This document provides an implementation plan for a seawall long-term maintenance program at Midway Atoll National Wildlife Refuge. The plan details environmental protection measures to be implemented during seven phases: design, construction material acquisition, shipping, staging, pre-construction, construction, and post-construction. Specific measures include minimizing the project footprint, conducting all work from land, sourcing clean armor rocks, implementing invasive species inspections and protocols for shipping and materials, establishing stockpile locations, conducting biological surveys and coral relocation pre-construction, appointing biological monitors during construction, using silt curtains and spill prevention plans, restricting work windows, and conducting post-construction monitoring. The plan aims to mitigate project impacts and involves coordination between the Fish and Wildlife Service, Federal Aviation Administration, Army Corps of Engineers, National Oceanic and Atmospheric Administration, and Environmental Protection Agency as the seawall repairs are implemented over a ten-year period from 2016-2026.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX B
IMPLEMENTATION PLAN
Seawall Long-Term Maintenance Program
Henderson Field Airport
Midway Atoll National Wildlife Refuge/
Battle of Midway National Memorial
DECEMBER 2018
US FISH AND WILDLIFE SERVICE
Midway Island National Wildlife Refuge
AND
FEDERAL AVIATION ADMINISTRATION
Western-Pacific Region
CONTENTS
Introduction
Designed Environmental Measures Construction Material and Invasive Species
Shipping and Invasive Species
Staging
Pre-Construction Construction Post-Construction http://www.google.com/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=VFd8iBZt_dLCYM&tbnid=G0cHZrliTwPrQM:&ved=0CAUQjRw&url=http://www.skullsunlimited.com/index_skulls_policies.php&ei=--RuUbvGE4P_igK0yoGYCQ&bvm=bv.45368065,d.cGE&psig=AFQjCNG0_zyXDDCilYDT5Kr9_nMUE7DtmA&ust=1366308470958329 https://upload.wikimedia.org/wikipedia/commons/d/de/US-FederalAviationAdmin-Seal.svg
IMPLEMENTATION PLAN DECEMBER 2018
SEAWALL LONG-TERM MAINTENANCE PROJECT APPENDIX B
Appendix B - Page | 1
INTRODUCTION
This plan specifies measures the Service will implement to mitigate impacts from maintenance and repair of the failing seawall at Mid-way Atoll National Wildlife Refuge (NWR). Multiple federal agen-cies and departments have regulatory jurisdiction over the seawall repairs. This plan provides a single, unified list of all environmental protection measures recommended, required, and approved by all agencies with jurisdiction, as identified in the following table.
AGENCY/DEPARTMENT JURISDICTION
FWS, MIDWAY ATOLL NWR Lead NEPA agency
FAA, WESTERN PACIFIC RE-
GION
Co-Lead NEPA agency
USACE, HONOLULU DISTRICT,
REGULATORY OFFICE
Rivers and Harbors Act, Section 10
Clean Water Act (CWA), Section
PAPAHĀNAUMOKUĀKEA MA-
RINE NATIONAL MONUMENT
(PMNM)
Monument Regulations (50 CFR Part
404.11)
FWS, PIFWO
AQUATIC ECOSYSTEM CONSER-
VATION
Fish and Wildlife Coordination Act
FWS, PIFWO
ENDANGERED SPECIES PRO-
GRAM
Endangered Species Act, Section 7
NOAA, PIRO, PROTECTED RE-
SOURCES DIVISION
Endangered Species Act, Section 7, Marine Mammal Protection Act
NOAA, PIRO, HABITAT CON-
SERVATION DIVISION
Magnuson‐Stevens Fishery Conser-vation and Management Act, Essen-tial Fish Habitat (EFH)
EPA, REGION IX Clean Water Act, Section 401
SOURCES OF ENVIRONMENTAL MEASURES
The measures listed in this plan have been developed based on the analysis in the EA and on consultations with the jurisdictional agen-cies. Many of the measures are based environmental review and per-mitting for repairs the Service completed in 2014 (FWS and FAA
2013). The 2014 armor rock revetment was typical of the types of repairs that the Service would continue as part of its seawall repair and maintenance program. Measures identified during this process and 2016 - 2018 consultations have been incorporated as fully as possible, but additional measures may need to be added as consul-tations progress.
All project staff should be familiar with the protocols and Best man-agement practices (BMPs) summarized in this Implementation Plan.
Project staff should be notified as additional measures are identified or recommended through consultation.
MEASURES ORGANIZED BY IMPLEMENTATION STEPS
Environmental protection measures have been organized into the seven overall implementation steps identified during the EA prepa-ration for the seawall maintenance program:
1. Design
2. Construction Material Acquisition
3. Shipping
4. Staging
5. Pre-Construction
6. Construction
7. Post-Construction
This plan lists (in table format) the specific environmental measures to be implemented during each step. The Service will use these ta-bles as a checklist for each repair action conducted over the 10-year planning period, as established in the USACE permit.
Appendix B - Page | 2
The tables organize “Measures” for each stage of the project. Each
Measure is identified with an “ID” for future reference. The
“source” field refers to the originating document for each measure by abbreviated form. They are as follows:
ABBREVI-
ATED REF-
ERENCE
SOURCE
FWCA
Final FWCA 2(b) Report for the Henderson Airfield Breach
Repair, Midway Atoll NWR. September 27, 2013
ESA 2013
Letter of Concurrence from NOAA PIRO dated September
25, 2013 in response to Request for Consultation dated Au-gust 19, 2013.
HAWAII
SHPO
Response dated December 11, 2015 to FWS Section 106 re-quest for consultation dated October 29, 2015.
CATEX
May 13, 2014 extension of USACE Permit File Number
POH-2013-00173. Originally authorized October 11, 2013.
PMNM
BMP
PNMN Standard BMPs as referenced at http://www.papaha-naumokuakea.gov/permit/bestmanagement.html
PMNM
Memo-to-File dated August 22, 2016 permitting Henderson
Field Runway Safety Area Seawall Repairs [2016-2020] pursuant to the Co-Trustee PMNM Permit.
2016 EA
Environmental Assessment to which this Implementation
Plan is an Appendix. Includes suggested measures identified during project NEPA review.
ESA 2018
Letter of Concurrence from NOAA PIRO dated January 12, 2018 in response to Request for Consultation dated May 17, 2017.
Explanation of table headers:
• Measure: Mitigation measure or BMP
• ID: Identifier for ease of reference
• Source: Source document or regulatory agency recommending measure.
• Description: Description of mitigation measure
• Responsible Agency/Person: Actor responsible to ensure meas-ure is carried out
• Required Action: Description of mitigation measure
PLANNING PROCESS
The Service will conduct repairs as sections of the seawall fails over the ten-year planning period (2016-2026). Because specific loca-tions and extent of repairs needed along the approximately 1-mile long seawall are unknown, the Service established an implementa-tion process that begins when a new failed section of seawall is dis-covered. This process includes four main phases:
1. Assess the situation, where the Service will determine the extent of needed repairs and whether any “significant new circum-stance or information” requires additional environmental re-view, revised permits, or environmental measures.
2. Design, where the Service will determine appropriate designs for repair and notify jurisdictional agencies.
3. Implement, where the Service will fund and issue contracts for construction. This phase contains the construction steps and as-sociated environmental measures contained in this plan.
4. Learn/Improve where the Service will identify any “lesson learned” and revise this Implementation Plan, as needed.
The chart on the following page illustrates the seawall repair imple-mentation process and indicates the steps that include the environ-mental measures identified in this plan. As shown on the chart, the
Service will document each of the four main phases in a NEPA ad-ministrative record it will maintain for its actions related to the sea-wall maintenance and repairs.
http://www.papahanaumokuakea.gov/permit/bestmanagement.html http://www.papahanaumokuakea.gov/permit/bestmanagement.html
Appendix B - Page | 3
Appendix B - Page | 4
DESIGNED ENVIRONMENTAL MEASURES
Avoidance is the first and preferred step to mitigate environmental impacts (per Council of Environmental Quality (CEQ) regulations, 40 CFR 1508.20).
For the seawall maintenance program, the Service will avoid im-pacts on the marine environment by minimizing the project footprint and by conducting all work from land, rather than from barges and vessels. Table 1 provides the specific environmental measures that will be included in each repair design.
Land-based construction during 2014 repair
TABLE 1. ENVIRONMENTAL MEASURES FOR ENGINEERING DESIGN
MEASURE ID SOURCE DESCRIPTION
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
MINIMIZE
FOOTPRINT
D-1
CatEx
2013, FWCA
Minimize project footprint and in-water work to protect the marine environment.
Design team Conducted as part of design
MINIMIZE
DISTURB-
ANCE
D-2
CatEx
Construction will be conducted entirely from land-based equipment to minimize disturbance of the marine environment. A barge will not be present at the project site in order to avoid further disturbance to ma-rine species.
D-3
Pile installation was eliminated from the design in order to avoid noise impacts to wildlife, including fish, marine mammals, sea turtles and birds
Appendix B - Page | 5
CONSTRUCTION MATERIAL AND INVASIVE SPECIES
Due to the critical need to prevent the introduction of invasive spe-cies, rock used to repair the seawall needs to be clean. The Service will specify the requirements listed in Table 2 as part of contracts issued for all seawall repairs.
Protocols prevent reintroduction of invasive species such as Verbesina encelioides, or golden crownbeard
TABLE 2. ENVIRONMENTAL MEASURES FOR CONSTRUCTION MATERIALS
MEASURE ID SOURCE DESCRIPTION
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
REPORTING M-1
CatEx
2013, ESA
Contractor1 shall provide the Refuge with information of types and quantities of materials being imported and location of obtaining these materials to Service staff prior to departure from Honolulu.
Contractor
Notify refuge
SOURCING M-2
Contractor will source armor rocks directly from a quarry that is free from insects and seeds. If this is not possible, the contractor will pres-sure wash armor rocks on a concrete surface prior to loading them onto the barges.
STORAGE M-3
Contractor will limit the amount of time that rocks are stored before being shipped. Contractor will ensure that materials, rocks, aggregate, etc. are packed and stored on clean concrete/asphalt.
STEAM
CLEANING
M-4
Before leaving Honolulu, Contractor will steam clean or pressure wash all machinery, equipment, shipping containers, vessel decks and holds, and all water-resistant construction materials to ensure the re-moval of all dirt, insects, and seeds.
1 Refers to entire construction team, including contractor and any subcontractors
Appendix B - Page | 6
SHIPPING AND INVASIVE SPECIES
Shipping issues relate primarily to invasive species, which is a major concern at Midway Atoll and throughout the larger Pa-pahānaumokuākea Marine National Monument. The Management
Monument permit required for the seawall maintenance program in-cludes several requirements for ensuring ships do not transport in-vasive species into the monument.
Table 3 lists these measures as well as similar measures identified by the USACE of Engineers as part of its Nationwide Permit issued for the 2014 repair.
Rock used for repairs would be barged to the Refuge, likely from existing sources in Hawaii or Alaska.
TABLE 3. SHIPPING ENVIRONMENTAL MEASURES
MEASURE ID SOURCE DESCRIPTION
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
PREVENTION
SH-1
CatEx
2013, Contractor will develop and implement a program to insure that non-native species have been eradicated from imported materials prior to offloading at the refuge.
Contractor
SH-2
CatEx
2013, ESA
Contractor will develop and implement a construction-worker educa-tion program that informs workers of the damage that can be done by unwanted introductions of non-native species.
Contractor
SH-3
PMNM
BMP
Contractor will follow Marine Alien Species Inspection Standards for
Maritime Vessels (PMNM BMP #001) Contractor http://www.papahanaumokuakea.gov/permit/bmp/001_marinealien.pdf http://www.papahanaumokuakea.gov/permit/bmp/001_marinealien.pdf
Appendix B - Page | 7
TABLE 3. SHIPPING ENVIRONMENTAL MEASURES
MEASURE ID SOURCE DESCRIPTION
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
ADVANCE
NOTICE
SH-4
CatEx
2013, PMNM
The Service’s Honolulu POC must be notified two days prior to de-parture of shipments from Honolulu.
All personnel must be identified and information provided to PMNM permit coordinators prior to each entry into the Monument. PMNM
Compliance Information Sheet
Contractor and
Refuge Manager
Document notifica-tion for administra-tive record
SCHEDUL-
ING
SH-5
PMNM
Up to two deployments [up to 20 days each] per year may be made to deliver specialized heavy equipment and gear to support the project, and to resupply the project and Refuge within dates approved by the
Refuge Manager for each project year.
Contractor and
Refuge Manager
RODENT
CONTROL
SH-6
CatEx
2013, PMNM
2016, ESA
Shipping containers must have a rat station inside with a baited sticky trap. Cargo inside containers shall be fumigated with a bug bomb.
Vessels must be inspected for rats and have a “rat-free certification.”
The contractor must install rat guards on vessel and barge lines at Mid-way Island to prevent rodents from reaching land.
Contractor
Document De-Rat
Certification for ad-ministrative record
SH-7
Refuge personnel will place rodent bait stations and traps containing rodenticide on the boat and barge decks, around the dock, and in areas where shipping containers are stored on the island.
Refuge Manager
INSPECTION
SH-8
FWCA
2013, Ca-tEx 2013, and
PMNM
2016, ESA
The Service’s Honolulu POC must be notified two days prior to de-parture of shipments from Honolulu in order to complete an inspection of all cargo, equipment, construction materials, and vessels for satis-faction of conditions, including absence of invasive species. Any ves-sel found to have a fouled hull will be required to have the entire hull cleared and re-inspected.
Contractor and
Service’s Hono-lulu POC
Document results of hull inspections to administrative rec-ord
SH-9
Additional inspection, except for hull invasive species, shall be con-ducted upon arrival at the Refuge. In the event of a failure to pass in-spection, the vessel shall not be allowed to leave for or unload cargo at the Refuge. Specimen of non-native species that are found by these inspections would be collected and destroyed. Containers that are too heavily infested to permit complete cleaning would be returned unde-livered.
http://www.papahanaumokuakea.gov/permit/pdf/comp_check_08.doc http://www.papahanaumokuakea.gov/permit/pdf/comp_check_08.doc
Appendix B - Page | 8
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
ANIMAL
AVOIDANCE
SH-
NMFS
Viewing
Guide-lines
Remain at least 100 yards from humpback whales, and at least 50 yards from other marine mammals (dolphins, other whale species, and
Hawaiian monk seals).
Contractor
SH-
Marine mammals and sea turtles should not be encircled or trapped between boats or shore.
If approached by a marine mammal or turtle while on a boat, put the engine in neutral and allow the animal to pass. Boat movement should be from the rear of the animal.
VESSEL OP-
ERATIONS
SH-
PMNM
2016, ESA
Vessels will be anchored on sandy substrate only, and all anchors must be lowered into place
Contractor
Gray water may only be discharged outside of all Special Preservation
Areas and the Midway Atoll Special Management Area.
Biodegradable solid waste associated with galley operations may only be discharged 3 nautical miles (if ground to 1 inch in diameter) or 12 nautical miles (if unground) outside of all Special Preservation Areas and the Midway Atoll Special Management Area.
VESSEL
TRACKING
SH-
PMNM
2016, Ca-tEx 2013
Vessels must have a Vessel Management System (VMS) device as they travel though the Monument. This system will be verified by
NOAA Office of Law Enforcement (OLE)
Contractor
Document VMS
Verification by
NOAA OLE
ARRIVAL
16 PMNM
2016, Ca-tEx 2013
All personnel will receive PMNM Pre-Access Briefings, and the Mid-way Atoll NWR and Battle of Midway National Memorial Briefings before commencing work on the project
Refuge Manager
Document PMNM
Pre-Access Brief-ings
Upon arrival to the Sand Island, shipping contractor shall submit doc-umentation to the Service to support that all shipping environmental measures requirements have been met.
Appendix B - Page | 9
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
BALLAST
WATER
SH-
PMNM
2016, ESA
Barges may utilize ballast water within the Midway Harbor, and dis-charge this water in the same location, in order to manipulate the trim and stability of the barge to execute offloading and loading of cargo, equipment, and supplies. The activity must be approved by the
PMNM hull inspector.
Ballast water will not be discharged within any Special Preservation
Areas or the Midway Atoll Special Management Area.
Contractor
RETURN
SHIPMENT
SH-
PMNM
Each deployment above may include returning household trash, recy-cling materials, collected marine debris, hazmat waste, and other in-dustrial waste to Honolulu, Hawaii or other designated areas within the United States.
Appendix B - Page | 10
STAGING
Construction materials may require storage on Sand Island for sev-eral weeks or even months prior to construction, depending on con-struction windows established to protect birds and on the logistics of getting materials and crews to the island. If barged early, the rock and other construction materials would be loaded onto trucks and driven to a temporary stockpile area void of any environmental con-cerns, as confirmed and approved by Refuge staff.
TABLE 5. STAGING ENVIRONMENTAL MEASURES
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
WORK WIN-
DOW
SP-1
FWCA
2013, PMNM
2016, ESA
Transport of construction materials across the island and project con-struction shall avoid the Hawaiian seabird nesting season, with the peak at approximately mid- November to mid-December.
STOCKPIL-
SP-2
CatEx
2013, ESA
Stockpiling of materials will occur only in the authorized stockpile lo-cation on existing paved surfaces. Transportation of materials to and from stockpiles will occur on existing travels roads and runway access routes.
SP-3
NMFS
ESA
Construction-related materials should be placed or stored in ways to avoid or minimize disturbance to marine resources.
ANIMAL
AVOIDANCE
SP-4
CatEx
2013, ESA
Prior to construction or material stockpiling, any sensitive areas near sites would be clearly marked to contain disturbance areas to the min-imum amount needed to work safely.
Refuge Manager
SP-5
FWCA
2013, ESA
If there are protected species in the area prior to performing any com-ponent of the permitted activity, that activity should not commence until the animal(s) voluntarily departs the area. If the protected species enters the area when that activity is already underway, that activity should cease until the animal voluntarily departs the area
Construction
Monitor
SP-6
ESA
Contractors and project participants will not approach or feed Laysan ducks
Appendix B - Page | 11
Proposed staging area and haul route
Appendix B - Page | 12
PRE-CONSTRUCTION
Several measures will be taken prior to construction to identify and protect sensitive biological resources, including biological surveys, coral translocation, and environmental training for construction crews.
Coral translocation efforts prior to 2014 repairs
TABLE 5. PRE-CONSTRUCTION ENVIRONMENTAL MEASURES
MEASURE ID SOURCE DESCRIPTION
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
LOGISTICS
PRE-
PMNM
Personnel approved by the Refuge Manager may access the Refuge via Service-chartered aircraft and complete the project directly on the refuge between August 1 and October 30.
CREW
TRAINING
PRE-
ESA
2013, ESA
All personnel will receive PMNM Pre-Access Briefings, and the Mid-way Atoll NWR and Battle of Midway National Memorial Briefings before commencing work on the project.
Refuge Manager
Conduct and docu-ment PMNM Pre-
Access Briefings
PRE-
PMNM
BMP,
ESA
All project staff should be familiar with Precautions for Minimizing
Human Impacts on Endangered Land Birds (PMNM BMP #012) or receive sufficient briefing to comply with its requirements, which gen-erally consist of housekeeping BMPs that prevent bird mortality.
Refuge Manager
PRE-
PMNM
BMP,
ESA
All project staff should be familiar with Human Hazards to Seabirds in Papahānaumokuākea Marine National Monument (PMNM BMP
#003) or receive sufficient briefing to comply with its requirements.
Refuge Manager http://www.papahanaumokuakea.gov/permit/bmp/012_minimize_landbirds.pdf http://www.papahanaumokuakea.gov/permit/bmp/012_minimize_landbirds.pdf http://www.papahanaumokuakea.gov/permit/bmp/003_humanhazardsseabirds.pdf http://www.papahanaumokuakea.gov/permit/bmp/003_humanhazardsseabirds.pdf http://www.papahanaumokuakea.gov/permit/bmp/003_humanhazardsseabirds.pdf
Appendix B - Page | 13
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
PRE-
PMNM
2016, ESA
All project staff will be informed of the potential presence of protected species and be given species information by the biological monitor.
Refuge Manager
PRE-CON-
STRUCTION
SURVEYS
PRE-
NMFS
ESA
Prior to specific repairs, surveys would be performed of all areas con-tained within the proposed project area for the presence/absence of corals, seals, turtles and marine mammals, as well as habitat suitability for these species (for potential relocation). Survey results would be considered valid for three years.
Refuge Manager Document in ad-ministrative record
2016 EA
Prior to construction or material stockpiling, any sensitive areas near sites would be clearly marked to contain disturbance areas to the min-imum amount needed to work safely.
2016 EA,
ESA
The site would be assessed to ensure that no new conditions have arisen and all appropriate pre-work mitigation measures have been im-plemented
CORAL RE-
LOCATION
PRE-
NMFS
ESA
Relocate, prior to the start of construction, the coral and macroinver-tebrates present within the project area that would be damaged by con-struction (both in the direct fill footprint and adjacent to this, if appro-priate) to an area that would not be disturbed (i.e., not alongside unre-paired sections of the seawall or other areas likely to be disturbed at some point in the future).
Refuge Manager
PRE-
PMNM
BMP
Coral team will follow General Storage and Transport Protocols for
Collected Samples (PMNM BMP #006) Refuge Manager
PRE-
PMNM
BMP
Coral team will follow Disease and Introduced Species Prevention
Protocol for Permitted Activities in the Marine Environment Pa-pahānaumokuākea Marine National Monument (PMNM BMP #011) for specific protocols for the proper management of coral sampling equipment, coral samples, and dive equipment.
Refuge Manager http://www.papahanaumokuakea.gov/permit/bmp/006_transport.pdf http://www.papahanaumokuakea.gov/permit/bmp/006_transport.pdf http://www.papahanaumokuakea.gov/permit/bmp/011_diseaseprevention.pdf http://www.papahanaumokuakea.gov/permit/bmp/011_diseaseprevention.pdf
Appendix B - Page | 14
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
INVASIVE
SPECIES
PRE-
CatEx
2013, ESA
All personnel entering the Refuge must comply with the general rules for alien species control to minimize the risk of alien species introduc-tions to the Refuge. All personnel shall ensure that boots, clothing and personal effects are free of dirt, seeds, and insects.
Refuge Manager
PRE-
PMNM
BMP,
ESA
All project staff will be familiar with the requirements of Special Con-ditions & Rules For Moving Between Islands & Atolls And Packing
For Field Camps (PMNM BMP #007) prior to entering the Monu-ment.
Refuge Manager
PRE-
PMNM
BMP
Contractor will follow Disease and Introduced Species Prevention
Protocol for Permitted Activities in the Marine Environment PMNM Contractor
SPILL PRE-
VENTION,
CONTROL
AND COUN-
TERMEAS-
URES
PRE-
FWCA
2013, ESA
A plan to control the accidental spills of petroleum products at the con-struction site shall be developed. Absorbent pads and containment booms will be stored on-site to facilitate the cleanup of petroleum spills.
Refuge Manager
Prepare hazardous materials/contin-gency plan
NMFS
ESA
All construction-related materials and equipment to be placed in the water should be cleaned of pollutants prior to use. When in service, if pollutants are found to be leaking from any equipment, that piece of equipment should be removed from service until the cause of the leak has been fixed.
Contractor
HAZARDOUS
MATERIALS
PRE-
2016 EA,
ESA
A plan to respond to previously unknown hazardous materials discov-ered during construction shall be developed. The plan shall include specific chain of communication and steps to contain and/or remove and dispose of hazardous materials.
Refuge Manager
Prepare hazardous materials/contin-gency plan
2016 EA,
ESA
Construction crews shall include members trained/experience in haz-ardous waste identification to monitor all disturbed areas for the po-tential of contaminated soils or other hazardous materials. Monitors shall immediately notify Refuge staff of any suspected hazardous ma-terials, who shall then implement hazardous material plan.
Contractor http://www.papahanaumokuakea.gov/permit/bmp/007_movingpacking.pdf http://www.papahanaumokuakea.gov/permit/bmp/007_movingpacking.pdf http://www.papahanaumokuakea.gov/permit/bmp/007_movingpacking.pdf
Appendix B - Page | 15
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
PRE-
2016 EA,
ESA
Coordinate with U.S. Navy explosives experts to determine appropri-ate steps needed to avoid unintended disturbance of unexploded ordi-nance (UXO’s).
Appendix B - Page | 16
CONSTRUCTION
The majority of environmental measures would take place during each specific construction effort. Construction environmental measures would be directed by Refuge staff or their designated rep-resentatives.
TABLE 6. CONSTRUCTION ENVIRONMENTAL MEASURES
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
CLOSED AR-
EAS
C-1
ESA
2013, ESA
The southern and western beaches on Sand Island as well as the beaches on Spit and Eastern Island will be closed to all contractor personnel. Closed beaches will be avoided at all times.
Contractor
SUPERVI-
SION AND
CREW
TRAINING
C-2
EA 2016,
ESA
Prior to and during work, designated personnel (biological monitor) will monitor the site during project activities to ensure that mitigation measures are followed and to observe for the presence of protected species.
Contractor and
Refuge Manager
Document in moni-toring report
Appendix B - Page | 17
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
C-3
PMNM
BMP,
ESA
Contractor and staff will comply with the following BMPs:
• Nonnative Species Inspection Requirements at Midway Atoll
(PMNM BMP #015).
• Human Hazards to Seabirds Briefing (PMNM BMP #003)
• Boat Operations and Diving Activities (PMNM BMP #004)
• Marine Wildlife Viewing Guidelines (PMNM BMP #010)
• Disease and Introduced Species Prevention Protocol for Permit-ted Activities in the Marine Environment (PMNM BMP #011)
• Precautions for Minimizing Human Impacts on Endangered
Land Birds (PMNM BMP #012)
Refuge staff.
CULTURAL
DISCOVER-
IES
C-4
Hawaii
State His-toric
Preserva-tion Divi-sion
In the event that historic resources – including human skeletal re-mains, cultural layers, cultural deposits, features, and artifacts – are identified during construction activities, all work should cease in the immediate vicinity of the find, the find should be protected from ad-ditional disturbance, and the Service Regional Archaeologist shall be notified immediately.
DEBRIS DIS-
POSAL
C-5
CatEx
2013, FWCA
2013, ESA
All manmade construction debris or debris removed from the seawall will be collected and not allowed to enter waters of the U.S. All de-bris removed from the seawall construction site will be disposed of at an approved upland site. Any project-related debris trash, or equip-ment will be removed from the beach or dune if not actively being used.
ENTRAP-
MENT PRE-
VENTION
C-6
FWCA
2013, ESA
Armor rocks and fill materials shall be placed in a manner that will not pose an entrapment hazard to fish and wildlife.
C-7
2013, ESA
At the end of each day of work at the seawall repair site, the biologi-cal monitor will inspect the area to determine if it may pose a hazard for seals or turtles to be trapped and the monitor will direct project staff to alter armor rocks to ensure no entrapment can occur.
http://www.papahanaumokuakea.gov/permit/bmp/015_midwayinspection.pdf http://www.papahanaumokuakea.gov/permit/bmp/015_midwayinspection.pdf http://www.papahanaumokuakea.gov/permit/bmp/003_humanhazardsseabirds.pdf http://www.papahanaumokuakea.gov/permit/bmp/004_boatoperations.pdf http://www.papahanaumokuakea.gov/permit/bmp/010_marinewildlifeviewing.pdf http://www.papahanaumokuakea.gov/permit/bmp/011_diseaseprevention.pdf http://www.papahanaumokuakea.gov/permit/bmp/011_diseaseprevention.pdf http://www.papahanaumokuakea.gov/permit/bmp/012_minimize_landbirds.pdf http://www.papahanaumokuakea.gov/permit/bmp/012_minimize_landbirds.pdf
Appendix B - Page | 18
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
C-8 CatEx
As the silt containment boom (curtain) is deployed, and prior to clos-ing it off, protocol will be followed to prevent entrapment of signifi-cant animal species within the boom.
Contractor and
INSPECTION C-9
CatEx
2013, ESA
All equipment shall be checked daily for leaks and any necessary re-pairs made prior to commencement of work.
Contractor
LIGHTING
C-10
CatEx
2013, ESA
Artificial nighttime lighting will not be employed in order to avoid disorientating seabirds.
Contractor
C-11
PMNM
BMP,
ESA
Contractor will comply with: Minimizing the Impact of Artificial
Light on Sea Turtles (PMNM BMP #009). To avoid project impacts to sea turtles from lighting, no construction activities will occur at night.
Contractor and
SHUTDOWNS C-12
2013, FWCA
A biological monitor will be on-site during all work activities and will conduct pre-work surveys to determine the presence of species of concern in the seawall repair area. Work will not commence until the monitor confirms to the construction foreman that all sensitive species have left the area of their own accord. The biological monitor will have the authority and responsibility to shut down disturbance-causing construction activities if a protected species is present within
150 feet of the seawall repair area.
Contractor and http://www.papahanaumokuakea.gov/permit/bmp/009_reducelight_turtles.pdf http://www.papahanaumokuakea.gov/permit/bmp/009_reducelight_turtles.pdf
Appendix B - Page | 19
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
SILT CON-
TAINMENT
C-13
CatEx
2013, FWCA
2013, ESA
A silt curtain will be deployed prior to placing fill in the water and during removal of sheet pile to contain turbidity and siltation. The
Service will consult with the design-engineering consultant to de-termine the correct silt curtain for the project location and needs.
The silt curtain would be installed during periods of low wave ac-tion using a Refuge boat located at Sand Island. The silt curtain would be removed during severe weather events to reduce the risk of damage. Refer to measure C-8 and C-27 for additional measures regarding silt curtain management.
Contractor and
SPILL PRE-
VENTION,
CONTROL
AND COUN-
TERMEAS-
URES PLAN
C-26
FWCA
2013, CatEx
2013, ESA
Fueling of construction related equipment shall occur away from the seawall construction site at a designated location with the ability to handle and accidental spill on Sand Island.
Contractor and
C-27
FWCA
2013, ESA
All construction-related materials and equipment (e.g., silt curtains, dredges, barges, pilings, cranes, etc.) to be placed in the water shall be cleaned of pollutants prior to use.
Contractor and
C-28
CatEx
2013, ESA
Contractor will follow protocol in the existing Spill Prevention, Con-trol and Countermeasures Plan for FWS, prepared in 2004 and last updated in 2009 (GeoEngineers, Inc).
Contractor and
C-29
NMFS
ESA
If debris or spill material accidentally enters the waterway, immedi-ate actions would be taken to remove the material and proper entities notified.
STOCKPIL-
C-30
CatEx
No construction material will be stockpiled in the marine environ-ment.
Contractor and
Appendix B - Page | 20
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
WORK WIN-
DOW
C-31
CatEx
2013, ESA
Construction will only occur during agency allowed work windows relative to protected species.
Contractor and
C-32
PMNM
Permit
2016, ESA
Contractors and subcontractors will be approved by the Refuge Man-ager to access and complete the project directly on the refuge be-tween August 1 and October 30.
Contractor and
Appendix B - Page | 21
POST-CONSTRUCTION
Post-construction follow-up is an important element of the overall environmental measures strategy for the seawall maintenance pro-gram, which includes post-construction reviews to support learning and continual improvement. Through this work, the Service will gain valuable lessons learned and be able to implement changes as needed to ensure that environmental measures goals are met.
A coral transplanted as part of the 2014 seawall repair is numbered as part of ongoing post-construction monitoring
TABLE 7. POST-CONSTRUCTION ENVIRONMENTAL MEASURES
MEASURE ID SOURCE DESCRIPTION
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
CORAL RE-
LOCATION
POC-
EFH
Post-construction, provide information on the species, size and the to-tal amount of any corals impacted from the salvage operations. Offset this resource loss, including the loss of EFH bottom habitat. If the overall unavoidable loss is minimal, NMFS would support environ-mental measures offset involving removal of long-standing uncolo-nized debris in areas adjacent to the project fill footprint to future dam-age to the corals and marine resources in the area. Other compensatory environmental measures alternatives may also be appropriate.
Refuge Manager and Post-con-struction team toring report, Appendix B - Page | 22
TABLE 7. POST-CONSTRUCTION ENVIRONMENTAL MEASURES
RESPONSIBLE
AGENCY/ROLE
REQUIRED AC-
TION
DATE COM-
PLETED AND
INITIAL
POST-CON-
STRUCTION
SURVEY
POC-
EA 2016
Conduct a post-construction marine biological survey to determine the actual project-related impact and the need for compensatory environ-mental measures. Lost ecological function associated with any project impact must be mitigated through compensatory environmental measures.
POC-
EA 2016
A post-construction environmental compliance inspection will be completed that identifies any environmental concerns or lessons learned that can be applied to subsequent repairs.
POC-
NFMS
ESA
Information on the species, size and the total amount of any corals im-pacted from the repairs would be provided to NMFS within 30 days of the completion of repairs. Post-construction marine biological sur-veys would be conducted to determine the actual project-related im-pact and the need for compensatory Environmental Measures. Lost ecological function associated with any project impact must be miti-gated through mutually agreed conditions.
| Contents |
| Introduction |
| Sources of Environmental Measures |
| Measures Organized by Implementation Steps |
| Planning Process |
| Designed Environmental Measures |
| Construction Material and Invasive Species |
| Shipping and Invasive Species |
| Staging |
| Pre-Construction |
| Construction |
| Post-Construction |