About this file

This document is a Statement of Work (SOW) for an HVAC System Replacement project at the Santa Monica Mountains National Recreation Area (SAMO) in Ventura County, California.

The purpose of this SOW is to contract for the replacement of an underperforming HVAC unit at the Franklin Canyon site located at 4124 W. Potrero Rd., Newbury Park, CA 91320. The work includes removing the old air handler, evaporator, and heat pump unit, and installing a new Energy Star digital, programmable thermostat, single stage air handler, R410a evaporator, and 15 SEER variable speed heat pump unit. The period of performance is estimated to be from 7/8/2024 through 8/8/2024.

The related federal contract opportunity, Solicitation Number 140P8624Q0045, is for the HVAC Replacement project at the SAMO site. It is a firm-fixed price purchase order with an estimated value under $25,000. The full solicitation package is available on SAM.gov, and a site visit is scheduled for 6/24/2024. All work must be performed in accordance with the SOW and project specifications.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE HVAC, newest first.
File Type Posted
B08_Att_04_140P8624Q0045_Tech_Info_Form.docx DOCX document
Sol_140P8624Q0045.pdf PDF
B08_Att_01_Quote_Sheet.xlsx XLSX spreadsheet
B08_Att_03_DOL_WD_DBA_CA20240015_VENTURA_COUNTY_.pdf PDF
B08_Attachment_5_140P8624Q0045_GenRefs.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 10 00 - 1 General Requirements

SAMO

RSV QTRS. 101 HVAC

DIVISION 1 DOCUMENT

SECTION 01 10 00

GENERAL REQUIREMENTS

PART 1 - DESCRIPTION OF WORK

1.1 BACKGROUND:

The purpose of this SOW is to perform an HVAC System Replacement of our HVAC unit at our Franklin Canyon site located at 4124 W. Potrero Rd., Newbury Park, CA 91320 in Ventura County. Currently there is (1) underperforming HVAC Systems at this location. All work shall be scheduled for weekdays (Monday-Friday) between 8:00 a.m.

and 4:00 p.m.

The goal of this project is to contract for a HVAC replacement at location mentioned above, as this location was determined to have a severely underperforming HVAC unit.

The HVAC unit should be replaced utilizing existing opening only. At no time shall new cutting of holes take place on the structure nor the enlarging of existing holes.

The replacement of the HVAC system shall be placed in the footprint of the existing HVAC unit. The period of performance for this contract is estimated to be from 7/8/2024 through 8/8/2024.

1.2 The overall contractual purpose is to provide a new HVAC System Replacement:

New HVAC System Replacement Specs

• Remove the old air handler, evaporator, and heat pump unit and haul off site.

• Remove and haul away an existing exterior ductless split system.

• Install a new Energy Star digital, programmable thermostat.

• Install a new single stage Air Handler Series

• Install a new gas shut off and connector.

• Recover and reclaim the old Freon per EPA standards.

• Install a new R410a evaporator.

• Install a safety drain float kit at secondary drain outlet to help prevent potential water damage.

• Install a new 15 seer, Heat Pump unit. (Variable speed Heat Pump) or equal.

• The unit is to be properly quake strapped.

• Perform a high-pressure nitrogen leak test and purge on the refrigeration system.

• Install a new fused service disconnect at condenser unit location and fuse down to proper amp using HVAC fuses only.

• Encase exterior low-voltage control wire.

• (1) new additional return grill for more intake air

01 10 00 - 2

WORK REQUIREMENTS- The contractor shall immediately notify the Contracting Officer (CO) of any ambiguities, inconsistencies, and errors discovered in the specification or between contracting documents and existing conditions.

Contractor shall take every precaution to prevent damage to government and personal property.

All work shall be done in a timely safe, clean, and professional manner. The contractor will supply all labor, equipment, tools, and material necessary to complete the job.

PART 2 - EXISTING UTILITIES

2.1 There should be no need for any excavation during this project or utility location.

PART 3 - CONTRACTOR’S USE OF PREMISES

3.1 ON-SITE WORK HOURS: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

3.2 CONSTRUCTION CAMP: N/A

3.3 STORAGE – STAGING AREAS:

A. Staging area for this project work will occur within the resident’s driveway under carport.

3.4 PRESERVATION OF NATURAL FEATURES: No cutting new holes for ductwork. Contractor must use existing ducting openings. No openings shall be enlarged to accommodate new replacement ductwork. No ground disturbance shall occur. No tree limbs shall be cut or removed for equipment access or roof access without consultation with the park’s arborist (contact COR). The project should not result in any modifications to the historic building.

3.5 HAULING RESTRICTIONS: None – please be sure to haul away old unit and any construction debris.

3.6 HOUSEKEEPING:

A. Keep project neat, orderly, and in a safe condition always. Store and use equipment, tools, and materials in a manner that does not present a hazard. Do not allow rubbish to accumulate. Dispose of construction rubbish daily during progress of work.

B. Dispose of waste materials legally. It is the contractor’s responsibility and at their cost to dispose of such debris. Do not use park trash receptacles.

01 10 00 - 3

PART 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work within 10 calendar days after the date of receipt of the "Notice to Proceed."

PART 5 - EXAMINATION OF THE SITE

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids. All bidders will be held to have the same knowledge concerning the site and the on-ground conditions as if they had inspected the job site. A pre bid site visit can be scheduled. Currently the site is closed to the public NPS personnel can allow access.

PART 6 - ABBREVIATIONS

6.1 The following list of abbreviations, which may be used in the Construction

Specifications or Special Provisions, refer to the organizations and specifications of the organizations listed below:

AASHTO - American Association of State Highway and Transportation Officials ACI - American Concrete Institute AISC - American Institute of Steel Construction AI - Asphalt Institute ANSI - American National Standards Institute ASTM - American Society for Testing and Materials AWWA - American Water Works Association Caltrans- State of California Department of Transportation FHWA - Federal Highway Administration FS - Federal Specifications MSHA - Mine Safety and Health Administration MUTCD - Manual on Uniform Traffic Control Devices NEC - National Electric Code NEMA - National Electrical Manufacturers Association NFPA - National Fire Protection Association NIOSH - National Institute of Occupational Safety and Health NPS - National Park Service NSF - National Sanitation Foundation OSHA - Occupational Safety and Health Administration PCA _ Portland Cement Association UBC - Uniform Building Code UL - Underwriters Laboratories, Inc.

PART 7 - ACCIDENT PREVENTION

7.1 DESCRIPTION: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors. Accident prevention plan for this

01 10 00 - 4 small project can be safety and PPE, electrical shock, freon disposal and nearest hospital.

7.2 SUBMITTALS:

A. ACCIDENT PREVENTION PROGRAM: At the preconstruction conference submit for approval an accident prevention program. The program shall include:

1. Name of responsible supervisor to carry out the program.

2. First aid procedures.

3. Planning for possible emergency situations.

4. Contractor to identify nearest location of medical facility for emergencies.

5. Recognition that work will be performed in remote areas with limited communication or cell phone coverage.

B. MEETING AND INSPECTION REPORTS: N\A.

7.3 QUALIFICATIONS OF EMPLOYEES:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.

D. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

7.4 ACCIDENT REPORTING: The Contractor shall report all accidents to the

Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

7.5 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.

7.6 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

01 10 00 - 5

7.7 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.8 PROTECTIVE EQUIPMENT:

A. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

7.9 SAFETY MEETINGS: As a minimum, conduct 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.

The contractor shall comply with all OSHA federal regulations (29 CFR 1910) and California state regulations governing the safety of workers performing the type of work described in the contract.

7.10 HAZARDOUS MATERIAL ACTION: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

PART 8 - PRECONSTRUCTION CONFERENCE:

8.1 PRECONSTRUCTION CONFERENCE: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following:

Roles and Responsibilities Key Personnel National Park Service regulations Documents required under the contract Subcontractors Labor standards provisions Modifications Payments to Contractor Payroll reports

01 10 00 - 6

Technical Issues Correspondence procedures Acceptance/Rejection of Work Construction Meetings Submittal of shop drawings, project data, and samples Accident prevention program (including name of responsible supervisor) Accident reporting Safety program (compliance with the "Accident Prevention" clause of the General Provisions) Spill Response Plan Saturday, Sunday, holiday and night work Contract Time Tentative construction schedule Notice to Proceed

PART 9 - SUBMITTALS

9.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.

9.2 Any work done before approval shall be at Contractor's own risk.

9.3 APPROVED EQUALS: A request for approval constitutes a representation that Contractor:

A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

B. Will provide the same warranties for the proposed item as for the item specified.

C. Has determined that the proposed item is compatible with interfacing items.

D. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

E. Waives all claims for additional expenses that may be incurred as a result of the substitution.

9.4 PROGRESS SCHEDULES: As soon as possible after Notice of Award and before beginning any work, submit a Schedule showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted.

PART 10 - TEMPORARY SERVICES

01 10 00 - 7

10.1 DESCRIPTION: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.

10.2 FIRE PREVENTION AND PROTECTION:

A. Hazard Control: Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

PART 11 - PROJECT CLOSEOUT

11.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.

11.2 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.

11.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project is substantially complete, and a final inspection is requested.

Contracting Officer will make an inspection within 10 days of receipt of request.

A. When Contracting Officer determines that the work is substantially complete; he will prepare a list of deficiencies (“Punch List”) to be corrected before final acceptance and issue a Letter of

B. Substantial Completion.

C. If Contracting Officer determines that the work is not substantially complete;

he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection.

11.4 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a

Letter of Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

END OF SECTION