B08_Att_3_Kirby_Cove_Vault_Toilet_Contract_Price_Schedule.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
RENEWAL OF KIRBY COVE VAULT TOILETS
Solicitation number
140P8624Q0056
Issued by

About this file

This document is a Contract Price Schedule for the Renovation of Kirby Cove Vault Toilets project at Golden Gate National Recreation Area. The solicitation number is PARK - PMIS: GOGA 310443.

The price schedule includes a single base line item for the Kirby Cove Campground Vault Toilet renovation with a lump sum price of $21,703. No option line items are included. The document specifies that all measurement and quantity information is contained in Division 01 Specifications Section 01 11 00 Summary of Work. The document also includes sample price schedules for Design-Bid-Build and Design-Build contract types, but these are for illustrative purposes and do not contain any details specific to the Kirby Cove project.

View the file

Other files

File Type Posted
B08_Att_5_140P8624Q0056_GenRefs.docx DOCX document
B08_Att_2_IMG_0805.jpg JPG image
B08_Att_2_Map_of_Location.JPG JPG image
Sol_140P8624Q0056.pdf PDF
B08_Att_6_DI_137_Release_of_Claims_.pdf PDF
B08_Att_2_IMG_0804.jpg JPG image
B08_Att_1_Construction_Specifications_-_Kirby_Cove_Vaults_8_12_24.docx DOCX document
B03_Att_4_WD_CA20240018_7_4_24.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule Template

Contract Price Schedule
National Park Service
Solicitation Number:
PARK - PMIS:GOGA 310443
Developed Area:Golden Gate National Recreation Area
Project Title:Rennovation of Kirby Cove Vault Toilets
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleUnit of MeasureUnit PriceTotal Price
1Kirby Cove Campground Vault Toiletslump sumN/A
TOTAL BASE PRICE (Contract Line Item Number 1) ------------------------------------------------------------------------
All measurement and quantity information is included in Division 01 Specifications Section 01 11 00 Summary of Work.

Filled In

Contract Price Schedule
National Park Service
Solicitation Number:
PARK - PMIS:GOGA 310443
Developed Area:Golden Gate National Recreation Area
Project Title:Rennovation of Kirby Cove Vault Toilets
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleUnit of MeasureUnit PriceTotal Price
1Kirby Cove Campground Vault Toiletlump sum$21,703$21,703
TOTAL BASE PRICE (Contract Line Item Number 1) ------------------------------------------------------------------------$21,703
All measurement and quantity information is included in Division 01 Specifications Section 01 11 00 Summary of Work.

Design-Bid-Build (DBB) Sample

Contract Price Schedule - Design-Bid-Build (DBB) SAMPLE
National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18
Solicitation Number:N2011080811
PARK - PMIS:YELL 012345
(Project Management Information System)
Developed Area:Old Faithful
Project Title:Johnstonian Visitors Center
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQuantityUnit of MeasureUnit PriceTotal Price
1Visitors Center1Lump Sum$0.00
2Water Line400Lineal Feet- 0
3Sanitary Sewer Line200Lineal Feet- 0
4Rock Excavation150Cubic Yards- 0
TOTAL BASE PRICE (Contract Line Item Number 1 through 4) ---------------------------------------------------------------------------------$0.00
5OPTION A, Geothermal Wells1Lump Sum- 0
6OPTION B, Photovoltaic System1Lump Sum- 0
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 5 and 6) -------------------------------------------------------------------$0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) ----------------------------$0.00
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.

Design-Build (DB) Sample

Contract Price Schedule - Design-Build (DB) SAMPLE
National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18
Solicitation Number:N2011080811
PARK - PMIS:YELL 012345
(Project Management Information System)
Developed Area:Yosemite Valley
Project Title:Design and Build a New Structure
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQuantityUnit of MeasureUnit PriceTotal Price
1Design1Lump Sum$0.00
2Construction1Lump Sum- 0
TOTAL BASE PRICE (Contract Line Item Number 1 and 2) ---------------------------------------------------------------------------------------$0.00
3OPTION A, Photovoltaic System1Lump Sum- 0
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3) ----------------------------------------------------------------------------$0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) ----------------------------$0.00
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.

File details come from the government source that posted it. Updated .