B08_Att_01_140PP027Q0018_Specs.pdf
PDF 4 MB Posted
- Attached to
- Rehab Kiosk Restrooms, NPS-ORCA
- Solicitation number
- 140PP027Q0018
- Issued by
- Not on record
About this file
This document is Construction Specifications for the rehabilitation of kiosk restrooms at Oregon Caves National Monument & Preserve (PMIS No. 215914), issued by the National Park Service Pacific West Region.
The project requires complete interior demolition and reconstruction of public restroom facilities to address deterioration, accessibility non-compliance, and rodent intrusion. Scope of work includes: removal of all interior finishes to structural framing; installation of new plumbing systems per IPC 2021 and electrical systems per NFPA 70 (NEC); installation of 884 SF of PVC sanitary wall and ceiling panels; implementation of ADA-compliant restroom layouts with one 60" x 60" wheelchair-accessible toilet compartment per restroom and additional 42" x 60" stalls; and rodent-proofing using 16-gauge stainless steel mesh and polyurethane sealants. Concrete floor repair encompasses 156 SF including crack repair, waterproofing membrane application, floor drain repairs, and installation of new 2"x2" slip-resistant porcelain tile with 4"x4" cove base. All work must comply with Secretary of the Interior's Standards for Rehabilitation to preserve the historic building exterior. Required products include sensor-operated ADA water closets (Zurn Elkay or approved equal), solid phenolic or stainless steel partitions, IK10 vandal-resistant LED lighting with occupancy sensors, and Trusscore PVC wall panels with antimicrobial sealant. The contractor must submit ADA partition shop drawings and product data for plumbing, lighting, PVC systems, rodent mesh, and concrete mix design using NPS Form CM-16. Performance period is 90 calendar days from Notice to Proceed, including 10 weather days. Payment will be made at CLIN lump sum price or per approved Schedule of Values milestones. Submittals must comply with OSHA 29 CFR 1926 Subpart T, EPA construction waste handling regulations, SMACNA IAQ Guidelines for dust containment, and ABA Accessibility Standards (ABAAS) and 2010 ADA Standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_Att_02_140PP027Q0018_Wage_Rates.pdf | ||
| B08_Att_03_140PP027Q0018_Tech_Info_Form.docx | DOCX document | |
| Sol_140PP027Q0018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OREGON CAVES NATIONAL
MONUMENT & PRESERVE
REHABILITATE KIOSK
RESTROOMS TO IMPROVE VISITOR
ACCESS AND EXPERIENCE
PMIS No. 215914
CONSTRUCTION SPECIFICATIONS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
Specifications - Rehabilitate Kiosk Restrooms, Oregon Caves NM&P
DIVISION 01 – GENERAL REQUIREMENTS
Section 01 10 00 – Summary of Work
PART 1 – GENERAL
ITEM 1 – DESCRIPTION OF WORK
1.1 Background
The existing public restroom facilities are deteriorated, outdated, and non-compliant with current accessibility and sanitation standards. Interior finishes have exceeded their service life and building envelope penetrations have allowed rodent intrusion. Plumbing and electrical systems are obsolete and no longer meet current safety codes.
The restroom interiors will be gutted to structural framing, replace mechanical, plumbing, and electrical systems, install sanitary wall finishes, construct fully compliant ADA restroom layouts, and implement permanent rodent exclusion measures in accordance with National Park Service cultural resource protection requirements.
1.2 Work Covered by Contract Documents
The contractor shall furnish all labor, materials, tools, supervision, and incidentals necessary to complete the following work:
A. Interior Demolition
• Remove all interior finishes to exposed structural framing, including:
o Ceramic wall tile and mortar bed o Gypsum board, paneling, and trim o Suspended and framed ceiling assemblies o Thermal and vapor insulation
• Remove all plumbing fixtures, piping, valves, and supports
• Remove all electrical fixtures, devices, wiring, and associated equipment
• Remove all restroom partitions and accessories
• Remove all floor tiles, adhesives, and setting bed to expose structural slab
• All materials that a removed need to be hauled off site to an approved disposal or recycling center.
All demolition shall comply with OSHA 29 CFR 1926 Subpart T and EPA construction waste handling regulations.
B. Reconstruction
The contractor shall reconstruct the restroom interiors including:
• Installation of new plumbing distribution and vent systems per IPC 2021
• Installation of new branch electrical circuits and lighting systems per NFPA 70
(NEC)
• Installation of new sanitary PVC wall and ceiling panel systems o Combined walls and ceilings: 884 SF o Wall panels shall overlap top lip of tile cove base and seal to create water-tight seam. See section 1.5 concrete floor repair for tile information.
• Installation of ADA compliant partitions and fixtures o One ADA stall per restroom at 60 in. x 60 in. clear space o Additional stalls sized at 42 in. x 60 in.
• Implementation of rodent-proofing of all penetrations and voids
1.3 ADA Restroom Requirements
Each restroom shall be reconfigured to meet ABA Accessibility Standards (ABAAS) and 2010 ADA Standards, including:
• One wheelchair accessible toilet compartment per restroom with:
o 60 in. minimum clear width o 60 in. minimum turning space
• Grab bars installed per ADA Section 604
• Accessible lavatories with:
o Knee clearance of 27 in. minimum o Insulated P-traps
• Mirror and accessory mounting heights compliant with ADA Section 603
• Door maneuvering clearances compliant with ADA Section 404
1.4 Rodent Exclusion Scope
All building envelope penetrations shall be sealed using:
• 16-gauge stainless steel rodent mesh
• Rodent-resistant polyurethane sealants
• Galvanized flashing closures were required
Repairs shall be concealed to preserve the historic exterior appearance.
1.5 Concrete Floor Repair
Full Concrete Slab Repair
Upon removal of existing floor finishes, the COR will evaluate the condition of the existing slab. The contractor will repair, seal and refinish 156 SF of concrete slab as follows:
• Wash slab removing all dirt, grease, residue etc. with approved detergent. Detergent shall be compatible with crack repair and slab membrane products. Rinse clean and dry thoroughly.
• Repair structural slab cracks 1/8” wide or greater with hybrid elastomeric adhesive-sealant (Laticrete Hydro Ban Fillet & Sealant or NPS approved equal).
• Apply load bearing waterproofing/crack isolation membrane throughout concrete slab surface (Laticrete Hydro Ban or NPS approved equal).
• Troubleshoot, clear, and repair non-functional floor drains, and verify function by testing for proper flow with no backup or leaks.
• Install new floor finish: Install new 2”x2” square tile floor finish. Tiles shall conform with ANSI A326.3, slip-resistant porcelain tile with dynamic coefficient of friction
(DCOF) of 0.42 or greater when wet. Install new 4”x4” glazed porcelain tile cove base over ¼” thick cement backer board. Provide manufacturer specifications for tile, mortar and grout for NPS approval prior to construction. Floor tile color to match similar to existing tan to dark-tan random assortment, cove base tile to match new PVC wall panel color.
1.6 Payment
Payment will be made at the CLIN lump sum price, or in accordance with milestones achieved per the approved Schedule of Values.
1.7 Period of Performance
All work shall be completed within:
90 calendar days from Notice to Proceed, including 10 weather days.
ITEM 2 – EXISTING UTILITIES
The contractor shall:
• Verify and locate all existing utilities prior to demolition
• Coordinate shutdowns with the COR at least 72 hours in advance
• Maintain lockout/tagout procedures per OSHA 1926.417
Any damage to utilities shall be repaired at no additional cost to the Government.
ITEM 3 – CONTRACTOR’S USE OF PREMISES
The building is a historic structure; therefore:
• Exterior fabric shall not be altered
• Penetrations shall not be enlarged
• All work shall comply with Secretary of the Interior’s Standards for Rehabilitation
Dust containment barriers shall be installed in accordance with SMACNA IAQ Guidelines.
ITEM 4 – COMMENCEMENT, PROSECUTION, AND COMPLETION
The contractor shall submit a baseline schedule showing:
• Demolition
• Rough-in work
• Flooring work
• Wall panel installation
• Fixture installation
• Inspection and closeout
ITEM 5 – EXAMINATION OF SITE
Bidders are required to visit the site and verify:
• Existing dimensions
• Structural conditions
• Utility routing
• ADA feasibility prior to bid submission
ITEM 6 – ABBREVIATIONS AND STANDARDS
The following standards govern this work:
• IBC 2021
• IPC 2021
• NFPA 70
• ABA Accessibility Standards
• OSHA 29 CFR 1926
• ACI 318 and ACI 302
• ASTM E84 (interior finish flame spread)
ITEM 7 – ACCIDENT PREVENTION
The contractor shall prepare a site-specific Accident Prevention Plan (APP) including:
• Silica exposure mitigation per OSHA 1926.1153
• Confined space hazard evaluation
• Demolition sequencing hazard analysis
ITEM 8 – PRECONSTRUCTION CONFERENCE
A preconstruction conference will be held to review:
• Historic protection requirements
• Rodent exclusion methods
• Utility shutdown procedures
• Construction sequencing
ITEM 9 – SUBMITTALS
The contractor shall submit:
• ADA partition shop drawings
• Product data for:
o Plumbing fixtures o Lighting fixtures o PVC wall systems o Rodent mesh o Concrete mix design
Submittals shall be transmitted using NPS Form CM-16.
ITEM 10 – TEMPORARY SERVICES
The contractor shall provide:
• Temporary lighting
• Temporary power
All temporary installations shall comply with OSHA 1926 Subpart K.
Note: Worker and visitor sanitation facilities are available at the Historic District, approximately 900 feet from the project site.
ITEM 11 – PROJECT CLOSEOUT
Closeout shall include:
• As-built drawings of plumbing and electrical
• Warranty documentation
• Photo documentation of concealed rodent exclusion measures
PART 2 – PRODUCTS
2.1 Plumbing Fixtures
• Sensor-operated ADA water closets, Zurn Elkay or approved equal
• Wall-mounted or floor ADA lavatories with concealed carriers
2.2 Partitions
Partitions shall be:
• Solid phenolic or stainless steel
• ADA compartment sized 60 in. x 60 in.
2.3 Lighting
Lighting shall be:
• IK10 vandal-resistant LED
• Wet location rated
• Equipped with occupancy sensors
2.4 Wall and Ceiling Panels
Provide:
• Extruded PVC sanitary panels: Trusscore wall panel or equal
• Antimicrobial sealant at all seams
• Class A flame spread rating per ASTM E84
PART 3 – EXECUTION
Phase 1 – Mobilization and Protection
• Install temporary barriers and signage
• Protect exterior historic materials
Phase 2 – Interior Demolition
• Remove all finishes and systems to structural framing
• Segregate recyclable materials
• Control silica dust using wet methods and HEPA vacuums
Phase 3 – Rodent Exclusion Installation
• Identify all penetrations and voids
• Install stainless steel mesh secured with corrosion-resistant fasteners
• Seal all joints and seams
Phase 4 – Rough-In Installation
• Install new water supply and DWV piping per IPC
• Install branch circuits in EMT where exposed
Phase 5 – Concrete Floor Repair
• Wash slab and repair structural slab cracks 1/8” wide or greater
• Apply load bearing waterproofing/crack isolation membrane
• Troubleshoot, clear, and repair non-functional floor drains
• Install new floor finish (tile)
Phase 6 – Wall and Ceiling Panel Installation
• Install PVC panels with concealed fasteners
• Seal joints to create cleanable, pest-resistant surfaces
Phase 7 – Fixture and Partition Installation
• Installing ADA compartments
• Install grab bars anchored to structural backing
• Install lavatories and accessories at ADA mounting heights
Phase 8 – Electrical and Lighting Commissioning
• Test GFCI and occupancy sensors
• Verify minimum 30 foot-candles illumination
Phase 9 – Testing and Inspection
• Perform plumbing pressure tests
• Conduct final ADA inspection with COR
END OF SECTION 01 10 00