B08_Att_01_140P8426Q0088_Specs.pdf

PDF 521 KB Posted

Attached to
Remove/Replace Turbidity Meters, NPS-ORCA Federal contract opportunity
Solicitation number
140P8426Q0088
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This is a Statement of Work for a federal construction contract at Oregon Caves National Monument & Preserve to remove and replace turbidity meters at the Lake Creek Raw Water Treatment Plant.

The project requires the contractor to remove existing Hach 1720D turbidity meters that have exceeded their service life and install Government-furnished modern equipment, including two Hach TU5300sc turbidity meters (one with basic cleaning head, one with self-cleaning head) and one Hach SC4500 controller. The contractor must furnish all labor, materials, tools, transportation, and supervision to complete the work, which includes removing existing meters, valves, tubing, and fittings; installing approximately twenty linear feet of new sample tubing, isolation valves, flow control valves, and fittings; providing electrical integration with 120V power connection and 4–20 mA output/Modbus communication; and installing a bypass/sample loop configuration to enable maintenance without system shutdown. The work is structured into three CLINs: Mobilization/Demobilization, Remove Meters & Valves, and Install Meters & Components. The contract must be completed within 30 calendar days, including trail access limitations and manual material transport. Site access is constrained to approximately 0.2 miles via Big Tree Trail with hand-transport only, no motorized equipment without written approval. Work hours are 8:00 AM to 5:00 PM unless otherwise approved. Water system shutdowns cannot exceed 2 hours, require 48-hour notice, and the contractor must submit a Water System Continuity Plan. The contractor must coordinate with the Government-scheduled Hach-certified technician for final inspection, calibration, and verification, then make any recommended adjustments. Deliverables include product data, shop drawings, construction schedule, accident prevention plan, calibration certificates (NIST-traceable), O&M manuals, and as-built documentation. A mandatory preconstruction conference must address access logistics, shutdown sequencing, and safety. The contractor must provide a minimum 1-year warranty and comply with EPA 40 CFR 141 Subpart H, OSHA 29 CFR 1926, NFPA 70, ANSI standards, UL certification, and AWWA standards.

View the file

Other files for this federal contract opportunity

Other files attached to Remove/Replace Turbidity Meters, NPS-ORCA, newest first.
File Type Posted
B08_Att_03_140P8426Q0088_Tech_Info_Form.pdf PDF
Sol_140P8426Q0088.pdf PDF
B08_Att_02_140P8426Q0088_Construction_Wages.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Oregon Caves National Monument & Preserve PMIS 244479 Remove/Replace Turbidity Meters at Lake Creek Water Treatment Plant

DIVISION 01 – GENERAL REQUIREMENTS

SECTION 01 10 00 – DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 – DESCRIPTION OF WORK

1.1 Background

The Lake Creek Raw Water Treatment Plant at Oregon Caves National Monument & Preserve (ORCA) provides potable water to critical park infrastructure including staff housing, the Visitor Center, and cave tour operations. The system is regulated under the EPA Safe Drinking Water Act and must comply with 40 CFR 141 Subpart H – Surface Water Treatment Rule (SWTR).

The existing Hach 1720D turbidity meters have exceeded their service life and present reliability risks. Turbidity monitoring is a critical control parameter used to verify filtration effectiveness and ensure safe drinking water. Failure of this instrumentation could result in undetected water quality issues and regulatory non-compliance.

This project replaces outdated turbidity monitoring equipment with Government-furnished modern, EPA- compliant instrumentation to ensure operational reliability, regulatory compliance, and protection of public health.

1.2 Work Covered by Contract Documents

Project Location:

Lake Creek Raw Water Treatment Plant, Oregon Caves National Monument & Preserve, Josephine County, Oregon. Refer to Appendix A – Site Logistics and Location Map.

CLIN Structure:

CLIN 1 – Mobilization/Demobilization CLIN 2 – Remove Meters & Valves CLIN 3 – Install Meters & Components

Scope of Work:

The Contractor shall furnish all labor, materials, tools, transportation, and supervision necessary to:

• Remove existing turbidity meters, valves, tubing, and fittings.

• Install Government-furnished equipment as follows:

o Two (2) Hach TU5300sc turbidity meters:

One (1) with basic cleaning head One (1) with self-cleaning head o One (1) Hach SC4500 controller

• Provide electrical integration including:

o 120V power connection (verify field conditions) o 4–20 mA output and/or Modbus communication integration with existing system

• Install approximately twenty (20) linear feet of sample tubing, isolation valves, flow control valves, and fittings.

• Install isolation valves and a bypass/sample loop configuration to allow maintenance without system shutdown.

• Once installation is complete, and after the Government schedules a Hach-certified technician to inspect, calibrate, and verify communications for all installed equipment, make any recommended installation corrections and/or adjustments necessary to ensure proper functionality.

Period of Performance

Work shall be completed within 30 calendar days, inclusive of:

• Trail access limitations

• Manual transport of materials

• Shutdown coordination

ITEM 2 – EXISTING UTILITIES

2.1 Utility Coordination

Contractor shall coordinate with COR prior to any system interruption.

2.2 Protection

Contractor shall protect all existing piping, instrumentation, and controls.

2.3 Utility Interruptions

• Water shutdowns shall not exceed 2 hours.

• Submit a Water System Continuity Plan for contingency operations.

• Provide 48-hour notice prior to shutdown.

ITEM 3 – CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations

Comply with all NPS regulations.

3.2 Site Access Constraints

• Site located approximately 0.2 miles via Big Tree Trail.

• All materials shall be transported by hand unless otherwise approved.

• No motorized or mechanized transport allowed without written approval.

3.3 Work Hours

8:00 AM – 5:00 PM unless approved otherwise.

3.4 Environmental Protection

• Protect vegetation and trails.

• Restore disturbed areas.

3.5 Storage and Staging

• Staging limited to COR-designated area shown on Appendix A.

ITEM 4 – COMMENCEMENT, PROSECUTION, AND COMPLETION

Contractor shall submit detailed schedule including:

• Mobilization

• Demolition

• Installation

• Shutdown coordination

• Coordination with Government-scheduled Hach-certified technician inspection

• Final Installation Adjustments (if needed)

ITEM 5 – EXAMINATION OF THE SITE

Contractor responsible for understanding:

• Terrain

• Trail access

• System layout

ITEM 6 – ABBREVIATIONS AND STANDARDS

Work shall comply with:

• EPA 40 CFR 141 Subpart H (SWTR)

• OSHA 29 CFR 1926

• NFPA 70 (NEC)

• ANSI standards

• UL certification

• AWWA applicable standards

• Manufacturer requirements (Hach)

ITEM 7 – ACCIDENT PREVENTION

Contractor shall submit APP including:

• Trail hazards (slip/trip)

• Manual handling risks

• Remote emergency response planning

PPE shall comply with OSHA 1926 Subpart E.

ITEM 8 – PRECONSTRUCTION CONFERENCE

Mandatory meeting to address:

• Access logistics

• Shutdown sequencing

• Safety

ITEM 9 – SUBMITTALS

Submit:

• Product Data

• Shop Drawings

• Construction Schedule

• Schedule of Values

• APP

• Calibration certificates (NIST-traceable)

• O&M Manuals

ITEM 10 – TEMPORARY SERVICES

Contractor shall provide all required temporary utilities and equipment.

ITEM 11 – PROJECT CLOSEOUT

11.1 Deliverables

• As-built documentation

11.2 Final Inspection

In coordination with Government-scheduled Hach-certified technician inspection of installation work, make any recommended installation adjustments to ensure system operation and compliance.

11.3 Warranty

Minimum 1-year warranty.

PART 3 – EXECUTION

PHASE 1 – MOBILIZATION

• Transport materials via trail

• Protect environment

PHASE 2 – DEMOLITION

• Remove existing meters

• Dispose per EPA regulations

PHASE 3 – INSTALLATION

• Install meters and controller

• Install tubing, valves, bypass loop

• Ensure leak-free system

PHASE 4 – INSPECTION

• Coordinate with Government-scheduled Hach-certified technician inspection

• Make any recommended final installation adjustments

PHASE 5 – CLOSEOUT

• Restore site

• Submit documentation

APPENDICES

Appendix A – Site Logistics and Location Map

END OF SECTION

Appendix A – Site Logistics and Location Map

Storage Tanks 38,000galeach

Caves Developed Area Water System

November 7, 2008 water Facilities Monument Features

Spigots

PART 1 – GENERAL
ITEM 1 – DESCRIPTION OF WORK
1.1 Background
1.2 Work Covered by Contract Documents
Project Location:
CLIN Structure:
Scope of Work:

Period of Performance

ITEM 2 – EXISTING UTILITIES
2.1 Utility Coordination
2.2 Protection
2.3 Utility Interruptions
ITEM 3 – CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations
3.2 Site Access Constraints
3.3 Work Hours
3.4 Environmental Protection
3.5 Storage and Staging
ITEM 4 – COMMENCEMENT, PROSECUTION, AND COMPLETION
ITEM 5 – EXAMINATION OF THE SITE
ITEM 6 – ABBREVIATIONS AND STANDARDS
ITEM 7 – ACCIDENT PREVENTION
ITEM 8 – PRECONSTRUCTION CONFERENCE
ITEM 9 – SUBMITTALS
ITEM 10 – TEMPORARY SERVICES
ITEM 11 – PROJECT CLOSEOUT
11.1 Deliverables
11.2 Final Inspection
11.3 Warranty
PART 3 – EXECUTION
PHASE 1 – MOBILIZATION
PHASE 2 – DEMOLITION
PHASE 3 – INSTALLATION
PHASE 4 – INSPECTION
PHASE 5 – CLOSEOUT
APPENDICES
Appendix A – Site Logistics and Location Map

File details come from the government source that posted it. Updated .