B08_Attach_1_Construction_Specifications.pdf

PDF 2 MB Posted

Attached to
PUHE REPLACE TELECOM LINES HQ TO VC
Solicitation number
140P8226B0003
Issued by

About this file

This document is a Construction Specifications file for a federal contract to replace telecommunications lines at Pu'ukohola Heiau National Historic Site (PUHE) in Hawai'i. The project (PMIS No. 340780) involves installing approximately 1,000 linear feet of new telecommunications lines within existing buried conduit between the visitor center and headquarters area, approximately 1,000 linear feet apart. The work includes installing new wires, new panels at both ends, connections to existing systems, troubleshooting for proper operation, and removal and proper disposal of all existing telecommunications wires and approximately 500 linear feet of conduit currently lying on the ground uphill of the concrete pedestrian trail. The project will be constructed under a single prime contract and completed in one work phase.

The specifications cover Division 01 General Requirements, Division 27 Communications, and Division 31 Utilities, addressing work restrictions, resource protection, quality requirements, safety, temporary facilities, product specifications, and execution standards. Key technical requirements include installation of fiber optic and copper telecommunications cables complying with TIA standards, underground electrical distribution per NEMA and UL standards, and comprehensive testing including OTDR tests, attenuation measurements, and bandwidth testing. The Contractor must comply with archaeological protections requiring hand-digging with archaeologist presence, invasive species prevention protocols, environmental restrictions, and work hours limited to 6:00 a.m. to 4:00 p.m., Monday through Friday. Telecommunications contractor qualifications, 10 percent cable overage on reels, proper cable handling procedures, and detailed documentation including T5 drawings per ANSI/TIA-606 standards are mandatory requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PU’UKOHOLA HEIAU NATIONAL

HISTORIC SITE (PUHE), HAWAI’I

REPLACE TELECOMMUNICATIONS LINES FROM

HEADQUARTERS TO THE VISITOR CENTER

PMIS No. 340780

CONSTRUCTION SPECIFICATIONS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

FEBRUARY 2026

THIS PAGE INTENTIONALLY LEFT BLANK

TABLE OF CONTENTS Page 1 of 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS NO. OF PAGES

01 11 00 Summary of Work NPS Hot Work Permit (Form HW-1)

01 11 40 Work Restrictions & Resource Protection 01 27 00 Definition of Contract Line Items (CLINs) 01 31 00 Project Management & Coordination

Request for Information (RFI) Form 01 32 16 Construction Schedule 01 33 23 Submittal Procedures

CM-16 Transmittal Form Statement & Acknowledgement (Form SF1413)

01 35 23 Safety Requirements 01 40 00 Quality Requirements

Quality Control (QC) Daily Report Form 01 50 00 Temporary Facilities & Controls 01 57 23 Temporary Stormwater Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management 01 77 00 Closeout Procedures

DIVISION 02 – 48 TECHNICAL REQUIREMENTS

DIVISION 27 - COMMUNICATIONS

27 10 00 Building Telecommunications Cabling System

DIVISION 31 - UTILITIES

33 71 02 Underground Electrical Distribution 33 82 00 Telecommunications Outside Plant (OSP)

TABLE OF CONTENTS Page 2 of 2

DIVISION 01

GENERAL REQUIREMENTS

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 1 of 9

SECTION 01 11 00 – SUMMARY OF WORK

PART 1 – GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases / Sequence

3. Work Under Other Contracts

4. Government-Furnished Items

5. Government-Furnished Documents

6. Conduct of Operations

7. Contractor Use of the Site

8. Public Use of the Site

9. Government Use of the Site

10. Occupancy Requirements for Buildings & Areas

11. Codes

12. Permits

13. Professional Services

14. Utility Interruptions

15. Vehicles & Equipment

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Pu’ukohola Heiau National Historic Site (PUHE), Hawai’i. The site is located approximately 1 hour drive north of Kailua-Kona near Kawaihae.

B. Project Background: The park visitor center and headquarters area are approximately 1,000 linear feet apart. There are telecommunication lines (fiber & copper) that run between these two areas along a concrete pedestrian trail used primarily by park service personnel. Refer to GFD #1

– Aerial Map & Photos for the Existing Conditions.

C. Project Scope of Work: The Work consists of the following:

1. This project will install approximately 1,000 linear feet of new telecommunication lines within the existing buried conduit between the visitor center and the headquarters area including new wires, new panels on both ends, connections to existing systems, and troubleshooting to ensure proper operation. This project also includes removal and proper disposal of all existing telecommunications wires and approximately 500 linear feet of conduit currently laying on the ground uphill of the concrete pedestrian trail.

2. Project will be constructed under a single prime contract. Refer also to Section 01 27 00 –

Definition of Contract Line Items.

D. Project Mitigations: The Contractor shall comply with Section 01 11 40 – Work Restrictions & Resource Protection. In addition, the Contractor shall complete the following mitigations:

1. Mitigation #1: Only minor digging around pull boxes is anticipated as part of this project.

All digging shall be done by hand using shovels and other hand tools. The park’s

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 2 of 9 archaeologist must be present during all ground disturbing activities. Refer also to Work

Restrictions & Resource Protection, Section 01 11 40, PART 3.5.

2. Mitigation #2: Prior to removal and disposal of the existing conduit, which is laying on the ground uphill of the concrete pedestrian trail, the Contractor shall notify the park archaeologist to identify sensitive areas to avoid.

1.3 WORK PHASES / SEQUENCE

A. Work Phases: The Work will be completed in one (1) single work phase.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate contractors so that all contracts may be carried out smoothly without interfering with or delaying Work under this or other contracts. If another contract is awarded that may have an impact on this contract, the Contractor will be promptly notified.

1.5 GOVERNMENT-FURNISHED ITEMS

A. General: The Government may furnish items such as materials, equipment, facilities, services, or housing for Contractor use on this contract. The government may furnish these items to lower the overall project costs, make use of existing item(s), or out of necessity in a remote location. The Contractor can assume that all items offered below are at no direct cost to the

Contractor.

B. Government-Furnished Materials: NONE IDENTIFIED AT THE OUTSET OF THE

CONTRACT.

In the event government-furnished materials are offered (at the outset or furnished later):

a) The Government will arrange and pay for delivery of government-furnished materials to the project site or agreed upon location based on the contractor’s approved construction schedule.

b) The Government will inspect the delivered items for damage after delivery. The Contractor shall be present for, and assist in, the Government’s inspection.

c) The Government will arrange for the replacement of materials if the government-furnished materials are damaged, defective, or missing.

d) The Contractor shall do their due diligence to protect government-furnished materials from damage during storage and handling, including damage from exposure to the elements.

e) The Contractor shall install or otherwise incorporate government-furnished materials into the

Work of this contract, as outlined in the contract documents.

C. Government-Furnished Equipment / Transportation: NONE IDENTIFIED AT THE OUTSET OF

THE CONTRACT.

In the event government-furnished equipment is offered (at the outset or furnished later):

a) The Government will make the equipment available for Contractor use based on the

Contractor’s approved construction schedule.

b) The Government will inspect the equipment and document its condition prior to Contractor use. The Contractor shall be present for, and assist in, the Government’s inspection.

c) The Contractor shall provide all licensed, certified equipment operators.

d) The Government will provide an orientation and training on the equipment prior to use.

e) The Contractor shall provide all fuels / oils to operate the equipment, unless stated otherwise.

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 3 of 9

f) The Government will arrange for the replacement or repair of equipment, or provide an alternative, if the government-furnished equipment breaks during use.

g) The Contractor shall do their due diligence to protect the government-furnished equipment from damage, including damage from exposure to the elements.

D. Government-Furnished Facilities: The following facilities will be available to the Contractor for use on this contract. Refer also to Section 01 50 00 Temporary Facilities & Controls.

1. Restroom: Public restrooms are available at both the visitor center and headquarters area.

2. Field Office: NOT AVAILABLE. A temporary field office may be permitted at the headquarters area. Request allowance through the Contracting Officer.

3. Storage Space: Temporary storage of materials may be permitted at the maintenance yard across the street from the park. Request storage space through the Contracting Officer.

E. Government-Furnished Utilities: The following utilities will be available to the Contractor for use on this contract. Refer also to Section 01 50 00 Temporary Facilities & Controls.

1. Potable Water: NOT AVAILABLE.

2. Non-Potable Water: Available. Contact the park Facility Manager.

3. Wastewater Disposal: NOT AVAILABLE.

4. Hydrotesting & Disinfection Water Disposal: NOT AVAILABLE.

5. Electrical Power: Available. Contact the park Facility Manager.

F. Government-Furnished Housing: NOT AVAILABLE ON THIS PROJECT.

1.6 GOVERNMENT-FURNISHED DOCUMENTS (GFD)

A. General: The Government may furnish reports or other documents for informational purposes to supplement the contract documents (labeled as GFD). In cases of conflict between a GFD and the drawings and specifications, the drawings and specifications will govern.

1.7 CONDUCT OF OPERATIONS

A. Park Regulations: The Contractor shall conduct their operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service (NPS), and applicable park rules and regulations prescribed by the Park Superintendent. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

B. Work Hours: Regular work hours shall be limited to daylight hours between 6:00 a.m. to 4:00 p.m. Monday through Friday, unless stated otherwise. No work shall be performed on weekends, state or federal holidays. Work outside regular hours requires advance approval from the

Contracting Officer to ensure key NPS personnel are present in the event of an emergency.

C. Advertisement: No signs or advertisements shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

D. COVID-19 (Coronavirus Disease 2019): The Contractor shall comply with the latest guidance on

Covid-19. The information provided below is not intended to provide a complete analysis of requirements for Contractor and is provided as a courtesy.

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 4 of 9

1. Occupational Safety & Health Administration (United States Department of Labor).

www.osha.gov/coronavirus.

2. Center for Disease Control (CDC) - www.cdc.gov/coronavirus/2019-ncov/index.html

3. Department of the Interior (DOI) - Our Response to COVID-19 | U.S. Department of the

Interior (doi.gov).

1.8 CONTRACTOR USE OF THE SITE

A. Park Entry: Vehicles associated with the contract shall be waived the entrance fee upon entering in marked company vehicles or by providing the full names, vehicle type, and the license plate numbers of employees entering in personal vehicles.

B. Site Access: The Contractor shall access the site as outlined in the drawings or attached map.

C. Project Area Limits: The Contractor will have limited use of the site for construction operations.

Limit operations to the project area limits as outlined in the drawings or attached map. Do not disturb portions of the park or site beyond areas where Work is indicated.

D. Storage of Materials: Confine storage of materials to the areas as outlined in the drawings or attached map. If no specific site is shown, assume storage of materials is allowed within the project area limits and arrange for storage of materials with the park facility manager so as not to disrupt normal operations. The park will attempt to provide a covered area, if available. The Contractor may also furnish conex storage containers for material / tool storage as long as they are placed on a hardened surface within the project area limits or other approved location, and as long as the Contractor protects all surfaces from damage. Damage to surfaces shall be restored to pre-construction conditions. The Contractor will also be responsible for the protection and security of all materials stored in the park.

E. Staging of Materials and Equipment: Confine staging of materials and equipment to the areas as outlined in the drawings or attached map. If no specific site is shown, assume staging of materials and equipment is allowed within the project area limits and arrange for staging of materials and equipment with the park facility manager so as not to disrupt normal operations.

Staging of heavy equipment at the jobsite overnight is permitted if the equipment remains within the designated locations within the project area limits, is checked for leaks and has the proper spill prevention measures (refer to PART 1.16.F), and has adequate surface protection to prevent permanent track marks, spalls, cracks, ruts, depressions, and other damage (refer to PART 1.16.K). The Contractor is responsible for the protection and security of all materials and equipment staged at the jobsite.

F. Stockpiling: Confine stockpiling of excavated soils to the area immediately adjacent to the trench or excavation, and, remove stockpiled materials from the jobsite if the materials will not be reused as part of the project. Confine imported soils and/or aggregate to the area(s) outlined in the drawings or attached map. If no specific site is shown, assume imported soils or aggregate is allowed within the project limits; however, consult with the park facility manager for an optimal location so as not to disrupt normal park operations. Protect all surfaces from damage. Damage to surfaces shall be restored to pre-construction conditions.

G. Rock Removal: When encountering large rock or a significant volume of rock during excavation, follow the guidance outlined in Section 1.8.F for initial stockpiling. If the contract documents

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 5 of 9 involve rock work, use the excavated rocks before importing rock. If the contract documents do not specify instructions regarding rock removal, relocation, or disposal, please submit a Request for Information (RFI) to the NPS for further instructions (with an estimated quantity of rock). All rock excavated at project sites on Molokai, Maui, and the Big Island of Hawai’i will remain within the project area limits or be relocated to a different location within the park.

H. Field Office: Establishment of a construction camp within the park will not be permitted. The park will make every attempt to furnish the contractor with indoor office space for up to two (2) contractor personnel; however, if the park cannot accommodate the Contractor with office space, the Contractor will be allowed to setup a temporary field office within the project area limits (final location to be approved by the park facility manager). Note that connection to NPS internet or computer networks is prohibited for security purposes. Refer also to Section 01 50 00.

I. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or NPS Dispatch at the first available opportunity at: (808) 985-6170.

J. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation.

Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

1.9 PUBLIC USE OF THE SITE

A. General: Cooperate with NPS and partner staff so that the Work may be carried out smoothly without interfering with or delaying the Work under this or other contracts.

B. Park Visitation: The project site (i.e. concrete pedestrian trail) will be CLOSED to park visitors during construction. The Contractor shall conduct their operations to minimize the inconvenience to the public.

C. Park Events: The following park events are anticipated during the Work. No work shall occur during park events:

1. Event #1: Cultural Festival – Mid-August every year.

1.10 GOVERNMENT USE OF THE SITE

A. General: Cooperate with NPS and partner staff so that the Work may be carried out smoothly without interfering with or delaying the Work under this or other contracts.

B. Hawaiian Blessing: Prior to field construction and/or immediately following all construction activities, the NPS may conduct a Hawaiian Blessing Ceremony to consecrate the site. A determination for the need of a blessing ceremony will be made by the Park Superintendent and discussed during the pre-construction meeting. The Contractor may attend the blessing ceremony, but no compensation will be made for attendance.

1.11 OCCUPANCY REQUIREMENTS FOR BUILDINGS & AREAS

A. Government Occupancy: The Government will occupy the building(s) or area(s) under construction until the construction phase is complete and final acceptance has been issued.

Cooperate with the Government during construction activities to minimize conflicts. Perform the

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 6 of 9

Work so as not to interfere with the Government’s day-to-day operations. Maintain existing building ingress, egress, doorways, corridors, access walkways, access roads, and public space unless the Contractor obtains written permission from the Contracting Officer to close, partially close, or temporarily close specific areas.

B. Government Occupancy of Completed Areas: The Government reserves the right to occupy portions of buildings or areas and resume operations where the Work has been completed, provided such occupancy does not interfere with the completion of the remaining Work.

1. The Contractor shall ensure all Work is completed; all systems are operational; all testing, balancing, and inspections have been performed; and all final cleaning is completed prior to Government occupancy.

2. The Contracting Officer will prepare a Letter of Beneficial Use / Occupancy for the portion(s) of the building or areas to be re-occupied by the Government.

3. Upon Government occupancy, the Government will assume responsibility for the maintenance and custodial services for occupied portions of the building or areas.

1.12 CODES

A. General: The Contractor shall complete all Work in accordance with the latest versions of applicable federal, state, and local codes, standards, and regulations. Per Policy Memorandum 23-01 approved on May 9, 2023, the National Park Services (NPS) has adopted the International Code Council’s (ICC) suite of codes and standards effective January 1, 2024. Additionally, the latest NFPA 70 (National Electric Code) is also adopted effective January 1, 2024. All work shall comply with the ICC suite of codes and standards and NFPA 70, where applicable. Additional codes, standards, and regulations may also apply. In the event of a conflict between codes, standards, regulations, and the contract documents, submit a Request for Information (RFI) with code references / citations to the Contracting Officer for a determination.

1.13 PERMITS

A. General: The Contractor shall comply with all permit conditions, whether they are from permits furnished by the government (PART 1.13.D) or permits obtained as part of this contract (PART 1.13.E). Identify the start dates and durations to obtain all permits in the construction schedule.

Note: A general building permit is not required for work on NPS land; however, the Contractor must still comply with all state and local building code provisions.

B. Hot Work Permit: Hot work is defined as work activities (such as welding, cutting, blazing, and related work) that can be a source of ignition when flammable materials are present. All hot work operations shall be conducted in accordance with the procedures contained in RM-58, NPS policy on Hot Work Permits (see Appendix 35.8), and 29 CFR 1910.252(a). If the project requires any activities considered “hot work,” submit a NPS Hot Work Permit (Form HW-1) application to the Contracting Officer at least 48 hours prior to the scheduled hot work. The NPS will then review and complete Form HW-1 and return a copy to the Contractor with the required conditions or precautions. No hot work shall occur without a completed and signed Form HW-1 and all the required precautions in place. See attached Form HW-1.

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 7 of 9

C. Confined Space Entry Permit: The Contractor and/or Employer shall adhere to, and implement, the permit-required confined space requirements of the Authority Having jurisdiction. Before each entry into a permit-required confined space, a permit must be completed, hazards must be assessed and controlled, proper ventilation and air-monitoring ensured, and personnel trained and equipped, with an attendant(s) stationed outside the space for constant communication and rescue readiness. A copy of the permit shall be furnished to the NPS for situational awareness.

D. Government-Furnished Permits: NONE.

E. Other Required Permits: NONE.

1.14 PROFESSIONAL SERVICES

A. General: Professional services include any business, department, or individual whose core output is a service or expertise rather than a manufactured product.

B. Shop Drawings: The Contractor shall submit shop drawings per Section 01 33 23, PART 1.4.F for the following components:

1. Component #1: Precast underground structures per Section 33 71 02.

C. Professional Land Surveyor (PLS): A professional land surveyor is NOT REQUIRED for this project.

D. Professional Engineer (P.E.): A professional engineer is NOT REQUIRED for this project.

1.15 UTILITY INTERUPTIONS

A. General: All Work shall be generally performed during normal business hours.

B. Existing Utilities: Notify the Contracting Officer and all applicable utility companies of the Work being performed on a utility prior to excavation or disruption. The Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs to a known utility, repair the utility at no additional expense to the Government. If damage occurs to an unknown utility: 1) submit a Request for Information (RFI) to the NPS for further instructions, or, if time is of essence, 2) repair the utility / restore service and an equitable adjustment will be made in accordance with the Changes Clause of the contract.

C. Utility Disruptions: Do not disrupt utility service to Government or NPS partner buildings or facilities unless required under the contract documents. If utility disruptions are required:

1. Notify the Contracting Officer and all applicable utility companies not less than seven (7) calendar days in advance of the proposed utility disruption.

2. Identify the affected services, location(s), start date, and duration of the disruption.

3. Install temporary utility services if required under the contract documents.

4. Do not proceed with utility disruptions without written permission from the Contracting

Officer and the local utility service provider (where applicable).

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 8 of 9

1.16 VEHICLES & HEAVY EQUIPMENT

A. General: The Contractor shall comply with the following work restrictions for vehicles and heavy equipment.

B. Rules of the Road: Vehicles and heavy equipment shall comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved pullouts to allow faster-moving traffic to pass.

Failure to comply with traffic regulations will result in a citation being issued to the driver.

C. Vehicle Parking: Confine parking of Contractor vehicles to the areas as outlined in the drawings or attached map. Vehicles are not permitted to park along park roads or in overlooks / pullouts.

Vehicles are not permitted to park overnight in the park.

D. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to Government employees, vendor deliveries, and emergency vehicles at all times.

E. Vehicle Exhaust: Vehicles shall be properly maintained to ensure the exhaust produced is within legal limits. The effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

F. Spills: The Contractor shall be responsible for prevention of spills and/or cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immediately notify a Law Enforcement Ranger or NPS Dispatch of any spills at: (808) 985-6170.

G. DOT Compliance: Vehicles and heavy equipment shall be compliant with all DOT requirements including but not limited to drivers with appropriate license class, possessing a medical examiner card with license class as appropriate, carrying three (3) triangles or three (3) flares, carrying a mounted fire extinguisher, and possessing a valid DOT safety sticker, as applicable.

H. Hauling & Load Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the park road (36 CFR § 4.11). No loads heavier than the current load rating for park roads and bridges will be permitted. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent.

I. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the park road corridor. Oversized vehicles will require an escort, and drivers must avoid driving on the shoulder of the road. Contractor shall notify the Contracting Officer of oversized vehicles, scheduled arrival dates & times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). The Contractor shall avoid transporting loads using oversized vehicles during peak visitation periods in the park.

These peak visitation periods may vary between parks and seasons. Submit an RFI at least seven

(7) days prior to entering the park with an oversized vehicle to obtain the optimal travel times.

J. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines.

PUHE #340780 SUMMARY OF WORK (01 11 00) Page 9 of 9

K. Tracked Equipment: Heavy equipment with rubber tires is preferred on projects within the national park. Heavy equipment with metal tracks may be allowed on paved asphalt surfaces, concrete surfaces, or ceremonial lawn areas only with adequate surface protection to prevent permanent track marks, spalls, cracks, ruts, depressions, and other damage. The means and methods of surface protection (such as plywood sheets or steel plates) shall also not damage surfaces. The exceptions listed below may apply. If the Contractor anticipates one of these exceptions, submit a Request for Information (RFI) to the NPS for further instructions.

1. Tracked equipment may be allowed on paved asphalt or concrete surfaces in lieu of surface protection if the Contractor repairs all the affected surfaces to pre-construction condition or replaces the surface with new asphalt or new concrete, as applicable.

2. Tracked equipment may be allowed on older paved asphalt surfaces if the asphalt surface is scheduled for pavement preservation (by others) within one (1) year of contract completion.

3. Tracked equipment may be allowed on un-paved gravel roads if the tracked equipment stays on the road and does not create ruts, damage, or impacts the surface water flow. If damage occurs, the Contractor shall re-grade / restore the terrain to pre-construction conditions.

4. Tracked equipment may be allowed on grass surfaces within the project area limits with adequate surface protection or the terrain is re-graded / restored to preconstruction conditions.

Reseeding of re-graded / restored areas is not required unless otherwise specified.

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION 01 11 00

Hot Work Permit (Form HW-1)

Hot Work Permitting Hot work shall only be performed in designated or permit-required areas. Before hot work operations begin in a non-designated location, a signed Hot Work Permit, issued by the Permit Authorizing Individual or his/her designee, shall be issued.

Designated Area A designated area shall be a specific area designed for, or approved by the Permit Authorizing Individual or his/her designee for, such work. A designated area can be a maintenance shop or a detached outside location that is of noncombustible or fire-resistive construction, essentially free of combustible and flammable contents, and suitably segregated from adjacent areas. All designated areas shall have been inspected and approved by the Permit Authorizing Individual or his/her designee.

Permit-Required Area A permit-required area shall be an area that is made fire safe and authorized by the issuance of a signed NPS Hot Work Permit. The Hot Work Permit shall be signed by Permit Authorizing Individual or his/her designee.

Non-permissible Areas Hot work shall not be allowed in the following areas:

(a) In areas not authorized by the Permit Authorizing Individual or his/her designee

(b) In sprinklered buildings while such protection is impaired

(c) In the presence of explosive atmospheres (that is, where mixtures of flammable gases, vapors, liquids, or dusts with air exist)

(d) In explosive atmospheres that can develop inside unclean or improperly prepared drums, tanks, or other containers and equipment that have previously contained such materials

(e) In explosive atmospheres that can develop in areas with an accumulation of combustible dusts

GENERAL

Park: District: Building: Floor:

Work to be done:

Special precautions:

PERSON PERFORMING WORK

Contractor Business Name:

Contractor Representative:

Contractor Contact Number:

NPS Employee’s Name:

NPS Office:

NPS Employee’s Contact Number:

CHECK

Work area and all adjacent areas to which sparks and heat might have spread (including floors above and below and on opposite side of wall(s) were inspected every 20 minutes for 1 hour after the work was completed and were found fire safe.

ATTENTION

Before approving any hot work permit, the Permit Authorizing Individual or his/her designee shall inspect the work area and confirm that the proper precautions have been taken to prevent fire, in accordance with the NPS Hot Work Permit Form (Form HW-1) and the NPS Hot Work Policy.

PRECAUTIONS

Sprinklers in service Hot work equipment in good repair

WITHIN 35 FEET OF HOT WORK AREA

Floors swept, clean of combustibles Combustible floors wetted down, covered w/ damp sand or other shields in place All wall and floor openings covered

WORK ON WALLS OR CEILINGS

Combustibles moved away from opposite side of wall

WORK ON ENCLOSED EQUIPMENT (tanks, containers, ducts, dust collectors etc.)

Equipment cleaned of all combustibles Containers purged of all flammable vapors

FIRE WATCH

To be provided during and 60 minutes after operation Supplied with a fully charged and operable fire extinguisher Trained in use of equipment and activating fire alarm system

FINAL CHECK

To be made every 20 minutes for 60 minutes after completion of any operation unless fire watch is provided

Is a fire watch required? Yes No

The location where the work is to be done has been examined, necessary precautions taken, and permission is granted for this work.

Permit Issue Date: Permit Expires:

Permit Authorizing Individual or Designee:

Signature: Date:

PUHE #340780 WORK RESTRICTIONS (01 11 40) Page 1 of 6

SECTION 01 11 40 – WORK RESTRICTIONS & RESOURCE PROTECTION

A. General: The NPS is the steward of unique resources found within the national parks. The NPS is committed to protecting natural, cultural, historical, archaeological, and other resources found within the parks and the adjacent lands.

B. Section includes work restrictions for protecting resources in the national parks including, but not limited to the following:

1. Preservation of Natural Features

2. Invasive Species Prevention

3. Invasive Species Inspections

4. Threatened & Endangered Species (T&E Species)

5. Archaeological Resources

6. Soundscape / Noise

7. Air Quality (Indoor & Outdoor)

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION

3.1 PRESERVATION OF NATURAL FEATURES

A. General: The Contractor shall comply with the following work restrictions:

1. Prevent damage to natural surroundings.

2. Provide temporary barriers to protect existing trees, tree roots, plants, grass areas and lawns that are directly impacted by construction operations. Temporary barriers should be free-standing orange traffic delineator posts with grabber / looper tops and plastic rails.

3. Do not fasten ropes, cables, or guys to existing trees, rock outcrops, or other natural features.

4. Do not remove, injure, or destroy existing trees, tree roots, or plants without approval by the

Contracting Officer or unless it’s explicitly required in the contract documents.

5. If a tree, tree branch, root, or mass of vegetation is preventing the Contractor from completing the work, notify the Contracting Officer immediately for a determination. Trees may need to be surveyed by park staff for bird nests prior to removal. Tree removal / trimming may be subject to additional restrictions if project is in Hawaiian hoary bat habitat.

6. Carefully supervise the excavation, grading, filling, equipment movement, and other construction operations near trees and tree branches to prevent damage.

3.2 INVASIVE SPECIES PREVENTION

A. General: The introduction of non-native species including invasive weeds and plants; invasive pests such coqui frogs and frog eggs, little fire ants (LFA), and insects including termites; other vertebrae species such as rats, mice, and reptiles; and diseases such as Rapid ‛Ōhi‛a Death (ROD) spread through contaminated soil can threaten the park’s rare and endangered plants and animals or can create new populations of non-native species not traditionally found in the park. Ensure all vehicles, equipment, machinery, cutting tools, base yards, staging areas, materials, material

PUHE #340780 WORK RESTRICTIONS (01 11 40) Page 2 of 6 packaging, material deliveries, material storage, and personal protective equipment (PPE) are clean and free of invasive weeds and plants, invasive pests, and ROD spread through soil.

B. Vehicles, Equipment, & Machinery: In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Vehicles, equipment, and machinery must be thoroughly pressure washed and visibly free of dirt, mud, plant debris, and invasive pests. Areas of particular concern include bumpers, grills, hood compartments, under the battery, wheel wells, undercarriage, cabs and truck beds.

2. The interior and exterior of vehicles, equipment and machinery must be free of rubbish. The interiors of vehicles and the cabs of machinery must be vacuumed clean. Floor mats must be sanitized with a solution of >70% isopropyl alcohol.

3. All vehicles, equipment, and machinery shall park on pavement and not under trees (where possible).

4. All vehicles, equipment, and machinery will be subject to inspection by NPS personnel.

5. All vehicles, equipment, and machinery that do not pass inspection will be turned away. The vehicle will not be allowed into the park for at least 48 hours.

6. All vehicles, equipment, and machinery leaving the park for any reason must be cleaned prior to re-entry into the park and will require re-inspection.

7. All vehicles, equipment, or machinery being stored at a private residence are to be kept in a pest free area, preferably in a garage, on pavement, and not under trees. Such vehicles, equipment, or machinery will be subject to additional inspection.

C. Cutting Tools: In order to prevent the spread of invasive species (most notably, the spread of

Rapid ‛Ōhi‛a Death) the Contractor shall comply with the following:

1. Cutting tools including handsaws, machetes, chainsaws, and loppers must be sanitized to remove visible dirt, contaminants, and potential pathogens prior to entry into the park and when moving to a new project area. Tools must be sanitized using a solution of >70% isopropyl alcohol. One minute after sanitizing, you may apply an oil-based lubricant to chainsaw chains or other metallic parts to prevent corrosion. This applies to all cutting tools for all types of trees (including coconut trees).

2. All cutting tools will be subject to inspection by NPS personnel.

3. Cutting tools that do not pass inspection shall not be used until they pass inspection.

D. Contractor Base Yards, Staging Areas, and Project Areas: In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Contractor base yards and staging areas, both inside and outside the park, shall be kept clean and free of invasive pests.

2. Base yards and staging areas may be inspected by NPS personnel for invasive pests.

3. Any invasive pests found at base yards or staging areas shall be removed immediately.

4. If new infestations or populations of invasive pests are detected in or near Contractor base yards, staging areas, or project areas, the NPS may dispatch personnel to conduct control measures. Work on the project may be temporarily delayed until the infestation or population no longer poses a thread of spreading (as determined by the NPS).

E. Materials, Packaging, Deliveries, and Storage: In order to prevent the spread of invasive species, the Contractor shall comply with the following:

PUHE #340780 WORK RESTRICTIONS (01 11 40) Page 3 of 6

1. Materials, packaging, deliveries, and storage containers shall be kept clean and free of invasive pests. This includes soil, aggregate, and rock material from quarries or the source location, as well as temporary facilities and best management practice (BMP) items employed to manage surface water drainage and erosion.

2. Materials, packaging, deliveries, and storage containers will be inspected by NPS personnel for invasive pests. This includes soil, aggregate, and rock material from quarries or the source location, as well as temporary facilities and best management practice (BMP) items employed to manage surface water drainage and erosion.

3. Any item that does not pass inspection will be turned away and not allowed into the park.

4. The pest control records from quarries, source locations, or Contractor base yards may be requested.

5. Fresh crushed aggregate is preferred (if readily available) over aggregate that has been stockpiled at a quarry for a lengthy period.

F. Personal Protective Equipment (PPE): In order to prevent the spread of invasive species, the Contractor shall comply with the following:

1. Before going into the field or the jobsite, visually inspect and clean all personal protective equipment (PPE) to include boots, clothes, hard hats, harnesses, belts, and equipment for dirt, mud, seeds, plant debris, and insects. Soles of shoes must be regularly sanitized using a solution of >70% isopropyl alcohol.

3.3 INVASIVE SPECIES INSPECTIONS

A. Inspections for Invasive Species: In order to prevent the spread of invasive species within the park and adjacent lands, NPS personnel from the park will perform inspections of vehicles, equipment, machinery, cutting tools, base yards, staging areas, materials, material packaging, material deliveries, material storage, and personal protective equipment (PPE). Please permit safe unfettered access to inspection sites or items being inspected for the NPS inspectors.

Inspections for invasive species may include the following:

1. NPS inspectors will perform visual inspections for signs of invasive weeds and plants;

invasive pests such coqui frogs and frog eggs, little fire ants (LFA), and insects including termites; other vertebrae species such as rats, mice, and reptiles; and mud and dirt that may carry Rapid ‛Ōhi‛a Death (ROD).

2. NPS inspectors will test vehicles, equipment, and machinery for little fire ants (LFA) by placing chopsticks baited with a dab of peanut butter for 30 minutes to 1 hour. About six

(6) chopsticks (baits) will be used to test personal vehicles and trucks. Larger vehicles, equipment, and machinery may require up to 10-20 baits. Baits will be placed in the shade, inside the cab, engine compartment, and truck bed if applicable. Please note that baits are only good for detection and do not control ants. Baits will not be left in the vehicle for more than 1 hour as this may attract ants from beyond the area of concern.

3. NPS inspectors may employ the same method of testing (as outlined above in G.2) on materials, material packaging, material deliveries, and material storage to include soil, aggregate, and rock material from quarries or source locations, temporary facilities and BMP items employed to manage surface water drainage and erosion.

4. Any LFA found will be collected, bagged, and labeled for identifications by NPS inspectors (or NPS partners) and the vehicle will not be allowed to enter the park until it is cleaned, sanitized, and re-tested following a minimum 48-hour resting period.

5. Infested vehicles will be sanitized following recommendations by the Hawaii Ant Lab (http://www.littlefireants.com) or other ant control expert and in accordance with all State http://www.littlefireants.com/

PUHE #340780 WORK RESTRICTIONS (01 11 40) Page 4 of 6 and Federal laws and baited with a granular or liquid insecticide bait prior to re-entry to the park. Control records will be required to confirm treatment. Treatment is the responsibility of the Contractor.

6. The park reserves the right to conduct additional tests for little fire ants (LFA) at any time during the project or require deployment of preventative granular or liquid insecticide baits.

7. Note that vehicles, equipment, machinery, and cutting tools previously used on the Big Island of Hawai’i will not be approved for entry into Haleakala National Park on Maui, and vice versa (items used on Maui will not be permitted into parks on the Big Island).

B. Invasive Species Disposal / Removal Recommendations: For current disposal / removal recommendations, refer to the following website links:

1. Little Fire Ants: http://www.littlefireants.com

2. Coqui Frogs: http://www.biisc.org

3. Rapid ōhi‛a death (ROD): https://cms.ctahr.hawaii.edu/rod

4. All taxa: http://www.biisc.org

C. Inspection Scheduling / Protocol: If inspections for invasive species are required, the

Contractor shall adhere to the following protocol:

1. The Contractor’s construction schedule shall identify the date of project mobilization as well as the preferred date(s) for invasive species inspections in advance of mobilization.

2. The name and contact information for the NPS primary and backup inspectors will be identified at the time of the preconstruction meeting and documented in the meeting notes.

3. Formal requests for inspections shall be made by the Contractor directly to the NPS inspector(s) via the inspector’s contact information.

4. Requests for the initial inspection(s) prior to mobilization shall be made at least three (3) days in advance of the inspection date.

5. Once the project is underway, inspections will be performed daily as needed (typically early morning) at the park’s preferred inspection site for the duration of the contract.

6. Inspection requests outside the pre-established days and times will be performed at the discretion and availability of the inspectors.

7. Inspections shall occur at the park’s preferred inspection sites identified below:

a. At Pu’ukohola Heiau National Historic Site – Outside the park, TBD by inspector.

8. Inspections of soil, aggregate, or rock materials may occur at the quarry or source location at the park’s discretion.

9. If a re-inspection is required, the Contractor shall clean and sanitize the item thoroughly. A re-inspection for a rejected item cannot be scheduled for at least 48 hours.

3.4 THREATENED & ENDANGERED SPECIES (T&E SPECIES)

A. General: Threatened & Endangered Plant and Animal Species are protected by Federal law.

Workers must obey all park regulations and drivers must obey all traffic laws and watch for animals on or alongside roads or within the project area. Contact NPS Dispatch at: (808) 985- 6170 immediately if an animal is hit or injured or will not move off the road.

B. General Mitigations: Within the project area, the following mitigation measures are required to minimize disturbance to T&E species:

1. The project area shall be cleaned-up at the end of each work shift so that tools, materials, debris, and trash are not left out in a manner that could be a hazard to T&E species.

http://www.littlefireants.com/ http://www.biisc.org/ https://cms.ctahr.hawaii.edu/rod http://www.biisc.org/

PUHE #340780 WORK RESTRICTIONS (01 11 40) Page 5 of 6

2. Noise and vibrations from tools and equipment shall be kept to a minimum when working in the vicinity of a listed T&E species.

3. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.

4. Tarps shall be used to contain all paint chips and building debris from exterior surfaces as these can be hazards to listed T&E species.

5. Ensure no standing water on tarps or other construction surfaces as it may be a breeding ground for mosquitoes which may carry Dengue fever, avian malaria / flu, and other diseases.

6. Ensure loose nails, screws, and fasteners do not fall on the ground when working on exterior surfaces as these can be a hazard to T&E species. If they do land on the ground, pick them up immediately and dispose of them properly.

3.5 ARCHAEOLOGICAL RESOURCES

A. General: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment. Archaeological resources are found above and below ground and underwater. Known archeological resources will be marked and flagged by the park. Do not disrupt known archaeological resources or flagged areas during construction activities. If required in Section 01 11 00, PART 1.2.D, the Contractor shall erect temporary barriers around the archaeological resource to help ensure avoidance. Temporary barriers shall be free-standing orange traffic delineator posts with grabber / looper tops and plastic rails (or a comparable barrier that does not involve digging but is an effective barrier). Submit a CM-16 with the proposed temporary barrier product for NPS approval.

The Contractor does not need to provide an Archaeological Monitor; however, the Contractor, or Contractor’s designee, will observe all ground-disturbing activities during earthwork and other construction operations. If the Contractor discovers archaeological resources, the Contractor shall stop work, notify the Contracting Officer immediately, and relocate to a non-sensitive area.

The park may have an Archaeological Monitor present at the jobsite who is authorized to stop work upon discovery of archaeological resources. Archaeological resources typically found in the park or at the project site will be discussed at the preconstruction meeting.

3.6 SOUNDSCAPE / NOISE

A. General: The Contractor shall minimize noise levels at the project site to protect the soundscape of the park and minimize noise to staff, visitors, neighbors, and habitat. Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week or as directed by the Contracting Officer. Repetitive and/or intermittent, high-level noise is permitted only during daytime hours. If the Contractor exceeds the thresholds below, the Contractor may be required to stop work, temporarily relocate to a non-sensitive area, or adjust the construction means and methods at no additional expense to the Government.

1. Maximum permissible construction equipment noise at 50 feet:

EARTHMOVING dB(A) MATERIALS HANDLING dB(A) Front Loaders 75 Concrete Mixers 75 Backhoes 75 Concrete Pumps 75 Dozers 75 Cranes 75 Tractors 75 Derricks Impact 75 Scrapers 80 Pile Drivers 95 Graders 75 Jack Hammers 75

PUHE #340780 WORK RESTRICTIONS (01 11 40) Page 6 of 6

Trucks 75 Rock Drills 80 Pavers, Stationary 80 Pneumatic Tools 80 Pumps 75 Saws 75 Generators 75 Vibrators 75 Compressors 75

2. Do not exceed the following dB(A) limitations at 50 feet:

TIME DURATION OF IMPACT NOISE dB(A) More than 12 minutes in any hour 70 More than 3 minutes in any hour 80

3.7 AIR QUALITY (INDOOR & OUTDOOR)

A. General: The Contractor shall minimize the negative impacts to indoor and outdoor air quality as a result of their operations. This may include:

1. Control of emissions from vehicles or heavy equipment.

2. Control of fumes, vapors, or gases from products or packaging.

3. Control of particulates and dust from indoor operations such as cutting and sanding.

4. Control of particulates and dust from outdoor operations.

5. Control of moisture during operations that may lead to damage, fumes, or mold.

B. Mitigations: The Contractor shall mitigate for negative impacts to indoor and outdoor air quality as a result of their operations. This may include:

1. Ensure vehicles and heavy equipment do not idle when not in use.

2. Ensure proper ventilation and air movement of indoor spaces.

3. Install temporary mechanical ventilation where appropriate.

4. Ensure tools are equipped with the proper guards or particulate catchment devices.

5. Ensure particulates and debris are collected and disposed of on a regular basis.

6. Consider water trucks or temporary irrigation devises for dust control on unpaved surfaces.

7. Ensure products are properly dried or cured prior to advancing the work.

8. Ensure materials are stored in a dry location.

9. Ensure wet / damp materials are not installed or covered.

END OF SECTION 01 11 40

PUHE #340780 DEFINITION OF CLINs (01 27 00) Page 1 of 1

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS (CLIN)

A. This section explains, in general, what is and is not included in a contract line item and defines where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 – PRODUCTS (Not Used)

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item (CLIN) 00010

1. This item consists of installing approximately 1,000 linear feet of new telecommunication lines within the existing buried conduit between the visitor center and the headquarters area including new wires, new panels on both ends, connections to existing systems, and troubleshooting to ensure proper operation. This project also includes removal and proper disposal of all existing telecommunications wires and approximately 500 linear feet of conduit currently laying on the ground uphill of the concrete pedestrian trail.

2.

This is the start of the file's text. The full file is on GovTribe.