. Tarps shall be used to contain all paint chips and building debris from exterior surfaces as these can be hazards to listed T&E species.

5. Ensure no standing water on tarps or other construction surfaces as it may be a breeding ground for mosquitoes which may carry Dengue fever, avian malaria / flu, and other diseases.

6. Ensure loose nails, screws, and fasteners do not fall on the ground when working on exterior surfaces as these can be a hazard to T&E species. If they do land on the ground, pick them up immediately and dispose of them properly.

C. Requirements for Specific T&E Species: The following are requirements for specific T&E species in the Hawaii national parks (delete those that are not applicable to the project).

1. Nēnē (Hawaiian goose) - Nēnē are frequently spotted along the roadside at Hawaii Volcanoes National Park (HAVO) and Haleakala National Park (HALE) and do not readily move when approached by cars. If there is a Nēnē on the road, drivers must stop and allow the Nēnē to move away on its own. Drivers should be aware that Nēnē may suddenly appear on the road from low brush and to be especially attentive of this on foggy and/or rainy days. In general, do not approach Nēnē and keep at least 60 feet away. Due to Nēnē breeding, construction activities may be limited Haleakala National Park (HALE) during the windows outlined below. Construction activities projected to occur during this window may not be permitted, or, may require additional mitigations measures. Refer also to “Working Around Endangered Birds.”

• Haleakala National Park (HQ Area only) - Nēnē breeding: From October 15 to April 15.

2. Other T&E Plants & Forest Birds – Prior to construction start, the park may survey the project area for threatened and endangered plants & forest birds (and their nests) and flag a buffer zone for protection.

Avoid flagged nest areas during construction activities.

D. Requirements for Other Species of Concern: The following are requirements for other species of concern in the Hawaii national parks (delete if not applicable to the project).

1. ‛Ōhi‛a Trees - Avoid wounding ‘ōhi‘a trees and roots with mowers, chainsaws, weed eaters, and other tools. Cut only a minimum amount of trees and branches as approved by the Contracting Officer and avoid making jagged cuts or stripping bark. Treat the cut, standing sections of ‘ōhi‘a with a wound sealant such as Spectracide Pruning Seal. Wound sealants other than Spectracide Pruning Seal will require review and approval by the Contracting Officer prior to use. ‘Ōhi‘a firewood, ‘ōhi‘a logs, ‘ōhi‘a parts, and ANY other cut vegetation, organic matter, or green waste that is not part of the project scope may not be brought into the park. All non-‘ōhi‘a firewood and logs imported into the park must be sourced from a park approved site free of invasive weeds and plants, invasive pests, and ROD.

3.4 ARCHAEOLOGICAL RESOURCES

A. General: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment. Archaeological resources are found above and below ground and underwater. Known archeological resources will be marked and flagged by the park. Do not disrupt known archaeological resources or flagged areas during construction activities. If necessary, the Contractor will erect temporary barriers around the archaeological resource to ensure avoidance. The Contractor does not need to provide an Archaeological Monitor; however, the Contractor, or Contractor’s designee, will observe all ground-disturbing activities during earthwork and other construction operations. If the Contractor discovers archaeological resources, the Contractor shall stop work, notify the Contracting Officer immediately, and relocate to a non-sensitive area. The park may have an Archaeological Monitor present at the jobsite who is authorized to stop work upon discovery of archaeological resources. Archaeological resources typically found in the park or at the project site will be discussed at the preconstruction meeting.

3.5 SOUNDSCAPE / NOISE

A. General: The Contractor shall minimize noise levels at the project site to protect the soundscape of the park and minimize noise to staff, visitors, neighbors, and habitat. Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week or as directed by the Contracting Officer. Repetitive and/or intermittent, high-level noise is permitted only during daytime hours. If the Contractor exceeds the thresholds below, the Contractor may be required to stop work, temporarily relocate to a non-sensitive area, or adjust the construction means and methods at no additional expense to the Government.

1. Maximum permissible construction equipment noise at 50 feet:

EARTHMOVING dB(A) MATERIALS HANDLING dB(A) Front Loaders 75 Concrete Mixers 75 Backhoes 75 Concrete Pumps 75 Dozers 75 Cranes 75 Tractors 75 Derricks Impact 75 Scrapers 80 Pile Drivers 95 Graders 75 Jack Hammers 75 Trucks 75 Rock Drills 80 Pavers, Stationary 80 Pneumatic Tools 80 Pumps 75 Saws 75 Generators 75 Vibrators 75 Compressors 75

2. Do not exceed the following dB(A) limitations at 50 feet:

TIME DURATION OF IMPACT NOISE dB(A)

More than 12 minutes in any hour 70 More than 3 minutes in any hour 80

3.6 AIR QUALITY (INDOOR & OUTDOOR)

A. General: The Contractor shall minimize the negative impacts to indoor and outdoor air quality as a result of their operations. This may include:

1. Control of emissions from vehicles or heavy equipment.

2. Control of fumes, vapors, or gases from products or packaging.

3. Control of particulates and dust from indoor operations such as cutting and sanding.

4. Control of particulates and dust from outdoor operations.

5. Control of moisture during operations that may lead to damage, fumes, or mold.

B. Mitigations: The Contractor shall mitigate for negative impacts to indoor and outdoor air quality as a result of their operations. This may include:

1. Ensure vehicles and heavy equipment do not idle when not in use.

2. Ensure proper ventilation and air movement of indoor spaces.

3. Install temporary mechanical ventilation where appropriate.

4. Ensure tools are equipped with the proper guards or particulate catchment devices.

5. Ensure particulates and debris are collected and disposed of on a regular basis.

6. Consider water trucks or temporary irrigation devises for dust control on unpaved surfaces.

7. Ensure products are properly dried or cured prior to advancing the work.

8. Ensure materials are stored in a dry location.

9. Ensure wet / damp materials are not installed or covered.

END OF SECTION 01 11 40

Commercial Pre-Inspection Checklist (Updated 02/20/2019)

Passing an invasive species inspection REQUIRES the removal of all organic matter including, but not limited to:

Dirt, mud, sand, seeds, insects, spider webs, live or dead animals, grass, manure, etc.

1) The truck or load-bearing vehicle must not be loaded prior to inspection in a way that prevents inspection of the contents. Please keep the load and vehicle separate at the designated inspection time to facilitate the process. Not doing so will delay your inspection.

2) The inspector must have full access to the vehicle. A vehicle that is actively being loaded for another project or contract cannot be adequately inspected. The inspector must have unobstructed access to the drivers cab, the wheel wells, engine compartment, attached toolboxes, etc.

3) The inspector will require a valid Special Park Use (SPU) or other permit issued by Haleakalā National Park before commencing inspection. A SPU without an inspector’s signature and clearance dates is not a valid permit and will be rejected at the entrance station.

Wash or powerwash vehicle inside and out

Vacuum interior, under seats and floor mats, door compartments, inside glove box, etc.

Clean wheel wells, checking mud flaps and inside of front and rear bumper for dirt and debris

Clean engine compartment: radiator, air filter, area beneath air filter, space between rubber seal and windshield

Truck beds: empty completely and wash thoroughly, under and inside tool box, any holes on racks

Low-boys, heavy equipment: tracks must be cleaned of debris, (it is understood that some rocks may be lodged in tracks), space beneath and underneath tracks, buckets, etc. all need to be cleaned

Surveying equipment, containers, ladders, delineators, etc: the base that sits on the ground must be cleaned, equipment must be removed from bags and cases, bags and cases must be cleaned

Raw materials from quarries/base yards: Needs to be fresh crush or cut, if the material has been sitting for greater than 1 day, the pile will have to be inspected and monitored while loaded

ANY vehicle, equipment, fabric, load, substrate (rocks or fill), soil, or other material that has been used or originates from the Big Island of Hawaii is banned from Haleakalā National Park due to the risk of spreading

Rapid ʻŌhiʻa Death into the park’s delicate ecosystems

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS (CLIN)

A. This…

This is the start of the file's text. The full file is on GovTribe.